#REDIRECT [[IR 05000333/1988010]]
{{Adams
| number = ML20155A291
| issue date = 09/27/1988
| title = Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-333/88-10
| author name = Bellamy R
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
| addressee name = Converse R
| addressee affiliation = POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
| docket = 05000333
| license number =
| contact person =
| document report number = NUDOCS 8810050271
| title reference date = 08-31-1988
| document type = CORRESPONDENCE-LETTERS, NRC TO UTILITY, OUTGOING CORRESPONDENCE
| page count = 2
}}
See also: [[see also::IR 05000333/1988010]]
 
=Text=
{{#Wiki_filter:___
_ _ _ - _ _ .
t
e
.-
,,
SEP 2 7 gggy
&
Docket No. 50-333
Power Authority of the State of New York
James A. FitzPatrick Nuclear Power Plant
ATTN: Mr. Radford J. Converse
Resident Manager
P. O. Box 41
Lycoming, New York 13093
Gentlemen:
Subject:
Inspection No. 50-333/88-10
This refers to your letter dated August 31, 1988, in response to our letter
dated August 8, 1988.
Thank you for informing us of the corrective and preventive actions documented
in your letter.
These actions will be examined during a future inspection of
your licensed program.
Your cooperation with us is appreciated.
Sincerely,
Cridnot signed By:
Rcnald R. Scitamy
Ronald R. Bellamy, Chief
Facilities Radiological Safety
and Safeguards Branch
Division of Radiation Safety
and Safeguards
cc w/ encl:
J. Phillip Bayne, President
Mr. Jol.n C. Brons, Executive Vice President
A. Klause nn, Senior Vice President - Appraisal and Compliance Services
"
R. L. Patch, Quality Assurance Superintendent
George M. Wilverding, Manager Nuclear Safety Evaluation
Gerald C. Goldstein, Assistant General Counsel
ngg
R. E. Beedle, Vice President Nuclear Support
Non.
S. S. Zulla. Vice President Nuclear Engineering
go
R. Burns, Vice President Nuclear Operation
gh
Dept. of Public Service, State of New York
State of New York, Department of Law
4
Licensing Project Manager, NRR
No
Public Document Room (POR)
f "*
$@
Local Public Document Room (LPOR)
7f*
p
b3J
g
Nuclear Safety Information Center (NSIC)
C h.
J
- ce
NRC Resident Inspector
$$c
State of New York
\\\\
OFFICIAL RECORD COPY
RL NYPA 88-10 - 0001.0.0
09/23/88
_
.
-
 
. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
..
o
*
.
Power Authority of the
2
SEP 2 7 ;ggg
State of New York
bec w/ encl:
Region I Docket Room (with concurrences)
Management Assistant, DRMA (w/o encl)
Section Chief, DRP
Robert J. Bores, DRSS
B, Clayton, EDO
d
OMS
RI.DRSS
RI:DRSYM
RI:DRSS
Davidson
O sciak
Bellamy
9/s.//88
9h 3/88
9/W/88
0FFICIAL RECORD COPY
RL NYPA 88-10 - 0002,0.0
09/23/88
-
J
 
--
b
*
James A. Fit: Patrick
Nuclear Power Plant
**
,
*
P O. Bcx 41
!
Lycommg. New Yom 13093
315 342 3840
*
.
#> NewWrkPower
4# Authority
AUGUST 31, 1988
JAFP 88- 0824
UNITED STATES NUCLEAR REGULATORY COMMISSION
Mail Station Pl-137
Washington, D.C.
Attention: Document Control Desk
SUBJECT:
James A. FitzPatrick Nuclear Power Plant
Docket No. 50-333
Inspection No. 88-10 - Radioactive Effluents Control Program
Dear Sirst
In accordance with 10CFR2.201, the Authority is submitting its response to
Appendix A, Notice of Violation. This Notice was transmitted to the Authority
August 8, 1988. The inspection was conducted by B. S. Davidson of Region I
office on June 6-10, 1988 at the FitzPatrick Nuclear Power Plant.
Notice of biolation
As a result of the inspection conducted on June 6-10, 1988 and in accordance
with the "General Statement of Policy and Procedure for NRC Enforcement
Actions," 10 CFR Part 2, Appendix C (Enforcement ?olicy) (1988), the following
violation was identified:
Technical Specification 6.5.2.8 of Appendix A to Facility Operating License
No. DPR-59, Technical Spacifications, requires audits of the conformance of
the facility operation to provisions contained within the Technical
Specifications (TS) and applicable license < .inditions at least once per 12
months; and audits of the Radiological Ervironmental Monitoring Program
(REMP) and results at least once per l' months.
Contrary to the above requirements, sn audit of the liquid and caseous
radioactive effluent portions of the TS and the REMP was not p,rformed
within the 12 month interval as required. The last stioit of the radioac-
tive effluents petion of the TS and the RD:P was conducted in November,
1986.
This is a Severity Level V Violation (Supplement 1) .
.
O f % O l '1 e l ) {
fl i)
!
l
ov ii/vi
i ;- *
-
[
 
*
t...
. . ' .
. - .
,,,
4
United States Nuclear Requiatory Commission
August 31, 1988
Attention: Document Control Desk
JAFP 88- 0824
SUBJB7F
INSPECTION'NO. 88-10
Page 2 of 2
Response to Notice of Violation A
The Authority agrees with the finding specified in the violation.
CAUSE - The Site Quality Assurance Organization has historically received tech-
nical support f rom the Corporate Appraisal and Compliance Services Department's
Operational Appraisal Group. This group was in the process of performing the
required Technical Specification Radiological and Environmental audits when they
were 41= banded as 4 result of a corporate reorganization. The Site QA
Organization then requested, through the Director of Quality Assurance, that the
Safety Review Committee (SRC) provide the necessary technical stipport for the
Site Quality Assurance Department to perform these audits. Communications bet-
ween the Chairman of the SRC and the Site QA Superintendent with regard to the
scope of these audits and specific manpower needs further delayed the audit per-
formance and resulted in this Technical Specification violation.
CORRECTIVE ACTIONS -
1)
Immediate - The Site Qualilty Assurance Organization has contracted for the
necessary technical assistance and is in the process of performing the
liquid and gaseous portions of the Technical Specifications and REMP
audits.
It is expected that these audits will be completed by September
30, 1988.
2)
The Site Quality Assurance Superintendent has been counseled on the impor-
tance of meeting the Technical Specification Audit commitments and the need
to escalate manpower requests to whatever appropriate levels of management
may be necessary to resolve any potential schedule delays.
LONG TERM CORRECTIVE ACTION - Funding has been established in the Quality
Assurance Department's annual budget for the purpose of ensuring that any
necessary technical expertise needed te support the variouc Technical
Specification Audit commitments is provided.
/
$Wl%W
RADPORD CONVERSE
RESIDENT MANAGER
RJC RLPacep
cc
Sr. Resident Inspector
Records Center - WPO
Director of Licensing
D. C. C.
Superintendent of Power
G. Wilverding
R. bellamy
F. Pesce
Nuclear Regulatory Commission
A. Klausmann
Region 1
E. Mulcahey
475 Allendale Road
King of Prussia. PA 19406
]
}}

Latest revision as of 10:08, 24 May 2025

Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-333/88-10
ML20155A291
Person / Time
Site: FitzPatrick 
Issue date: 09/27/1988
From: Ronald Bellamy
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Radford Converse
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
References
NUDOCS 8810050271
Download: ML20155A291 (2)


See also: IR 05000333/1988010

Text

___

_ _ _ - _ _ .

t

e

.-

,,

SEP 2 7 gggy

&

Docket No. 50-333

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN: Mr. Radford J. Converse

Resident Manager

P. O. Box 41

Lycoming, New York 13093

Gentlemen:

Subject:

Inspection No. 50-333/88-10

This refers to your letter dated August 31, 1988, in response to our letter

dated August 8, 1988.

Thank you for informing us of the corrective and preventive actions documented

in your letter.

These actions will be examined during a future inspection of

your licensed program.

Your cooperation with us is appreciated.

Sincerely,

Cridnot signed By:

Rcnald R. Scitamy

Ronald R. Bellamy, Chief

Facilities Radiological Safety

and Safeguards Branch

Division of Radiation Safety

and Safeguards

cc w/ encl:

J. Phillip Bayne, President

Mr. Jol.n C. Brons, Executive Vice President

A. Klause nn, Senior Vice President - Appraisal and Compliance Services

"

R. L. Patch, Quality Assurance Superintendent

George M. Wilverding, Manager Nuclear Safety Evaluation

Gerald C. Goldstein, Assistant General Counsel

ngg

R. E. Beedle, Vice President Nuclear Support

Non.

S. S. Zulla. Vice President Nuclear Engineering

go

R. Burns, Vice President Nuclear Operation

gh

Dept. of Public Service, State of New York

State of New York, Department of Law

4

Licensing Project Manager, NRR

No

Public Document Room (POR)

f "*

$@

Local Public Document Room (LPOR)

7f*

p

b3J

g

Nuclear Safety Information Center (NSIC)

C h.

J

- ce

NRC Resident Inspector

$$c

State of New York

\\\\

OFFICIAL RECORD COPY

RL NYPA 88-10 - 0001.0.0

09/23/88

_

.

-

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

..

o

.

Power Authority of the

2

SEP 2 7 ;ggg

State of New York

bec w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

Section Chief, DRP

Robert J. Bores, DRSS

B, Clayton, EDO

d

OMS

RI.DRSS

RI:DRSYM

RI:DRSS

Davidson

O sciak

Bellamy

9/s.//88

9h 3/88

9/W/88

0FFICIAL RECORD COPY

RL NYPA 88-10 - 0002,0.0

09/23/88

-

J

--

b

James A. Fit: Patrick

Nuclear Power Plant

,

P O. Bcx 41

!

Lycommg. New Yom 13093

315 342 3840

.

  1. > NewWrkPower

4# Authority

AUGUST 31, 1988

JAFP 88- 0824

UNITED STATES NUCLEAR REGULATORY COMMISSION

Mail Station Pl-137

Washington, D.C.

Attention: Document Control Desk

SUBJECT:

James A. FitzPatrick Nuclear Power Plant

Docket No. 50-333

Inspection No. 88-10 - Radioactive Effluents Control Program

Dear Sirst

In accordance with 10CFR2.201, the Authority is submitting its response to

Appendix A, Notice of Violation. This Notice was transmitted to the Authority

August 8, 1988. The inspection was conducted by B. S. Davidson of Region I

office on June 6-10, 1988 at the FitzPatrick Nuclear Power Plant.

Notice of biolation

As a result of the inspection conducted on June 6-10, 1988 and in accordance

with the "General Statement of Policy and Procedure for NRC Enforcement

Actions," 10 CFR Part 2, Appendix C (Enforcement ?olicy) (1988), the following

violation was identified:

Technical Specification 6.5.2.8 of Appendix A to Facility Operating License

No. DPR-59, Technical Spacifications, requires audits of the conformance of

the facility operation to provisions contained within the Technical

Specifications (TS) and applicable license < .inditions at least once per 12

months; and audits of the Radiological Ervironmental Monitoring Program

(REMP) and results at least once per l' months.

Contrary to the above requirements, sn audit of the liquid and caseous

radioactive effluent portions of the TS and the REMP was not p,rformed

within the 12 month interval as required. The last stioit of the radioac-

tive effluents petion of the TS and the RD:P was conducted in November,

1986.

This is a Severity Level V Violation (Supplement 1) .

.

O f % O l '1 e l ) {

fl i)

!

l

ov ii/vi

i ;- *

-

[

t...

. . ' .

. - .

,,,

4

United States Nuclear Requiatory Commission

August 31, 1988

Attention: Document Control Desk

JAFP 88- 0824

SUBJB7F

INSPECTION'NO. 88-10

Page 2 of 2

Response to Notice of Violation A

The Authority agrees with the finding specified in the violation.

CAUSE - The Site Quality Assurance Organization has historically received tech-

nical support f rom the Corporate Appraisal and Compliance Services Department's

Operational Appraisal Group. This group was in the process of performing the

required Technical Specification Radiological and Environmental audits when they

were 41= banded as 4 result of a corporate reorganization. The Site QA

Organization then requested, through the Director of Quality Assurance, that the

Safety Review Committee (SRC) provide the necessary technical stipport for the

Site Quality Assurance Department to perform these audits. Communications bet-

ween the Chairman of the SRC and the Site QA Superintendent with regard to the

scope of these audits and specific manpower needs further delayed the audit per-

formance and resulted in this Technical Specification violation.

CORRECTIVE ACTIONS -

1)

Immediate - The Site Qualilty Assurance Organization has contracted for the

necessary technical assistance and is in the process of performing the

liquid and gaseous portions of the Technical Specifications and REMP

audits.

It is expected that these audits will be completed by September

30, 1988.

2)

The Site Quality Assurance Superintendent has been counseled on the impor-

tance of meeting the Technical Specification Audit commitments and the need

to escalate manpower requests to whatever appropriate levels of management

may be necessary to resolve any potential schedule delays.

LONG TERM CORRECTIVE ACTION - Funding has been established in the Quality

Assurance Department's annual budget for the purpose of ensuring that any

necessary technical expertise needed te support the variouc Technical

Specification Audit commitments is provided.

/

$Wl%W

RADPORD CONVERSE

RESIDENT MANAGER

RJC RLPacep

cc

Sr. Resident Inspector

Records Center - WPO

Director of Licensing

D. C. C.

Superintendent of Power

G. Wilverding

R. bellamy

F. Pesce

Nuclear Regulatory Commission

A. Klausmann

Region 1

E. Mulcahey

475 Allendale Road

King of Prussia. PA 19406

]