ML18017B619

From kanterella
Revision as of 18:11, 9 September 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Responds to NRC 820118 Ltr Re Violations Noted in IE Insp Repts 50-400/81-25,50-401/81-25,50-402/81-25 & 50-403/81-25. Corrective Actions:Program Implemented to Verify That safety-related Items Meet Specs
ML18017B619
Person / Time
Site: Harris  
Issue date: 02/17/1982
From: BANKS H R
CAROLINA POWER & LIGHT CO.
To: OREILLY J P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML18017B618 List:
References
NUDOCS 8203170446
Download: ML18017B619 (6)


See also: IR 05000400/1981025

Text

February 17, 1982 CSQE, ,, Carolina Power&Light Company i 7<~~EGJ J5/,AMTA r EG~....-, 82I'EB23 All.3r Mr.James P.O'Reilly United States Nucleav Regulatovy

Commission

Region XI 101 Marietta Stveet, Novthwest Atlanta, Georgia 30303 Dear Mv.O'Reilly: Xn reference to youv lettev of January 18, 1982,'eferving

to RX1: GFM 50-400/401/402/403/81-25,.the, attached is Carolina Power&Light Company's reply to the deficiencies

identified

in Appendix A.Xt is considered

that the corrective

and preventive

actions taken will be satisfactor

y fov resolution

of these items, once completed.

Thank you fov your consideration

in this matter.H.R.Banks Manager Corporate Quality Assuvance NJC:jp Attachment

cc: Mv.J.A.Jones Sworn to and subscribed

before me this 17th day of February, 1982.Notary Public My commission

expires: ate 411 Fayetteville

Street o P.O.Box 1551 I Raleigh, N.C.27602 8203i70446

820308 PDR ADOCK 05000400 8,, (,.,.PDR

Exhibit 6 Mr.James P.O'Reilly United States Nuclear Regulatory

Commission

Region II 101 Marietta Street, Northwest Atlanta, Georgia 30303 Dear Mr O'Reill: In reference to your letter of January 18, 1982, referring to RII: GFM 50-400/401/402/403/81-25, the attached is Carolina Power 4 Light Company's reply to the deficiencies

identified

in Appendix A.It is considered

that the corrective

and preventive

actions taken will be satisfactory

for resolution

of these items, once completed.

Thank you for your consideration

in this matter.Yours very truly, H.R.Banks Manager Corporate Quality Assurance NJC'jp Attachment

cc: Mr.J.A.Jones

Severity Level V Violations

A.10 CFR 50, Appendix B, Criterion XV as implemented

by CP&L PSAR section 1.8.5.15;CP8L Corporate QA Program section 15.1,3 and construction

procedure CQC-2, section 4.2 and 4.3 require that nonconforming

conditions

be identified

and corrected.

Contrary to the above, on December 8, 1981 three nonconforming

welded conditions

were found that had not been identified

previously

by CPKL or the material supplier.One undersized

fillet weld was found on cable tray suppor t section A (a supplier weld), one separation

crack was found on a weld on cable tray support CD-2616 (a shop weld)and the field-applied

tack welds had not been removed fr om or authorized

to remain on cable tray su~crt CD-2618.Each of th~etlt~r.

Dmncon-T electrical

cable tray supports located in the auxiliary building at about elevation 276'.B.10 CFR 50, Appendix B, Criterion IX as implemented

by CPAL PSAR section 1.8.5.9;CP8L Corporate QA Program section 8.4.1.d and construction

procedure MP-08, section 4.10.2 and AW-1 require that special processes such as welding be accom-plished in accordance

with applicable

codes or standards.

The applicable

welding code for seismic I electrical

cable tray supports is AWS-D1.1-1975, section 9.Contrary to the above, on December 8, 1981, a field-applied

welded"Lap Joint" on electrical

cable tt ay support identified

as CD-2618, was found not to have the minimum overlap that AWS-D1.1-1975, section 9.10 requires.Instead of the required five times the thickness of the base metal, the overlap was only four times the thickness of the base metal.Denial or Admission and Reasons for Violation:

A.The conditions

did exist as identified

i n the Notice of Violation.

The actual cause of the separation

crack could not be determined

and the undersized

fillet weld was due to poor vendor workmanship.

Failure to remove the tack welds was due to weld inspector oversight.

B.The violation is correct as stated.Field personnel (cr afts)installing"loose" support members (including

beam angles, longitudinal

and diagonal braces)failed to exercise care in locating these members during erection.There were also cases when detailed shop drawings utilizing work points did not allow for the required"lap joint" when utilizing material fabricated

in accordance

with the bill of material.This was a contributing

factor to the lack of attention to this detail.-continued-

-2-Corrective

Steps Taken and Results Achieved: A.Deficiency

and Disposition

Repor t num ber 748 was issued on December 10, 1981, for control and resolution

of the vendor items with the separation

crack and the undersized

fillet weld.Nonconformance

Report number W-256 was issued to resolve the tack weld item.The undersized

fillet weld and the separation

crack on the cable tray support were repaired.The deficient welds were ground out and the items were rewelded.The tack welds were ground out and removed.B.A complete reinspection

of the field applied welded lap joints on electrical

cable tray suppor ts installed prior to December 28, 1981, is presently in progress to identify all similar cases.The reinspection

is expected to be complete by April 1, 1982.Upon completion

of the reinspection, each case shall be evaluated by the Architect Engineer for structural

integrity.

Any rework warranted will then by performed.

Corrective

Steps Taken to Avoid Further Noncompliance:

A.A program hos been implemented

whereby CP&L QC Receiving Inspection

will verify that nuclear safety-related

items received under an Ebasco or Westinghouse

Quality Release meet the requirements

of the applicable

procurement

documents.

These inspections

will be based on a statistical

sampling and shall be accanplished

in accordance

with the QC Procedures.

Characteristics

to be verified shall include the following, as appropr iate: physical properties, dimensions, weld preparations, workmanship

and welding, lubricants, oils and electrical

insulation.

Procedure CQC-19 has been revised to insure that inspectors

pay special attention to the removal of tack welds on the back side of members welded.Written instructions

were issued on January 11, 1982, by memorandum

to the Ware-house Supervisor

and the Iron Worker Superintendent

to exercise care when handling cable tray support hangers to prevent possible damage.Instructions

were also given to repor t accidentally

dropped or damaged items to a QA inspector or the discipline

engineer.The vendor was contacted on December 16, 1981, and agreed to emphasize a more strenuous inspection

in areas of handling, porosity, undersized, undercut and cracked shopwelds.

B.The QA Inspectors

have been instructed

to inspect for proper overlap of field applied lap joints installed on or after December 28, 1981, and likewise the craft has been instructed

as to proper and improper overlaps.Field Change Request AS-1048 reduces the acceptable

overlap from"five times the thickness of the thinner part being joined" to one inch.Any joints found to violate the minimum one inch over lap shall be evaluated by the Architect Engineer to determine if any rework is necessary.-continued-

Date When Full Compliance

Will Be Achieved: A.Full compliance

is considered

to have been achieved on January 25, 1982.B.Full compliance

vill be achieved by May 1, 1982.