1CAN011004, Summary of Analysis Related to ANO-1 Once-Through Steam Generator Tube Thermal Loads Due to Breaks in RCS Upper Hot Leg Large-Bore Piping

From kanterella
Revision as of 13:07, 9 February 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Summary of Analysis Related to ANO-1 Once-Through Steam Generator Tube Thermal Loads Due to Breaks in RCS Upper Hot Leg Large-Bore Piping
ML100280146
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 01/26/2010
From: David Bice
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
1CAN011004, TAC MD7178
Download: ML100280146 (3)


Text

1CAN011004

January 26, 2010

U.S. Nuclear Regulatory Commission

Attn: Document Control Desk

Washington, DC 20555

SUBJECT:

Summary of Analysis Related to ANO-1 Once-Through Steam Generator Tube Thermal Loads due to Breaks in RCS Upper Hot Leg Large-Bore Piping

Arkansas Nuclear One, Unit 1

Docket No. 50-313

License No.

DPR-51

REFERENCES:

1. Entergy letter to the NRC, dated October 26, 2009, "Supplemental to Response to Request for Information Regarding Steam Generator Tube

Integrity During Break in Upper Hot Leg Piping" (1CAN100903)

2. NRC letter to ANO, dated November 4, 2009, "Arkansas Nuclear One, Unit No. 1 - Once-Through Steam Generator Tube Loads Under

Conditions Resulting from Postulated Breaks in Reactor Coolant System

Upper Hot Leg Large-Bore Piping"" (TAC No. MD 7178)

Dear Sir or Madam:

In Reference 1, Entergy Operations, Inc. (Entergy) committed to verify that the Arkansas

Nuclear One, Unit 1 (ANO-1) Steam Generators are designed to withstand the thermal loading

associated with the worst-case large break Loss of Coolant Accident (LBLOCA), specifically a

LBLOCA in the upper hot leg (candy-cane) piping, and that tube integrity will be maintained for

this LBLOCA as verified through implementation of Technical Specification (TS) 5.5.9, Steam

Generator (SG) Program. Entergy further committed to notify the NRC of the acceptability of

the ANO-1 SGs with regard to the aforementioned LBLOCA within 30 days following the

completion of the verification.

In Reference 2, the NRC acknowledged the above commitment. In addition, the NRC

presented its expectation that the ANO-1 Safety Analysis Report (SAR) would be updated as

necessary to reflect the ANO-1 SG design and management of SG tube integrity for LBLOCA loads. The SAR update would include removal of any reference to the Pressurized Water

Reactor Owners Group (PWROG) Topical Report BAW-2374, Revision 2, "Risk-Informed

Assessment of Once-Through Steam Generator Tube Thermal Loads Due to Breaks in Reactor

Coolant System Upper Hot Leg Large-Bore Piping," because this Topical Report has not been

endorsed or approved by the NRC.

Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802

Tel 479-858-5338 David Bice A cting Manager, Licensing A rkansas Nuclear One

1CAN011004 Page 2 of 3

Following completion of the aforementioned verification of SG tube integrity considering the

RCS upper hot leg LBLOCA, Entergy implemented necessary changes to the ANO-1 SAR. No

references to Topical Report BAW-2374 were noted. The Alternate Source Term (AST) for

ANO-1 approved by the NRC by letter dated October 29, 2009 (1CNA100901) was

implemented at the site in conjunction with the SAR update following the aforementioned

verification. The updated SAR is currently scheduled for submittal to the NRC by October 2010

in accordance with 10 CFR 50.71.

The verification of SG tube integrity with regard to the upper hot leg LBLOCA was completed by

AREVA on January 8, 2010 (AREVA-10-00083). The results are summarized in AREVA Report

51-9125139-001 "Summary Report for Qualification of EOTSG for LBLOCA Loading." This

analysis parametrically evaluated the tube-to-tubesheet weld of the SGs for the tube axial load

resulting from LBLOCA long-term differentia l thermal expansion between the tube and the SG shell (determined to be the only area of significant concern). AREVA concluded that tube

integrity is maintained with regard to the structural integrity for the tube axial load resulting from

LBLOCA long-term differential thermal expansion. The report additionally verified that the

current 40% through-wall (TW) plugging limit for SG tubes at ANO-1 as designated in TS 5.5.9

remains conservative to ensure tube integrity is maintained. AREVA Report 51-9125139-001

will be referenced in the ANO-1 Steam Generat or Inspection Program document as a bases document for the plugging limit. Based on these results, no TS changes will be required for

ANO-1.

The AREVA report is proprietary in nature, but can be reviewed by the NRC at the AREVA

office or at ANO. The report is not proposed to be docketed at this time.

The verification performed by AREVA is based on t he TS 5.5.9 SG program which implements inspection requirements that ensure SG tube integrity is assessed on a routine basis and that

degrading tubes are removed from service prior to exceeding the 40% TW limit. The program requires projected flaw growth to be determined to provide high confidence that a degraded

tube will not exceed the TS TW limit prior to the next scheduled unit shutdown.

Based on the above information, Entergy considers the Reference 1 licensee commitment to be

closed.

This letter contains no new commitments.

If you have any questions or require additional information, please contact David Bice at

479-858-5338.

Sincerely,

DBB/dbb

1CAN011004 Page 3 of 3

cc: Mr. Elmo E. Collins Regional Administrator U. S. Nuclear Regulatory Commission Region IV 612 E. Lamar Blvd., Suite 400 Arlington, TX 76011-4125

NRC Senior Resident Inspector Arkansas Nuclear One P. O. Box 310

London, AR 72847

U. S. Nuclear Regulatory Commission

Attn: Mr. Alan B. Wang

MS O-7 D1

One White Flint North

11555 Rockville Pike

Rockville, MD 20852

U. S. Nuclear Regulatory Commission

Attn: Mr. Kaly Kalyanam

MS O-8 B1

One White Flint North

11555 Rockville Pike

Rockville, MD 20852

Mr. Bernard R. Bevill

Arkansas Department of Health

Radiation Control Section

4815 West Markham Street Slot #30 Little Rock, AR 72205