ENS 52825: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 06/23/2017 20:18 CDT
| event date = 06/23/2017 20:18 CDT
| last update date = 06/24/2017
| last update date = 06/24/2017
| title = Automatic Reactor Scram On Main Generator Trip
| title = Automatic Reactor Scram on Main Generator Trip
| event text = While performing a scheduled generator voltage regulator test, River Bend Station experienced an automatic scram when the main generator tripped. It is unknown at this time why the main generator tripped.
| event text = While performing a scheduled generator voltage regulator test, River Bend Station experienced an automatic scram when the main generator tripped. It is unknown at this time why the main generator tripped.
There were no equipment issues that materially impacted post scram operator response.
There were no equipment issues that materially impacted post scram operator response.

Latest revision as of 21:42, 1 March 2018

ENS 52825 +/-
Where
River Bend Entergy icon.png
Louisiana (NRC Region 4)
Reporting
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation
Time - Person (Reporting Time:+-1.33 h-0.0554 days <br />-0.00792 weeks <br />-0.00182 months <br />)
Opened: Timothy Gates
23:58 Jun 23, 2017
NRC Officer: Howie Crouch
Last Updated: Jun 24, 2017
52825 - NRC Website
Loading map...