MONTHYEARIR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection LR-N24-0048, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal IR 05000272/20244032024-03-20020 March 2024 and Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) 2024-09-04
[Table view] |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 0 PSEG Nuclear LLC 10CFR50.46 LR-N07-0261 September 28, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 HOPE CREEK GENERATING STATION FACILITY OPERATING LICENSE NO. NPF-57 DOCKET NO. 50-354
Subject:
10CFR50.46 REPORT Pursuant to the requirements of 1OCFR50.46, PSEG Nuclear LLC (PSEG) hereby reports changes in the application of the Emergency Core Cooling System (ECCS)evaluation models for the Hope Creek Generating Station. 10 CFR 50.46(a)(3)(ii) requires licensees to report at least annually each change to or error discovered in evaluation models used for calculating ECCS performance and the estimated effect on the limiting ECCS analysis.
For significant changes or errors, licensees are required to submit a 30 day report and include a proposed schedule for providing a reanalysis or taking other action necessary to show compliance with 10 CFR 50.46 requirements.
This report satisfies the annual reporting requirement.
For the current operating cycle, the Hope Creek core contains a mixture of Westinghouse SVEA-96+ and GE14 fuel.If you have any questions regarding this submittal, please contact Mr. Francis D.Possessky at (856) 339-1160.Sincerely, Michael aftn a As ur nce Manager- Hope Creek Attachments (2) .2 P -(95-2168 REV. 7/99 LR-N07-0261 Page 2 C Mr. S. Collins, Administrator
-Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 U. S. Nuclear Regulatory Commission Mr. R. Ennis, Project Manager -Hope Creek Mail Stop 08B1 Washington, DC 20555-0001 USNRC Senior Resident Inspector
-Hope Creek (X24)Mr. P. Mulligan, Manager IV (Acting)Bureau of Nuclear Engineering PO Box 415 Trenton, New Jersey 08625 Attachment 1 (Pages -1)10 CFR 50.46 Report LR-N07-0261 Attachment 1 Hope Creek Generating Station 10 CFR 50.46 Report Peak Cladding Temperature Rack-up Sheets PLANT NAME: ECCS EVALUATION MODEL: REPORT REVISION DATE: CURRENT OPERATING CYCLE: Hope Creek Generating Station SAFER/GESTR-LOCA 9/6/2007 14 ANALYSIS OF RECORD Evaluation Model: The GESTR-LOCA and SAFER Models for the Evaluation of the Loss-of-Coolant Accident, Volume Ill, SAFER/GESTR Application Methodology, NEDE-23785-1-PA, General Electric Company, Revision 1, October 1984."SAFE R/G ESTR-LOCA Loss-of-Coolant Accident Analysis for Hope Creek generating Station," NEDC-33153P, Revision 1, GE Nuclear Energy, September 2004.Calculations:
Fuel: SVEA-96+ and GE14 Limiting Fuel Type: SVEA-96+Limiting Single Failure: Battery Limiting Break Size and Location:
1.0 Double-Ended Guillotine Suction Pipe in a Recirculation Fuel Type: SVEA-96+ GE14 Reference PCT 1540 OF 1370 OF MARGIN ALLOCATION A. PRIOR LOCA MODEL ASSESSMENTS 10 CFR 50.46 Report Dated June 1, 2004 (See note 1) APCT = 0°F APCT = 0°F 10 CFR 50.46 Report Dated September 29, 2006 (See APCT = 0°F APCT = 0°F note 2)Net PCT 1540 OF 1370 OF B. CURRENT LOCA MODEL ASSESSMENTS None APCT = 0°F APCT = 0°F Total PCT change from current assessments ZAPCT = 0°F ZAPCT = 0°F Cumulative PCT change from current assessments Y Z APCT I = 0 0 F Y IAPCT I = 0°F Net PCT 1540 OF 1370 OF Attachment 2 (Pages -1)10 CFR 50.46 Report Assessment Notes LR-N07-0261 Attachment 2 Hope Creek Generating Station 10 CFR 50.46 Report Assessment Notes 1. Prior LOCA Model Assessment A 10 CFR 50.46 report for Hope Creek was submitted in June 1, 2004.Subsequent to this report and with the startup of cycle 13 in November 2004, Hope Creek discharged all GE9B fuel and implemented GE14 fuel. The Referenced LOCA analysis was implemented as analysis of record for GEI4 fuel and SVEA-96+ fuel.[
Reference:
"SAFER/GESTR-LOCA Loss-of-Coolant Accident Analysis for Hope Creek generating Station," NEDC-33153P, Revision 1, GE Nuclear Energy, September 2004.]2. Prior LOCA Model Assessment In the referenced letter to the NRC, the impact of a GE postulated new heat source applicable to the LOCA event was reported.
This heat source is due to recombination of hydrogen and excess oxygen drawn into the vessel from containment during core heatup. The PCT impact for all fuel types was 0 0 F. The referenced letter also reported the impact of the top peak axial power shape on the small break LOCA. The impact of the top peak axial power shape on the licensing basis PCT was zero degree for both GE 14 fuel and SVEA-96+ fuel for Hope Creek.[
Reference:
Letter (LR-N06-0401) from Michael Jesse (PSEG) to U.S. NRC, "10 CFR 50.46 Report."]