Safety Guide 6, Independence Between Redundant Standby (Onsite) Power Sources and Between Their Distribution SystemsML003739924 |
Person / Time |
---|
Issue date: |
08/10/1971 |
---|
From: |
Office of Nuclear Regulatory Research |
---|
To: |
|
---|
References |
---|
Download: ML003739924 (2) |
|
|
---|
Category:Regulatory Guide
MONTHYEARML24038A3102024-04-30030 April 2024 Rev 1 Dedication of Commercial-Grade Items for Use in Nuclear Power Plants ML23263A9972024-02-0202 February 2024 Watermarked - DG-5072 - Rev 0 of RG 5.90 - Guidance for Alternative Physical Security Requirements for Small Modular Reactors and Non-Light-Water Reactors ML23286A2512024-02-0202 February 2024 Watermarked DG-5073 - Fitness for Duty Program for Part 53 - 10-13-23 ML23286A2682024-02-0202 February 2024 Watermarked - DG-5074 - Access Authorization - Econcurrence Version Clean (02-03-23) ML23286A2862024-02-0202 February 2024 Watermarked - DG-5078, Fatigue Management for Nuclear Power Plant Personnel -10-13-23 ML23286A2822024-02-0202 February 2024 Watermarked - DG-5076 - Physical Protection for Part 53 - 10-13-23 ML23286A2782024-02-0202 February 2024 Watermarked - DG-5075 - Cyber Security 10-13-23 ML23194A1942023-08-31031 August 2023 Draft Regulatory Guide DG-1404, Revision 1 (RG 1.253 Rev 0) Guidance on Ticap for Non-LWRs ML22165A0722023-02-28028 February 2023 DG-4027, Draft Regulatory Guide 4.2 Supplement 1, Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications, Revision 2 ML23012A2422023-02-28028 February 2023 DG-1374 RG 1.152 Rev 4 Criteria for Programmable Digital Devices in Safety-Related Systems of Nuclear Power Plants ML23018A2932023-02-16016 February 2023 Draft Regulatory Guide DG-1418 (RG 1.212 Rev 2), Sizing Large Lead-Acid Storage Batteries. (ACRS Copy) Regulatory Guide 5.892022-11-0101 November 2022 Rev.0, Fitness-for-Duty Programs for Commercial Power Reactor and Category I Special Nuclear Material Licensees ML22067A0142022-03-31031 March 2022 Rev 3 ACRS Spent Fuel Heat Generation in an ISFSI ML22048B8222022-02-18018 February 2022 DG-1389 (ACRS Version for 3-16-22 Meeting) - Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors ML22040A0822021-10-30030 October 2021 Document to Support ACRS Subcommittee Meeting - Redline RG 1.57, Rev 3, Design Limits and Loading Combinations for Metal Primary Reactor Containment System Components ML21167A3512021-06-0101 June 2021 Rev 5 Final Watermarked for ACRS ML21092A1512021-05-0505 May 2021 Rev. 4 ACRS Version ML21092A1342021-05-0505 May 2021 Rev. 2 ACRS Version ML21181A2492021-04-30030 April 2021 Watermark for ACRS Fc Meeting RG 1.9 Rev 5 ML21006A3372021-04-0101 April 2021 Regulatory Analysis - DG 1381 - Control of Heavy Loads for Nuclear Facilities ML21006A3352021-04-0101 April 2021 DG 1381 for Rev 0 of RG 1.244 - Control of Heavy Loads for Nuclear Facilities ML20168A8832021-04-0101 April 2021 DG-1371, Proposed Rev 6 of RG 1.26, Quality Group Classifications and Standards for Water-, Steam-, and Radioactive-Waste-Containing Components of Nuclear Power Plants ML21083A2892021-02-28028 February 2021 Draft for Acrs Review ML21048A4482021-02-17017 February 2021 Rev. 2 ML21011A2312021-01-31031 January 2021 Rev 4 (Draft for ACRS Fc Review on 2-3-21) ML20120A6312021-01-31031 January 2021 Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1, Revision 20, (DG-1367) ML20120A6292021-01-31031 January 2021 Operation and Maintenance Code Case Acceptability, ASME OM Code, Revision 4, (DG-1368) ML20120A6332021-01-31031 January 2021 Design, Fabrication, and Materials Code Case Acceptability, ASME Section III, Revision 39, (DG-1366) ML20120A6272021-01-31031 January 2021 ASME Code Cases Not Approved for Use, Revision 7 (DG-1369) ML21012A1972021-01-12012 January 2021 a Performance-Based Approach to Define the Site-Specific Earthquake Ground Motion, RG 1.208, Revision 0 Regulatory Guide 1.200, Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities2020-12-31031 December 2020 Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities ML20183A4232020-12-31031 December 2020 Draft Regulatory Guide DG-1361 (Proposed Rev. 2 to Reg. Guide 1.89), Environmental Qualification of Certain Electrical Equipment Important to Safety for Nuclear Power Plants ML20238B8732020-12-29029 December 2020 Public Comment Resolutions on DG-1362 for RG 1.200, Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities ML20282A2982020-12-0404 December 2020 DG-3055, Rev 0, Regulatory Guide (RG) 3.76, Implementation of Aging Management Requirements for Spent Fuel Storage Renewals ML20282A2992020-12-0404 December 2020 Regulatory Analysis for DG-3055, Rev 0, Regulatory Guide (RG) 3.76, Implementation of Aging Management Requirements for Spent Fuel Storage Renewals ML20210M0472020-12-0101 December 2020 Draft Regulation Guide DG-1288: Plant-Specific, Risk-Informed Decisionmaking for Inservice Inspections of Piping ML20231A8562020-11-30030 November 2020 Draft Regulatory Guide DG-1360, Risk-Informed, Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants ML20231A8352020-11-30030 November 2020 Draft Regulatory Guide DG-1359, Fire Protection for Nuclear Power Plants ML20307A0462020-11-0202 November 2020 Draft for ACRS Public Meeting, RG 1.200, R3, Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities ML20210M0442020-10-28028 October 2020 Regulatory Analysis: Draft Regulatory Guide DG-1288 - an Approach for Plant-Specific, Risk-Informed Decisionmaking for Inservice Inspection of Piping (Proposed Revision 2 of Regulatory Guide 1.178, Dated September 2003) ML20154K5842020-09-17017 September 2020 Results of Periodic Review of Regulatory Guide (RG) 1.78 ML20182A7882020-08-31031 August 2020 DG 1373 for RG 1.240 - Fresh and Spent Fuel Pool Criticality Analyses ML20055G8232020-08-0707 August 2020 DG 1363 for Proposed Rev 4 to Regulatory Guide (RG) 1.105 - Setpoints for Safety-Related Instrumentation Regulatory Guide 3.152020-07-31031 July 2020 Regulatory Guide 3.15. Rev 2, Standard Format and Content of License Applications for Receipt and Storage of Unirradiated Power Reactor Fuel and Associated Radioactive Material at a Nuclear Power Plant Regulatory Guide 1.2362020-07-30030 July 2020 Draft for ACRS Review ML20119A6142020-04-28028 April 2020 Response to Comments for RG 1.236 for ACRS ML20105A4672020-04-14014 April 2020 Memo to OCA - for Revision 1 of Regulatory Guide 8.39, Release of Patients Administered Radioactive Material ML20099F0262020-04-0707 April 2020 Public Comment Resolution Table for DG 1341 (Regulatory Guide (RG) 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses, Rev. 2 ML19206A4892020-02-0606 February 2020 Draft Regulatory Guide DG-1287, an Approach for Plant-Specific, risk-Informed Decisionmaking: Technical Specifications ML19116A0772019-08-31031 August 2019 Draft Regulatory Guide DG-5040, Urine Specimen Collection and Test Results Review Under 10 CFR Part 26, Fitness for Duty Programs. 2024-04-30
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
8/10/71 SAFETY GUIDE 6 INDEPENDENCE BETWEEN REDUNDANT STANDBY (ONSITE) POWER SOURCES AND BETWEEN THEIR DISTRIBUTION SYSTEMS A. Introduction General Design Criterion 17 requires that onsite electrical power systems have sufficient independence to perform their safety functions assuming a single failure. This safety guide describes an acceptable degree of independence between redundant standby (onsite) power sources and between their distribution systems.
This guide does not address the suitability of nearby hydroelectric, nuclear, or fossil units as standby power sources at multiple-unit sites. This matter will be evaluated on an individual case basis. B. Definitions Preferred Power System: The offsite external commercial power system. Standby Power System: Those onsite power sources and their distribution equipment provided to energize devices essential to safety and capable of operation independ ently of the preferred power system. Standby Power Source: An electrical generat ing unit and all necessary auxiliaries, usually a diesel generator set, which is part of the standby power system. Load Group: An arrangement of buses, trans formers, switching equipment, loads, etc., fed from the same power source. C. Discussion There is evidence based on operating experi ence and analytical considerations that the par allel operation of standby power sources renders them vulnerable to common mode failures.
Cur rent designs are therefore based on the concept of independent, redundant load groups. In these designs, the standby power source for one load group is never automatically interconnected under accident conditions with the standby power source of a redundant counterpart.
There can also be compromises of independ ence resulting from automatic bus ties (both a-c and d-c) which connect the loads of one load group to the power source of another in the event the power source of the first load group has failed. The slightly improved defense against random failures achieved by these bus ties is more than offset by the additional vul nerability to common mode failures which they create. A special case of the foregoing is the bus that is automatically transferred to one or the other of two redundant standby power sources; this is commonly referred to as a swing bus. This arrangement also compromises the independ ence of redundant power sources and their load groups while adding little to the defense against random single failures.
The inclusion of a swing bus in an otherwise well designed system often results from an in compatibility between the number of standby power sources (whether a-c or d-c) and the number of redundant load groups. For example, an engineered safety feature system design which depends on the operation of at least two of three electrically driven pumps and which derives power from either of two redundant standby power sources must provide for the swinging of one of the three pump motors in order to meet the single failure criterion.
A compatible design, such as one based on three' power sources, would not utilize the swing fea ture. The necessity for a swing bus can also result from an incompatibility between the a-c and d-c power sources themselves.
An example would be a three diesel generator, three bus system utilizing d-c control circuits.
If only two 5.1 d-c sources are provided, the switching of diesel generator control circuits between the d-c sources becomes necessary in order to provide the necessary redundancy.
Again, a compatible design such as one based on three d-c sources, one for each generator, would not utilize a swing bus. A diesel generator that swings between the load groups of different units at a multiple unit site is not an example of the foregoing since such load groups are not redundant to each other. D. Regulatory Position 1. The electrically powered safety loads (a-c and d-c) should be separated into redundant load groups such that loss of any one group will not prevent the minimum safety functions from being performed.
- 2. Each a-c load group should have a con nection to the preferred (offsite) power source and to a standby (onsite) power source (usually a single diesel genera tor). The standby power source should have no automatic connection to any other redundant load group. At mul tiple nuclear unit sites, the standby power source for one load group may have an automatic connection to a load group of a different unit. A preferred power source bus, however, may serve redundant load groups. 8. Each d-c load group should be energized by a battery and battery charger. The battery-charger combination should have no automatic connection to any other redundant d-c load group.4. When operating from the standby sources, redundant load groups and the redundant standby sources should be independent of each other at least to the following extent: a. The standby source of one load group should not be automatically paralleled with the standby source of another load group under acci dent conditions;
- b. No provisions should exist for auto matically connecting one load group to another load group; c. No provisions should exist for auto matically transferring loads be tween redundant power sources; d. If means exist for manually con necting redundant load groups tu gether, at least one interlock should be provided to prevent an operator error that would parallel their standby power sources.
- 5. A single generator driven by a single prime mover is acceptable as the standby power source for each a-c load group of the size and characteristics typical of recent applications.
If other arrangements such as multiple diesel generators operated in parallel or mul tiple prime movers driving a single generator are proposed, the applicant should demonstrate that the proposed arrangement has an equivalent reliabil ity. Common mode failures as well as random single failures should be con sidered in the analysis.6.2