| Q | CCA | Title |
---|
05000293/FIN-2009002-01 | 2009Q1 | | Failure to Establish and Maintain Adequate Design Measures to Monitor Critical Parameters of the EDG Air Start System |
05000293/FIN-2009002-02 | 2009Q1 | H.2 | Failure to Implement Scaffolding Procedure Requirement |
05000293/FIN-2009003-01 | 2009Q2 | H.12 | Failure to Follow Procedure Resulting in Damage to Refueling Mast |
05000293/FIN-2009004-03 | 2009Q3 | | Failure of the A Standby Liquid Control Train |
05000293/FIN-2009004-01 | 2009Q3 | | Failure to Include Security Diesel Generator into the Maintenance Rule Scoping Document |
05000293/FIN-2009004-02 | 2009Q3 | H.7 | Inadequate Procedures Result in the Failure to Evaluate Operability of the B RBCCW/SSW Heat Exchanger |
05000293/FIN-2009004-04 | 2009Q3 | H.11 H.12 | Human Error Resulting in Unplanned High Pressure Coolant Injection (HPCI) Isolation |
05000293/FIN-2009005-01 | 2009Q4 | | Incomplete licensed operator medical examinations |
05000293/FIN-2009007-01 | 2009Q4 | | Failure to establish adequate procedures to prevent adverse impact due to spurious valve closure casued by fire damage |
05000293/FIN-2009005-03 | 2009Q4 | H.7 | Inadequate Surveillance Procedure Resulting in Failed Standby Liquid Control Train |
05000293/FIN-2009005-02 | 2009Q4 | | Procedure change to allow disabling HPCI during transients |
05000293/FIN-2009403-01 | 2009Q4 | H.5 | Security |
05000293/FIN-2009403-02 | 2009Q4 | P.2 | Security |