Issue date | From | Title | Project stage | |
---|---|---|---|---|
CP-201201518, License Amendment Request (LAR) 12-007, Revision to Technical Specification 3.8.1, AC Sources - Operating, for Two 14-Day Completion Times for Offsite Circuits | 19 December 2012 | Luminant Flores R | License Amendment Request (LAR) 12-007, Revision to Technical Specification 3.8.1, AC Sources - Operating, for Two 14-Day Completion Times for Offsite Circuits | Request |
CP-201300546, Response to Request for Additional Information for License Amendment Request (LAR) 12-007, Revision to Technical Specification 3.8.1, AC Sources - Operating, for Two, 14-Day Completion Times for Offsite Circuits | 16 May 2013 | Luminant Mays R | Response to Request for Additional Information for License Amendment Request (LAR) 12-007, Revision to Technical Specification 3.8.1, AC Sources - Operating, for Two, 14-Day Completion Times for Offsite Circuits | Response to RAI |
CP-201301252, Request for Enforcement Discretion Regarding Compliance with Technical Specifications 3.8.1, AC Sources - Operating. | 9 December 2013 | Luminant Flores R Thomas McCool | Request for Enforcement Discretion Regarding Compliance with Technical Specifications 3.8.1, AC Sources - Operating. | Request |
CP-201400140, Correction to Figures Provided in Response to Request for Additional Information for LAR 12-007 Regarding Two, 14-Day, One-Time, Completion Times for Offsite Circuits. | 13 February 2014 | Luminant Flores R Madden F | Correction to Figures Provided in Response to Request for Additional Information for LAR 12-007 Regarding Two, 14-Day, One-Time, Completion Times for Offsite Circuits. | Response to RAI |
ML13032A241 | 31 January 2013 | Balwant Singal Plant Licensing Branch IV | Acceptance Review Email, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, for Extension of Two 14-Day Completion Times for Offsite Circuits | Acceptance Review |
ML13108A153 | 18 April 2013 | Balwant Singal Plant Licensing Branch IV | Request for Additional Information Email, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, for Extension of Two 14-Day Completion Times for Offsite Circuits (TAC Nos. MF0405 and - | RAI |
ML13232A143 | 18 September 2013 | Balwant Singal Plant Licensing Branch IV | Issuance of Amendment Nos. 160 and 160, Revise Technical Specification 3.8.1, AC Sources - Operating, for Extension of Two 14-Day Completion Times for Offsite Circuits | Approval |