Semantic search

Jump to navigation Jump to search
 Start dateSiteTitleDescription
IR 05000245/201600225 July 2016MillstoneMillstone Power Station - Integrated Inspection Report 05000336/2016002 and 05000423/2016002, 04/01/2016 - 06/30/2016
IR 05000261/201300331 July 2013RobinsonIR 05000261-13-003 on April 1, 2013 June 30, 2013, H.B. Robinson Steam Electric Plant, Unit 2, Maintenance Effectiveness
IR 05000261/201300430 October 2013RobinsonIR 05000261-13-004, on 07/01/2013 - 09/30/2013; H.B. Robinson Steam Electric Plant, Unit 2; Integrated Inspection
IR 05000261/201300531 January 2014RobinsonIR 05000261-13-005 and 05000261-13-502, on 10/01/2013 - 12/31/2013; H.B. Robinson Steam Electric Plant, Unit 2; Adverse Weather Protection, Refueling and Outage Activities, and Radiological Hazard Assessment and Exposure.
IR 05000261/201400229 April 2014RobinsonIR 05000261-14-002, Duke Energy Progress, Inc.: 1/01/2014-3/31/2014; H.B. Robinson Steam Electric Plant, Unit 2; Fire Protection, Inservice Inspection Activities, Maintenance Effectiveness, Operability Determinations
IR 05000261/201400321 July 2014RobinsonIR 05000261-14-003, 4/01/2014 - 6/30/2014; H.B. Robinson Steam Electric Plant, Unit 2; Follow-up of Events and Notices of Enforcement Discretion
IR 05000261/201400428 October 2014RobinsonIR 05000261/2014004, on July 1, 2014 Through September 30, 2014; H. B. Robinson Steam Electric Plant, Unit 2; Integrated Inspection Report
IR 05000261/201400717 December 2014RobinsonIR 05000261/2014007, October 20-24, 2014 and November 3-7, 2014 H.B. Robinson, Unit 2, Triennial Fire Protection
IR 05000261/201400810 June 2014RobinsonIR 05000261-14-008; on 04/21/2014 - 05/05-08/2014; H.B. Robinson Steam Electric Plant, Unit 2; Biennial Inspection of the Problem Identification and Resolution Program
IR 05000317/201700820 September 2017Calvert CliffsProblem Identification and Resolution Inspection Report 05000317/2017008 and 05000318/2017008
IR 05000324/20060073 August 2006BrunswickIR 05000324-06-007 on 06/05/2006 - 07/05/2006 for Brunswick, Unit 2; Supplemental Inspection IP 95001 for a White Performance Indicator in the Initiating Events Cornerstone
IR 05000324/201000228 April 2010BrunswickIR 05000325-10-002 and 05000324-10-002; on 01/01/2010 - 03/31/2010; Brunswick Steam Electric Plant, Units 1 & 2; Refueling and Other Outage Activities, and Radioactive Gaseous and Liquid Effluent Treatment
IR 05000324/201200226 April 2012BrunswickIR 05000325-12-002, 05000324-12-002, 05000325-12-501, 05000324-12-501, on 01/01/12 -03/31/12, Brunswick Steam Electric Plant, Units 1 & 2, Follow-up of Events
IR 05000324/201300230 April 2013BrunswickIR 05000325-13-002, 05000324-13-002; 01/01/13 - 03/31/13; Brunswick Steam Electric Plant, Units 1 & 2; Plant Modifications
IR 05000336/201600225 July 2016MillstoneIntegrated Inspection Report 05000336/2016002 and 05000423/2016002, 04/01/2016 - 06/30/2016
IR 05000352/20160033 November 2016LimerickIntegrated Inspection Report 05000352-2016003 and 05000353-2016003 and Independent Spent Fuel Storage Installation (ISFSI) Report 07200065/2016001
IR 05000400/20130054 February 2014HarrisIR 05000400-13-005 and 05000400-13-502, on October 1, 2013 - December 31, 2013; Shearon Harris Nuclear Power Plant, Unit 1; Plant Modifications and Identification and Resolution of Problems
IR 05000400/201301010 July 2013HarrisIR 05000400-13-010; 5/22/2013 - 6/11/2013; Shearon Harris Nuclear Power Plant, Unit 1; Special Inspection
IR 05000440/200401623 December 2004PerryIR 05000440-04-016 on 10/04/2004 - 11/19/2004 for Perry Nuclear Power Plant; Other Activities
ML14070A25113 March 2014FarleyProject Manager Assignment
ML14071A16924 March 2014SummerRequest for Additional Information
ML14073A05328 March 2014FarleyRequest for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805
ML14098A47516 April 2014FarleyUnit 1 - Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident
ML14101A11916 April 2014FarleyStaff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident
ML14107A33230 April 2014SummerAlternative Request Weld Repair for Reactor Vessel Upper Head Penetrations
ML14107A36123 April 2014SummerAcceptance Review Concerning Amendment Request for Approval of Revision to the Radiation Emergency Plan (TAC No. MF3830)(RC-14-0039)
ML14108A00418 April 2014FarleyApril 23, 2014, Category 1 Public Meeting, J.M. Farley Presentation Slides, Residual Heat Removal Autoclosure Interlock Deletion
ML14108A00523 April 2014FarleyApril 23, 2014, Public Meeting Presentation Slides, Southern Nuclear Company, SNC Degraded Grid Design Criteria.
ML14108A3768 May 2014FarleySummary of Meeting with Southern Nuclear Operating Company to Discuss Deletion of the Residual Heat Removal Autoclosure Interlock
ML14120A22523 April 2014FarleyApril 23, 2014, Category 1 Public Meeting, J.M. Farley Presentation Slides, Residual Heat Removal Autoclosure Interlock Deletion.
ML14122A0378 May 2014Hatch
Farley
April 23, 2014 Summary of Meeting with Southern Nuclear Operating Company to Discuss Grid Design Criteria
ML14122A30929 May 2014SummerIssuance of Amendment 198 Regarding the Cyber Security Plan Implementation Schedule Milestone 8
ML14126A18814 May 2014SummerAcceptance Review Concerning Amendment Request to Revise Emergency Action Levels to a Scheme Based on NEI 99-01, Revision 6 (TAC No. MF3927)(RC-14-0032)
ML14128A0833 June 2014FarleyStaff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3
ML14128A33312 May 2014SummerAlternative Request Regarding Class 2 and 3 Pump Testing Requirements During the Fourth Ten-Year Inservice Inspection Interval
ML14134A03122 May 2014FarleySummary of May 16, 2014, Meeting with Southern Nuclear Operating Company to Discuss the Joseph M. Farley Flooding Hazard Reevaluation Extension Request
ML14135A17326 February 2014FarleyMay 16, 2014, J.M. Farley Category 1 Meeting Handout, Duration for Completion of the Flood Hazard Re-evaluation.
ML14148A2353 July 2014SurryIssuance of Amendment to Extend the Containment Type a and Type C Leak Rate Test Frequency
ML14154A0876 June 2014FarleyUnit 2, Acceptance Review Concerning Alternative to Inservice Inspection for Reactor Vessel Flange Leak-Off Lines (TAC Nos. MF4206 and MF4207)
ML14155A30215 August 2014FarleyIssuance of Amendment Regarding Minimum Condensate Storage Tank Level Technical Specifications
ML14157A02230 June 2014FarleyAcceptance Review License Amendment to Revise Reactor Trip System Instrumentation Technical Specifications
ML14169A19511 July 2014FarleyAlternative Request Regarding Containment Building Tendon Examination Schedule
ML14174B1292 July 2014Farley
05000384
Request for Additional Information
ML14175A5562 July 2014FarleyRequest for Withholding Information from Public Disclosure for Joseph M. Farley
ML14176A07011 July 2014FarleyRequest for Additional Information
ML14182A47311 July 2014SummerRequest for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805
ML14183B44114 July 2014FarleyTransmittal of Draft Safety Evaluation for Proposed Amendment Regarding Minimum Condensate Storage Tank Level Technical Specification
ML14189A02015 July 2014FarleyRequest for Additional Information
ML14189A39315 July 2014OconeeAcceptence of License Amendment Request ONS-2014-020
ML14195A35521 October 2014OconeeIssuance of Amendments