TSTF-505 Near Term Revised Draft - Change Tracking Copy for 09/12/2017 Teleconference
ML17258A126
Person / Time
Site: Technical Specifications Task Force
Issue date: 09/12/2017
From:
Technical Specifications Task Force
To:
Office of Nuclear Reactor Regulation
Honcharik M, 301-415-1774, DSS/STSB
Shared Package
ML17258A124 List:
References
Download: ML17258A126 (96)


Text

TECHNICAL SPECIFICATIONS TASK FORCE A JOINT OWNERS GROUP ACTIVIT Y TSTF3

-Aseveral -A inoperability of all trains of a TS required system-A these -A-A-Afollow the guidance in the attachments to this letter. Acti ons related to the inoperability of all trains of a TS required system should not be included in LARs submitted prior to approval of the companion traveler. and incorporating the other changes recommende d in the attachment s to this letter -A in LARs submitted prior to approval of the companion traveler. Attachment 1 also includes -A Attachment 2 contains a list of Actions revised by TSTF-505-A that have conditions on their inclus ion in a plant-specific LAR. Attachment 3 contains a revised Mode Applicatio n for requesting adoption of TSTF-505-A.-A-Afollow the recommendations in the attachments to this letter.

Mirella GavrilasJennifer WhitmanActing Chief of the Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests TSTF-505 Markup to Action 3.3.2.A Reactor Protection System (RPS) Manual Reactor Trip Do not include. Action 3.4.10.A Pressurizer Safety Valves Do not include. Action 3.4.14.C RCS Pressure Isolation Valve (PIV) Leakage Do not include. Action 3.5.1.B CFTs Do not include Action 3.5.3.B ECCS - Shutdown Do not include. Action 3.5.4.B BWST Do not include Action 3.6.3.B Containment Isolation Valves Do not include Action 3.6.3.D Containment Isolation Valves Do not include Action 3.7.4.B AVVs Do not include. Action 3.7.6.A CST Do not include.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests TSTF-505 Markup to Action 3.8.1.E AC Sources - Operating Do not include Action 3.8.4.A.1 DC Sources - Operating Do not include. Required Action outside the scope of TSTF-505.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.3.1.S RTS Instrumentation Do not include Action 3.3.1.V RTS Instrumentation Do not include Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.3.2.V ESFAS Instrumentation Do not include. Required Action outside the scope of TSTF-505. Action 3.4.10.A Pressurizer Safety Valves Do not include. Action 3.4.11.E Pressurizer Power Operated Relief Valves (PORVs) Do not include. Action 3.4.11.F Pressurizer Power Operated Relief Valves (PORVs) Do not include. Action 3.4.14.C RCS Pressure Isolation Valve (PIV) Leakage Do not include. Action 3.5.1.B Accumulators Do not include. Action 3.5.3.B ECCS - Shutdown Do not include. Action 3.5.4.B RWST Do not include. Action 3.5.6.A Boron Injection Tank Do not include. Action 3.6.3.B Containment Isolation Valves Do not include. Action 3.6.3.C Containment Isolation Valves Do not include. Action 3.6.3.D Containment Isolation Valves Do not include. Action 3.6.3.E Containment Isolation Valves Do not include.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.6.9.B Hydrogen Mixing System Do not include. Action 3.6.15.A Ice Bed Do not include. Action 3.6.17.A Divider Barrier Integrity (Ice Condenser) Do not include. Action 3.6.17.B Divider Barrier Integrity (Ice Condenser) Do not include. Action 3.7.6.A Condensate Storage Tank Do not include. Action 3.8.1.E AC Sources - Operating Do not include Action 3.8.4.A.1 DC Sources - Operating Do not include. Required Action outside the scope of TSTF-505.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.3.6.A ESFAS Logic and Manual Trip (Digital) Do not include. Action 3.4.10.A Pressurizer Safety Valves Do not include. Action 3.4.11.E Pressurizer Power Operated Relief Valves (PORVs) Do not include. Action 3.4.11.F Pressurizer Power Operated Relief Valves (PORVs) Do not include. Action 3.4.14.C RCS Pressure Isolation Valve (PIV) Leakage Do not include. Action 3.5.1.B SITs Do not include. Action 3.5.3.A ECCS - Shutdown Do not include. Action 3.5.4.B RWT Do not include. Action 3.6.3.C Containment Isolation Valves Do not include. Action 3.6.3.E Containment Isolation Valves Do not include. Action 3.6.3.F Containment Isolation Valves Do not include. Action 3.6.9.B Hydrogen Mixing System Do not include.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.7.4.B Atmospheric Dump Valves Do not include. Action 3.7.6.A Condensate Storage Tank Do not include. Action 3.8.1.E AC Sources - Operating Do not include. Action 3.8.4.A.1 DC Sources - Operating Do not include. Required Action outside the scope of TSTF-505.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.1.7.C SLC System Do not include. Action 3.3.1.1.C Reactor Protection System (RPS) Instrumentation Do not include. Action 3.3.4.1.B End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation Do not include. Action 3.3.4.2.B Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT)

InstrumentationDo not include. Action 3.3.4.2.C Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT) Do not include. Action 3.3.5.2.C Reactor Core Isolation Cooling (RCIC) System Instrumentation Do not include. Action 3.3.6.1.B Primary Containment Isolation Instrumentation Do not include. Action 3.3.6.3.C LLS Instrumentation Do not include. Action 3.6.1.3.B PCIVs Do not include. Required Action outside the scope of TSTF-505. Action 3.6.1.3.C PCIVs Do not include. Required Action outside the scope of TSTF-505. Action 3.6.2.3.B Residual Heat Removal (RHR) Suppression Pool Cooling Do not include. Action 3.6.2.4.B Residual Heat Removal (RHR) Suppression Pool Spray Do not include. Action 3.6.3.3.B Containment Atmosphere Dilution (CAD) System Do not include. Action 3.7.1.D Residual Heat Removal Service Water (RHRSW) System Do not include. Action 3.8.1.E AC Sources - Operating Do not include Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.8.4.A.1 DC Sources - Operating Do not include. Required Action outside the scope of TSTF-505.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.1.7.C SLC System Do not include. Action 3.3.1.1.C Reactor Protection System (RPS) Instrumentation Do not include. Action 3.3.4.1.B End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation Do not include. Action 3.3.4.2.B Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT)

InstrumentationDo not include. Action 3.3.4.2.C Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT)

InstrumentationDo not include. Action 3.3.5.2.C Reactor Core Isolation Cooling (RCIC) System Instrumentation Do not include. Action 3.3.6.1.B Primary Containment Isolation Instrumentation Do not include. Action 3.3.6.4.B Suppression Pool Makeup (SPMU) System Instrumentation Do not include. Action 3.3.6.4.C Suppression Pool Makeup (SPMU) System Instrumentation Do not include. Action 3.6.1.3.B Primary Containment Isolation Valves (PCIVs) Do not include. Action 3.6.1.3.C Primary Containment Isolation Valves (PCIVs) Do not include. Action 3.6.1.3.D Primary Containment Isolation Valves (PCIVs) Do not include. Action 3.6.1.7.B Residual Heat Removal (RHR) Containment Spray System Do not include. Action 3.6.2.3.B Residual Heat Removal (RHR) Suppression Pool Cooling Do not include.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests Action 3.6.2.4.A SPMU System Do not include. Action 3.6.2.4.B SPMU System Do not include. Action 3.6.3.1.B Drywell Cooling System Fans Do not include. Action 3.6.3.2.B Drywell Purge System Do not include. Action 3.6.5.1.A Drywell Do not include. Action 3.6.5.3.B Drywell Isolation Valve[s] Do not include. Action 3.6.5.6.D Drywell Vacuum Relief System Do not include. Action 3.6.5.6.E Drywell Vacuum Relief System Do not include. Action 3.8.1.E AC Sources - Operating Do not include Action 3.8.4.A.1 DC Sources - Operating Do not include. Required Action outside the scope of TSTF-505.

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific Amendment Requests change to the , as defined in NEI 06-09-A, Appendix A,

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific Amendment Requests

Recommended Variations from TSTF-505-A in Near-Term Plant-Specific Amendment Requests Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperable See Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS

or both

or modify the Action to

not apply a RICT when

all required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperable3.6.2.C LCO: [Two] containment air lock[s] shall be OPERABLE.

Condition:

One or more containment air locks inope rable for reasons other than an inoperable door or inoperable interlock

mechanism.

Licensee must justify that an inoperable containment air lock is not a condition in

which all required

trains or subsystems of

a TS required system

are inoperable. An

acceptable argument

may be that a note in

TS 3.6.2 requires the

condition to be

assessed in accordance

with TS 3.6.1, Containment Integrity, and any loss of function

would require an

immediate plant

shutdown under that

TS.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS

two ormore Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1430, Babcock and Wilcox STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS

The justification can

include that the Actions

require periodic

monitoring of spacial

power distribution and imposition of compensatory limits

and reduced power.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS The licensee must include information regarding how the

TSTF-411 conditions and limitations will be implemented (or similar conditions if

TSTF-411 has not been adopted), including

discussion of ATWS

Mitigation System Actuation (AMSAC),

and why those actions

are sufficient, including

a discussion of defense

in depth.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS or more

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS 3.6.2.C LCO: [Two] containment air lock[s] shall be OPERABLE.

Condition:

One or more containment air locks inope rable for reasons other than an inoperable door or inoperable interlock

mechanism.

Licensee must justify that an inoperable containment air lock is not a condition in

which all required

trains or subsystems of

a TS required system

are inoperable. An

acceptable argument

may be that a note in

TS 3.6.2 requires the

condition to be

assessed in accordance

with TS 3.6.1, Containment Integrity, and any loss of function

would require an

immediate plant

shutdown under that

TS.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS

or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS or more ormore

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1431, Westinghouse STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS more than two

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS or more

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS 3.6.2.C LCO: [Two] containment air lock[s] shall be OPERABLE.

Condition:

One or more containment air locks inope rable for reasons other than an inoperable door or inoperable interlock

mechanism.

Licensee must justify that an inoperable containment air lock is not a condition in

which all required

trains or subsystems of

a TS required system

are inoperable. An

acceptable argument

may be that a note in

TS 3.6.2 requires the

condition to be

assessed in accordance

with TS 3.6.1, Containment Integrity, and any loss of function

would require an

immediate plant

shutdown under that

TS.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS

two ormore Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1432, Combustion Engineering STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperableSee Note 1 at the end of

.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS or more Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS

or more

or modify the Action to

not apply a RICT when

all required trains or

subsystems are

inoperableSee Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS 3.6.1.2.C LCO: The primary containment air lock shall be OPERABLE.

Condition:

Primary containment air lock inoperable for reasons other than Condition A

or B. Licensee must justify that an inoperable

containment air lock is

not a condition in

which all required

trains or subsystems of

a TS required system

are inoperable. An

acceptable argument

may be that a note in

TS 3.6.1.2 requires the

condition to be

assessed in accordance

with TS 3.6.1.1, Primary Containment, and any loss of function

would require an

immediate plant

shutdown under that

TS.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS

oneor more

two or more lines

or modify the Action to not apply a RICT when all

required trains or

subsystems are

inoperable See Note 1 at the end of

.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1433, BWR/4 STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS or more

or modify the Action to not apply a RICT when all

required trains or

subsystems are inoperableSee Note 1 at the end of

.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS or more

or modify the Action to

not apply a RICT when

all required trains or

subsystems are

inoperableSee Note 1 at the end of

.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS or more Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS

or more

or modify the Action to not apply a RICT when

all required trains or

subsystems are

inoperable See Note 1 at the end of .

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS 3.6.1.2.C LCO: The primary containment air lock shall be OPERABLE.

Condition:

Primary containment air lock inoperable for reasons other than Condition A

or B. Licensee must justify that an inoperable

containment air lock is

not a condition in

which all required

trains or subsystems of

a TS required system

are inoperable. An

acceptable argument

may be that a note in

TS 3.6.1.2 requires the

condition to be

assessed in accordance

with TS 3.6.1.1, Primary Containment, and any loss of function would require an immediate plant

shutdown under that

TS.

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests NUREG-1434, BWR/6 STS

Conditional Variations from TSTF-505-A in Near-Term Plant-Specific License Amendment Requests

Note 1 Some Conditions are applicable when an unspecified number of subsystems or instrument channels are inoperable, typically written as "One or more-" or "Two or more-". These conditions currently apply when all subsystems or channels required to be operable to perform a function are inoperable, and application of a RICT in this situation is prohibited in the near-term TSTF-505 submittals.

To address this, it is recommended that the follo wing modification to TSTF-505 be made to the Required Actions indicated in the Attachment 2 t ables for Completion Time s potentially applicable when all required subsystems or channels are inoperable.

The typical Completion Time is m odified by TSTF-505 to state: 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (i.e., the existing Completion Time)

OR In accordance with the Risk Informed

Completion Time

Program It is recommended that the second Completion Time be modified with a Note, as shown below: 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (i.e., the existing Completion Time)

OR -------------NOT E------------- Not applicable when [all/four/both] required channels are inoperable.



In accordance with the Risk Informed

Completion Time

Program The bracketed number of channels will depend on the specification. This approach retains the existing requirements and limits the use of a RICT to conditions in which the function can still be performed. The licensee must justify that the required functio n can still be performed absent an additional failure when a RICT is applied.

Alternatively, the licensee may m odify the Condition to only apply wh en at least one subsystem or channel is operable, but this approach may require creating a new Condition or modifying an existing condition to retain the current requirements, or a ccepting a more restrictive requirement (such a LCO 3.0.3 entry).

REFERENCE:

Letter from the TSTF to U.S. NRC, "Response to NRC Questions on TSTF-505, 'Provide Risk-Informed Extended Completion Times'," dated

DATE

Code of Federal Regulations

, as modified by the [DATE] letter from the TSTF to the NRC (Reference).

March 15, 2012 7715399)**

-ANEI -A

, as modified by the TSTF's [DATE] letter to the NRC, "Response to NRC Questions on TSTF-505, 'Provide Risk-Informed Extended Completion Times'."

, as well as the TSTF's [DATE] letter on TSTF-505

, , as modified by the TSTF letter on TSTF-505

-A

, except as described in the TSTF letter dated [DATE]

TS conditions with insufficient TS operable equipment to meet the specified safety function of the system, ar e not to be included in the application.

List each TS Required Action to which the RICT Program may be applied and, for each Required Action, describe the following:

  • The TS Required Action;
  • The corresponding SSC;
  • Each design basis function of the SSC;
  • How each design basis function is modeled in the PRA. If one of the design basis functions of an SSC or the SSC is not modeled in the PRA, describe any proposed surrogates and why the proposed surrogate adequately captures the configuration risk; and
  • The success criteria used in the PRA model compared to the licensing basis criteria. The success criteria should include both train-level and component/parameter level.

Note that the above description should be at the level of the TS condition/TS Required Action (not at the LCO level only). If the TS condition

/ TS Required action covers multiple SSCs or multiple design basis functions, such as in the case ESFAS Instrumentation or Containment Sprays, describe each one individually.

The enclosure should also include clear definit ions of any used terms, such as "train," "division," "loop," "subsystem," etc.

The enclosure should provide a detailed system description of TS 3.8, "Electrical Power Systems," Required Actions if the loading scheme is not uniform (e.g., Train A and B have similar loading, except Train B supplies power to additi onal SSCs.) Also, provide a description in Enclosure 12 of representative RMAs for non-uniform trains to demonstrate that the system's safety function is ma intained with either train or subsystem operable.

Licensees are strongly encouraged to apply the guidance in Appendix X, "Close out of Facts and Observations," of NEI 05-04, "Process for Performing Internal Events PRA Peer Reviews Using the ASME/ANS PRA Standard, Rev 3, November 2009," NEI 07-12, "Fire Probabilistic Risk Assessment Peer Review Process Guidelines, Rev 1, June 2010," and NEI 12-13, "External Hazards PRA Peer Review Process Guidelines, Rev 0, August 2012," to close PRA peer review findings , as this will make more efficient use of the NRC and industry resources needed to develop and review of the application.

External hazards screened out from incl usion in RICT calculations should be clearly identified as such, and should be done in a manner consistent with Part 6 of the ASME ANS PRA Standard. The justification should address baseline and configuration-specific considerations.

For external hazards that are not screened out from inclusion in RICT calculations, the licensee may propos e a bounding approach to address the hazard. If the bounding approach involves assuming a uniform increase in

baseline risk to address the hazard, t he licensee will need to address potential RICT-specific impacts by doing one of the following:

  • Demonstrate in the LAR that this approach is bounding for all TS actions included in the LAR, or
  • Establish a procedure to evaluate the validity of the bounding approach when calculating an RICT that is not de monstrated to be bounded in the LAR, or
  • For RICTs not demonstrated to be bounded in the LAR, establish a procedure to qualitatively evaluate the impact of the specific external hazard for each RICT when calculated and apply risk m anagement actions as appropriate.
  • Provide example RMAs for TS 3.8 Required Actions. These should be representative examples, such as a long and short RICTs.

See the Plant Vogtle April 14, 2017 RAI response (ADAMS Accession No. ML17108A253) for an example.

If the TS-required electrical power loading scheme is not uniform (e.g., Train A and B have similar loading, except Train B supplies power to additional SSCs,) provide a description of representative RMAs for non-uniform trains to ensure that the system's safety function is maintained with either train or subsystem inoperable.