RS-13-158, Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051): Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:1 n                            ti RS-13-158 RS-13-158                                                                                              Order Order No. EA-12-051 3, 2013 July 3,2013 U.S. Nuclear Nuclear Regulatory Regulatory Commission Commission ATTN: Document Control  Control Desk Washington, DC Washington,      DC 20555-0001 LaSalle County Station, Units 1 and 22 LaSalle Facility Operating Facility  Operating License License Nos.
{{#Wiki_filter:RS-13-158 Order No. EA-12-051 July 3, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374
Nos. NPF-11 NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374          50-374


==Subject:==
==Subject:==
Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)


===Response===
==References:==
1.
Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-1 2-051), dated February 28, 2013 (RS-13-031) 2.
NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 3.
USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7, 2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the LaSalle County Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).
The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the LaSalle County Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-1 2-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to LaSalle County Station, Units 1 and 2. This item is included and addressed in to this letter.
The LaSalle County Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1. The enclosed responses to the NRC request for additional information are intended not to provide preliminary or 1
n ti RS-13-158 Order No. EA-12-051 July 3,2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374


==Subject:==
==Subject:==
ResponsetotoRequest Requestfor    forAdditional Additional Information Information - Overall Overall Integrated Integrated PlanPlan in in Response
Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)  
 
===Response===
to Commission Order   Order Modifying        License Requirements Modifying License         Requirements for    for Reliable Reliable Spent SpentFuelFuelPool Pool Instrumentation (Order (Order No. No. EA-12-051)
EA-12-051)


==References:==
==References:==
: 1. Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28,2013 (RS-13-031)
: 2. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012
: 3. USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7,2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the LaSalle County Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).
The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the LaSalle County Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to LaSalle County Station, Units 1 and 2. This item is included and addressed in to this letter.
The LaSalle County Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1. The enclosed responses to the NRC request for additional information are intended not to provide preliminary or


Exelon Generation Company, LLC
U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-12-051)
: 1. Exelon                                            Letter to LLC Letter    to USNRC, USNRC, OverallOverallIntegrated Integrated PlanPlan inin Response
July 3, 2013 Page 2 conceptual information. The requested information, when fully developed, will be provided upon detailed design completion based on the milestone schedule dates provided in each response.
This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.
Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC


===Response===
==Enclosure:==
to March 12, 2012 Commission Order Modifying                        Licenses      with Modifying Licenses with Regard to    Regard    to Requirements for Reliable for Reliable Spent Fuel    Fuel Pool Pool Instrumentation Instrumentation (Order (Order Number NumberEA-1           2-051), dated EA-12-051),      dated February February 28, 2013 (RS-13-031) 28,2013      (RS-13-031)
1.
NRC Order Number EA-12-051, Issuance
LaSalle County Station, Units 1 and 2 - Response to Request for Additional Information -
: 2. NRC                                          Issuance of of Order Orderto to Modify Modify Licenses Licenses withwith Regard Regard to  to Reliable Spent Spent Fuel Fuel Pool Pool Instrumentation, Instrumentation, dated dated March March 12, 12, 2012 2012
Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:
: 3. USNRC letter to Exelon Generation    Generation Company, Company,LLC,  LLC, Request Requestfor  forAdditional Additional Information Information Regarding Overall Integrated Plan for Reliable Spent Fuel                  Fuel Pool Pool Instrumentation, Instrumentation, dated  dated June June 7,    2013 7,2013 In In Reference 1,  1, Exelon Exelon Generation Generation Company, Company, LLC  LLC (EGC)
Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - LaSalle County Station, Units 1 and 2 NRC Project Manager, NRR - LaSalle County Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-12-051)
(EGC) provided the LaSalle County Station, Units Units 1 and 2, Overall Overall Integrated Integrated Plan  Plan in in Response Response to   to the theMarch March 12,  12,2012 2012Commission CommissionOrder  Order Modifying   Licenses with Modifying Licenses        with Regard to Requirements Requirements for  for Reliable Reliable SpentSpentFuel FuelPool PoolInstrumentation, Instrumentation, pursuant to NRCNRC Order Order No.No. EA    051 (Reference EA-12-051     (Reference 2). 2).
July 3,2013 Page 2 conceptual information. The requested information, when fully developed, will be provided upon detailed design completion based on the milestone schedule dates provided in each response.
The purpose purpose of of this this letter letter is is to to provide provide thethe response responsetotothe  theNRC NRCrequest requestfor foradditional additionalinformation information (Reference (Reference 3)  3) regarding regarding the the LaSalle LaSalle County County Station, Station, Units Units 11and and22Overall Overall Integrated IntegratedPlan Planinin
This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.
 
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.
===Response===
Respectfully submitted, A4,7:¥ Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC  
Responseto  tothe theCommission CommissionOrder    OrderModifying Modifying Licenses Licenses withwith Regard Regard to  to Requirements Requirementsfor      for Reliable Spent Spent FuelFuel Pool Pool Instrumentation Instrumentation (Order(Order No.
No. EA-1       2-051). Subsequent EA-12-051).          Subsequent to    toissuance issuanceofof Reference Reference 3,  3, the theNRC NRCidentified identified thatthat Request Requestfor  forAdditional Additional Information Information Item No. 6.a was        was also also applicable to LaSalle County Station,    Station, Units Units 11 and and 2.2. This This item item is is included included and and addressed addressedinin Enclosure 1 to to this this letter.
letter.
The The LaSalle LaSalle County Station, Units 1 and 2 Spent          Spent Fuel Fuel Pool Pool Instrumentation Instrumentation design  design is is proceeding proceeding on the the schedule scheduleidentified identified in in the Overall Overall Integrated Plan provided in          in Reference 1. The    Theenclosed enclosed responses responsestotothe  theNRC NRCrequest requestfor  foradditional additionalinformation information are areintended intendednot  nottotoprovide providepreliminary preliminary or or
 
U.S. Nuclear Regulatory Regulatory Commission Commission Response to Request for Additional Information Information (Order (OrderEA-12-051)
EA-12-051)
July 3,  2013 3,2013 Page 2 conceptual information.
information. The The requested requestedinformation, information,when whenfully fully developed, developed, will will be provided upon completion based detailed design completion       based on the milestone milestone schedule schedule dates dates provided provided in in each response.
response.
This letter contains no new regulatory regulatory commitments.
commitments. If     you have any questions If you            questions regarding regarding this this response, please response,    pleasecontact contactDavid David P.P. Helker Helker atat 610-765-5525.
610-765-5525.
II declare declare under penalty of perjury       that the foregoing perjury that        foregoing is true and correct. Executed Executedon  onthe  3rd day the3rd  day of July 2013.
Respectfully submitted, A4,7:¥ Glen T. Kaegi Director - Licensing Licensing & Regulatory Regulatory Affairs Affairs Exelon Generation Company, LLC


==Enclosure:==
==Enclosure:==
: 1. LaSalle County Station, Units 1 and 22 -- ResponseResponsetotoRequest Request for forAdditional AdditionalInformation Information--
: 1. LaSalle County Station, Units 1 and 2 - Response to Request for Additional Information -
Overall Integrated Overall  Integrated Plan in Response Response to  to Commission CommissionOrder OrderModifying Modifying License Requirements Requirements for Reliable for Reliable Spent Spent Fuel Fuel Pool Pool Instrumentation Instrumentation (Order (Order No.
Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:
No. EA-12-051)
Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - LaSalle County Station, Units 1 and 2 NRC Project Manager, NRR - LaSalle County Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety LaSalle County Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)
EA-12-051) cc:   Director, Office of Nuclear Reactor Reactor Regulation Regulation NRC Regional Administrator -- Region Region IIIIII NRC Senior NRC    Senior Resident Inspector -- LaSalle LaSalle County County Station, Units Units 1 and 2 NRC Project NRC    Project Manager, NRR NRR -- LaSalle LaSalle County County Station, Station, Units Units 11 and and 22 Mr. Robert J. Fretz, Mr.            Fretz, Jr, Jr,NRRIJLD/PMB, NRRIJLD/PMB, NRC    NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, Mr.                        NRRIDSS/SCVB, NRC      NRC Mr. Blake Purnell, NRC Project Mr.                          Project Manager, Manager, NRR NRR IllinoisEmergency Illinois Emergency Management Management Agency  Agency -- Division Division of Nuclear Safety Safety
(12 pages)
LaSalle County Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-0S1)
(12 pages)


Enclosure 1 Enclosure LaSalle County LaSalle  County Station, Station, Units 1 and 2 Response to Response   to Request Request for Additional Information Overall Integrated Overall  Integrated Plan Plan in in Response Response toto Commission Commission Order Modifying License Requirements for Reliable Spent Fuel License                                      Fuel Pool Pool Instrumentation Instrumentation (Order No. EA-12-051)
Response to Request for Additional Information (Order EA-1 2-051)
(Order No. EA-12-0S1)
Page 1 of 12
(12 pages)
(12


Response to Response      to Request for Additional Additional Information Information(Order     (OrderEA-1     2-051)
==1.0 INTRODUCTION==
EA-12-051)
By {{letter dated|date=February 28, 2013|text=letter dated February 28, 2013}} (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13063A323), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12, 2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for LaSalle County Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation,"
Enclosure 11 Enclosure Page 1 of 12 Page 1.0
Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).
The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.
2.0 LEVELS OF REQUIRED MONITORING The OIP states, in part, that:
Level adequate to support operation of the normal fuel pool cooling system (Level 1): For both units, indicated level on either primary or backup instrument channel must be greater than 842' 1" to maintain normal operation of the Fuel Pool Cooling system. 842' 1" is the elevation of the bottom of the fuel pool weirs which maintain the flowpath for re-circulation of water from the pool through the system.
Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (Level 2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet plus instrument channel accuracy above the top of the storage racks. The specification of this level is based on JLD-ISG-2012-03 and NEI 12-02. This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored fuel.
Level where fuel remains covered (Level 3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 820') plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.


==1.0      INTRODUCTION==
===RAI-1===
Please provide the following:
Response to Request for Additional Information (Order EA-12-051)
Page 1 of 12


INTRODUCTION By letter By  letterdated dated February February 28, 28, 2013 2013 (Agencywide (AgencywideDocuments    DocumentsAccess  Access and    and Management System    System (ADAMS)Accession (ADAMS)        AccessionNo. No.ML ML13063A323),
==1.0 INTRODUCTION==
13063A323), Exelon     ExelonGeneration Generation Company, LLC,          LLC, submitted an     an overall integrated overall   integrated planplan (OIP)
By {{letter dated|date=February 28, 2013|text=letter dated February 28, 2013}} (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13063A323), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12,2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for LaSalle County Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation,"
(OIP) inin response response to the March     March 12,      2012, U.S.
Revision 0, dated August 29,2012 (ADAMS Accession No. ML12221A339).
12,2012,       U.S. Nuclear Nuclear Regulatory Regulatory Commission (NRC)
The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.
Commission        (NRC) Order Order modifying modifying licenses licenses with  with regard regard to reliable spent   spent fuel fuel pool pool (SFP)
2.0 LEVELS OF REQUIRED MONITORING The 01 P states, in part, that:
(SFP) instrumentation (Order instrumentation        (Order EA-12-051; EA-12-051; ADAMS ADAMS Accession Accession No. No. ML12054A679)
Level adequate to support operation of the normal fuel pool cooling system (Level 1): For both units, indicated level on either primary or backup instrument channel must be greater than 842' 1/1 to maintain normal operation of the Fuel Pool Cooling system. 842' 1" is the elevation of the bottom of the fuel pool weirs which maintain the flowpath for re-circulation of water from the pool through the system.
ML12054A679) for        for LaSalle LaSalle County County Station, Units Station,   Units 1 andand 2. TheTheNRCNRC staff staff endorsed endorsedNuclear  NuclearEnergy EnergyInstitute, Institute,NEI NEI12-02, 12-02,"Industry "Industry Guidance for  for Compliance Compliance with  with NRC OrderOrder EA-12-051, EA-12-051, to    to Modify       Licenses with Modify Licenses          with Regard Regard to   to Reliable SFP Reliable   SFP Instrumentation," Revision 1, dated             dated August August 2012 2012(ADAMS (ADAMS Accession No. ML No. ML12240A307),
Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (Level 2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet plus instrument channel accuracy above the top of the storage racks. The specification of this level is based on JLD-ISG-2012-03 and NEI 12-02. This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored fuel.
12240A307), with    with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance 2012-03,    "Compliance with  with Order EA-12-051, EA-12-051, Reliable Spent Fuel Pool Instrumentation,"
Level where fuel remains covered (Level 3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 820') plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.
Revision 0, Revision    0, dated dated August 29,2012 29, 2012 (ADAMS Accession No. ML12221A339).        ML12221A339).
Please provide the following:
NRC staff The NRC      staffhas has reviewed reviewedthe  the February February 28,    28, 2013, 2013, response response by the licensee and          and determined determined that the following       request for additional information (RAI) following request                                                (RAI) is is needed needed to    to complete completeits  itstechnical technical review.
2.0     LEVELS OF REQUIRED MONITORING The OIP 01 P states, in  in part, that:
Level adequate Level    adequate to  to support support operation operation of      of the the normal normal fuelfuel pool pool cooling cooling system system (Level 1):
(Level    1): For For both units, indicated level      level on either primary or backup instrument channel must must bebe greater greaterthanthan842'842'1"  1/1 to to maintain maintain normal normal operation operation of    of the Fuel Fuel Pool Cooling Pool     Cooling system.
system. 842' 842'1" 1" isis the theelevation elevationof  of the thebottom bottom of    of the the fuel fuel pool pool weirs weirs which which maintain the flowpath for re-circulation  re-circulation of   of water water from from the pool through the        the system.
Level    adequate to Level adequate         to provide provide substantial substantial radiation radiation shielding shielding for for aa person personstanding standingon    on the spent spent fuel fuel pool pool operating operating deckdeck (Level (Level 2): For   Forboth bothunits, units,indicated indicatedlevel levelon on either the primary or backup instrument channel of                       of greater greater than than 10 10feet feetplus plus instrument       channel accuracy instrument channel          accuracy aboveabove the    the top top ofofthe the storage storage racks.
racks. TheThe specification specification of  of this this level level isis based based on JLD-ISG-2012-03 and NEI                    NEI 12-02. This  This monitoring monitoring level levelensures ensures there is an adequate adequatewater  waterlevellevel to to provide provide substantial substantial radiation     shielding for radiation shielding        foraa person person standing standing on the spent   spent fuelfuel pool operating deck from direct gammagamma radiation radiation from from stored storedfuel. fuel.
Level Level where fuel  fuel remains covered (Level     (Level 3):  3): For For both both units, units, indicated indicated level level on on either either the the primary primary or  or backup backup instrument channel of             of greater greater than than 00 feet feet (elevation (elevation 820')
820') plus plus instrument       channel accuracy above the top of the storage racks instrument channel                                                                        racks based basedupon uponthe thedesign design accuracy accuracy (which(which is to be determined) determined) of       of the the instrument instrument channel channel for  for both both thethe primary primary and and backup instrument instrument channels.
channels. This This monitoring monitoring level  level assures assures that  that water water is is covering covering the the stored fuelfuel seated seated in in the the racks.
racks.


===RAI-1===
Response to Request for Additional Information (Order EA-12-051)
Please provide provide the the following:
Page 2 of 12 a) For Level 1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.
following:
b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing Level 1, Level 2, and Level 3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the Level 1, Level 2, and Level 3 datum points.


Response to Respons'e   to Request Request for for Additional Additional Information (Order EA-12-051) EA-12-051) 1 Enclosure Page 22 of Page    of 12 12 a) For a)  For Level Level 1, 1, specify specify how how the the identified identified location location represents represents the the higher higher of of the the two two points points described in described    in the the NEI NEI 12-02 guidance for this level.
===Response===
b) AAclearly b)      clearlylabeled labeled sketch sketch depicting the elevation view      view of the proposed proposedtypical typical mounting mounting arrangement for arrangement        for the the portions portions of of instrument instrumentchannel channel consisting consisting of of permanent permanent measurement channel equipment measurement                    equipment (e.g.,(e.g., fixed fixed level level sensors sensors and/or and/orstilling      wells, and stilling wells, mountingbrackets).
a) The Spent Fuel Pool at LaSalle Station has skimmers and scuppers located at the 842'-
mounting     brackets). Indicate on this sketch the datum        datum values values representing representingLevel    Level 1,1, Level2,2, and Level       and Level Level 33 as as well well as as the top of the fuel. fuel. Indicate Indicate on on this this sketch sketchthe  theportion portionof of the level the  level sensor sensor measurement measurement range range thatthat isis sensitive sensitive toto measurement measurementof        of the the fuel fuel pool pool level, with level,  withrespect respect to to the the Level Level 11,, Level Level 2,2, and Level Level 3 datum points.
1" elevation that water must flow into. From there the water is routed to the surge tanks from which the Fuel Pool Cooling (FC) Pumps draw suction. The suction trip is at an approximate 819'-6" elevation. Thus the 842'-l" elevation reflects the higher of the two points noted in NEI 12-02, section 2.3.1.
points.
b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.
Respons'e to Request for Additional Information (Order EA-12-051)
Page 2 of 12 a) For Level 1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.
b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing Level 1,
Level 2, and Level 3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the Level 1, Level 2, and Level 3 datum points.  


===Response===
===Response===
Response a) The a)  The Spent Fuel Pool at LaSalle LaSalle Station Station hashas skimmers and scuppers scuppers located located at  at the the 842'-
a) The Spent Fuel Pool at LaSalle Station has skimmers and scuppers located at the 842'-
842'-
1" elevation that water must flow into. From there the water is routed to the surge tanks from which the Fuel Pool Cooling (FC) Pumps draw suction. The suction trip is at an approximate 819'-6" elevation. Thus the 842'-1" elevation reflects the higher of the two points noted in NEI12-02, section 2.3.1.
1" elevation 1"  elevationthat thatwater watermust must flow flowinto.
b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.  
into. From Fromtherethere the the water water isis routed routed to to the the surge surge tanks from which from    whichthethe Fuel Fuel Pool Pool Cooling Cooling (FC)(FC)Pumps Pumps draw draw suction.
suction. The The suction suction trip trip is is at at an an approximate 819'-6" approximate       819'-6" elevation.
elevation. Thus the  the 842'-l" 842'-1"elevation elevation reflects reflects the the higher higherof  of the the two two points noted in    NEI  12-02, in NEI12-02,     section   2.3.1.
2.3.1.
b) Please b)  Please reference reference the  the sketch sketch below.
below. Instrument Instrumentprobe  probemounting mounting details details in in the the Spent Spent Fuel Fuel area will Pool area          be provided in accordance will be                accordance with    with the the response responsetotoRAI-3.
RAI-3.


Response to Response        to Request Request for    for Additional Additional Information (Order EA-12-051)                EA-12-0S1)
Response to Request for Additional Information (Order EA-12-051)
Enclosure 11 Enclosure Page 33 of Page    of 12 12 EL FlOOR a..EL 843'-6'
Page 3 of 12 EL 842'-7h" r-EL 842'-7h-3'-8' L 842 '-1" LL
                      +
. 3RM'2' WATER LEVEL ORb1M WATER LEVEL FLOOR EL 84 f--- -----j1 rEL
842'-7h" 84 3'-8' f---    -----j1 E L 842 '-1" r L            !  EL.
)
                                                                    .RMIL 3RM'2'WAlUl LL 842'-6' WATER LEVEL LEVEL
EL. 642'-5 EL 842'-1' EL 843'-G
                                                                                                          ~' **
)!' I LEVEL I 1 I
                                                                                                        '-14.1; f
`- EL 842'-1° LEVEL 1 x
                                                                                                                            ,..,,"~
Z^
                                                                                                                                )!' I        ~~f~~4; r- EL 842'-7h-
UNIT #2 SPENT FUEL N
                                                                                                                                                                            )
STORAGE POOL h w yyy,,,Z
ORb1M ~lUl CflMoIL EL.
(,W N =A iz OR TOP/FUEL RACK EL. 819'-84{
WATER LEVEL EL. 842'-6' 642'-5 LEVEL EL EL842'-1*
ME' SKDNNER SURG£ TANK UNIT #1 SPENT FUEL STORAGE POOL TOP/FUEL RACK EL 819'-5W DLk 7
842'-1' LEVEL LEVEL 1 I    1 I FLOOR EL 843'-G LEVEl:                                                    LEVEL LEVEL
a CL EFFECTIVE BOTTOM r
                                                                                                                  `- EL EL 8+2'-1' 842'-1°                     PROBE PROIlE ME' lEVEL LEVEL 1   1 PROBE 0:
TRANSFER CANAL
Ow                                                                    x f!:
-EL. 819'-8r EL 874 LEVEL EL 8301-O' LEVEL LEVEL PROBE KDNNER SURGE TANK 5'-3 O(A.
SKDNNER SURCE SKINtiER    SURG£ UNIT UNIT #1
EL 816'-51 S-1 TO FG PUMPS EL. 818'-fr TO FC PUMPS 344' UNIT 11 UNIT 12 34'-8' ELEVATION VIEW Response to Request for Additional Information (Order EA-12-0S1)
                                                          #1 SPENT SPENT FUEL     FUEL          Vl(!l
Page 3 of 12
                                                                                            ~z                                                                   ~~       UNIT UNIT #2 #2 SPENT      FUEL SPENT FUEL K!lINER KDNNER SURGE
+
                                                                                                                                                              **I~~>....
FlOOR a.. 843'-6' SKINtiER SURCE TANK RMIL WAlUl LEVEL EL. 842'-6' UNIT #1 SPENT FUEL STORAGE POOL LEVEl:
STORAGE STORAGE POOLPOOL                                                                                                      STORAGE STORAGE POOL
PROIlE 0:
                                                                                          '~I!I)~
Ow Vl(!l  
SURGE TANK TANK                                                                                                                                                      N Z^                    POOL                                  TANK TANK 7cl iz
~z  
                                                                                          ~~~       II              a..EL 8301-O' 8]l'-0' LEVELLEVEL 2       !I
~' ** f
                                                                                                                                                              ;';.J,..
'-14.1;
r-lIJ
,..,,"~
                                                                                                                                                              ,I h w    z yyy,,,Z
EL 8+2'-1' lEVEL 1
(,W t'l N
~~f~~4; LEVEL PROBE f!:
                                                                                                                                                                  ~"
~~
                                                                                                                                                                  =A  !.oJ
CflMoIL ~lUl LEVEL EL. 842'-6' EL 842'-1*
                                                                                              'f!:                                                                '0:
LEVEL 1 UNIT #2 SPENT FUEL STORAGE POOL  
x::l7 x:J iz
'~I!I)~
                                                                                            ~~
7cliz
a CL                      EFFECTIVE EFFECTIVE BOTTOM SOITOI.!                   ~
~~~ I I a.. 8]l'-0' LEVEL 2  
OR
! I  
                                                                                            ~"                  r  TMlSrER TRANSFER CANAL  oow.                       ~~                                              S'-1' 5'-3 DLk                                                                            -EL. 819'~~'
**I~~
EL819'-8r                                                                                    O(A.
;';.J,..
TOP/FUEL RACK TOP/fUEL      RACK                                                                                              TOP/fUEL  RACK TOP/FUEL RACK EL 819'-5W EL  B19'-5¥t                                          EL EL 620'-0' 874 LEVEL  LEVEL 5                                EL, 8l9'-Sf,'
r-lIJz
EL. 819'-84{
,I >....
EL 816'-51 EL. 818'-fr TO FG PUMPS S-1 TO FC PUMPS
t'l ~"  
                                                                                                                                                                                  ~~
!.oJ TOP/fUEL RACK EL B19'-5¥t
UNIT 11 UNIT  #1    I    UNIT UNIT 12
'f!:
                                                                                                                                            #2 I
x::l
4 344' u                                    ~I
~~
                                                                                                      ~1 I.                          34'-8'                        J ELEVATION VIEW ELEVATION              VIEW
~"
I u
I 4
~  
~1 EFFECTIVE SOITOI.!
TMlSrER oow.
EL 819'~~'
EL 620'-0' LEVEL 5 UNIT #1 I UNIT #2 ELEVATION VIEW
'0:
x:J
~
~~
TOP/fUEL RACK EL, 8l9'-Sf,'
I.  
~~
J S'-1' K!lINER SURGE TANK


Response to Response    to Request Request for  for Additional Additional Information Information (Order EA-12-0S1)
Response to Request for Additional Information (Order EA-12-051)
EA-12-051) 1 Enclosure Page 4 of 12 Page 3.0 3.0     INSTRUMENTATION DESIGN FEATURES INSTRUMENTATION 3.2     Arrangement OIP The 01 P states, in part, that:
Page 4 of 12 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The OIP states, in part, that:
plan is to The plan      to install install SFP SFP level level sensors sensors in in the southeast southeastcorner cornerof ofthe theUnit Unit 11 SFP SFP and in the the northeast corner of the Unit     Unit 22 SFP; SFP; separated separated by a distance distance of  of approximately 103 approximately        103feet.
The plan is to install SFP level sensors in the southeast corner of the Unit 1 SFP and in the northeast corner of the Unit 2 SFP; separated by a distance of approximately 103 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB
feet. The sensors sensors themselves themselveswill    will be mounted, mounted, to  to the extent extent practical, near practical,   near the pool wallswalls and below the pool    pool curb to minimize their    their exposure exposure to damaging debris and not to                                not interfere interfere with    SFP activities.
[Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services.
with SFP       activities. Instrument Instrument channel electronics and power suppliessupplies willwill be located in seismic and    and missile missile protected protected areas either areas   either below below thethe SFP SFPoperating operatingfloor floororor in in buildings buildings other other than than the theRBRB Building]. The areas
[Reactor Building].               areas toto be beselected selectedwill will provide provide suitable suitable radiation radiation shielding and environmental conditions for shielding                                            for the equipment consistent consistent with with instrument manufacturer's instrument    manufacturer's recommendations. Equipment         Equipmentand  andcabling cablingfor for power power supplies and indication indication for for each each channel will       be separated will be    separated equivalent equivalent to that provided for provided    for redundant redundant safety related services.services.


===RAI-2===
===RAI-2===
Please provide Please  provide aa clearly clearly labeled labeled sketch sketchor ormarked-up marked-upplant  plantdrawing drawingof  ofthe theplan planview view of of the the SFP SFP area, depicting depicting the SFPSFP inside inside dimensions, dimensions, the theplanned plannedlocations/placement locations/placementofofthe    theprimary primary andand back-up SFP level level sensor, sensor, and andthetheproposed proposedrouting routingof ofthe thecables cablesthat thatwill will extend extend from from the the sensors toward sensors  toward the thelocation location of of the the read-out/display read-out/displaydevice.device.
Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.
 
===Response===
Please reference the attached sketch provided in the response for RAI-1 for dimensions and proposed placement of primary and backup level sensors. Note that the locations of the level sensors have changed since the submittal of the overall integrated plan. Please reference the sketches below for proposed cable routing.
Response to Request for Additional Information (Order EA-12-0S1)
Page 4 of 12 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The 01 P states, in part, that:
The plan is to install SFP level sensors in the southeast corner of the Unit 1 SFP and in the northeast corner of the Unit 2 SFP; separated by a distance of approximately 103 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB
[Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services.
Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.  


===Response===
===Response===
Please Please reference reference the theattached attachedsketch sketchprovided providedininthe theresponse responsefor  forRAI-1 RAI-1 for for dimensions dimensionsand  and proposed placement placement of  of primary primary and backup level   level sensors.
Please reference the attached sketch provided in the response for RAI-1 for dimensions and proposed placement of primary and backup level sensors. Note that the locations of the level sensors have changed since the submittal of the overall integrated plan. Please reference the sketches below for proposed cable routing.  
sensors. Note Notethat thatthe thelocations locationsofofthethelevel level sensors sensors have have changed changedsince  sincethe thesubmittal submittal of of the overall      integrated plan.
overall integrated       plan. Please Please reference reference thethe sketches sketches below below for for proposed proposed cablecable routing.
routing.


Response to Response      to Request for Additional Information (Order (Order EA-1             2-051)
Response to Request for Additional Information (Order EA-1 2-051)
EA-12-051) 1 Enclosure Page 55 of Page      of 12 12 1+
Page 5 of 12 17'-10Y2' EXIST. 2" EMBEDED CONDUIT TO BE USED FOR ROUTING Of NEW PROBE CAUX 2FC301 2LE-FtB43A-^
2~"-iI'                            27"-11"                                                                          28"4 1l'-lh*                    17'-10Y2' 17'-1"""-
MEOW PRCAOSEo 4' CURB PLAN VIEW REFUEL FLOOR EL. 843`-67 Response to Request for Additional Information (Order EA-12-051)
1                                                            1
Page 5 of 12 l'-10h'  
                                    !I~                        ',                            I                        pi'                  !I~
~
I l'-10h'
l 1+
                                    ~                              EXIST. 'Z D.tIlEDED          EXIST.Z'2" EMBEDEI>
2~"-iI' 1l'-lh*
                                                                                              ,EXIST.
!I~  
l1 EMBEDED                       '10-J CONDVIT 'TO BE  I,Ism FOR ROIJllNC OF NEl't' PROOE c;.osLE 1 FC.'l8 I I  CONDUIT 'TO CONDUIT fOR TO BE USED FOR ROUTING ROUTING Of'"
~ ----- -------
PROBE c\1lI.E PROBE USED Of N f.W NEW 2FC3~1 CAUX 2FC301
+-----------11---
                                                                                                                                \
I i
                                                                                                                                                                , I;,
Ii I
I
I
                                                          'LE-FeIl13A ItllfftoSED 2LE-FOIl-h1'l 2LE-FtB43A-^
-l-----------,-----
                                                                                                                ~:II~OSED MEOW PRCAOSEo
                                                                                                                                  --  ~----------
I                  --I II  a, F
        ,..                                              f4' CURB CURB
        ~
(TYP.)
I,                                  ,roW'l /                      I ...I I,                                                                    :..
I,                                                                        'I/A"""""'
                +-----------11---
                  ,                          ,              --------r--------
l I
i,                    Ii, I
1/'
I I
I I
I I'
27"-11" 17'-1"""-
                                                                                                                                                                  'Ii>
1 I
I                         I SHIPPING CASK STOAAGE AREA
1 I
                  -l-----------,-----
l1' EXIST. 'Z D.tIlEDED
I                         I
,EXIST. Z' EMBEDEI> pi CONDVIT 'TO BE I,Ism CONDUIT 'TO BE USED J
                                                                                  ---1---     ,                                        I             -------1 1 D
FOR ROIJllNC OF NEl't' I fOR ROUTING Of'" N f.W
TRANSFER CANNPL I                 lRANSFER CANNA!.
\\
3L~-'
PROOE c;.osLE 1 FC.'l8 I PROBE c\\1lI.E 2FC3~1
                                                                                                                                                                  "i!>
'LE-FeIl13A 2LE-FOIl-h1'l ItllfftoSED
8        PlAN VIEW PLAN    VIEW REFUELREFUEL FLOOR  FLOOR EL. EL. B43'-6~
~:II~OSED f CURB (TYP.)
843`-67
I,
I,
I,
--------r--------
TRANSFER CANNPL I
SHIPPING CASK STOAAGE AREA
---1---
I lRANSFER CANNA!.
8 PlAN VIEW REFUEL FLOOR EL.
B43'-6~
28"4
!I~
'10-I
--I  
~----------
I I
,roW'l
/
I I 1/'
I I
I 1
I  
-------1 3L~-'
I;,
I a, I :..
'Ii>,
i!>
F
'I/A"""""'
D


Response to Response      to Request Request for  for Additional Information (Order    (Order EA-12-051)
Response to Request for Additional Information (Order EA-12-051)
EA-12-0S1)
Page 6 of 12 3.3 Mounting The OIP states, in part, that:
Enclosure 11 Enclosure Page 66 of Page      of 12 3.3 3.3      Mounting Mounting The 01 The    OIP P states, in part, that:
Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Installed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.
Design of Design      ofthe the mounting mountingofofthe    thesensors sensors in in the the SFP shall be consistent consistent withwith the seismic seismic Class I criteria.
Class      criteria. Installed Installed equipment equipment will  will be verified verified to  be  seismically    adequate to be seismically adequate for        for the the seismic    motions      associated seismic motions associated with          with the maximum maximum seismic ground motion      motion considered in the    the design of the plant area     areain in which which itit is installed.
installed.


===RAI-3===
===RAI-3===
Please provide the following:
Please provide the following:
Please a) The design criteria that will a)                                          be used will be     used to estimate estimate the the total total loading loading on on the the mounting mounting device(s), including device(s),    including staticstatic weight weightloads loads and and dynamic dynamic loads.      Describe the loads. Describe       the methodology methodology that will that         be used will be   used to estimate estimate thethe total total loading, loading, inclusive inclusive of design basis basismaximum maximum seismicseismic loads and the the hydrodynami hydrodynamic       c loads loads thatthatcould could result resultfrom from pool pool sloshing sloshing oror other other effects effects that could that  could accompany such      such seismic seismic forces.
a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.
forces.
b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical connections.
b) b) A description of the manner     mannerin  in which which thethelevel levelsensor sensor(and (andstilling stillingwell, well,ififappropriate) appropriate)will will be attached attached to  to the the refueling refueling floor floor and/or other support structures for each planned point                point of attachment of    of the the probe assembly. Indicate   Indicateininaaschematic schematicthe  theportions portionsofofthe thelevel level sensor sensorthat thatwill will serve as  as points pointsof  of attachment attachmentfor  formechanical/m mechanical/mountingounting or orelectrical electrical connections.
c) A description of the manner by which the mechanical connections will attach the level instrument to permanent SFP structures so as to support the level sensor assembly.
c) A description of the manner    manner by  by which which thethe mechanical mechanicalconnections connectionswill  will attach attachthethelevel level instrument       to permanent SFP structures so instrument to permanent                                    so asasto tosupport supportthe thelevel level sensor sensorassembly.
assembly.


===Response===
===Response===
Response The current plan for the SFPI design of              of the system system based basedon onthe thecurrent currentExelon ExelonNuclear Nuclear program    schedule    for  LaSalle      started program schedule for LaSalle started the designphase  the  design     phaseininJune Juneofof2013 2013with withdesign designcompletion completion and and 100%
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
100% acceptance acceptanceof      of the the design designin  in January January2014.2014.The Therequested requested       informationwill information         will be be provided provided in the February 2014, 6-month       6-month Integrated Integrated PlanPlan Update.
3.4 Qualification The OIP states, in part, that:
Update.
Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:
3.4 3.4      Qualification Qualification The The OIP 01 P states, states,ininpart, part,that:
components are supplied by manufacturers using commercial quality programs (such as ISO9001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; and/or Response to Request for Additional Information (Order EA-12-0S1)
that:
Page 6 of 12 3.3 Mounting The 01 P states, in part, that:
Components Componentsof      ofthe theinstrument instrumentchannels channelswill  willbe bequalified qualifiedfor forshock shockand  andvibration vibration using using one oneor ormore moreof  ofthe thefollowing following methods:
Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Installed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.
methods:
Please provide the following:
    **  components components are     aresupplied suppliedby  bymanufacturer manufacturers     s using usingcommercial commercialquality quality programs programs(such (suchasas ISO9001,     "Quality       management         systems IS09001, "Quality management systems- -Requirements           Requirements") ") with withshock shockand andvibration vibration requirements requirements included included in  in the thepurchase purchasespecification specificationatatlevels levelscommensurat commensurate         with e with portable portable hand-held hand-helddevices devicesorortransportation transportationapplications; applications; and/or and/or
a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.
b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical connections.
c) A description of the manner by which the mechanical connections will attach the level instrument to permanent SFP structures so as to support the level sensor assembly.


===Response===
===Response===
Response to  to Request Request for  for Additional Additional Information Information(Order (OrderEA-1     2-051)
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
EA-12-0S1) 1 Enclosure Page 77 ofof 12 12
3.4 Qualification The 01 P states, in part, that:
* components componentshave    havesubstantial substantialhistory historyofofoperational operationalreliability reliabilityininenvironments environmentswith      with significant significant shock and vibration            loadings, such vibration loadings,         such as portable hand-held hand-held devicesdevices or  or transportation transportation applications; applications; and/or and/or
Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:
* components components are    are inherently inherently resistant to shock shock and and vibration    loadings, such vibration loadings,         such as cables.
components are supplied by manufacturers using commercial quality programs (such as IS09001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; and/or
cables.
 
For seismic effects on instrument channel components      components used   usedafter afteraapotential potential seismic seismiceventevent for only only installed installed components components (with         the exception of (with the                  of battery chargers and     and replaceable replaceable batteries), the the following      measures will following measures           will be used used to to verify verify that the design design and  and installation installation is  is adequate.
Response to Request for Additional Information (Order EA-1 2-051)
adequate. Applicable Applicable components componentsare    arerated ratedby  bythe themanufacturer manufacturer(or     (orotherwise otherwise tested) tested)for  for seismic effects at levels commensurate with                     those of with those          postulated design basis event of postulated                          event conditions in in the the area of instrument channel component use                use using using one oneor ormore moreof  of the the following methods:
Page 7 of 12 components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; and/or components are inherently resistant to shock and vibration loadings, such as cables.
following    methods:..  ....
For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:...


===RAI-4===
===RAI-4===
Please provide the following:
Please provide the following:
a) A description of     of the the specific method or combination of methods        methods you  you intend intend to to apply applyto  to demonstrate demonstrate the  thereliability    of the reliability of   the permanently installed equipment under            under beyond-design-beyond-design-basis ambient basis  ambient temperature, temperature,humidity, humidity, shock, shock, vibration, vibration, andand radiation radiation conditions.
a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.
conditions.
b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.
b) A b)      description of A description      ofthe thetesting testing and/or and/or analyses analyses that will       be conducted will be    conducted to    to provide provide assurance assurance that the equipment equipment will         perform reliably will perform    reliablyunder underthe the worst-case worst-case credible credible design basis   basis loading at loading   at the the location location where where thethe equipment will   willbebemounted.
c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.
mounted. Include a discussion discussion of    of this seismic reliability       demonstration as reliability demonstration          as itit applies applies toto a) a) the level sensor sensor mounted mounted in  in the the SFP area, area, and andb)  b) any anycontrol control boxes, boxes, electronics, electronics, or orread-out read-out andandre-transmitting re-transmitting devices devices that will be employed will be  employed to convey the level      level information information fromfrom the the level level sensor sensor to the  the plant plant operators or emergency responders.
 
c) c) A A description description of of the the specific specific method or combination of methods       methods that  that will will be used used toto confirm the confirm    the reliability reliabilityofofthe thepermanently permanently installed equipmentequipment such such thatthatfollowing following aa seismic event event thethe instrument instrumentwill will maintain its required accuracy.accuracy.
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
3.5 Independence The OIP states, in part, that:
Response to Request for Additional Information (Order EA-12-0S1)
Page 7 of 12 components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; and/or components are inherently resistant to shock and vibration loadings, such as cables.
For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:...
Please provide the following:
a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.
b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.
c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.  


===Response===
===Response===
Response The current planplan for for the the SFPI SFPI design design ofof the the system system based based on on the the current current Exelon Exelon Nuclear Nuclear program schedule for LaSalle program                      LaSalle started started the design phase   phaseinin June Juneof of2013 2013with  with design designcompletion completion and 100% acceptance of        of the design in January 2014. The           Therequested requestedinformation information will will be provided in provided    in the the February February 2014, 2014, 6-month 6-month Integrated Plan Update.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
3.5     Independence Independence The The OIP states, in  in part, that:
3.5 Independence The OIP states, in part, that:  


Response to Response      to Request Request for for Additional Additional Information (Order (Order EA-12-051)
Response to Request for Additional Information (Order EA-12-051)
EA-12-0S1)
Page 8 of 12 The primary instrument channel will be independent of the backup instrument channel.
Enclosure Page 88 of Page    of 12 The primary The    primary instrument instrument channel channel will willbebeindependent independent of    of the the backup instrument channel.
This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.
This independence This    independence will willbe be achieved achieved through through physical physical and and electrical electrical separation separation of of each channels' components commensurate channels'                      commensurate with    with hazard and electrical electrical isolation    needs.
isolation needs.


===RAI-5===
===RAI-5===
Please provide Please  provide thethe following:
Please provide the following:
following:
a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.
a) AA description a)      descriptionofofhow howthethetwotwochannels channelsofofthe  theproposed proposed levellevelmeasurement measurement system meet       meet this requirement this   requirement so that the potential for       for aa common common cause cause event event toto adversely adversely affect affect both both channels is minimized to        to the extent practicable.
b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.
practicable.
b) Further b)   Further information informationon  onhowhoweach eachlevel levelmeasurement measurement system, system, consisting of level level sensor sensor electronics, cabling, electronics,      cabling, and and readout devices will         be designed and installed will be                      installed to address address independence through the application application and and selection selection of of independent independent powerpower sources, sources, the use of physical physical and spatial separation, independence independenceof      ofsignals signalssentsenttotothe thelocation(s) location(s)ofof the readout devices, and the      the independence independenceof      of the thedisplays.
displays.


===Response===
===Response===
Response The current plan for  for the the SFPI SFPI design of  of the the system basedbasedon    onthe thecurrent currentExelon Exelon Nuclear Nuclear program schedule for LaSalle started the design program                                                design phase phaseininJune Juneofof2013 2013with with design designcompletion completion and 100% acceptance acceptance of  of the design design in in January January 2014.2014. The Therequested requestedinformation informationwill will be provided in in the the February 2014, 6-month Integrated Integrated PlanPlan Update.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
Update.
3.6 Power supplies The OIP states, in part, that:
3.6     Power supplies supplies The OIP 01 P states, states, in in part, part, that:
Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049. Additionally, each channel will have provisions for connection to another suitable power source.
that:
Each channel channelwillwill be be normally normally powered poweredfrom  from aadifferent different120Vac 120Vac[120[120volts-alternating volts-alternating current] bus. Upon Uponloss lossofofnormal normalac acpower, power,individual individual channel channelinstalled installedbatteries batterieswill will automatically      maintain continuous automatically maintain           continuous channel channel operation.
operation. The  The batteries batterieswillwill be replaceable replaceable and be be sized sized toto maintain maintain channel channel operation operation until until off-site off-site resources can can bebedeployed deployedby  by the mitigating mitigating strategies strategies resulting resulting from from Order OrderEA-12-049.
EA-12-049. Additionally, Additionally, each eachchannel channelwill will have provisions provisions for connection to another another suitable suitable power power source.
source.


===RAI-6===
===RAI-6===
Please provide the the following:
Please provide the following:
following:
a) A description of the electrical ac power sources and capacities for the primary and backup channels.
a) a) A A description of the the electrical electrical ac power sources sources and andcapacities capacitiesfor forthe theprimary primaryand and backup     channels.
b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the Response to Request for Additional Information (Order EA-12-0S1)
backup channels.
Page 8 of 12 The primary instrument channel will be independent of the backup instrument channel.
b) b) If  the level If the level measurement measurement channelschannels areareto tobebepowered poweredthrough throughaabattery batterysystem system(either (either directly directly or through an uninterruptible uninterruptible power supply), please     pleaseprovide providethethedesign designcriteria criteria that that will will be applied to size the batterybattery inin aa manner mannerthat  thatensures, ensures,with withmargin, margin,thatthatthe the channel channelwill will be be available availableto  torun runreliably reliably andandcontinuously continuouslyfollowing following thetheonset onsetofofthe the
This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.
Please provide the following:
a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.
b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.
 
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
3.6 Power supplies The 01 P states, in part, that:
Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049. Additionally, each channel will have provisions for connection to another suitable power source.
Please provide the following:
a) A description of the electrical ac power sources and capacities for the primary and backup channels.
b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the  


Response to Request for Additional Information Response                                    Information (Order(Order EA-12-051)
Response to Request for Additional Information (Order EA-12-051)
EA-12-051) 1 Page 9 of 12 c) beyond-design-basis event c)                            event for for the minimum          duration needed, minimum duration         needed, consistent consistent with with the plant mitigationstrategies mitigation   strategies forfor beyond-design-basis beyond-design-basis external events        events (Order (OrderEA-12-049).
Page 9 of 12 c) beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).
EA-12-049).


===Response===
===Response===
The current plan for for the the SFPI SFPI design of the system based       basedon  onthe thecurrent currentExelon Exelon Nuclear Nuclear program schedule for LaSalle started the design program                                              design phase phaseininJune Juneofof2013 2013withwith design designcompletion completion and 100% acceptance acceptance of  of the design design in  in January January 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
2014. The Therequested requestedinformation informationwill will be provided in provided in the the February 2014, 6-month Integrated Plan           Plan Update.
3.7 Accuracy The OIP states, in part, that:
Update.
The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.
3.7   Accuracy The OIP DIP states, in part, that:
The instrument channels channels willwill be designed designed to  to maintain maintain their their design design accuracy accuracyfollowing following a interruption or power interruption     or change change in  in power source without recalibration.
recalibration. Instrument Instrument channel channel accuracy, to be  be determined determined during during detailed detailed design, design,will will consider consider Spent SpentFuel FuelPool Pool conditions (e.g.,
conditions    (e.g., saturated water, water, steamsteam environment),
environment), as     aswell well as, as, other otherapplicable applicable radiological and radiological    and environmental environmental conditions conditions and and include display accuracy. Instrument  Instrument channel accuracy      will accuracy will     be sufficient sufficient to allow trained personnel to determine when the to allow    trained  personnel    to  determine actual level exceeds exceeds the thespecified specifiedlower lower level level ofof each each indicating indicating range range(levels (levels 1,1,22or or3) 3)
without conflicting conflicting oror ambiguous ambiguous indications.
indications.


===RAI-7===
===RAI-7===
Please provide the following:
Please provide the following:
a) An   estimate of An estimate    of the the expected instrument channel accuracy      accuracy performance performance under under both both (a)
a) An estimate of the expected instrument channel accuracy performance under both (a) normal SFP level conditions (approximately Level 1 or higher) and (b) at the beyond design-basis conditions (i.e., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the Level 2 and Level 3 datum points.
(a) normal SFP levellevel conditions (approximately (approximately Level 1 or higher) and         and (b)(b) at at the the beyond beyond design-basis conditions design-basis    conditions (i.e.,
b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.
(Le., radiation, radiation, temperature, temperature, humidity, humidity, post-seismic post-seismic and   andpost-post-shock conditions) that would would be present present ifif the SFP SFP level level were were atatthe theLevel Level 22and andLevel Level 33 datum points.
b) A description of the methodology methodology that    that will will be used usedfor for determining determiningthe  themaximum maximumallowedallowed deviation from from the the instrument instrument channel channel design accuracy accuracy that that will will be employed under  under normal operating conditions as an        an acceptance acceptancecriterion criterionforforaacalibration calibration procedure proceduretotoflag flag to operators andand to to technicians technicians that  that the the channel channelrequires requiresadjustment adjustmenttotowithin within the the normal normal condition condition design accuracy.


===Response===
===Response===
The current plan for for the the SFPI SFPI design of the system based       basedon  onthe thecurrent currentExelon Exelon Nuclear Nuclear program schedule for for LaSalle started the design  design phase phaseininJune Juneofof2013 2013withwith design designcompletion completion and 100%
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
100% acceptance acceptance of  of the the design design in in January January 2014.
Response to Request for Additional Information (Order EA-12-051)
2014. The Therequested requestedinformation informationwill will be provided in in the February 2014, 6-month6-month Integrated Plan      Plan Update.
Page 9 of 12 c) beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).  
Update.


Response to Request for Additional Additional Information Information (Order (OrderEA-12-051)
===Response===
EA-12-0S1) 1 Enclosure Page 1010 of 12 12 3.8     Testing The OIP 01 P states, inin part, part, that:
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
that:
3.7 Accuracy The DIP states, in part, that:
Instrument channel Instrument      channel design design will will provide provide for for routine testing and andcalibration calibration consistent consistentwith  with the guidelines of NRC JLD-ISG-2012-03 and NEI                     12-02. Details will NEI12-02.                  will be determined during detailed during  detailed design design engineering.
The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.
Please provide the following:
a) An estimate of the expected instrument channel accuracy performance under both (a) normal SFP level conditions (approximately Level 1 or higher) and (b) at the beyond design-basis conditions (Le., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the Level 2 and Level 3 datum points.
b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.
 
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
 
Response to Request for Additional Information (Order EA-12-051)
Page 10 of 12 3.8 Testing The OIP states, in part, that:
Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 and NEI 12-02. Details will be determined during detailed design engineering.


===RAI-8===
===RAI-8===
Please provide the following:
Please provide the following:
a) A   description of A description      of the the capability capability andand provisions the proposed proposedlevellevelsensing sensingequipment equipmentwill  will have to enable enable periodic periodic testing testing and andcalibration, calibration, including including how this capability enables   enables thethe equipment to be tested tested in-situ.
a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.
in-situ.
b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation, c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.
b) A b)     description of A description     of how how such such testing and and calibration calibration will will enable thethe conduct conductof  of regular regular channel checks of each independent channel against the other, and against any                          any other other permanently-installed SFP     SFP level level instrumentation, instrumentation.
d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.
c) A c)    description of A description      of how how functional functional checks checks will willbebe performed, performed, and and the frequency frequency at   at which which they will   be conducted. Describe     how calibration will be conducted. Describe how calibration tests will     tests  will be   performed,     and performed, and the  the frequency at which frequency         which they theywill willbebeconducted.
 
conducted. Provide Provide aa discussion discussion as to how these    these surveillances will       be incorporated into the plant will be                              plant surveillance surveillance program.
===Response===
program.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.
d) A d)    description of A description      ofwhat whatpreventative preventativemaintenance maintenance taskstasks are required to be performed performed during normal during  normal operation, operation, and the planned planned maximum maximum surveillance surveillance interval interval that is is necessary to necessary      to ensure ensurethatthatthe thechannels channelsare  arefully fullyconditioned conditioned to  to accurately accuratelyand andreliably reliably perform their perform    their functions functions when when needed.
3.9 Display The OIP states, in part, that:
needed.
The primary and backup instrument displays will be located at the control room, remote shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design.
Response to Request for Additional Information (Order EA-12-0S1)
Page 10 of 12 3.8 Testing The 01 P states, in part, that:
Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 and NEI12-02. Details will be determined during detailed design engineering.
Please provide the following:
a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.
b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation.
c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.
d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.  


===Response===
===Response===
The current plan for for the the SFPI SFPI design of the system based   basedon  onthe thecurrent currentExelon Exelon Nuclear Nuclear program schedule for LaSalle started the design program                                              design phase phaseininJuneJuneofof2013 2013with with design designcompletion completion and 100% acceptance acceptance of    of the design design inin January January 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.
2014. Following Following thethe issue issueof of the the design, design, procedures will procedures          start being will start   being developed developed withwith aa projected projected July July 2014 2014 completion completion date. date. The The requested information requested   information will      be provided will be provided in in the the August 2014, 6-month Integrated Integrated PlanPlanUpdate.
3.9 Display The OIP states, in part, that:
Update.
The primary and backup instrument displays will be located at the control room, remote shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design.  
3.9     Display The OIP states, in  in part, part, that:
The primary primary and and backup instrument instrument displays will       be located at the control will be                      control room, remote shutdown panel, or other appropriate and accessible   accessiblelocation.
location. The Thespecific specificlocation locationwill will be determined during detailed design.


Responseto Response       to Request Requestfor    for Additional Additional Information Information (Order(Order EA-12-0S1)
Response to Request for Additional Information (Order EA-12-051)
EA-12-051)
Page 11 of 12
Enclosure 1 Enclosure Page 11 Page    11 of of 12 12


===RAI-9===
===RAI-9===
Please provide Please    provide thethe following:
Please provide the following:
following:
a) The specific location for each of the primary and backup instrument channel displays.
a) The a)    The specific specific location locationfor foreach each ofofthe the primary primaryand  and backup backup instrument channel displays.
b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.
b) IfIfthe b)      theprimary primaryand  and backup backup display display location location is is other other than the main main control control room, room, provide provide justificationfor justification     forprompt promptaccessibility accessibilitytotodisplays displays including includingprimary primaryand andalternate alternate route route evaluation, habitability evaluation,      habitability at at display display location(s),
c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.
location(s), continual continual resource availability        for personnel availability for   personnel responsible to promptly responsible          promptly read read displays, and provisions provisions for for communications with    with decision makers for makers      for the the various various SFP SFP drain drain down down scenarios scenarios and external events.
c) The reasons c)          reasons justifying justifying whywhy thethe locations selected selected enable enablethe theinformation information fromfrom these these instruments to instruments        to be be considered "promptly            accessible" to "promptly accessible"         to various various drain-down drain-downscenarios scenarios and external events.
external


===Response===
===Response===
Response The current plan for   for the the SFPI SFPI design of the system based       basedon onthe thecurrent currentExelon Exelon Nuclear Nuclear program schedule for LaSalle started the design program                                                      design phase phaseininJune Juneofof2013 2013with with design designcompletion completion and 100% acceptance acceptance of      of the design design in in January January 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
2014. The Therequested requestedinformation informationwill will be provided in provided    in the the February 2014, 6-month Integrated Plan               Plan Update.
4.0 PROGRAM FEATURES 4.2 Procedures The OIP states, in part, that:
Update.
Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.
4.0 4.0      PROGRAM FEATURES 4.2     Procedures The OIP DIP states, states, inin part, part, that:
that:
Procedures Procedures will  will be developed using    using guidelines and   and vendor vendor instructions instructions to address addressthe the maintenance, operationoperation and and abnormal abnormal response responseissuesissuesassociated associatedwith withthe theprimary primaryandand backup channels            of SFP    instrumentation.
channels of SFP instrumentation.


===RAI-10===
===RAI-10===
RAI-10 Please Pleaseprovide provideaadescription descriptionof    ofthe thestandards, standards,guidelines guidelinesand/orand/orcriteria criteriathat thatwill willbebeutilized utilizedto to develop develop procedures procedures for   for inspection, inspection, maintenance, repair,    repair, operation, abnormal response, response, and and administrative    controls associated administrative controls           associated with with the SFPSFP level level instrumentation, as   as well well as storage storage and and installation  of portable      instruments.
Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.
installation of portable instruments.


===Response===
===Response===
Response The The current current plan plan for for the SFPI SFPI design design of of the the system system based basedon  onthe thecurrent currentExelon ExelonNuclear Nuclear program program schedule schedulefor  for LaSalle LaSalle started startedthe thedesign designphase phaseininJune Juneofof2013 2013withwithdesign designcompletion completion and  100%    acceptance      of  the design   in January    2014. Following and 100% acceptance of the design in January 2014. Following the issue of the design,    the  issue  of the  design, procedures procedureswill  will start being being developed developed with with a projected projected July 2014 completion completion date. The  The requested requestedinformation informationwill  will be be provided provided in  in the the August August 2014,2014,6-month 6-monthIntegrated IntegratedPlan PlanUpdate.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.
Update.
Response to Request for Additional Information (Order EA-12-0S1)
Page 11 of 12 Please provide the following:
a) The specific location for each of the primary and backup instrument channel displays.
b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.
c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.  


Responseto Response       to Request Request for  for Additional Additional IInformation nformation (Order EA-12-051)
===Response===
Enclosure 1 Enclosure Page 12 Page   12 of of 12 12 4.3 4.3       Testing and Calibration Testing            Calibration The OIP The  OI Pstates, states, inin part, part, that:
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.
that:
4.0 PROGRAM FEATURES 4.2 Procedures The DIP states, in part, that:
Processes shall be established Processes                    established and  and maintained maintained forfor scheduling and   and implementin implementing     g necessary testing and calibration of necessary                                        of the the primary primary and and backup backup    SFP   level   instrument channels to channels       to maintain maintainthe  theinstrument instrumentchannels channelsatatthethedesign designaccuracy.
 
accuracy. The testing testing    and   calibration calibration of  of the the instrumentation instrumentation shall shall be be consistent with with vendor recommendations or recommendations            or other other documented documented basis. basis. Calibration Calibration shall be specific to        to the the mounted instrument mounted      instrument and the monitor.monitor.
===RAI-10===
Surveillances or testing to validate functionality Surveillances                                      functionality ofof an an installed installed instrument channelchannel shall shall  be   performed     within    60  days within 60 days of     of aa planned refueling refueling outage considering considering normal testing normal    testing scheduling scheduling allowances allowances (e.g.,(e.g., 25%).
Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.
25%). This This isis not not required required to be be performed more performed       more than than once once per 12 months.
Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.
 
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.
 
Response to Request for Additional Information (Order EA-12-051)
Page 12 of 12 4.3 Testing and Calibration The OI P states, in part, that:
Processes shall be established and maintained for scheduling and implementing necessary testing and calibration of the primary and backup SFP level instrument channels to maintain the instrument channels at the design accuracy. The testing and calibration of the instrumentation shall be consistent with vendor recommendations or other documented basis. Calibration shall be specific to the mounted instrument and the monitor.
Surveillances or testing to validate functionality of an installed instrument channel shall be performed within 60 days of a planned refueling outage considering normal testing scheduling allowances (e.g., 25%). This is not required to be performed more than once per 12 months.
 
===RAI-11===
Please provide the following:
a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.
b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.
c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.
 
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.
Response to Request for Additional I nformation (Order EA-12-051)
Page 12 of 12 4.3 Testing and Calibration The OIP states, in part, that:


===RAI-11===
===RAI-11===
RAI-11 Please provide the following:
Processes shall be established and maintained for scheduling and implementing necessary testing and calibration of the primary and backup SFP level instrument channels to maintain the instrument channels at the design accuracy. The testing and calibration of the instrumentation shall be consistent with vendor recommendations or other documented basis. Calibration shall be specific to the mounted instrument and the monitor.
Please a) Further information a)              informationdescribing describingthe  the maintenance maintenance and testingtesting program program thethelicensee licenseewillwill establish and implement establish          implement to ensure ensure thatthat regular regular testing testing andandcalibration calibration is is performed performed and and verified by verified   by inspection inspectionand  and audit audit to to demonstrate demonstrate conformance conformance with  with design design and system readiness requirement readiness      requirements. s. Include Includeaadescription descriptionof of your your plans plans for for ensuring that necessary necessary channel channel checks, checks, functional functional tests, tests, periodic periodiccalibration, calibration, and and maintenance maintenancewill  will be beconducted conducted for  the level for the           measurement system level measurement           system and anditsitssupporting supporting equipment.
Surveillances or testing to validate functionality of an installed instrument channel shall be performed within 60 days of a planned refueling outage considering normal testing scheduling allowances (e.g., 25%). This is not required to be performed more than once per 12 months.
equipment.
Please provide the following:
b) A b)    description of A description       of how how thethe guidance in NEI          12-02 Section NEI 12-02     Section 4.3 regarding compensato compensatory   ry actions actions forfor one or or both both non-functio non-functioning ning channels channels will    be addressed.
a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.
will be addressed.
b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.
c) c) AA description description of   of what what compensatory compensatory actions are planned in            in the event event that that oneoneofof the the instrument      channels instrument channels cannot be cannot    berestored restoredtotofunctional functional status statuswithin within 90 90 days.
c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.  
days.


===Response===
===Response===
Response The The current current plan plan forfor the SFPI design deSign of of the system system based basedon  onthethecurrent currentExelon ExelonNuclear Nuclear program program schedule schedule for  for LaSalle LaSalle started started thethedesign designphase phaseininJune Juneofof20132013with withdesign designcompletion completion and  100%    acceptance      of   the  design and 100% acceptance of the design in January2014. in  January     2014.Following Followingthe  theissue issueofofthe thedesign, design, procedures procedureswill  will start being developed with      with a projected July 2014 completion date. The              The requested requestedinformation informationwill  will be be provided provided in  in the the August August 2014, 2014,6-month 6-monthIntegrated IntegratedPlan PlanUpdate.
The current plan for the SFPI deSign of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.}}
Update.}}

Latest revision as of 07:15, 11 January 2025

Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)
ML13186A004
Person / Time
Site: LaSalle  
Issue date: 07/03/2013
From: Kaegi G
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-051, RS-13-158
Download: ML13186A004 (15)


Text

RS-13-158 Order No. EA-12-051 July 3, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374

Subject:

Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)

References:

1.

Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-1 2-051), dated February 28, 2013 (RS-13-031) 2.

NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 3.

USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7, 2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the LaSalle County Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).

The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the LaSalle County Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-1 2-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to LaSalle County Station, Units 1 and 2. This item is included and addressed in to this letter.

The LaSalle County Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1. The enclosed responses to the NRC request for additional information are intended not to provide preliminary or 1

n ti RS-13-158 Order No. EA-12-051 July 3,2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374

Subject:

Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)

References:

1. Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28,2013 (RS-13-031)
2. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012
3. USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7,2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the LaSalle County Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).

The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the LaSalle County Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to LaSalle County Station, Units 1 and 2. This item is included and addressed in to this letter.

The LaSalle County Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1. The enclosed responses to the NRC request for additional information are intended not to provide preliminary or

U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-12-051)

July 3, 2013 Page 2 conceptual information. The requested information, when fully developed, will be provided upon detailed design completion based on the milestone schedule dates provided in each response.

This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.

Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1.

LaSalle County Station, Units 1 and 2 - Response to Request for Additional Information -

Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:

Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - LaSalle County Station, Units 1 and 2 NRC Project Manager, NRR - LaSalle County Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-12-051)

July 3,2013 Page 2 conceptual information. The requested information, when fully developed, will be provided upon detailed design completion based on the milestone schedule dates provided in each response.

This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.

Respectfully submitted, A4,7:¥ Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1. LaSalle County Station, Units 1 and 2 - Response to Request for Additional Information -

Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:

Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - LaSalle County Station, Units 1 and 2 NRC Project Manager, NRR - LaSalle County Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety LaSalle County Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)

(12 pages)

LaSalle County Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-0S1)

(12 pages)

Response to Request for Additional Information (Order EA-1 2-051)

Page 1 of 12

1.0 INTRODUCTION

By letter dated February 28, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13063A323), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12, 2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for LaSalle County Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation,"

Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).

The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.

2.0 LEVELS OF REQUIRED MONITORING The OIP states, in part, that:

Level adequate to support operation of the normal fuel pool cooling system (Level 1): For both units, indicated level on either primary or backup instrument channel must be greater than 842' 1" to maintain normal operation of the Fuel Pool Cooling system. 842' 1" is the elevation of the bottom of the fuel pool weirs which maintain the flowpath for re-circulation of water from the pool through the system.

Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (Level 2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet plus instrument channel accuracy above the top of the storage racks. The specification of this level is based on JLD-ISG-2012-03 and NEI 12-02. This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored fuel.

Level where fuel remains covered (Level 3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 820') plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.

RAI-1

Please provide the following:

Response to Request for Additional Information (Order EA-12-051)

Page 1 of 12

1.0 INTRODUCTION

By letter dated February 28, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13063A323), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12,2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for LaSalle County Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation,"

Revision 0, dated August 29,2012 (ADAMS Accession No. ML12221A339).

The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.

2.0 LEVELS OF REQUIRED MONITORING The 01 P states, in part, that:

Level adequate to support operation of the normal fuel pool cooling system (Level 1): For both units, indicated level on either primary or backup instrument channel must be greater than 842' 1/1 to maintain normal operation of the Fuel Pool Cooling system. 842' 1" is the elevation of the bottom of the fuel pool weirs which maintain the flowpath for re-circulation of water from the pool through the system.

Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (Level 2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet plus instrument channel accuracy above the top of the storage racks. The specification of this level is based on JLD-ISG-2012-03 and NEI 12-02. This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored fuel.

Level where fuel remains covered (Level 3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 820') plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.

Please provide the following:

Response to Request for Additional Information (Order EA-12-051)

Page 2 of 12 a) For Level 1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.

b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing Level 1, Level 2, and Level 3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the Level 1, Level 2, and Level 3 datum points.

Response

a) The Spent Fuel Pool at LaSalle Station has skimmers and scuppers located at the 842'-

1" elevation that water must flow into. From there the water is routed to the surge tanks from which the Fuel Pool Cooling (FC) Pumps draw suction. The suction trip is at an approximate 819'-6" elevation. Thus the 842'-l" elevation reflects the higher of the two points noted in NEI 12-02, section 2.3.1.

b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.

Respons'e to Request for Additional Information (Order EA-12-051)

Page 2 of 12 a) For Level 1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.

b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing Level 1,

Level 2, and Level 3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the Level 1, Level 2, and Level 3 datum points.

Response

a) The Spent Fuel Pool at LaSalle Station has skimmers and scuppers located at the 842'-

1" elevation that water must flow into. From there the water is routed to the surge tanks from which the Fuel Pool Cooling (FC) Pumps draw suction. The suction trip is at an approximate 819'-6" elevation. Thus the 842'-1" elevation reflects the higher of the two points noted in NEI12-02, section 2.3.1.

b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.

Response to Request for Additional Information (Order EA-12-051)

Page 3 of 12 EL 842'-7h" r-EL 842'-7h-3'-8' L 842 '-1" LL

. 3RM'2' WATER LEVEL ORb1M WATER LEVEL FLOOR EL 84 f--- -----j1 rEL

)

EL. 642'-5 EL 842'-1' EL 843'-G

)!' I LEVEL I 1 I

`- EL 842'-1° LEVEL 1 x

Z^

UNIT #2 SPENT FUEL N

STORAGE POOL h w yyy,,,Z

(,W N =A iz OR TOP/FUEL RACK EL. 819'-84{

ME' SKDNNER SURG£ TANK UNIT #1 SPENT FUEL STORAGE POOL TOP/FUEL RACK EL 819'-5W DLk 7

a CL EFFECTIVE BOTTOM r

TRANSFER CANAL

-EL. 819'-8r EL 874 LEVEL EL 8301-O' LEVEL LEVEL PROBE KDNNER SURGE TANK 5'-3 O(A.

EL 816'-51 S-1 TO FG PUMPS EL. 818'-fr TO FC PUMPS 344' UNIT 11 UNIT 12 34'-8' ELEVATION VIEW Response to Request for Additional Information (Order EA-12-0S1)

Page 3 of 12

+

FlOOR a.. 843'-6' SKINtiER SURCE TANK RMIL WAlUl LEVEL EL. 842'-6' UNIT #1 SPENT FUEL STORAGE POOL LEVEl:

PROIlE 0:

Ow Vl(!l

~z

~' ** f

'-14.1;

,..,,"~

EL 8+2'-1' lEVEL 1

~~f~~4; LEVEL PROBE f!:

~~

CflMoIL ~lUl LEVEL EL. 842'-6' EL 842'-1*

LEVEL 1 UNIT #2 SPENT FUEL STORAGE POOL

'~I!I)~

7cliz

~~~ I I a.. 8]l'-0' LEVEL 2

! I

    • I~~
';.J,..

r-lIJz

,I >....

t'l ~"

!.oJ TOP/fUEL RACK EL B19'-5¥t

'f!:

x::l

~~

~"

I u

I 4

~

~1 EFFECTIVE SOITOI.!

TMlSrER oow.

EL 819'~~'

EL 620'-0' LEVEL 5 UNIT #1 I UNIT #2 ELEVATION VIEW

'0:

x:J

~

~~

TOP/fUEL RACK EL, 8l9'-Sf,'

I.

~~

J S'-1' K!lINER SURGE TANK

Response to Request for Additional Information (Order EA-12-051)

Page 4 of 12 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The OIP states, in part, that:

The plan is to install SFP level sensors in the southeast corner of the Unit 1 SFP and in the northeast corner of the Unit 2 SFP; separated by a distance of approximately 103 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB

[Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services.

RAI-2

Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.

Response

Please reference the attached sketch provided in the response for RAI-1 for dimensions and proposed placement of primary and backup level sensors. Note that the locations of the level sensors have changed since the submittal of the overall integrated plan. Please reference the sketches below for proposed cable routing.

Response to Request for Additional Information (Order EA-12-0S1)

Page 4 of 12 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The 01 P states, in part, that:

The plan is to install SFP level sensors in the southeast corner of the Unit 1 SFP and in the northeast corner of the Unit 2 SFP; separated by a distance of approximately 103 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB

[Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services.

Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.

Response

Please reference the attached sketch provided in the response for RAI-1 for dimensions and proposed placement of primary and backup level sensors. Note that the locations of the level sensors have changed since the submittal of the overall integrated plan. Please reference the sketches below for proposed cable routing.

Response to Request for Additional Information (Order EA-1 2-051)

Page 5 of 12 17'-10Y2' EXIST. 2" EMBEDED CONDUIT TO BE USED FOR ROUTING Of NEW PROBE CAUX 2FC301 2LE-FtB43A-^

MEOW PRCAOSEo 4' CURB PLAN VIEW REFUEL FLOOR EL. 843`-67 Response to Request for Additional Information (Order EA-12-051)

Page 5 of 12 l'-10h'

~

l 1+

2~"-iI' 1l'-lh*

!I~

~ ----- -------

+-----------11---

I i

Ii I

I

-l-----------,-----

I I

27"-11" 17'-1"""-

1 I

1 I

l1' EXIST. 'Z D.tIlEDED

,EXIST. Z' EMBEDEI> pi CONDVIT 'TO BE I,Ism CONDUIT 'TO BE USED J

FOR ROIJllNC OF NEl't' I fOR ROUTING Of'" N f.W

\\

PROOE c;.osLE 1 FC.'l8 I PROBE c\\1lI.E 2FC3~1

'LE-FeIl13A 2LE-FOIl-h1'l ItllfftoSED

~:II~OSED f CURB (TYP.)

I,

I,

I,


r--------

TRANSFER CANNPL I

SHIPPING CASK STOAAGE AREA

---1---

I lRANSFER CANNA!.

8 PlAN VIEW REFUEL FLOOR EL.

B43'-6~

28"4

!I~

'10-I

--I

~----------

I I

,roW'l

/

I I 1/'

I I

I 1

I


1 3L~-'

I;,

I a, I :..

'Ii>,

i!>

F

'I/A"""""'

D

Response to Request for Additional Information (Order EA-12-051)

Page 6 of 12 3.3 Mounting The OIP states, in part, that:

Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Installed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.

RAI-3

Please provide the following:

a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.

b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical connections.

c) A description of the manner by which the mechanical connections will attach the level instrument to permanent SFP structures so as to support the level sensor assembly.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.4 Qualification The OIP states, in part, that:

Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:

components are supplied by manufacturers using commercial quality programs (such as ISO9001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; and/or Response to Request for Additional Information (Order EA-12-0S1)

Page 6 of 12 3.3 Mounting The 01 P states, in part, that:

Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Installed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.

Please provide the following:

a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.

b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical connections.

c) A description of the manner by which the mechanical connections will attach the level instrument to permanent SFP structures so as to support the level sensor assembly.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.4 Qualification The 01 P states, in part, that:

Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:

components are supplied by manufacturers using commercial quality programs (such as IS09001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; and/or

Response to Request for Additional Information (Order EA-1 2-051)

Page 7 of 12 components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; and/or components are inherently resistant to shock and vibration loadings, such as cables.

For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:...

RAI-4

Please provide the following:

a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.

b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.

c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.5 Independence The OIP states, in part, that:

Response to Request for Additional Information (Order EA-12-0S1)

Page 7 of 12 components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; and/or components are inherently resistant to shock and vibration loadings, such as cables.

For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:...

Please provide the following:

a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.

b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.

c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.5 Independence The OIP states, in part, that:

Response to Request for Additional Information (Order EA-12-051)

Page 8 of 12 The primary instrument channel will be independent of the backup instrument channel.

This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.

RAI-5

Please provide the following:

a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.

b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.6 Power supplies The OIP states, in part, that:

Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049. Additionally, each channel will have provisions for connection to another suitable power source.

RAI-6

Please provide the following:

a) A description of the electrical ac power sources and capacities for the primary and backup channels.

b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the Response to Request for Additional Information (Order EA-12-0S1)

Page 8 of 12 The primary instrument channel will be independent of the backup instrument channel.

This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.

Please provide the following:

a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.

b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.6 Power supplies The 01 P states, in part, that:

Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049. Additionally, each channel will have provisions for connection to another suitable power source.

Please provide the following:

a) A description of the electrical ac power sources and capacities for the primary and backup channels.

b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the

Response to Request for Additional Information (Order EA-12-051)

Page 9 of 12 c) beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.7 Accuracy The OIP states, in part, that:

The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.

RAI-7

Please provide the following:

a) An estimate of the expected instrument channel accuracy performance under both (a) normal SFP level conditions (approximately Level 1 or higher) and (b) at the beyond design-basis conditions (i.e., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the Level 2 and Level 3 datum points.

b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

Response to Request for Additional Information (Order EA-12-051)

Page 9 of 12 c) beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

3.7 Accuracy The DIP states, in part, that:

The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.

Please provide the following:

a) An estimate of the expected instrument channel accuracy performance under both (a) normal SFP level conditions (approximately Level 1 or higher) and (b) at the beyond design-basis conditions (Le., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the Level 2 and Level 3 datum points.

b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

Response to Request for Additional Information (Order EA-12-051)

Page 10 of 12 3.8 Testing The OIP states, in part, that:

Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 and NEI 12-02. Details will be determined during detailed design engineering.

RAI-8

Please provide the following:

a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.

b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation, c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.

d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.

3.9 Display The OIP states, in part, that:

The primary and backup instrument displays will be located at the control room, remote shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design.

Response to Request for Additional Information (Order EA-12-0S1)

Page 10 of 12 3.8 Testing The 01 P states, in part, that:

Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 and NEI12-02. Details will be determined during detailed design engineering.

Please provide the following:

a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.

b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation.

c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.

d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.

3.9 Display The OIP states, in part, that:

The primary and backup instrument displays will be located at the control room, remote shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design.

Response to Request for Additional Information (Order EA-12-051)

Page 11 of 12

RAI-9

Please provide the following:

a) The specific location for each of the primary and backup instrument channel displays.

b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.

c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

4.0 PROGRAM FEATURES 4.2 Procedures The OIP states, in part, that:

Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.

RAI-10

Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.

Response to Request for Additional Information (Order EA-12-0S1)

Page 11 of 12 Please provide the following:

a) The specific location for each of the primary and backup instrument channel displays.

b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.

c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. The requested information will be provided in the February 2014, 6-month Integrated Plan Update.

4.0 PROGRAM FEATURES 4.2 Procedures The DIP states, in part, that:

RAI-10

Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.

Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.

Response to Request for Additional Information (Order EA-12-051)

Page 12 of 12 4.3 Testing and Calibration The OI P states, in part, that:

Processes shall be established and maintained for scheduling and implementing necessary testing and calibration of the primary and backup SFP level instrument channels to maintain the instrument channels at the design accuracy. The testing and calibration of the instrumentation shall be consistent with vendor recommendations or other documented basis. Calibration shall be specific to the mounted instrument and the monitor.

Surveillances or testing to validate functionality of an installed instrument channel shall be performed within 60 days of a planned refueling outage considering normal testing scheduling allowances (e.g., 25%). This is not required to be performed more than once per 12 months.

RAI-11

Please provide the following:

a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.

b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.

c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.

Response to Request for Additional I nformation (Order EA-12-051)

Page 12 of 12 4.3 Testing and Calibration The OIP states, in part, that:

RAI-11

Processes shall be established and maintained for scheduling and implementing necessary testing and calibration of the primary and backup SFP level instrument channels to maintain the instrument channels at the design accuracy. The testing and calibration of the instrumentation shall be consistent with vendor recommendations or other documented basis. Calibration shall be specific to the mounted instrument and the monitor.

Surveillances or testing to validate functionality of an installed instrument channel shall be performed within 60 days of a planned refueling outage considering normal testing scheduling allowances (e.g., 25%). This is not required to be performed more than once per 12 months.

Please provide the following:

a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.

b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.

c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.

Response

The current plan for the SFPI deSign of the system based on the current Exelon Nuclear program schedule for LaSalle started the design phase in June of 2013 with design completion and 100% acceptance of the design in January 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan Update.