ML17340A854

From kanterella
Revision as of 11:17, 18 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Responds to NRC 810130 Ltr Re Violations Noted in IE Insp Repts 50-250/80-36 & 50-251/80-34.Corrective Actions:Pipe Support Returned to Original Configuration & Insulation Reinstalled.No Proprietary Info
ML17340A854
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 02/24/1981
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML17340A853 List:
References
L-81-63, NUDOCS 8103190294
Download: ML17340A854 (10)


See also: IR 05000250/1980036

Text

il~~l,p-.3,-~~.;.

.~';, fl,-.FLORIDA POWER 4 LIGHT COMPANY f.f:q gj'ebruary

24, 1981 L-81-63 Mr.James P.O'Reilly, Director, Region II Office of Inspection

and Enforcement

U.S.Nuclear Regulatory

Commission

101 Marietta Street, Sutie 3100 Atlanta, Georgia 30303 Dear Mr.O'Reilly:

Re: Turkey Point Units 3&4 Docket Nos.50-250, 50-251 Ins ection Re ort Nos.80-36 and 80-34 Florida Power&Light Company has reviewed the subject inspection

reports and a response is attached.There is no proprietary

information

in the report.Very truly yours, ViCe President" Advanced Systems'and

Technology" REU/PLP/ras

Attachment

cc: Harold F.Reis, Esquire PEOPLE..SERVING PEOPLE

ATTACHMENT

RE: Turkey Point Units 3 6 4 Docket Nos.50-250, 50-251 Ins ection Re ort Nos.80-36 and 80-34~F1nddn: Technical.

Specification

6.8.1 requires implementation

of written procedures

and administrative

policies that meet or exceed the requirements

and recommendations

of Section 5.1 and 5.3 of ANSI 18.7-1972 and USNRC Regulatory

Guide 1.33.Procedure 0103.11 requires that following maintenance, safety related systems are restored to their normal condition.

Contrary to the above, during facility tours of Units 3 and 4 this inspection

period, it was noted that maintenance

supervisors

failed to implement existing procedures

to ensure complete restoration

of safety related systems to normal operating condition following maintenance

in that: The Mechanical

Supervisor

on shift during the completion

of maintenance

on Unit 4 blender station failed to have the pipe support between manual isolation valve 4363 and flow control valve 4114A made up and the wooden wedges providing temporary support removed at conclusion

of maintenance

activity.The Mechanical

Supervisor

on shift during the completion

of maintenance

on the Unit 3 Boron Injection Tank failed to have the insulation

over the manway cover~properly replaced at the conclusion

of the maintenance

activity.4~*, 3'.Electrical

Supervisors

allowed the spray t'ight covers for all heat tracing'hermostats.,to

be left,off as a'routine practice instead of properly positioned

.at'the conclusion

of.maintenance

activities.

I\~Res ense:', (1-1)FPL'oncurs

with the'finding.

(1-2)This particular

pipe support was either-inadvertently

omitted due to lack of follow-up or was still in the process of being repaired at the time this finding was noticed.This was found during the hanger and pipe support inspections

and repairs pursuant to I and E Bulletin 79-79-02 which were in progress when Unit 4 was in cold shutdown condition for its annual overhaul/refueling.

(1-3)As corrective

action, the pipe support in question was returned to its original configuration

in December 1980.(1-4)As corrective

action in order to avoid further problems, a procedure is being developed to control removal, reinstallation, and maintenance

of hangers and pipe supports by plant maintenance

forces in order to: a)Prevent recurrence

of the same type of problem., b)~Provide guidelines

for returning hangers and/or'ipe.supports to'their original configura'tion

after their remov'al for maintenance

s

c)Provide guidelines

on the specifications

for each type of bolt on each hangers (i.e., torqueing of bolts)2.(1-5), This procedure is now being formulated.

It is being actively pursued and it is scheduled to be reviewed and approved by April 27, 1981.Full compliance

will be achieved when't is approved.(2-1)FPL concurs with the finding..(2-2)(2-3)The insulation

on the Unit 3 Boron Injection Tank manway cover was not reinstalled

after maintenance

due to lack of follow-up.

As corrective

action, the insulation

on the manway cover in question was reinstalled

prior to January 1981.(2-4)As'corrective

action to avoid further problems, we are taking the following steps: A specific crew will be designated

to maintain each nuclear unit's primary systems.The supervisor

in charge of each crew will be responsible

for compliance

with applicable

plant procedures (including

AP 0103.11)and following up after'is crew completes each job.This responsibility

will.be implemented

by instructing

personnel and dessiminating

job descriptions.

One of the two crews assigned to primary systems will be responsible

for housekeeping.

(2-5)Full compliance

will be achieved no later than March 27, 1981.3.(3-1)FPL concurs, with the finding.(3-2)The practice in the finding developed gradually following several'instances'f

varying degrees of solidification

in boric acid systems~.requiring heat tracing.The Electrical

Maintenance

Department

initiated: weekly checks'f'=each'eat

'tracing'irc'uit

to.'verify.'proper

circ'uit

operation., Many minor.adjustments

and repairs were made as a result of these, checks., Most'of these adjustments

and repairs required access to the heat tracing thermostat

boxes.The practice of not replacing the covers evolved due to the awareness that the cover being reinstalled

would probably be removed again with a week.Also, this practice allowed the shift operators to make minor thermostat

adjustments.

to a circuit during times when Electrical

personnel were not available.

0 (3-3)In order to improve the reliability

and performance

of the heat tracing circuits, the originally

installed Chromalox type heat tracing circuits are being replaced with a much improved Chemelex type.The replacement

program is planned to continue until all heat tracing circuits are replaced.The new type of heat tracing has already proven to be more reliable and to require far less maintenance.

Consequently, for the new circuits there is no need to'leave the covers off.

r0

(3-4).Corrective

action that will be taken;a)Znstallation

of covers which are now available.-

b)The installation

of necessary replacement

covers which have been ordered.c)Meetings within the Electrical

Department

will be held to stress the importance

of the re-installation

of these qovers.d)Preventive

Maintenance

Program plant work orders will be revised to include a specific step calling for installation

of the covers following the work.(3-5)Full compliance

is scheduled to be completed by May 15, 1981.

)>a~STATE OF FLORIDA))COlB'TY OF DADE)ss~heing irst duly sworn, deposes and says: That he is Executive Vice President'f Florida Power a Light Company, the licensee herein;That he has executed.the foregoing document;that the state-ments made in this said document are true and correct to the best.of his knowledge, information, and bel'ef, and that he is authorized

to execute the document.on behalf of said, E.A.Adomat J Subscribed

and sworn'o h'efore me this ctay o+z-.&AA.~~'-A~

NOTARY?UBLXC, S"ate of Florida and for the County of Dade, thtsry Pub:"ic, Steno Of Rari".s"t Lrgo Mv CcemM"n Exirea Oclober 30.3KG3 My commission

exp'res:.".."-.".""'"rJ i','"vr."rd

30ndivg Agency