Joint Motion on Timing of Summary Disposition Motions
ML13122A463
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 05/02/2013
From: Hamrick S, Doris Lewis, Walsh T
NextEra Energy Seabrook
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 24456, 50-443-LR, ASLBP 10-906-02-LR-BD01
Download: ML13122A463 (3)


Text

May 2, 2013 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )

)

NextEra Energy Seabrook, LLC ) Docket No. 50-443-LR

) ASLBP No. 10-906-02-LR (Seabrook Station, Unit 1) )

JOINT MOTION REGARDING TIMING OF

SUMMARY

DISPOSITION MOTIONS NextEra Energy Seabrook, LLC (NextEra) has prepared motions for summary disposition of Contentions 4B and 4D, which to avoid any question of compliance with 10 C.F.R. § 2.323(a), NextEra intended to file on May 6, 2013 - ten days after the April 26, 2013 release of the NRCs second draft supplemental environment impact statement for Seabrook reviewing the updated analysis of severe accident mitigation alternatives. During NextEras consultation with the parties pursuant to 10 C.F.R. § 2.323(b) to determine whether any resolution of the issues raised in these contentions is possible, the representative of the New England Coalition and Friends of the Coast (NEC/FOTC) has requested that NextEra not file this motion before noon on May 10, 2013, in order to allow NEC/FOTCs representative time to confer with NECs Board on this matter. The NRC Staff has no objection to this request.

Accordingly, NextEra, NEC/FOTC and the NRC Staff hereby jointly move the Board to accept the parties agreement that NextEra may submit its motions for summary disposition of Contentions 4B and 4D on May 10, 2013, and that the twenty-day period in which answers may be submitted pursuant to 10 C.F.R. 2.1205(b) shall run from the date of that submittal.

NEC/FOTC and the NRC Staff have reviewed this joint motion and have authorized NextEra to file it on their behalf.

Respectfully Submitted,

/Signed (electronically) by David R. Lewis /

Steven C. Hamrick David R. Lewis NextEra Energy Seabrook, LLC Timothy J. V. Walsh 801 Pennsylvania Avenue, NW Suite 220 2300 N Street, NW Washington, DC 20004 Washington, DC 20037 Telephone: 202-349-3496 Telephone: 202-663-8474 Counsel for NextEra Energy Seabrook, LLC Dated: May 2, 2013 2

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )

)

NextEra Energy Seabrook, LLC ) Docket No. 50-443-LR

) ASLBP No. 10-906-02-LR (Seabrook Station, Unit 1) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Joint Motion Regarding Timing of Summary Disposition Motions has been served through the E-Filing system on the participants in the above-captioned proceeding, this 2nd day of May 2013.

/Signed electronically by David R. Lewis/

David R. Lewis 403961228v1