Semantic search

Jump to navigation Jump to search
 Issue dateFromTitleProject stage
ML20079P8704 May 1983WEC Energy Group
Burstein S
Application to Amend Licenses DPR-24 & DPR-27,consisting of Tech Spec Change Request 91 Re Limiting Conditions for Operation Requiring Both RHR Loops Be Operable Unless Reactor Sys Is in Refueling Shutdown ConditionRequest
ML20080J9906 February 1984Fay C
WEC Energy Group
Requests Repeal of 791130 & 800103 Confirmatory Orders Re Provisions for Operation Pertaining to Steam Generator Tubes.Steam Generator Lower Assemblies ReplacedOther
ML20081C1535 March 1984Fay C
WEC Energy Group
Advises That,Due to Delays in Delivery & Installation of Auxiliary Safety Instrumentation Panels (Asips),Installation of Six Accident Monitors Addressed in NUREG-0737,Items II.F.1.1 Through II.F.1.6 Will Not Be Completed by 840630Other
ML20092N65226 June 1984Fay C
WEC Energy Group
Advises That,Due to Delays in Final Fabrication & Delivery of Auxiliary Safety Instrumentation Panels,Per , Panels Will Be Delivered in Sequence Which Best Enables Installation to ProceedOther
ML20092P33429 June 1984WEC Energy Group
Britt R
Lists Measures Implemented to Minimize Schedule Delays of post-TMI NUREG-0737,Items II.F.1.1 - 6,per 840626 Request, Including Timely QA Insps of Panel Welding & Detailed pre- Installation Plans & Preparation ProceduresOther
ML20101M41028 December 1984Fay C
WEC Energy Group
Informs That Accident Monitors Addressed by NUREG-0737,Items II.F.1.3 - II.F.1.6 Installed on Panels in Control Room, Powered by Interim Safety Grade Power Supplies & Accepted for Use by Plant Operations as of 841228Other
ML20101M58326 December 1984Fay C
WEC Energy Group
Confirms Position That Application for Amend to License Concerning Request for Mod of Dates Contained in Commission 830712 Confirmatory Order Unnecessary,Because of Ruling That Confirmatory Order Conditions Not License ConditionsRequest