ML17355A561: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 15: Line 15:
| page count = 13
| page count = 13
}}
}}
See also: [[see also::IR 05000454/2017009]]
See also: [[followed by::IR 05000454/2017009]]


=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES  
                            NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION  
                                                REGION III
REGION III  
                                    2443 WARRENVILLE RD. SUITE 210
2443 WARRENVILLE RD. SUITE 210  
                                      LISLE, ILLINOIS 60532-4352
LISLE, ILLINOIS 60532-4352  
                                        December 21, 2017
EA-17-138
December 21, 2017  
Mr. Bryan C. Hanson
EA-17-138  
Senior VP, Exelon Generation Company, LLC
Mr. Bryan C. Hanson  
President and CNO, Exelon Nuclear
Senior VP, Exelon Generation Company, LLC  
4300 Winfield Road
President and CNO, Exelon Nuclear  
Warrenville, IL 60555
4300 Winfield Road  
SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION DOCUMENTED IN BYRON
Warrenville, IL 60555  
              STATION, UNITS 1 AND 2EVALUATIONS OF CHANGES, TESTS, AND
SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION DOCUMENTED IN BYRON  
              EXPERIMENTS BASELINE INSPECTION REPORT 05000454/2017009;
STATION, UNITS 1 AND 2EVALUATIONS OF CHANGES, TESTS, AND  
              05000455/2017009
EXPERIMENTS BASELINE INSPECTION REPORT 05000454/2017009;  
Dear Mr. Hanson:
05000455/2017009  
On July 31, 2017, Exelon Generation Company (EGC), LLC, provided a written response to
Dear Mr. Hanson:  
the U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000454/2017009;
On July 31, 2017, Exelon Generation Company (EGC), LLC, provided a written response to  
05000455/2017009 issued on June 29, 2017, concerning an Evaluations of Changes, Tests,
the U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000454/2017009;  
and Experiments Inspection completed at Byron Station, Units 1 and 2. Specifically, the
05000455/2017009 issued on June 29, 2017, concerning an Evaluations of Changes, Tests,  
letter contested Non-Cited Violation (NCV) 05000454/2017009-01; 05000455/2017009-01
and Experiments Inspection completed at Byron Station, Units 1 and 2. Specifically, the  
associated with the failure to perform an evaluation of a change to the facility as described in
letter contested Non-Cited Violation (NCV) 05000454/2017009-01; 05000455/2017009-01  
the Updated Final Safety Analysis Report (UFSAR) pursuant to Title 10 of the Code of Federal
associated with the failure to perform an evaluation of a change to the facility as described in  
Regulations (CFR), Part 50.59(d)(1). The letter explained that EGC concluded that a
the Updated Final Safety Analysis Report (UFSAR) pursuant to Title 10 of the Code of Federal  
10 CFR 50.59(d)(1) evaluation was not required because the UFSAR change satisfied the
Regulations (CFR), Part 50.59(d)(1). The letter explained that EGC concluded that a  
10 CFR 50.59(c)(4) exemption.
10 CFR 50.59(d)(1) evaluation was not required because the UFSAR change satisfied the  
The NRC carefully reviewed EGCs reply and determined that the original enforcement
10 CFR 50.59(c)(4) exemption.  
decision to disposition this issue as a violation of 10 CFR 50.59(d)(1) was valid. Specifically,
The NRC carefully reviewed EGCs reply and determined that the original enforcement  
the NRC-approved Surveillance Frequency Control Program recognizes 10 CFR 50.59 to be the
decision to disposition this issue as a violation of 10 CFR 50.59(d)(1) was valid. Specifically,  
governing change control process for any proposed change to UFSAR commitments associated
the NRC-approved Surveillance Frequency Control Program recognizes 10 CFR 50.59 to be the  
with codes and standards. This handling of changes to UFSAR commitments is deliberately
governing change control process for any proposed change to UFSAR commitments associated  
distinct and separate from the Surveillance Frequency Control Program in order to maintain
with codes and standards. This handling of changes to UFSAR commitments is deliberately  
sufficient safety margin by ensuring the proposed surveillance test frequency change is not in
distinct and separate from the Surveillance Frequency Control Program in order to maintain  
conflict with approved industry codes and standards. In addition, the NRC staff noted that the
sufficient safety margin by ensuring the proposed surveillance test frequency change is not in  
contrary to the above paragraph of the Enforcement Section of NCV 05000454/2017009-01;
conflict with approved industry codes and standards. In addition, the NRC staff noted that the  
05000455/2017009-01 included an explanatory statement that was open to interpretation.
contrary to the above paragraph of the Enforcement Section of NCV 05000454/2017009-01;  
Based on a review of licensee documents associated with the disputed NCV, the NRC staff
05000455/2017009-01 included an explanatory statement that was open to interpretation.
determined that the intended message of the explanatory statement was consistent with the
Based on a review of licensee documents associated with the disputed NCV, the NRC staff  
NRC staff conclusions derived during this review of the disputed NCV. The basis for the NRC
determined that the intended message of the explanatory statement was consistent with the  
staff conclusion is enclosed.
NRC staff conclusions derived during this review of the disputed NCV. The basis for the NRC  
staff conclusion is enclosed.  


B. Hanson                                   -2-
B. Hanson  
This letter, its enclosure, EGCs July 31, 2017, response, and your response (if any) will be
-2-  
made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html
This letter, its enclosure, EGCs July 31, 2017, response, and your response (if any) will be  
and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections,
made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html  
Exemptions, Requests for Withholding.
and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections,  
                                              Sincerely,
Exemptions, Requests for Withholding.  
                                              /RA/
Sincerely,  
                                              Kenneth G. OBrien
                                              Deputy Regional Administrator
/RA/  
Docket Nos. 50-454; 50-455
License Nos. NPF-37; NPF-66
Enclosure:
Kenneth G. OBrien  
NRC Staff Assessment of Disputed
Deputy Regional Administrator  
NCV 05000454/2017009-01;
Docket Nos. 50-454; 50-455  
NCV 05000455/2017009-01
License Nos. NPF-37; NPF-66  
cc: Distribution via LISTSERV
Enclosure:  
NRC Staff Assessment of Disputed  
  NCV 05000454/2017009-01;  
  NCV 05000455/2017009-01  
cc: Distribution via LISTSERV  


B. Hanson                               -3-
B. Hanson  
Letter to Byron C. Hanson from Kenneth G. OBrien dated December 21, 2017
-3-  
SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION DOCUMENTED IN BYRON
Letter to Byron C. Hanson from Kenneth G. OBrien dated December 21, 2017  
            STATION, UNITS 1 AND 2EVALUATIONS OF CHANGES, TESTS, AND
SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION DOCUMENTED IN BYRON  
            EXPERIMENTS BASELINE INSPECTION REPORT 05000454/2017009;
STATION, UNITS 1 AND 2EVALUATIONS OF CHANGES, TESTS, AND  
            05000455/2017009
EXPERIMENTS BASELINE INSPECTION REPORT 05000454/2017009;  
DISTRIBUTION:
05000455/2017009  
Jeremy Bowen
DISTRIBUTION:  
RidsNrrDorlLpl3
Jeremy Bowen  
RidsNrrPMByron Resource
RidsNrrDorlLpl3  
RidsNrrDirsIrib Resource
RidsNrrPMByron Resource  
Cynthia Pederson
RidsNrrDirsIrib Resource  
Steven West
Cynthia Pederson  
Kenneth OBrien
Steven West  
Richard Skokowski
Kenneth OBrien  
Allan Barker
Richard Skokowski  
Carole Ariano
Allan Barker  
Linda Linn
Carole Ariano  
DRPIII
Linda Linn  
DRSIII
DRPIII  
ADAMS Accession Number ML17355A561
DRSIII  
  OFFICE RIII                   RIII               RIII               RIII
  NAME       MJeffers for      MJeffers           JGeisner for       KOBrien
              NFeliz-Adorno:cl                     RSkokowski
  DATE       12/21/17           12/21/17           12/21/17           12/21/17
                                OFFICIAL RECORD COPY
ADAMS Accession Number ML17355A561  
OFFICE  
RIII  
RIII  
RIII  
RIII  
NAME  
MJeffers for  
NFeliz-Adorno:cl  
MJeffers
JGeisner for
RSkokowski  
KOBrien
DATE  
12/21/17  
12/21/17  
12/21/17  
12/21/17  
OFFICIAL RECORD COPY  


                            NRC STAFF ASSESSMENT OF DISPUTED
                        NCV 05000454/2017009-01; 05000455/2017009-01
Enclosure
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the information provided in
NRC STAFF ASSESSMENT OF DISPUTED  
Exelon Generation Company (EGC) letter dated July 31, 2017, to determine whether Non-Cited
NCV 05000454/2017009-01; 05000455/2017009-01  
Violation (NCV) 05000454/2017009-01; 05000455/2017009-01 was valid. This review was
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the information provided in  
performed by an NRC staff member having relevant regulatory knowledge and who did not
Exelon Generation Company (EGC) letter dated July 31, 2017, to determine whether Non-Cited  
participate in the inspection documented in Inspection Report 05000454/2017009;
Violation (NCV) 05000454/2017009-01; 05000455/2017009-01 was valid. This review was  
05000455/2017009, which dispositioned the disputed violation. The NRC staff referenced
performed by an NRC staff member having relevant regulatory knowledge and who did not  
several documents that are listed in the Reference Section of this Enclosure and consulted
participate in the inspection documented in Inspection Report 05000454/2017009;  
with other NRC staff members that were independent from the original enforcement decision,
05000455/2017009, which dispositioned the disputed violation. The NRC staff referenced  
including members of the Office of Nuclear Reactor Regulation.
several documents that are listed in the Reference Section of this Enclosure and consulted  
1.     BACKGROUND
with other NRC staff members that were independent from the original enforcement decision,  
        On June 29, 2017, the NRC issued Inspection Report 05000454/2017009;
including members of the Office of Nuclear Reactor Regulation.  
        05000455/2017009 documenting the results of an Evaluations of Changes, Tests,
1.  
        and Experiments Inspection at Byron Station, Units 1 and 2. The report included a
BACKGROUND  
        SL-IV violation of Title 10 of the Code of Federal Regulations (CFR), Part 50.59(d)(1) for
On June 29, 2017, the NRC issued Inspection Report 05000454/2017009;  
        the failure to provide a written evaluation which provided the basis for the determination
05000455/2017009 documenting the results of an Evaluations of Changes, Tests,  
        that a change did not require a license amendment. The violation was associated with a
and Experiments Inspection at Byron Station, Units 1 and 2. The report included a  
        change to a Updated Final Safety Analysis Report (UFSAR) commitment related to the
SL-IV violation of Title 10 of the Code of Federal Regulations (CFR), Part 50.59(d)(1) for  
        emergency diesel generators (EDGs) made in support of surveillance frequency (SF)
the failure to provide a written evaluation which provided the basis for the determination  
        changes evaluated under the Byron Station SF Control Program (SFCP). This violation
that a change did not require a license amendment. The violation was associated with a  
        was dispositioned as NCV 05000454/2017009-01; 05000455/2017009-01.
change to a Updated Final Safety Analysis Report (UFSAR) commitment related to the  
        On July 31, 2017, EGC provided a written response to the NRC contesting the
emergency diesel generators (EDGs) made in support of surveillance frequency (SF)  
        enforcement decision associated with NCV 05000454/2017009-01; 05000455/
changes evaluated under the Byron Station SF Control Program (SFCP). This violation  
        2017009-01. In the letter, EGC explained that a 10 CFR 50.59(d)(1) evaluation
was dispositioned as NCV 05000454/2017009-01; 05000455/2017009-01.  
        was not required because the associated change to the UFSAR satisfied the
On July 31, 2017, EGC provided a written response to the NRC contesting the  
        10 CFR 50.59(c)(4) exemption.
enforcement decision associated with NCV 05000454/2017009-01; 05000455/  
2.     ORIGINAL ENFORCEMENT DECISION
2017009-01. In the letter, EGC explained that a 10 CFR 50.59(d)(1) evaluation  
        Inspection Report 05000454/2017009; 05000455/2017009 described the violation as:
was not required because the associated change to the UFSAR satisfied the  
            Title 10 CFR 50.59, Changes, Tests, and Experiments, Section (d)(1) requires
10 CFR 50.59(c)(4) exemption.  
            the licensee to maintain records of changes in the facility, of changes in
2.  
            procedures, and of tests and experiments made pursuant to 10 CFR 50.59(c).
ORIGINAL ENFORCEMENT DECISION  
            Title 10 CFR 50.59(d)(1) requires that these records include a written evaluation
Inspection Report 05000454/2017009; 05000455/2017009 described the violation as:  
            which provides the basis for the determination that a change, test, or experiment did
Title 10 CFR 50.59, Changes, Tests, and Experiments, Section (d)(1) requires  
            not require a license amendment. Title 10 CFR 50.59(c)(2) requires a licensee to
the licensee to maintain records of changes in the facility, of changes in  
            obtain a license amendment prior to implementing a proposed change, test, or
procedures, and of tests and experiments made pursuant to 10 CFR 50.59(c).
            experiment if the change, test, or experiment would result in more than a minimal
Title 10 CFR 50.59(d)(1) requires that these records include a written evaluation  
            increase in the likelihood of occurrence of a malfunction of an SSC [structure,
which provides the basis for the determination that a change, test, or experiment did  
            system, or component] important to safety.
not require a license amendment. Title 10 CFR 50.59(c)(2) requires a licensee to  
            Contrary to the above, between February 14, 2014, and June 1, 2017, the licensee
obtain a license amendment prior to implementing a proposed change, test, or  
            failed to provide a written evaluation which provided the basis for determining that a
experiment if the change, test, or experiment would result in more than a minimal  
            change, test, or experiment made pursuant to 10 CFR 50.59(c) did not require a
increase in the likelihood of occurrence of a malfunction of an SSC [structure,  
            license amendment. Specifically, the licensee failed to provide a basis for why a
system, or component] important to safety.  
            change to the surveillance frequencies of EDGs described in the Updated Final
Contrary to the above, between February 14, 2014, and June 1, 2017, the licensee  
                                                                                          Enclosure
failed to provide a written evaluation which provided the basis for determining that a  
change, test, or experiment made pursuant to 10 CFR 50.59(c) did not require a  
license amendment. Specifically, the licensee failed to provide a basis for why a  
change to the surveillance frequencies of EDGs described in the Updated Final  


        Safety Analysis Report did not require prior NRC approval. The licensee did not
        provide a basis for why the change would not result in more than a minimal increase
2
        in the likelihood of occurrence of a malfunction of an SSC important to safety.
Safety Analysis Report did not require prior NRC approval. The licensee did not  
3. LICENSEE POSITION
provide a basis for why the change would not result in more than a minimal increase  
  In letter dated July 31, 2017, EGC concluded that UFSAR changes associated with
in the likelihood of occurrence of a malfunction of an SSC important to safety.  
  SF changes performed in accordance with an NRC-approved SFCP are not subject to
3.  
  10 CFR 50.59(d)(1) evaluations because these changes satisfy 10 CFR 50.59(c)(4),
LICENSEE POSITION  
  which states that the requirements of 10 CFR 50.59 do not apply to changes to the
In letter dated July 31, 2017, EGC concluded that UFSAR changes associated with  
  facility or procedures when the applicable regulations establish more specific criteria for
SF changes performed in accordance with an NRC-approved SFCP are not subject to  
  accomplishing such changes. In summary, the bases for EGCs position included:
10 CFR 50.59(d)(1) evaluations because these changes satisfy 10 CFR 50.59(c)(4),  
  1. The NRC-approved the use of Revision 1 of Nuclear Energy Institute (NEI) Topical
which states that the requirements of 10 CFR 50.59 do not apply to changes to the  
        Report 04-10, Risk-Informed Method for Control of Surveillance Frequencies, to
facility or procedures when the applicable regulations establish more specific criteria for  
        identify, assess, implement, and monitor changes to the SFs listed in Byron Station
accomplishing such changes. In summary, the bases for EGCs position included:  
        SFCP.
1. The NRC-approved the use of Revision 1 of Nuclear Energy Institute (NEI) Topical  
  2. The NEI 04-10 process became a regulatory requirement because it was
Report 04-10, Risk-Informed Method for Control of Surveillance Frequencies, to  
        incorporated in the Administrative Controls section of Byron Station Technical
identify, assess, implement, and monitor changes to the SFs listed in Byron Station  
        Specifications (TS).
SFCP.  
  3. The NEI 04-10 process applies more specific criteria than 10 CFR 50.59 to evaluate
2. The NEI 04-10 process became a regulatory requirement because it was  
        SF changes.
incorporated in the Administrative Controls section of Byron Station Technical  
  4. The NEI 04-10 methodology evaluates all aspects of the current licensing basis
Specifications (TS).  
        (CLB), including the UFSAR and industry codes/standards insights and compliance,
3. The NEI 04-10 process applies more specific criteria than 10 CFR 50.59 to evaluate  
        because TS requirements are inextricably linked to the rest of the CLB.
SF changes.  
4. NRC STAFF REVIEW
4. The NEI 04-10 methodology evaluates all aspects of the current licensing basis  
  The NRC staff carefully reviewed the EGC position as it applied to the specific
(CLB), including the UFSAR and industry codes/standards insights and compliance,  
  circumstances surrounding NCV 05000454/2017009-01; 05000455/2017009-01 as
because TS requirements are inextricably linked to the rest of the CLB.  
  follows:
4.  
  1. NRC Approval of NEI 04-10, Revision 1
NRC STAFF REVIEW  
        During this review, the NRC staff confirmed that Revision 1 of NEI 04-10
The NRC staff carefully reviewed the EGC position as it applied to the specific  
        was approved by the NRC to revise SFs within a licensee-controlled SFCP.
circumstances surrounding NCV 05000454/2017009-01; 05000455/2017009-01 as  
        Specifically, NRC Final Safety Evaluation (SE) for Revision 1 of NEI 04-10, dated
follows:  
        September 19, 2007, states The NRC staff has found that NEI 04-10, Revision 1, is
1. NRC Approval of NEI 04-10, Revision 1  
        acceptable for referencing by licensees proposing to amend their TS to establish a
During this review, the NRC staff confirmed that Revision 1 of NEI 04-10  
        Surveillance Frequency Control Program, to the extent specified and under the
was approved by the NRC to revise SFs within a licensee-controlled SFCP.
        limitations delineated in NEI 04-10, Revision 1, and in the enclosed final SE.
Specifically, NRC Final Safety Evaluation (SE) for Revision 1 of NEI 04-10, dated  
        In addition, the NRC staff confirmed that the NRC approved a TS amendment to
September 19, 2007, states The NRC staff has found that NEI 04-10, Revision 1, is  
        establish a SFCP based on the methodology contained in Revision 1 of NEI 04-10
acceptable for referencing by licensees proposing to amend their TS to establish a  
        for Byron Station. Specifically, NRC SE for Byron Station Amendment No. 171,
Surveillance Frequency Control Program, to the extent specified and under the  
        dated February 24, 2011, states This methodology supports relocating surveillance
limitations delineated in NEI 04-10, Revision 1, and in the enclosed final SE.  
        frequencies from TS to a licensee-controlled document, provided those frequencies
In addition, the NRC staff confirmed that the NRC approved a TS amendment to  
        are changed in accordance with NEI 04-10, Revision 1, which is specified in the
establish a SFCP based on the methodology contained in Revision 1 of NEI 04-10  
        Administrative Controls of the TSs.
for Byron Station. Specifically, NRC SE for Byron Station Amendment No. 171,  
                                              2
dated February 24, 2011, states This methodology supports relocating surveillance  
frequencies from TS to a licensee-controlled document, provided those frequencies  
are changed in accordance with NEI 04-10, Revision 1, which is specified in the  
Administrative Controls of the TSs.  


  As a result of the above review, the NRC staff concluded that the NRC-approved
  Byron Stations establishment of a licensee-controlled SFCP provided SF changes
3
  are made in accordance with Revision 1 of NEI 04-10.
As a result of the above review, the NRC staff concluded that the NRC-approved  
2. Byron Station SFCP Relationship with Regulatory Requirements
Byron Stations establishment of a licensee-controlled SFCP provided SF changes  
  During this review, the NRC staff determined that the NRC-approved a TS
are made in accordance with Revision 1 of NEI 04-10.  
  amendment to include Byron Station SFCP in their TS. Specifically, NRC SE for
2. Byron Station SFCP Relationship with Regulatory Requirements  
  Byron Station Amendment No. 171 states Byron Station has included the SFCP
During this review, the NRC staff determined that the NRC-approved a TS  
  and specific requirements into the TSs, Section 5.5.19, Administrative Controls,
amendment to include Byron Station SFCP in their TS. Specifically, NRC SE for  
  Section 5.5.19, Surveillance Frequency Control Program, of Byron Station TS,
Byron Station Amendment No. 171 states Byron Station has included the SFCP  
  Amendment 171, was added to state:
and specific requirements into the TSs, Section 5.5.19, Administrative Controls,
        This program provides controls for Surveillance Frequencies. The program shall
Section 5.5.19, Surveillance Frequency Control Program, of Byron Station TS,  
        ensure that Surveillance Requirements specified in the Technical Specifications
Amendment 171, was added to state:  
        are performed at intervals sufficient to assure the associated Limiting Conditions
This program provides controls for Surveillance Frequencies. The program shall  
        for Operation are met.
ensure that Surveillance Requirements specified in the Technical Specifications  
        a. The SFCP shall contain a list of Frequencies of those Surveillance
are performed at intervals sufficient to assure the associated Limiting Conditions  
            Requirements for which the Frequency is controlled by the program.
for Operation are met.  
        b. Changes to the Frequencies listed in the SFCP shall be made in
a. The SFCP shall contain a list of Frequencies of those Surveillance  
            accordance with NEI 04-10, Risk-Informed Method for Control of
Requirements for which the Frequency is controlled by the program.  
            Surveillance Frequencies, Revision 1 [emphasis added].
b. Changes to the Frequencies listed in the SFCP shall be made in  
        c. The provisions of Surveillance Requirements 3.0.2 and 3.0.3 are applicable
accordance with NEI 04-10, Risk-Informed Method for Control of  
            to the Frequencies established in the SFCP.
Surveillance Frequencies, Revision 1 [emphasis added].  
  Furthermore, the NRC staff determined that TS 5.5.19 is a legally binding
c. The provisions of Surveillance Requirements 3.0.2 and 3.0.3 are applicable  
  requirement because it was incorporated into the Administrative Controls
to the Frequencies established in the SFCP.  
  section of TS. Compliance to TS is required as a license condition. Specifically,
Furthermore, the NRC staff determined that TS 5.5.19 is a legally binding  
  Section 2.C(2) of Byron Station Renewed Facility Operating License No. NPF-37
requirement because it was incorporated into the Administrative Controls  
  states The licensee shall operate the facility in accordance with the TS and the
section of TS. Compliance to TS is required as a license condition. Specifically,  
  Environmental Protection Plan. In addition, the NRC Enforcement Policy, dated
Section 2.C(2) of Byron Station Renewed Facility Operating License No. NPF-37  
  November 1, 2016, states Requirement, as used in this Policy, means a
states The licensee shall operate the facility in accordance with the TS and the  
  legally binding requirement such as a statute, regulation, license condition,
Environmental Protection Plan. In addition, the NRC Enforcement Policy, dated  
  TS [emphasis added], or Order. Similar definitions were found in the NRC
November 1, 2016, states Requirement, as used in this Policy, means a  
  Enforcement Manual, Revision 10, and Office of Nuclear Reactor Regulations Office
legally binding requirement such as a statute, regulation, license condition,  
  Instruction LIC-105, Managing Regulatory Commitments Made by Licensees to the
TS [emphasis added], or Order. Similar definitions were found in the NRC  
  NRC, Revision 7 (publicly available).
Enforcement Manual, Revision 10, and Office of Nuclear Reactor Regulations Office  
  As a result of the above review, the NRC staff concluded that changing SFs listed in
Instruction LIC-105, Managing Regulatory Commitments Made by Licensees to the  
  the SFCP in accordance with Revision 1 of NEI 04-10 was compliant with Byron
NRC, Revision 7 (publicly available).  
  Station TS 5.5.19, Amendment 171, which was a legally binding requirement.
As a result of the above review, the NRC staff concluded that changing SFs listed in  
3. NEI 04-10 Change Process and the 10 CFR 50.59(c)(4) Exemption
the SFCP in accordance with Revision 1 of NEI 04-10 was compliant with Byron  
  During this review, the NRC staff noted that the scope of the 10 CFR 50.59
Station TS 5.5.19, Amendment 171, which was a legally binding requirement.  
  obligation, which is further clarified by the definitions included therein, is limited to
3. NEI 04-10 Change Process and the 10 CFR 50.59(c)(4) Exemption  
  the facility and procedures as described in the UFSAR [emphasis added]. For
During this review, the NRC staff noted that the scope of the 10 CFR 50.59  
  example, Paragraph (c)(1) of the obligation states A licensee may make changes
obligation, which is further clarified by the definitions included therein, is limited to  
  in the facility as described in the final FSAR [Final Safety Analysis Report] (as
the facility and procedures as described in the UFSAR [emphasis added]. For  
                                          3
example, Paragraph (c)(1) of the obligation states A licensee may make changes  
in the facility as described in the final FSAR [Final Safety Analysis Report] (as  


updated) [emphasis added], make changes in the procedures as described in
the FSAR (as updated) [emphasis added], and conduct tests or experiments not
4
described in the FSAR (as updated) [emphasis added] The definition of
updated) [emphasis added], make changes in the procedures as described in  
tests or experiments not described in the FSAR (as updated) [emphasis added]
the FSAR (as updated) [emphasis added], and conduct tests or experiments not  
contained in 10 CFR 50.59(a)(6) was based on design bases and safety analyses as
described in the FSAR (as updated) [emphasis added] The definition of  
described in the FSAR (as updated) [emphasis added]. In the specific case of
tests or experiments not described in the FSAR (as updated) [emphasis added]  
NCV 05000454/2017009-01; 05000455/2017009-01, the SF changes themselves
contained in 10 CFR 50.59(a)(6) was based on design bases and safety analyses as  
were not changes to the facility or procedures as described in the UFSAR. Thus, the
described in the FSAR (as updated) [emphasis added]. In the specific case of  
10 CFR 50.59 obligation did not apply, including the 10 CFR 50.59(c)(4) exemption.
NCV 05000454/2017009-01; 05000455/2017009-01, the SF changes themselves  
Instead, Byron Station TS 5.5.19, Amendment 171, requires Revision 1 of NEI 04-10
were not changes to the facility or procedures as described in the UFSAR. Thus, the  
as the governing change process for the SF changes involved in the disputed
10 CFR 50.59 obligation did not apply, including the 10 CFR 50.59(c)(4) exemption.
violation, consistent with the conclusion of Section 4.2 of this Enclosure.
Instead, Byron Station TS 5.5.19, Amendment 171, requires Revision 1 of NEI 04-10  
However, the NRC staff noted that TS 5.5.19, Amendment 171, requires Revision 1
as the governing change process for the SF changes involved in the disputed  
of NEI 04-10 as the governing change process only for SF changes [emphasis
violation, consistent with the conclusion of Section 4.2 of this Enclosure.  
added]. That is, this process is not specified as the governing change process to
However, the NRC staff noted that TS 5.5.19, Amendment 171, requires Revision 1  
evaluate changes to NRC commitments made in support of SF changes.
of NEI 04-10 as the governing change process only for SF changes [emphasis  
Specifically, Revision 1 of NEI 04-10, Step 1, requires checking for NRC
added]. That is, this process is not specified as the governing change process to  
commitments related to the proposed SF change. When commitments are
evaluate changes to NRC commitments made in support of SF changes.
identified, Steps 2 through 4 require changing the commitments using a method
Specifically, Revision 1 of NEI 04-10, Step 1, requires checking for NRC  
acceptable to the NRC prior to changing the SF if the commitments could be
commitments related to the proposed SF change. When commitments are  
changed. Alternatively, these steps require canceling the proposed SF change if the
identified, Steps 2 through 4 require changing the commitments using a method  
commitments could not be changed. The NRC staff further noted that these steps
acceptable to the NRC prior to changing the SF if the commitments could be  
were incorporated into the EGC SFCP procedures listed in the References Section
changed. Alternatively, these steps require canceling the proposed SF change if the  
of this Enclosure.
commitments could not be changed. The NRC staff further noted that these steps  
Revision 1 of NEI 04-10 emphasizes that Evaluating changes to the NRC
were incorporated into the EGC SFCP procedures listed in the References Section  
commitments is a separate activity based on a method acceptable to the NRC
of this Enclosure.  
for managing and changing regulatory commitments, e.g., NEI 99-04 [emphasis
Revision 1 of NEI 04-10 emphasizes that Evaluating changes to the NRC  
added]. The potential need to perform separate change evaluations is also
commitments is a separate activity based on a method acceptable to the NRC  
recognized by Revision 1 of NEI 96-07, Guidelines for 10 CFR 50.59
for managing and changing regulatory commitments, e.g., NEI 99-04 [emphasis  
Implementation, which was endorsed by the NRC as an acceptable method for
added]. The potential need to perform separate change evaluations is also  
complying with the provisions of 10 CFR 50.59 in Regulatory Guide (RG) 1.187,
recognized by Revision 1 of NEI 96-07, Guidelines for 10 CFR 50.59  
Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments,
Implementation, which was endorsed by the NRC as an acceptable method for  
dated November 2000. For example, it states To the extent the UFSAR changes
complying with the provisions of 10 CFR 50.59 in Regulatory Guide (RG) 1.187,  
are directly related to the activity implemented via another regulation, applying
Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments,  
10 CFR 50.59 is not required However, there may be certain activities for
dated November 2000. For example, it states To the extent the UFSAR changes  
which a licensee would need to apply both the requirements of 10 CFR 50.59
are directly related to the activity implemented via another regulation, applying  
and that of another regulation [emphasis added].
10 CFR 50.59 is not required However, there may be certain activities for  
Revision 1 of NEI 04-10 prompts the consideration for a separate 10 CFR 50.59
which a licensee would need to apply both the requirements of 10 CFR 50.59  
evaluation for NRC commitment changes associated with the proposed SF changes
and that of another regulation [emphasis added].  
by stating In Step 3, change the commitments using a method acceptable to the
Revision 1 of NEI 04-10 prompts the consideration for a separate 10 CFR 50.59  
NRC, e.g., NEI 99-04, such that the STI [surveillance test interval; aka., SFs] can
evaluation for NRC commitment changes associated with the proposed SF changes  
be revised using the SFCP process. Revision 0 of NEI 99-04, Guidelines for
by stating In Step 3, change the commitments using a method acceptable to the  
Managing NRC Commitment Changes, states Commitments that are embodied
NRC, e.g., NEI 99-04, such that the STI [surveillance test interval; aka., SFs] can  
in the UFSAR as descriptions of the facility or procedures are changed by
be revised using the SFCP process. Revision 0 of NEI 99-04, Guidelines for  
applying the provisions of 10 CFR 50.59 [emphasis added] to determine if a
Managing NRC Commitment Changes, states Commitments that are embodied  
change requiring prior NRC approval exists. NEI 99-04 defined commitment as
in the UFSAR as descriptions of the facility or procedures are changed by  
an explicit statement to take a specific action agreed to, or volunteered by, a
applying the provisions of 10 CFR 50.59 [emphasis added] to determine if a  
                                        4
change requiring prior NRC approval exists. NEI 99-04 defined commitment as  
an explicit statement to take a specific action agreed to, or volunteered by, a  


  licensee and submitted in writing on the docket to the NRC. In addition, Revision 1
  of EGC procedure ER-AA-425-1002, Step 4.5.2, states Examples of commitments
5
  within Exelon include but are not limited to the following UFSAR.
licensee and submitted in writing on the docket to the NRC. In addition, Revision 1  
  In the specific case of NCV 05000454/2017009-01; 05000455/2017009-01, the
of EGC procedure ER-AA-425-1002, Step 4.5.2, states Examples of commitments  
  licensee changed explicit statements embodied in the UFSAR in support of the
within Exelon include but are not limited to the following UFSAR.  
  involved SF changes. For instance, the UFSAR stated that Byron Station complied
In the specific case of NCV 05000454/2017009-01; 05000455/2017009-01, the  
  with Revision 3 of RG 1.9, Selection, Design, Qualification, and Testing of
licensee changed explicit statements embodied in the UFSAR in support of the  
  Diesel-Generator Units Used as Class 1E Onsite Electric Power Systems at Nuclear
involved SF changes. For instance, the UFSAR stated that Byron Station complied  
  Power Plants, which endorses Institute of Electrical and Electronic Engineers (IEEE)
with Revision 3 of RG 1.9, Selection, Design, Qualification, and Testing of  
  Standard 387-1984, IEEE Standard Criteria for Diesel-Generator Units Applied as
Diesel-Generator Units Used as Class 1E Onsite Electric Power Systems at Nuclear  
  Standby Power Supplies for Nuclear Power Generating Stations. Because these
Power Plants, which endorses Institute of Electrical and Electronic Engineers (IEEE)  
  statements were embodied in the UFSAR, they were submitted in writing on the
Standard 387-1984, IEEE Standard Criteria for Diesel-Generator Units Applied as  
  docket to the NRC in accordance with 10 CFR 50.71, Maintenance of records,
Standby Power Supplies for Nuclear Power Generating Stations. Because these  
  making of reports. Therefore, the NRC staff determined that these explicit
statements were embodied in the UFSAR, they were submitted in writing on the  
  statements were NRC commitments. In addition, the NRC staff noted that the
docket to the NRC in accordance with 10 CFR 50.71, Maintenance of records,  
  licensee recognized that these explicit statements were commitments in SFCP
making of reports. Therefore, the NRC staff determined that these explicit  
  evaluation BY-13-003, DG and Integrated Safeguards LOOP ESF Surveillance
statements were NRC commitments. In addition, the NRC staff noted that the  
  Test Surveillance Frequency STI Evaluation, Revision 0. For example, Section C.7
licensee recognized that these explicit statements were commitments in SFCP  
  states RG 1.9 to which Byron is committed to, with some exceptions, in the
evaluation BY-13-003, DG and Integrated Safeguards LOOP ESF Surveillance  
  UFSAR, Appendix A.
Test Surveillance Frequency STI Evaluation, Revision 0. For example, Section C.7  
  As a result of the above review, the NRC staff concluded that, in the case of
states RG 1.9 to which Byron is committed to, with some exceptions, in the  
  NCV 05000454/2017009-01; 05000455/2017009-01, the NEI 04-10 process was
UFSAR, Appendix A.  
  the governing change process for the subject SF changes while the 10 CFR 50.59
As a result of the above review, the NRC staff concluded that, in the case of  
  process was the governing change process for changing the UFSAR commitments
NCV 05000454/2017009-01; 05000455/2017009-01, the NEI 04-10 process was  
  made in support of the involved SF changes.
the governing change process for the subject SF changes while the 10 CFR 50.59  
4. NEI 04-10 Treatment of Codes and Standards Related to Proposed SF Changes
process was the governing change process for changing the UFSAR commitments  
  During this review, the NRC staff noted that the NRC SE for Byron Station
made in support of the involved SF changes.  
  Amendment No. 171 states that Revision 1 of NEI 04-10 was acceptable because, in
4. NEI 04-10 Treatment of Codes and Standards Related to Proposed SF Changes  
  part, it meets each key safety principle required for risk-informed changes to the TSs
During this review, the NRC staff noted that the NRC SE for Byron Station  
  identified in Revision 1 of RG 1.177, An Approach for Plant-Specific, Risk-Informed
Amendment No. 171 states that Revision 1 of NEI 04-10 was acceptable because, in  
  Decisionmaking: Technical Specifications. This RG describes an acceptable
part, it meets each key safety principle required for risk-informed changes to the TSs  
  approach for assessing the nature and impact of proposed TS changes in completion
identified in Revision 1 of RG 1.177, An Approach for Plant-Specific, Risk-Informed  
  times and SFs by considering engineering issues and applying risk insights. It states
Decisionmaking: Technical Specifications. This RG describes an acceptable  
  that In implementing risk-informed decisionmaking, TS changes are expected to
approach for assessing the nature and impact of proposed TS changes in completion  
  meet a set of key principles. Revision 2 of RG 1.174, An Approach for Using
times and SFs by considering engineering issues and applying risk insights. It states  
  Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes
that In implementing risk-informed decisionmaking, TS changes are expected to  
  to the Licensing Basis, which is referenced by RG 1.177, further clarified that One
meet a set of key principles. Revision 2 of RG 1.174, An Approach for Using  
  aspect of the engineering evaluations [conducted to justify any proposed CLB
Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes  
  change] is to show that the fundamental safety principles on which the plant design
to the Licensing Basis, which is referenced by RG 1.177, further clarified that One  
  was based are not compromised by the proposed change. This risk-informed
aspect of the engineering evaluations [conducted to justify any proposed CLB  
  approach to TS is consistent with the NRC general review guidance for TS
change] is to show that the fundamental safety principles on which the plant design  
  contained in Revision 1 of Section 16.1, Risk-Informed Decision Making: Technical
was based are not compromised by the proposed change. This risk-informed  
  Specifications, of NUREG-0800, Standard Review Plan for the Review of Safety
approach to TS is consistent with the NRC general review guidance for TS  
  Analysis Reports for Nuclear Power Plants: LWR EditionTechnical Specifications.
contained in Revision 1 of Section 16.1, Risk-Informed Decision Making: Technical  
                                        5
Specifications, of NUREG-0800, Standard Review Plan for the Review of Safety  
Analysis Reports for Nuclear Power Plants: LWR EditionTechnical Specifications.  


The third key safety principle identified by the RGs is that the proposed TS change
maintains sufficient safety margin. The RG 1.177 states that sufficient safety margin
6
is maintained when, in part, Codes and standards (e.g., American Society of
The third key safety principle identified by the RGs is that the proposed TS change  
Mechanical Engineers, Institute of Electrical and Electronic Engineers (IEEE)) or
maintains sufficient safety margin. The RG 1.177 states that sufficient safety margin  
alternatives approved for use by the NRC are met, (e.g., the proposed TS
is maintained when, in part, Codes and standards (e.g., American Society of  
completion time or SF change is not in conflict with approved codes and
Mechanical Engineers, Institute of Electrical and Electronic Engineers (IEEE)) or  
standards relevant to the subject system [emphasis added]). Accordingly, the
alternatives approved for use by the NRC are met, (e.g., the proposed TS  
NRC SE for Byron Station Amendment No. 171 states that an engineering evaluation
completion time or SF change is not in conflict with approved codes and  
will be conducted by the licensee under the SFCP that will assess the impact of the
standards relevant to the subject system [emphasis added]). Accordingly, the  
proposed SF change with the principle that sufficient safety margin is maintained. It
NRC SE for Byron Station Amendment No. 171 states that an engineering evaluation  
further states that The guidelines used for making that assessment will include
will be conducted by the licensee under the SFCP that will assess the impact of the  
ensuring the proposed surveillance test frequency change is not in conflict
proposed SF change with the principle that sufficient safety margin is maintained. It  
with approved industry codes and standards [emphasis added]... The SE also
further states that The guidelines used for making that assessment will include  
states Thus, safety margins are maintained by the proposed methodology, and the
ensuring the proposed surveillance test frequency change is not in conflict  
third key safety principle of RG 1.177 is satisfied. The NRC staff found similar
with approved industry codes and standards [emphasis added]... The SE also  
statements in relevant Statements of Considerations published by the NRC in
states Thus, safety margins are maintained by the proposed methodology, and the  
73 FR 74202 (December 5, 2008) and 74 FR 31996 (July 6, 2009).
third key safety principle of RG 1.177 is satisfied. The NRC staff found similar  
In the case of NCV 05000454/2017009-01; 05000455/2017009-01, the SF changes
statements in relevant Statements of Considerations published by the NRC in  
were in conflict with the UFSAR commitment to comply with Revision 3 of RG 1.9,
73 FR 74202 (December 5, 2008) and 74 FR 31996 (July 6, 2009).  
which endorses IEEE Standard 387-1984, and the licensee did not resolve this
In the case of NCV 05000454/2017009-01; 05000455/2017009-01, the SF changes  
conflict in accordance with the NRC risk-informed philosophy as incorporated into
were in conflict with the UFSAR commitment to comply with Revision 3 of RG 1.9,  
Revision 1 of NEI 04-10. Specifically, Steps 1 through 4 of NEI 04-10 include
which endorses IEEE Standard 387-1984, and the licensee did not resolve this  
guidelines for checking for NRC commitments related to the proposed SF change
conflict in accordance with the NRC risk-informed philosophy as incorporated into  
and, when commitments are identified, changing the commitments using a method
Revision 1 of NEI 04-10. Specifically, Steps 1 through 4 of NEI 04-10 include  
acceptable to the NRC prior to changing the SF or canceling the proposed SF
guidelines for checking for NRC commitments related to the proposed SF change  
change if the commitments cannot be changed. However, the licensee did not
and, when commitments are identified, changing the commitments using a method  
identify the UFSAR commitment to comply with Revision 3 of RG 1.9 when
acceptable to the NRC prior to changing the SF or canceling the proposed SF  
performing these steps. Their UFSAR review only consisted of a search of the
change if the commitments cannot be changed. However, the licensee did not  
key-words test (and all its word forms), surveillance, frequency, interval,
identify the UFSAR commitment to comply with Revision 3 of RG 1.9 when  
refueling, and outage as documented in Byron Station SFCP evaluation
performing these steps. Their UFSAR review only consisted of a search of the  
BY-13-003. Despite the deficient implementation of Steps 1 through 4, the licensee
key-words test (and all its word forms), surveillance, frequency, interval,  
identified the UFSAR commitment while performing Step 7 of NEI 04-10, which
refueling, and outage as documented in Byron Station SFCP evaluation  
prompted the licensee to update the UFSAR in support of the SF changes via
BY-13-003. Despite the deficient implementation of Steps 1 through 4, the licensee  
DRP 15-073, Revise Diesel Generator and Integrated Safeguards LOOP/ESF
identified the UFSAR commitment while performing Step 7 of NEI 04-10, which  
Surveillance Test Frequency from 18 Months to 18 Months on a Staggered Test
prompted the licensee to update the UFSAR in support of the SF changes via  
Basis, Revision 0. This UFSAR revision package included a 10 CFR 50.59
DRP 15-073, Revise Diesel Generator and Integrated Safeguards LOOP/ESF  
screening for the UFSAR commitment change to determine if an evaluation pursuant
Surveillance Test Frequency from 18 Months to 18 Months on a Staggered Test  
to 10 CFR 50.59 was required.
Basis, Revision 0. This UFSAR revision package included a 10 CFR 50.59  
However, the licensees 10 CFR 50.59 screening incorrectly concluded that a
screening for the UFSAR commitment change to determine if an evaluation pursuant  
10 CFR 50.59 evaluation was not required by, in relevant part, crediting SFCP
to 10 CFR 50.59 was required.  
evaluation BY-13-003, which was performed in accordance with the NEI 04-10
However, the licensees 10 CFR 50.59 screening incorrectly concluded that a  
process instead. Specifically, Step 2 of the SFCP change process from Revision 1
10 CFR 50.59 evaluation was not required by, in relevant part, crediting SFCP  
of NEI 04-10 emphasizes that Evaluating changes to the NRC commitments is a
evaluation BY-13-003, which was performed in accordance with the NEI 04-10  
separate activity based on a method acceptable to the NRC for managing and
process instead. Specifically, Step 2 of the SFCP change process from Revision 1  
changing regulatory commitments, e.g., NEI 99-04. Step 1 of Revision 0 of
of NEI 04-10 emphasizes that Evaluating changes to the NRC commitments is a  
NEI 99-04 for handling regulatory commitments states Commitments that are
separate activity based on a method acceptable to the NRC for managing and  
embodied in the UFSAR as descriptions of the facility or procedures are changed by
changing regulatory commitments, e.g., NEI 99-04. Step 1 of Revision 0 of  
applying the provisions of 10 CFR 50.59 to determine if a change requiring prior
NEI 99-04 for handling regulatory commitments states Commitments that are  
NRC approval exists. However, instead of performing the 10 CFR 50.59 evaluation
embodied in the UFSAR as descriptions of the facility or procedures are changed by  
                                      6
applying the provisions of 10 CFR 50.59 to determine if a change requiring prior  
NRC approval exists. However, instead of performing the 10 CFR 50.59 evaluation  


  as identified by NEI 99-4, the licensee incorrectly applied the 10 CFR 50.59(c)(4)
  exemption crediting the SFCP to provide more specific criteria to accomplish the
7
  change. This created a circular logic as stated in the Description Section of
as identified by NEI 99-4, the licensee incorrectly applied the 10 CFR 50.59(c)(4)  
  NCV 05000454/2017009-01; 05000455/2017009-01.
exemption crediting the SFCP to provide more specific criteria to accomplish the  
  As a result of the above review, the NRC staff concluded that evaluations performed
change. This created a circular logic as stated in the Description Section of  
  in accordance with Byron Station SFCP, as approved by the NRC, must ensure that
NCV 05000454/2017009-01; 05000455/2017009-01.  
  the proposed SF changes are not in conflict with approved industry codes and
As a result of the above review, the NRC staff concluded that evaluations performed  
  standards. In the case of NCV 05000454/2017009-01; 05000455/2017009-01, the
in accordance with Byron Station SFCP, as approved by the NRC, must ensure that  
  SF changes were in conflict with a UFSAR commitment to comply with an approved
the proposed SF changes are not in conflict with approved industry codes and  
  industry standard and the licensee addressed this conflict by changing the
standards. In the case of NCV 05000454/2017009-01; 05000455/2017009-01, the  
  commitment without applying the 10 CFR 50.59 process, which was the governing
SF changes were in conflict with a UFSAR commitment to comply with an approved  
  change process for this UFSAR commitment change as discussed in Section 4.3 of
industry standard and the licensee addressed this conflict by changing the  
  this Enclosure. Specifically, the NRC-approved SFCP recognizes 10 CFR 50.59 to
commitment without applying the 10 CFR 50.59 process, which was the governing  
  be the governing change control process for any proposed change to UFSAR
change process for this UFSAR commitment change as discussed in Section 4.3 of  
  commitments associated with codes and standards, in order to maintain sufficient
this Enclosure. Specifically, the NRC-approved SFCP recognizes 10 CFR 50.59 to  
  safety margin by ensuring the proposed surveillance test frequency change is not in
be the governing change control process for any proposed change to UFSAR  
  conflict with approved industry codes and standards. Code-required surveillance
commitments associated with codes and standards, in order to maintain sufficient  
  requirements reside within codes outside the technical specifications framework, and
safety margin by ensuring the proposed surveillance test frequency change is not in  
  may be relied upon for other allowances within those codes, and therefore are
conflict with approved industry codes and standards. Code-required surveillance  
  appropriately treated differently from technical specification surveillance
requirements reside within codes outside the technical specifications framework, and  
  requirements.
may be relied upon for other allowances within those codes, and therefore are  
5. Evaluation of the Original Enforcement Action
appropriately treated differently from technical specification surveillance  
  The NRC staff noted that the contrary to the above paragraph of the Enforcement
requirements.  
  Section of NCV 05000454/2017009-01; 05000455/2017009-01 included an
5. Evaluation of the Original Enforcement Action  
  explanatory statement that was open to interpretation. The contrary to the above
The NRC staff noted that the contrary to the above paragraph of the Enforcement  
  paragraph is quoted below showing the explanatory statement in bold.
Section of NCV 05000454/2017009-01; 05000455/2017009-01 included an  
      Contrary to the above, between February 14, 2014, and June 1, 2017, the
explanatory statement that was open to interpretation. The contrary to the above  
      licensee failed to provide a written evaluation which provided the basis for
paragraph is quoted below showing the explanatory statement in bold.  
      determining that a change, test, or experiment made pursuant to 10 CFR
Contrary to the above, between February 14, 2014, and June 1, 2017, the  
      50.59(c) did not require a license amendment. Specifically, the licensee failed
licensee failed to provide a written evaluation which provided the basis for  
      to provide a basis for why a change to the surveillance frequencies of
determining that a change, test, or experiment made pursuant to 10 CFR  
      emergency diesel generators described in the Updated Final Safety
50.59(c) did not require a license amendment. Specifically, the licensee failed  
      Analysis Report did not require prior NRC approval. The licensee did not
to provide a basis for why a change to the surveillance frequencies of  
      provide a basis for why the change would not result in more than a minimal
emergency diesel generators described in the Updated Final Safety  
      increase in the likelihood of occurrence of a malfunction of an SSC important to
Analysis Report did not require prior NRC approval. The licensee did not  
      safety.
provide a basis for why the change would not result in more than a minimal  
  In the context of the information documented in the Description Section of
increase in the likelihood of occurrence of a malfunction of an SSC important to  
  NCV 05000454/2017009-01; 05000455/2017009-01, the explanatory statement
safety.  
  could be interpreted to convey, at least, the following messages:
In the context of the information documented in the Description Section of  
  1. The licensee failed to apply the 10 CFR 50.59 evaluation change process to
NCV 05000454/2017009-01; 05000455/2017009-01, the explanatory statement  
      EDG SF changes and the 10 CFR 50.59 evaluation change process was
could be interpreted to convey, at least, the following messages:  
      applicable because the SFs were described in the UFSAR; or
1. The licensee failed to apply the 10 CFR 50.59 evaluation change process to  
  2. The licensee failed to apply the 10 CFR 50.59 evaluation change process to a
EDG SF changes and the 10 CFR 50.59 evaluation change process was  
      UFSAR commitment change made in support of EDG SF changes.
applicable because the SFs were described in the UFSAR; or  
                                          7
2. The licensee failed to apply the 10 CFR 50.59 evaluation change process to a  
UFSAR commitment change made in support of EDG SF changes.  


        Based on a review of licensee documents associated with the disputed NCV, the
        NRC staff determined that the second interpretation conveys the intended message
8
        of the explanatory statement. Further, it was determined that this intended message
Based on a review of licensee documents associated with the disputed NCV, the  
        was consistent with the NRC staff conclusions derived during this review of the
NRC staff determined that the second interpretation conveys the intended message  
        disputed NCV.
of the explanatory statement. Further, it was determined that this intended message  
        As a result of the above review along with the reviews included in Sections 4.1
was consistent with the NRC staff conclusions derived during this review of the  
        through 4.4 of this Enclosure, the NRC staff determined that the original enforcement
disputed NCV.  
        action of NCV 05000454/2017009-01; 05000455/2017009-01 was valid.
As a result of the above review along with the reviews included in Sections 4.1  
5. CONCLUSION
through 4.4 of this Enclosure, the NRC staff determined that the original enforcement  
  The NRC staff determined that the licensee performed two changes: (1) SF changes;
action of NCV 05000454/2017009-01; 05000455/2017009-01 was valid.  
  and (2) a UFSAR change to address a conflict between the SF changes and a standard
5.  
  that the licensee was committed to. The licensee evaluated both changes using their
CONCLUSION  
  NRC-approved SFCP, which was based on Revision 1 of NEI 04-10. However, this
The NRC staff determined that the licensee performed two changes: (1) SF changes;  
  process was only approved for evaluating SF changes. Evaluating a UFSAR
and (2) a UFSAR change to address a conflict between the SF changes and a standard  
  commitment change involving an approved standard and accepting a conflict between
that the licensee was committed to. The licensee evaluated both changes using their  
  proposed SF changes and a committed standard using Byron Station SFCP was not in
NRC-approved SFCP, which was based on Revision 1 of NEI 04-10. However, this  
  accordance with: (1) the limitations delineated in Revision 1 of NEI 04-10; (2) the EGC
process was only approved for evaluating SF changes. Evaluating a UFSAR  
  procedures established to implement the NEI 04-10 process; and (3) the NRC SE
commitment change involving an approved standard and accepting a conflict between  
  approving Byron Stations SFCP.
proposed SF changes and a committed standard using Byron Station SFCP was not in  
  Based on this review and after careful consideration of the information provided by
accordance with: (1) the limitations delineated in Revision 1 of NEI 04-10; (2) the EGC  
  EGC in letter dated July 31, 2017, the NRC staff determined that the violation of
procedures established to implement the NEI 04-10 process; and (3) the NRC SE  
  10 CFR 50.59(d)(1) occurred as stated in NCV 05000454/2017009-01; 05000455/
approving Byron Stations SFCP.  
  2017009-01. The NRC staff gave importance to the fact that the NRC SE approving
Based on this review and after careful consideration of the information provided by  
  Byron Station SFCP accepted its methodology because, in relevant part, it would
EGC in letter dated July 31, 2017, the NRC staff determined that the violation of  
  ensure that the proposed SF changes would not be in conflict with approved industry
10 CFR 50.59(d)(1) occurred as stated in NCV 05000454/2017009-01; 05000455/  
  codes and standards to meet the NRC key safety principles for risk-informed changes
2017009-01. The NRC staff gave importance to the fact that the NRC SE approving  
  to the TSs and not compromise the fundamental safety principles on which the plant
Byron Station SFCP accepted its methodology because, in relevant part, it would  
  design was based. The NRC staff also gave importance to the fact that Revision 1 of
ensure that the proposed SF changes would not be in conflict with approved industry  
  NEI 04-10 explicitly recognized its limitation to evaluate NRC commitment changes.
codes and standards to meet the NRC key safety principles for risk-informed changes  
  In addition, the NRC staff determined that the Enforcement Section of NCV 05000454/
to the TSs and not compromise the fundamental safety principles on which the plant  
  2017009-01; 05000455/2017009-01 included an explanatory statement that was open
design was based. The NRC staff also gave importance to the fact that Revision 1 of  
  to interpretation. Based on a review of licensee documents associated with the disputed
NEI 04-10 explicitly recognized its limitation to evaluate NRC commitment changes.  
  NCV, the NRC staff determined that the intended message of the explanatory statement
In addition, the NRC staff determined that the Enforcement Section of NCV 05000454/  
  was that the licensee failed to provide a basis for why a change to the UFSAR
2017009-01; 05000455/2017009-01 included an explanatory statement that was open  
  commitment to comply with Revision 3 of RG 1.9 did not require prior NRC approval.
to interpretation. Based on a review of licensee documents associated with the disputed  
  Further, it was determined that this intended message was consistent with the NRC
NCV, the NRC staff determined that the intended message of the explanatory statement  
  staff conclusions derived during this review of the disputed NCV.
was that the licensee failed to provide a basis for why a change to the UFSAR  
6. REFERENCES
commitment to comply with Revision 3 of RG 1.9 did not require prior NRC approval.
  1. Letter from Robert C. Daley to Bryan C. Hanson; Byron Station, Units 1 and 2 -
Further, it was determined that this intended message was consistent with the NRC  
        Evaluation of Changes, Tests, and Experiments Baseline Inspection Report
staff conclusions derived during this review of the disputed NCV.  
        05000454/2017009; 05000455/2017009; June 29, 2017.
6.  
  2. Letter from Mark Kanavos to the NRC Document Control Desk; Response to NRC
REFERENCES  
        Evaluation of Changes, Tests, and Experiments Baseline Inspection Report
1. Letter from Robert C. Daley to Bryan C. Hanson; Byron Station, Units 1 and 2 -  
        05000454/2017009, 05000455/2017009; July 31, 2017.
Evaluation of Changes, Tests, and Experiments Baseline Inspection Report  
                                            8
05000454/2017009; 05000455/2017009; June 29, 2017.  
2. Letter from Mark Kanavos to the NRC Document Control Desk; Response to NRC  
Evaluation of Changes, Tests, and Experiments Baseline Inspection Report  
05000454/2017009, 05000455/2017009; July 31, 2017.  


3. Technical specifications; 10 CFR 50.36; 2017.
4. Changes, Tests, and Experiments; 10 CFR 50.59; 2017.
9
5. Maintenance of records, making of reports; 10 CFR 50.71; 2017.
3. Technical specifications; 10 CFR 50.36; 2017.  
6. Regulatory Guide 1.9; Rev. 3; Selection, Design, Qualification, and Testing of
4. Changes, Tests, and Experiments; 10 CFR 50.59; 2017.  
    Diesel-Generator Units Used as Class 1E Onsite Electric Power Systems at Nuclear
5. Maintenance of records, making of reports; 10 CFR 50.71; 2017.  
    Power Plants; U.S. Nuclear Regulatory Commission; Washington, DC.
6. Regulatory Guide 1.9; Rev. 3; Selection, Design, Qualification, and Testing of  
7. Regulatory Guide 1.174; Rev. 2; An Approach for Using Probabilistic Risk
Diesel-Generator Units Used as Class 1E Onsite Electric Power Systems at Nuclear  
    Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing
Power Plants; U.S. Nuclear Regulatory Commission; Washington, DC.  
    Basis;  U.S. Nuclear Regulatory Commission; Washington, DC.
7. Regulatory Guide 1.174; Rev. 2; An Approach for Using Probabilistic Risk  
8. Regulatory Guide 1.177; Rev. 1; An Approach for Plant-Specific, Risk-Informed
Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing  
    Decisionmaking: Technical Specifications; U.S. Nuclear Regulatory Commission;
Basis;  U.S. Nuclear Regulatory Commission; Washington, DC.  
    Washington, DC.
8. Regulatory Guide 1.177; Rev. 1; An Approach for Plant-Specific, Risk-Informed  
9. Regulatory Guide 1.187; Nov. 2000; A Guidance for Implementation of 10 CFR
Decisionmaking: Technical Specifications; U.S. Nuclear Regulatory Commission;  
    50.59, Changes, Test, and Experiments; U.S. Nuclear Regulatory Commission;
Washington, DC.  
    Washington, DC.
9. Regulatory Guide 1.187; Nov. 2000; A Guidance for Implementation of 10 CFR  
10. NUREG-0800; Chapter 16; Standard Review Plan for the Review of Safety Analysis
50.59, Changes, Test, and Experiments; U.S. Nuclear Regulatory Commission;  
    Reports for Nuclear Power Plants: LWR Edition - Technical Specifications,
Washington, DC.  
    Section 16.1; Rev. 1; Risk-Informed Decision Making: Technical Specifications.
10. NUREG-0800; Chapter 16; Standard Review Plan for the Review of Safety Analysis  
11. 64 FR 53582; Changes, Tests, and Experiments; Federal Register; Volume 64;
Reports for Nuclear Power Plants: LWR Edition - Technical Specifications,  
    p. 53582; Washington, DC; October 4, 1999.
Section 16.1; Rev. 1; Risk-Informed Decision Making: Technical Specifications.  
12. 73 FR 74202; Notice of Opportunity to Comment on Model Safety Evaluation on
11. 64 FR 53582; Changes, Tests, and Experiments; Federal Register; Volume 64;  
    Technical Specification Improvement to Relocate Surveillance Frequencies to
p. 53582; Washington, DC; October 4, 1999.  
    Licensee Control-Risk-Informed Technical Specification Task Force (RITSTF)
12. 73 FR 74202; Notice of Opportunity to Comment on Model Safety Evaluation on  
    Initiative 5b, Technical Specification Task Force-425, Revision 2; Federal Register;
Technical Specification Improvement to Relocate Surveillance Frequencies to  
    Volume 73; p. 74202; Washington, DC; December 5, 2008.
Licensee Control-Risk-Informed Technical Specification Task Force (RITSTF)  
13. 74 FR 31996; Notice of Availability of Technical Specification Improvement to
Initiative 5b, Technical Specification Task Force-425, Revision 2; Federal Register;  
    Relocate Surveillance Frequencies to Licensee Control-Risk-Informed Technical
Volume 73; p. 74202; Washington, DC; December 5, 2008.  
    Specification Task Force (RITSTF) Initiative 5b, Technical Specification Task
13. 74 FR 31996; Notice of Availability of Technical Specification Improvement to  
    Force-425, Revision 3; Federal Register; Volume 74; p. 31996; Washington, DC;
Relocate Surveillance Frequencies to Licensee Control-Risk-Informed Technical  
    July 6, 2009.
Specification Task Force (RITSTF) Initiative 5b, Technical Specification Task  
14. Final Safety Evaluation for Nuclear Energy Institute (NEI) Topical Report
Force-425, Revision 3; Federal Register; Volume 74; p. 31996; Washington, DC;  
    (TR) 04-10, Revision 1, Risk-Informed Technical Specification Initiative 5B,
July 6, 2009.  
    Risk-Informed Method for Control of Surveillance Frequencies; U.S. Nuclear
14. Final Safety Evaluation for Nuclear Energy Institute (NEI) Topical Report  
    Regulatory Commission; September 19, 2007.
(TR) 04-10, Revision 1, Risk-Informed Technical Specification Initiative 5B,  
15. Safety Evaluation by the Office of Nuclear Reactor Regulation Related to
Risk-Informed Method for Control of Surveillance Frequencies; U.S. Nuclear  
    Amendment No. 171 to Facility Operating License No. NPF-37 and Amendment No.
Regulatory Commission; September 19, 2007.  
    171 to Facility Operating License No. NPF-66; U.S. Nuclear Regulatory
15. Safety Evaluation by the Office of Nuclear Reactor Regulation Related to  
    Commission; February 24, 2011.
Amendment No. 171 to Facility Operating License No. NPF-37 and Amendment No.  
16. NRC Enforcement Manual; Revision 10.
171 to Facility Operating License No. NPF-66; U.S. Nuclear Regulatory  
                                          9
Commission; February 24, 2011.  
16. NRC Enforcement Manual; Revision 10.  


17. NRC Enforcement Policy; November 1, 2016.
18. NRR Office Instruction LIC-105; Managing Regulatory Commitments Made by
10
    Licensees to the NRC; Revision 7 (publicly available).
17. NRC Enforcement Policy; November 1, 2016.  
19. IEEE 387-1984; IEEE Standard Criteria for Diesel-Generator Units Applied
18. NRR Office Instruction LIC-105; Managing Regulatory Commitments Made by  
    as Standby Power Supplies for Nuclear Power Generating Stations;
Licensees to the NRC; Revision 7 (publicly available).  
    November 21, 1984.
19. IEEE 387-1984; IEEE Standard Criteria for Diesel-Generator Units Applied  
20. NEI 96-07; Guidelines for 10 CFR 50.59 Implementation; Revision 1.
as Standby Power Supplies for Nuclear Power Generating Stations;  
21. NEI 99-04; Guidelines for Managing NRC Commitment Changes; Revision 0.
November 21, 1984.  
22. NEI 04-10; Risk-Informed Method for Control of Surveillance Frequencies;
20. NEI 96-07; Guidelines for 10 CFR 50.59 Implementation; Revision 1.  
    Revision 1.
21. NEI 99-04; Guidelines for Managing NRC Commitment Changes; Revision 0.  
23. Byron/Braidwood Nuclear Stations Updated Final Safety Analysis Report;
22. NEI 04-10; Risk-Informed Method for Control of Surveillance Frequencies;  
    Revision 14.
Revision 1.  
24. Byron/Braidwood Nuclear Stations Updated Final Safety Analysis Report;
23. Byron/Braidwood Nuclear Stations Updated Final Safety Analysis Report;  
    Revision 15.
Revision 14.  
25. Byron Station Technical Specification 3.8.1; AC Sources - Operating;
24. Byron/Braidwood Nuclear Stations Updated Final Safety Analysis Report;  
    Amendment 194.
Revision 15.  
26. Byron Station Technical Specification 5.5.19; Surveillance Frequency Control
25. Byron Station Technical Specification 3.8.1; AC Sources - Operating;  
    Program; Amendment 171.
Amendment 194.  
27. EGC Procedure ER-AA-425; Implementation of the Technical Specification
26. Byron Station Technical Specification 5.5.19; Surveillance Frequency Control  
    Surveillance Frequency Control Program; Revision 1.
Program; Amendment 171.  
28. EGC Procedure ER-AA-425-1000; Selecting a Candidate to be Evaluated for a
27. EGC Procedure ER-AA-425; Implementation of the Technical Specification  
    Proposed Surveillance Test Interval (STI) Change; Revision 1.
Surveillance Frequency Control Program; Revision 1.  
29. EGC Procedure ER-AA-425-1001; Surveillance Test Interval (STI) Evaluation
28. EGC Procedure ER-AA-425-1000; Selecting a Candidate to be Evaluated for a  
    Form; Revision 1.
Proposed Surveillance Test Interval (STI) Change; Revision 1.  
30. EGC Procedure ER-AA-425-1002; Engineering Evaluation of Proposed Surveillance
29. EGC Procedure ER-AA-425-1001; Surveillance Test Interval (STI) Evaluation  
    Test Interval Changes; Revision 1.
Form; Revision 1.  
31. Byron Station Evaluation BY-13-003; DG and Integrated Safeguards LOOP ESF
30. EGC Procedure ER-AA-425-1002; Engineering Evaluation of Proposed Surveillance  
    Surveillance Test Surveillance Frequency STI Evaluation; Revision 0.
Test Interval Changes; Revision 1.  
32. Byron Station UFSAR Change DRP 15-073; Revise Diesel Generator and
31. Byron Station Evaluation BY-13-003; DG and Integrated Safeguards LOOP ESF  
    Integrated Safeguards LOOP/ESF Surveillance Test Frequency from 18 Months to
Surveillance Test Surveillance Frequency STI Evaluation; Revision 0.  
    18 Months on a Staggered Test Basis; Revision 0.
32. Byron Station UFSAR Change DRP 15-073; Revise Diesel Generator and  
                                        10
Integrated Safeguards LOOP/ESF Surveillance Test Frequency from 18 Months to  
18 Months on a Staggered Test Basis; Revision 0.
}}
}}

Latest revision as of 07:59, 7 January 2025

Ltr. 12/21/17 Response to Disputed Non-Cited Violation Documented in Byron Station, Units 1 and 2 - Evaluations of Changes, Tests, and Experiments Baseline Inspection Report 05000454/2017009; 05000455/2017009 (DRS-N.Feliz-Adorno)
ML17355A561
Person / Time
Site: Byron  Constellation icon.png
Issue date: 12/21/2017
From: O'Brien K
Region 3 Administrator
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
EA-17-138 IR 2017009
Download: ML17355A561 (13)


See also: IR 05000454/2017009

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, ILLINOIS 60532-4352

December 21, 2017

EA-17-138

Mr. Bryan C. Hanson

Senior VP, Exelon Generation Company, LLC

President and CNO, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION DOCUMENTED IN BYRON

STATION, UNITS 1 AND 2EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS BASELINE INSPECTION REPORT 05000454/2017009;

05000455/2017009

Dear Mr. Hanson:

On July 31, 2017, Exelon Generation Company (EGC), LLC, provided a written response to

the U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000454/2017009;

05000455/2017009 issued on June 29, 2017, concerning an Evaluations of Changes, Tests,

and Experiments Inspection completed at Byron Station, Units 1 and 2. Specifically, the

letter contested Non-Cited Violation (NCV)05000454/2017009-01; 05000455/2017009-01

associated with the failure to perform an evaluation of a change to the facility as described in

the Updated Final Safety Analysis Report (UFSAR) pursuant to Title 10 of the Code of Federal

Regulations (CFR), Part 50.59(d)(1). The letter explained that EGC concluded that a

10 CFR 50.59(d)(1) evaluation was not required because the UFSAR change satisfied the

10 CFR 50.59(c)(4) exemption.

The NRC carefully reviewed EGCs reply and determined that the original enforcement

decision to disposition this issue as a violation of 10 CFR 50.59(d)(1) was valid. Specifically,

the NRC-approved Surveillance Frequency Control Program recognizes 10 CFR 50.59 to be the

governing change control process for any proposed change to UFSAR commitments associated

with codes and standards. This handling of changes to UFSAR commitments is deliberately

distinct and separate from the Surveillance Frequency Control Program in order to maintain

sufficient safety margin by ensuring the proposed surveillance test frequency change is not in

conflict with approved industry codes and standards. In addition, the NRC staff noted that the

contrary to the above paragraph of the Enforcement Section of NCV 05000454/2017009-01; 05000455/2017009-01 included an explanatory statement that was open to interpretation.

Based on a review of licensee documents associated with the disputed NCV, the NRC staff

determined that the intended message of the explanatory statement was consistent with the

NRC staff conclusions derived during this review of the disputed NCV. The basis for the NRC

staff conclusion is enclosed.

B. Hanson

-2-

This letter, its enclosure, EGCs July 31, 2017, response, and your response (if any) will be

made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html

and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

/RA/

Kenneth G. OBrien

Deputy Regional Administrator

Docket Nos. 50-454; 50-455

License Nos. NPF-37; NPF-66

Enclosure:

NRC Staff Assessment of Disputed

NCV 05000454/2017009-01;

NCV 05000455/2017009-01

cc: Distribution via LISTSERV

B. Hanson

-3-

Letter to Byron C. Hanson from Kenneth G. OBrien dated December 21, 2017

SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION DOCUMENTED IN BYRON

STATION, UNITS 1 AND 2EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS BASELINE INSPECTION REPORT 05000454/2017009;

05000455/2017009

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3

RidsNrrPMByron Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven West

Kenneth OBrien

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

ADAMS Accession Number ML17355A561

OFFICE

RIII

RIII

RIII

RIII

NAME

MJeffers for

NFeliz-Adorno:cl

MJeffers

JGeisner for

RSkokowski

KOBrien

DATE

12/21/17

12/21/17

12/21/17

12/21/17

OFFICIAL RECORD COPY

Enclosure

NRC STAFF ASSESSMENT OF DISPUTED

NCV 05000454/2017009-01; 05000455/2017009-01

The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the information provided in

Exelon Generation Company (EGC) letter dated July 31, 2017, to determine whether Non-Cited

Violation (NCV)05000454/2017009-01; 05000455/2017009-01 was valid. This review was

performed by an NRC staff member having relevant regulatory knowledge and who did not

participate in the inspection documented in Inspection Report 05000454/2017009;

05000455/2017009, which dispositioned the disputed violation. The NRC staff referenced

several documents that are listed in the Reference Section of this Enclosure and consulted

with other NRC staff members that were independent from the original enforcement decision,

including members of the Office of Nuclear Reactor Regulation.

1.

BACKGROUND

On June 29, 2017, the NRC issued Inspection Report 05000454/2017009;

05000455/2017009 documenting the results of an Evaluations of Changes, Tests,

and Experiments Inspection at Byron Station, Units 1 and 2. The report included a

SL-IV violation of Title 10 of the Code of Federal Regulations (CFR), Part 50.59(d)(1) for

the failure to provide a written evaluation which provided the basis for the determination

that a change did not require a license amendment. The violation was associated with a

change to a Updated Final Safety Analysis Report (UFSAR) commitment related to the

emergency diesel generators (EDGs) made in support of surveillance frequency (SF)

changes evaluated under the Byron Station SF Control Program (SFCP). This violation

was dispositioned as NCV 05000454/2017009-01; 05000455/2017009-01.

On July 31, 2017, EGC provided a written response to the NRC contesting the

enforcement decision associated with NCV 05000454/2017009-01; 05000455/

2017009-01. In the letter, EGC explained that a 10 CFR 50.59(d)(1) evaluation

was not required because the associated change to the UFSAR satisfied the

10 CFR 50.59(c)(4) exemption.

2.

ORIGINAL ENFORCEMENT DECISION

Inspection Report 05000454/2017009; 05000455/2017009 described the violation as:

Title 10 CFR 50.59, Changes, Tests, and Experiments, Section (d)(1) requires

the licensee to maintain records of changes in the facility, of changes in

procedures, and of tests and experiments made pursuant to 10 CFR 50.59(c).

Title 10 CFR 50.59(d)(1) requires that these records include a written evaluation

which provides the basis for the determination that a change, test, or experiment did

not require a license amendment. Title 10 CFR 50.59(c)(2) requires a licensee to

obtain a license amendment prior to implementing a proposed change, test, or

experiment if the change, test, or experiment would result in more than a minimal

increase in the likelihood of occurrence of a malfunction of an SSC [structure,

system, or component] important to safety.

Contrary to the above, between February 14, 2014, and June 1, 2017, the licensee

failed to provide a written evaluation which provided the basis for determining that a

change, test, or experiment made pursuant to 10 CFR 50.59(c) did not require a

license amendment. Specifically, the licensee failed to provide a basis for why a

change to the surveillance frequencies of EDGs described in the Updated Final

2

Safety Analysis Report did not require prior NRC approval. The licensee did not

provide a basis for why the change would not result in more than a minimal increase

in the likelihood of occurrence of a malfunction of an SSC important to safety.

3.

LICENSEE POSITION

In letter dated July 31, 2017, EGC concluded that UFSAR changes associated with

SF changes performed in accordance with an NRC-approved SFCP are not subject to

10 CFR 50.59(d)(1) evaluations because these changes satisfy 10 CFR 50.59(c)(4),

which states that the requirements of 10 CFR 50.59 do not apply to changes to the

facility or procedures when the applicable regulations establish more specific criteria for

accomplishing such changes. In summary, the bases for EGCs position included:

1. The NRC-approved the use of Revision 1 of Nuclear Energy Institute (NEI) Topical

Report 04-10, Risk-Informed Method for Control of Surveillance Frequencies, to

identify, assess, implement, and monitor changes to the SFs listed in Byron Station

SFCP.

2. The NEI 04-10 process became a regulatory requirement because it was

incorporated in the Administrative Controls section of Byron Station Technical

Specifications (TS).

3. The NEI 04-10 process applies more specific criteria than 10 CFR 50.59 to evaluate

SF changes.

4. The NEI 04-10 methodology evaluates all aspects of the current licensing basis

(CLB), including the UFSAR and industry codes/standards insights and compliance,

because TS requirements are inextricably linked to the rest of the CLB.

4.

NRC STAFF REVIEW

The NRC staff carefully reviewed the EGC position as it applied to the specific

circumstances surrounding NCV 05000454/2017009-01; 05000455/2017009-01 as

follows:

1. NRC Approval of NEI 04-10, Revision 1

During this review, the NRC staff confirmed that Revision 1 of NEI 04-10

was approved by the NRC to revise SFs within a licensee-controlled SFCP.

Specifically, NRC Final Safety Evaluation (SE) for Revision 1 of NEI 04-10, dated

September 19, 2007, states The NRC staff has found that NEI 04-10, Revision 1, is

acceptable for referencing by licensees proposing to amend their TS to establish a

Surveillance Frequency Control Program, to the extent specified and under the

limitations delineated in NEI 04-10, Revision 1, and in the enclosed final SE.

In addition, the NRC staff confirmed that the NRC approved a TS amendment to

establish a SFCP based on the methodology contained in Revision 1 of NEI 04-10

for Byron Station. Specifically, NRC SE for Byron Station Amendment No. 171,

dated February 24, 2011, states This methodology supports relocating surveillance

frequencies from TS to a licensee-controlled document, provided those frequencies

are changed in accordance with NEI 04-10, Revision 1, which is specified in the

Administrative Controls of the TSs.

3

As a result of the above review, the NRC staff concluded that the NRC-approved

Byron Stations establishment of a licensee-controlled SFCP provided SF changes

are made in accordance with Revision 1 of NEI 04-10.

2. Byron Station SFCP Relationship with Regulatory Requirements

During this review, the NRC staff determined that the NRC-approved a TS

amendment to include Byron Station SFCP in their TS. Specifically, NRC SE for

Byron Station Amendment No. 171 states Byron Station has included the SFCP

and specific requirements into the TSs, Section 5.5.19, Administrative Controls,

Section 5.5.19, Surveillance Frequency Control Program, of Byron Station TS,

Amendment 171, was added to state:

This program provides controls for Surveillance Frequencies. The program shall

ensure that Surveillance Requirements specified in the Technical Specifications

are performed at intervals sufficient to assure the associated Limiting Conditions

for Operation are met.

a. The SFCP shall contain a list of Frequencies of those Surveillance

Requirements for which the Frequency is controlled by the program.

b. Changes to the Frequencies listed in the SFCP shall be made in

accordance with NEI 04-10, Risk-Informed Method for Control of

Surveillance Frequencies, Revision 1 [emphasis added].

c. The provisions of Surveillance Requirements 3.0.2 and 3.0.3 are applicable

to the Frequencies established in the SFCP.

Furthermore, the NRC staff determined that TS 5.5.19 is a legally binding

requirement because it was incorporated into the Administrative Controls

section of TS. Compliance to TS is required as a license condition. Specifically,

Section 2.C(2) of Byron Station Renewed Facility Operating License No. NPF-37

states The licensee shall operate the facility in accordance with the TS and the

Environmental Protection Plan. In addition, the NRC Enforcement Policy, dated

November 1, 2016, states Requirement, as used in this Policy, means a

legally binding requirement such as a statute, regulation, license condition,

TS [emphasis added], or Order. Similar definitions were found in the NRC

Enforcement Manual, Revision 10, and Office of Nuclear Reactor Regulations Office

Instruction LIC-105, Managing Regulatory Commitments Made by Licensees to the

NRC, Revision 7 (publicly available).

As a result of the above review, the NRC staff concluded that changing SFs listed in

the SFCP in accordance with Revision 1 of NEI 04-10 was compliant with Byron

Station TS 5.5.19, Amendment 171, which was a legally binding requirement.

3. NEI 04-10 Change Process and the 10 CFR 50.59(c)(4) Exemption

During this review, the NRC staff noted that the scope of the 10 CFR 50.59

obligation, which is further clarified by the definitions included therein, is limited to

the facility and procedures as described in the UFSAR [emphasis added]. For

example, Paragraph (c)(1) of the obligation states A licensee may make changes

in the facility as described in the final FSAR [Final Safety Analysis Report] (as

4

updated) [emphasis added], make changes in the procedures as described in

the FSAR (as updated) [emphasis added], and conduct tests or experiments not

described in the FSAR (as updated) [emphasis added] The definition of

tests or experiments not described in the FSAR (as updated) [emphasis added]

contained in 10 CFR 50.59(a)(6) was based on design bases and safety analyses as

described in the FSAR (as updated) [emphasis added]. In the specific case of

NCV 05000454/2017009-01; 05000455/2017009-01, the SF changes themselves

were not changes to the facility or procedures as described in the UFSAR. Thus, the

10 CFR 50.59 obligation did not apply, including the 10 CFR 50.59(c)(4) exemption.

Instead, Byron Station TS 5.5.19, Amendment 171, requires Revision 1 of NEI 04-10

as the governing change process for the SF changes involved in the disputed

violation, consistent with the conclusion of Section 4.2 of this Enclosure.

However, the NRC staff noted that TS 5.5.19, Amendment 171, requires Revision 1

of NEI 04-10 as the governing change process only for SF changes [emphasis

added]. That is, this process is not specified as the governing change process to

evaluate changes to NRC commitments made in support of SF changes.

Specifically, Revision 1 of NEI 04-10, Step 1, requires checking for NRC

commitments related to the proposed SF change. When commitments are

identified, Steps 2 through 4 require changing the commitments using a method

acceptable to the NRC prior to changing the SF if the commitments could be

changed. Alternatively, these steps require canceling the proposed SF change if the

commitments could not be changed. The NRC staff further noted that these steps

were incorporated into the EGC SFCP procedures listed in the References Section

of this Enclosure.

Revision 1 of NEI 04-10 emphasizes that Evaluating changes to the NRC

commitments is a separate activity based on a method acceptable to the NRC

for managing and changing regulatory commitments, e.g., NEI 99-04 [emphasis

added]. The potential need to perform separate change evaluations is also

recognized by Revision 1 of NEI 96-07, Guidelines for 10 CFR 50.59

Implementation, which was endorsed by the NRC as an acceptable method for

complying with the provisions of 10 CFR 50.59 in Regulatory Guide (RG) 1.187,

Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments,

dated November 2000. For example, it states To the extent the UFSAR changes

are directly related to the activity implemented via another regulation, applying

10 CFR 50.59 is not required However, there may be certain activities for

which a licensee would need to apply both the requirements of 10 CFR 50.59

and that of another regulation [emphasis added].

Revision 1 of NEI 04-10 prompts the consideration for a separate 10 CFR 50.59

evaluation for NRC commitment changes associated with the proposed SF changes

by stating In Step 3, change the commitments using a method acceptable to the

NRC, e.g., NEI 99-04, such that the STI [surveillance test interval; aka., SFs] can

be revised using the SFCP process. Revision 0 of NEI 99-04, Guidelines for

Managing NRC Commitment Changes, states Commitments that are embodied

in the UFSAR as descriptions of the facility or procedures are changed by

applying the provisions of 10 CFR 50.59 [emphasis added] to determine if a

change requiring prior NRC approval exists. NEI 99-04 defined commitment as

an explicit statement to take a specific action agreed to, or volunteered by, a

5

licensee and submitted in writing on the docket to the NRC. In addition, Revision 1

of EGC procedure ER-AA-425-1002, Step 4.5.2, states Examples of commitments

within Exelon include but are not limited to the following UFSAR.

In the specific case of NCV 05000454/2017009-01; 05000455/2017009-01, the

licensee changed explicit statements embodied in the UFSAR in support of the

involved SF changes. For instance, the UFSAR stated that Byron Station complied

with Revision 3 of RG 1.9, Selection, Design, Qualification, and Testing of

Diesel-Generator Units Used as Class 1E Onsite Electric Power Systems at Nuclear

Power Plants, which endorses Institute of Electrical and Electronic Engineers (IEEE)

Standard 387-1984, IEEE Standard Criteria for Diesel-Generator Units Applied as

Standby Power Supplies for Nuclear Power Generating Stations. Because these

statements were embodied in the UFSAR, they were submitted in writing on the

docket to the NRC in accordance with 10 CFR 50.71, Maintenance of records,

making of reports. Therefore, the NRC staff determined that these explicit

statements were NRC commitments. In addition, the NRC staff noted that the

licensee recognized that these explicit statements were commitments in SFCP

evaluation BY-13-003, DG and Integrated Safeguards LOOP ESF Surveillance

Test Surveillance Frequency STI Evaluation, Revision 0. For example, Section C.7

states RG 1.9 to which Byron is committed to, with some exceptions, in the

UFSAR, Appendix A.

As a result of the above review, the NRC staff concluded that, in the case of

NCV 05000454/2017009-01; 05000455/2017009-01, the NEI 04-10 process was

the governing change process for the subject SF changes while the 10 CFR 50.59

process was the governing change process for changing the UFSAR commitments

made in support of the involved SF changes.

4. NEI 04-10 Treatment of Codes and Standards Related to Proposed SF Changes

During this review, the NRC staff noted that the NRC SE for Byron Station

Amendment No. 171 states that Revision 1 of NEI 04-10 was acceptable because, in

part, it meets each key safety principle required for risk-informed changes to the TSs

identified in Revision 1 of RG 1.177, An Approach for Plant-Specific, Risk-Informed

Decisionmaking: Technical Specifications. This RG describes an acceptable

approach for assessing the nature and impact of proposed TS changes in completion

times and SFs by considering engineering issues and applying risk insights. It states

that In implementing risk-informed decisionmaking, TS changes are expected to

meet a set of key principles. Revision 2 of RG 1.174, An Approach for Using

Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes

to the Licensing Basis, which is referenced by RG 1.177, further clarified that One

aspect of the engineering evaluations [conducted to justify any proposed CLB

change] is to show that the fundamental safety principles on which the plant design

was based are not compromised by the proposed change. This risk-informed

approach to TS is consistent with the NRC general review guidance for TS

contained in Revision 1 of Section 16.1, Risk-Informed Decision Making: Technical

Specifications, of NUREG-0800, Standard Review Plan for the Review of Safety

Analysis Reports for Nuclear Power Plants: LWR EditionTechnical Specifications.

6

The third key safety principle identified by the RGs is that the proposed TS change

maintains sufficient safety margin. The RG 1.177 states that sufficient safety margin

is maintained when, in part, Codes and standards (e.g., American Society of

Mechanical Engineers, Institute of Electrical and Electronic Engineers (IEEE)) or

alternatives approved for use by the NRC are met, (e.g., the proposed TS

completion time or SF change is not in conflict with approved codes and

standards relevant to the subject system [emphasis added]). Accordingly, the

NRC SE for Byron Station Amendment No. 171 states that an engineering evaluation

will be conducted by the licensee under the SFCP that will assess the impact of the

proposed SF change with the principle that sufficient safety margin is maintained. It

further states that The guidelines used for making that assessment will include

ensuring the proposed surveillance test frequency change is not in conflict

with approved industry codes and standards [emphasis added]... The SE also

states Thus, safety margins are maintained by the proposed methodology, and the

third key safety principle of RG 1.177 is satisfied. The NRC staff found similar

statements in relevant Statements of Considerations published by the NRC in

73 FR 74202 (December 5, 2008) and 74 FR 31996 (July 6, 2009).

In the case of NCV 05000454/2017009-01; 05000455/2017009-01, the SF changes

were in conflict with the UFSAR commitment to comply with Revision 3 of RG 1.9,

which endorses IEEE Standard 387-1984, and the licensee did not resolve this

conflict in accordance with the NRC risk-informed philosophy as incorporated into

Revision 1 of NEI 04-10. Specifically, Steps 1 through 4 of NEI 04-10 include

guidelines for checking for NRC commitments related to the proposed SF change

and, when commitments are identified, changing the commitments using a method

acceptable to the NRC prior to changing the SF or canceling the proposed SF

change if the commitments cannot be changed. However, the licensee did not

identify the UFSAR commitment to comply with Revision 3 of RG 1.9 when

performing these steps. Their UFSAR review only consisted of a search of the

key-words test (and all its word forms), surveillance, frequency, interval,

refueling, and outage as documented in Byron Station SFCP evaluation

BY-13-003. Despite the deficient implementation of Steps 1 through 4, the licensee

identified the UFSAR commitment while performing Step 7 of NEI 04-10, which

prompted the licensee to update the UFSAR in support of the SF changes via

DRP 15-073, Revise Diesel Generator and Integrated Safeguards LOOP/ESF

Surveillance Test Frequency from 18 Months to 18 Months on a Staggered Test

Basis, Revision 0. This UFSAR revision package included a 10 CFR 50.59

screening for the UFSAR commitment change to determine if an evaluation pursuant

to 10 CFR 50.59 was required.

However, the licensees 10 CFR 50.59 screening incorrectly concluded that a

10 CFR 50.59 evaluation was not required by, in relevant part, crediting SFCP

evaluation BY-13-003, which was performed in accordance with the NEI 04-10

process instead. Specifically, Step 2 of the SFCP change process from Revision 1

of NEI 04-10 emphasizes that Evaluating changes to the NRC commitments is a

separate activity based on a method acceptable to the NRC for managing and

changing regulatory commitments, e.g., NEI 99-04. Step 1 of Revision 0 of

NEI 99-04 for handling regulatory commitments states Commitments that are

embodied in the UFSAR as descriptions of the facility or procedures are changed by

applying the provisions of 10 CFR 50.59 to determine if a change requiring prior

NRC approval exists. However, instead of performing the 10 CFR 50.59 evaluation

7

as identified by NEI 99-4, the licensee incorrectly applied the 10 CFR 50.59(c)(4)

exemption crediting the SFCP to provide more specific criteria to accomplish the

change. This created a circular logic as stated in the Description Section of

NCV 05000454/2017009-01; 05000455/2017009-01.

As a result of the above review, the NRC staff concluded that evaluations performed

in accordance with Byron Station SFCP, as approved by the NRC, must ensure that

the proposed SF changes are not in conflict with approved industry codes and

standards. In the case of NCV 05000454/2017009-01; 05000455/2017009-01, the

SF changes were in conflict with a UFSAR commitment to comply with an approved

industry standard and the licensee addressed this conflict by changing the

commitment without applying the 10 CFR 50.59 process, which was the governing

change process for this UFSAR commitment change as discussed in Section 4.3 of

this Enclosure. Specifically, the NRC-approved SFCP recognizes 10 CFR 50.59 to

be the governing change control process for any proposed change to UFSAR

commitments associated with codes and standards, in order to maintain sufficient

safety margin by ensuring the proposed surveillance test frequency change is not in

conflict with approved industry codes and standards. Code-required surveillance

requirements reside within codes outside the technical specifications framework, and

may be relied upon for other allowances within those codes, and therefore are

appropriately treated differently from technical specification surveillance

requirements.

5. Evaluation of the Original Enforcement Action

The NRC staff noted that the contrary to the above paragraph of the Enforcement

Section of NCV 05000454/2017009-01; 05000455/2017009-01 included an

explanatory statement that was open to interpretation. The contrary to the above

paragraph is quoted below showing the explanatory statement in bold.

Contrary to the above, between February 14, 2014, and June 1, 2017, the

licensee failed to provide a written evaluation which provided the basis for

determining that a change, test, or experiment made pursuant to 10 CFR

50.59(c) did not require a license amendment. Specifically, the licensee failed

to provide a basis for why a change to the surveillance frequencies of

emergency diesel generators described in the Updated Final Safety

Analysis Report did not require prior NRC approval. The licensee did not

provide a basis for why the change would not result in more than a minimal

increase in the likelihood of occurrence of a malfunction of an SSC important to

safety.

In the context of the information documented in the Description Section of

NCV 05000454/2017009-01; 05000455/2017009-01, the explanatory statement

could be interpreted to convey, at least, the following messages:

1. The licensee failed to apply the 10 CFR 50.59 evaluation change process to

EDG SF changes and the 10 CFR 50.59 evaluation change process was

applicable because the SFs were described in the UFSAR; or

2. The licensee failed to apply the 10 CFR 50.59 evaluation change process to a

UFSAR commitment change made in support of EDG SF changes.

8

Based on a review of licensee documents associated with the disputed NCV, the

NRC staff determined that the second interpretation conveys the intended message

of the explanatory statement. Further, it was determined that this intended message

was consistent with the NRC staff conclusions derived during this review of the

disputed NCV.

As a result of the above review along with the reviews included in Sections 4.1

through 4.4 of this Enclosure, the NRC staff determined that the original enforcement

action of NCV 05000454/2017009-01; 05000455/2017009-01 was valid.

5.

CONCLUSION

The NRC staff determined that the licensee performed two changes: (1) SF changes;

and (2) a UFSAR change to address a conflict between the SF changes and a standard

that the licensee was committed to. The licensee evaluated both changes using their

NRC-approved SFCP, which was based on Revision 1 of NEI 04-10. However, this

process was only approved for evaluating SF changes. Evaluating a UFSAR

commitment change involving an approved standard and accepting a conflict between

proposed SF changes and a committed standard using Byron Station SFCP was not in

accordance with: (1) the limitations delineated in Revision 1 of NEI 04-10; (2) the EGC

procedures established to implement the NEI 04-10 process; and (3) the NRC SE

approving Byron Stations SFCP.

Based on this review and after careful consideration of the information provided by

EGC in letter dated July 31, 2017, the NRC staff determined that the violation of

10 CFR 50.59(d)(1) occurred as stated in NCV 05000454/2017009-01; 05000455/

2017009-01. The NRC staff gave importance to the fact that the NRC SE approving

Byron Station SFCP accepted its methodology because, in relevant part, it would

ensure that the proposed SF changes would not be in conflict with approved industry

codes and standards to meet the NRC key safety principles for risk-informed changes

to the TSs and not compromise the fundamental safety principles on which the plant

design was based. The NRC staff also gave importance to the fact that Revision 1 of

NEI 04-10 explicitly recognized its limitation to evaluate NRC commitment changes.

In addition, the NRC staff determined that the Enforcement Section of NCV 05000454/

2017009-01;05000455/2017009-01 included an explanatory statement that was open

to interpretation. Based on a review of licensee documents associated with the disputed

NCV, the NRC staff determined that the intended message of the explanatory statement

was that the licensee failed to provide a basis for why a change to the UFSAR

commitment to comply with Revision 3 of RG 1.9 did not require prior NRC approval.

Further, it was determined that this intended message was consistent with the NRC

staff conclusions derived during this review of the disputed NCV.

6.

REFERENCES

1. Letter from Robert C. Daley to Bryan C. Hanson; Byron Station, Units 1 and 2 -

Evaluation of Changes, Tests, and Experiments Baseline Inspection Report 05000454/2017009; 05000455/2017009; June 29, 2017.

2. Letter from Mark Kanavos to the NRC Document Control Desk; Response to NRC

Evaluation of Changes, Tests, and Experiments Baseline Inspection Report 05000454/2017009, 05000455/2017009; July 31, 2017.

9

3. Technical specifications; 10 CFR 50.36; 2017.

4. Changes, Tests, and Experiments; 10 CFR 50.59; 2017.

5. Maintenance of records, making of reports; 10 CFR 50.71; 2017.

6. Regulatory Guide 1.9; Rev. 3; Selection, Design, Qualification, and Testing of

Diesel-Generator Units Used as Class 1E Onsite Electric Power Systems at Nuclear

Power Plants; U.S. Nuclear Regulatory Commission; Washington, DC.

7. Regulatory Guide 1.174; Rev. 2; An Approach for Using Probabilistic Risk

Assessment in Risk-Informed Decisions on Plant-Specific Changes to the Licensing

Basis; U.S. Nuclear Regulatory Commission; Washington, DC.

8. Regulatory Guide 1.177; Rev. 1; An Approach for Plant-Specific, Risk-Informed

Decisionmaking: Technical Specifications; U.S. Nuclear Regulatory Commission;

Washington, DC.

9. Regulatory Guide 1.187; Nov. 2000; A Guidance for Implementation of 10 CFR

50.59, Changes, Test, and Experiments; U.S. Nuclear Regulatory Commission;

Washington, DC.

10. NUREG-0800; Chapter 16; Standard Review Plan for the Review of Safety Analysis

Reports for Nuclear Power Plants: LWR Edition - Technical Specifications,

Section 16.1; Rev. 1; Risk-Informed Decision Making: Technical Specifications.

11. 64 FR 53582; Changes, Tests, and Experiments; Federal Register; Volume 64;

p. 53582; Washington, DC; October 4, 1999.

12. 73 FR 74202; Notice of Opportunity to Comment on Model Safety Evaluation on

Technical Specification Improvement to Relocate Surveillance Frequencies to

Licensee Control-Risk-Informed Technical Specification Task Force (RITSTF)

Initiative 5b, Technical Specification Task Force-425, Revision 2; Federal Register;

Volume 73; p. 74202; Washington, DC; December 5, 2008.

13. 74 FR 31996; Notice of Availability of Technical Specification Improvement to

Relocate Surveillance Frequencies to Licensee Control-Risk-Informed Technical

Specification Task Force (RITSTF) Initiative 5b, Technical Specification Task

Force-425, Revision 3; Federal Register; Volume 74; p. 31996; Washington, DC;

July 6, 2009.

14. Final Safety Evaluation for Nuclear Energy Institute (NEI) Topical Report

(TR) 04-10, Revision 1, Risk-Informed Technical Specification Initiative 5B,

Risk-Informed Method for Control of Surveillance Frequencies; U.S. Nuclear

Regulatory Commission; September 19, 2007.

15. Safety Evaluation by the Office of Nuclear Reactor Regulation Related to

Amendment No. 171 to Facility Operating License No. NPF-37 and Amendment No.

171 to Facility Operating License No. NPF-66; U.S. Nuclear Regulatory

Commission; February 24, 2011.

16. NRC Enforcement Manual; Revision 10.

10

17. NRC Enforcement Policy; November 1, 2016.

18. NRR Office Instruction LIC-105; Managing Regulatory Commitments Made by

Licensees to the NRC; Revision 7 (publicly available).

19. IEEE 387-1984; IEEE Standard Criteria for Diesel-Generator Units Applied

as Standby Power Supplies for Nuclear Power Generating Stations;

November 21, 1984.

20. NEI 96-07; Guidelines for 10 CFR 50.59 Implementation; Revision 1.

21. NEI 99-04; Guidelines for Managing NRC Commitment Changes; Revision 0.

22. NEI 04-10; Risk-Informed Method for Control of Surveillance Frequencies;

Revision 1.

23. Byron/Braidwood Nuclear Stations Updated Final Safety Analysis Report;

Revision 14.

24. Byron/Braidwood Nuclear Stations Updated Final Safety Analysis Report;

Revision 15.

25. Byron Station Technical Specification 3.8.1; AC Sources - Operating;

Amendment 194.

26. Byron Station Technical Specification 5.5.19; Surveillance Frequency Control

Program; Amendment 171.

27. EGC Procedure ER-AA-425; Implementation of the Technical Specification

Surveillance Frequency Control Program; Revision 1.

28. EGC Procedure ER-AA-425-1000; Selecting a Candidate to be Evaluated for a

Proposed Surveillance Test Interval (STI) Change; Revision 1.

29. EGC Procedure ER-AA-425-1001; Surveillance Test Interval (STI) Evaluation

Form; Revision 1.

30. EGC Procedure ER-AA-425-1002; Engineering Evaluation of Proposed Surveillance

Test Interval Changes; Revision 1.

31. Byron Station Evaluation BY-13-003; DG and Integrated Safeguards LOOP ESF

Surveillance Test Surveillance Frequency STI Evaluation; Revision 0.

32. Byron Station UFSAR Change DRP 15-073; Revise Diesel Generator and

Integrated Safeguards LOOP/ESF Surveillance Test Frequency from 18 Months to

18 Months on a Staggered Test Basis; Revision 0.