05000338/FIN-2007005-04
From kanterella
Revision as of 17:51, 8 October 2017 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Finding | |
---|---|
Title | |
Description | The inspectors identified that the licensee failed to incorporate a heavy load lift analysis into their UFSAR. Failure to update the UFSAR to reflect aspects of heavy load lifts involving the reactor vessel head and include information from a reactor vessel head drop analysis was a violation of 10 CFR 50.71(e). The NRC has found industry uncertainty regarding the licensing bases for handling of reactor vessel heads, and as a result issued EGM 07-006, Enforcement Discretion for Heavy Load Handling Activities, on September 28, 2007. The Nuclear Energy Institute (NEI) has informed NRC of industry approval of a formal initiative that specifies actions each plant will take to ensure that heavy load lifts continue to be conducted safely and that plant licensing bases accurately reflect plant practices. The NRC staff believes implementation of the initiative will resolve uncertainty in the licensing bases for heavy load handling, and enforcement discretion related to the uncertain aspects of the licensing basis is appropriate during the implementation of the initiative. During inspection of heavy load lifts, the inspectors determined that the licensee implemented interim actions prior to the specified lifts in accordance with the industry initiative, thereby meeting the following criteria to warrant enforcement discretion: 1) The licensee did not have either a single-failure-proof crane nor a load drop analysis (generic or plant-specific) that bounded the planned lifts with respect to load weight, load height, and medium present, so the licensee conducted the head lift at the minimum practicable height and flooded the refueling cavity with water during the head movement to limit the maximum potential impact velocity of the head. The licensee maintained the bottom of the head less than 15 feet above the refueling cavity water surface when the head was lifted above the guide studs, so that the energy that could be transferred to the reactor vessel in the event of a load drop. Once the cavity was fully flooded [greater than 23 feet above the reactor vessel flange], the reactor vessel head was allowed to be lifted more than 15 feet above the water surface as necessary to lift the head above immovable structures around the refueling cavity. 2) Included the movement of heavy loads as a configuration management activity in administrative controls established to implement 10 CFR50.65(a)(4). Therefore, consistent with EGM 07-006, we are exercising enforcement discretion for the above violation in accordance with Section VII.B.6 of the NRC Enforcement Policy and are not issuing enforcement action for the violation. |
Site: | North Anna |
---|---|
Report | IR 05000338/2007005 Section 1R20 |
Date counted | Dec 31, 2007 (2007Q4) |
Type: | Violation: Severity level Enforcement Discretion |
cornerstone | Emergency Prep, Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.2 |
Inspectors (proximate) | R Taylor J Reece E Lea R Clagg |
INPO aspect | |
' | |
Finding - North Anna - IR 05000338/2007005 | |||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (North Anna) @ 2007Q4
| |||||||||||||||||||||