ML23346A068: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot change
StriderTol Bot change
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION COMMISSIONERS:
 
Christopher T. Hanson, Chair David A. Wright Annie Caputo Bradley R. Crowell In the Matter of KAIROS POWER LLC (Hermes Test Reactor)
COMMISSIONERS:
Docket No. --CP CLI--
 
MEMORANDUM AND ORDER On October,, we held a hearing on the application of Kairos Power LLC (Kairos) for a construction permit for the Hermes non-power test reactor.1 In this uncontested proceeding, we consider the sufficiency of the NRC Staffs review of Kaiross application. As discussed below, we find that the Staffs review was sufficient to support the regulatory findings.
Christopher T. Hanson, Chair David A. Wright Annie Caputo Bradley R. Crowell
 
In the Matter of
 
KAIROS POWER LLC Docket No. - -CP
 
(Hermes Test Reactor)
 
CLI--
 
MEMORANDUM AND ORDER
 
On October,, we held a hearing on the application of Kairos Power LLC (Kairos)
 
for a construction permit for the Hermes non-power test reactor. 1 In this uncontested
 
proceeding, we consider the sufficiency of the NRC Staffs review of Kaiross application. As
 
discussed below, we find that the Staffs review was sufficient to support the regulatory findings.
 
We authorize issuance of the construction permit.
We authorize issuance of the construction permit.
1 See Kairos Power LLC; Construction Permit Application; Notice of Hearing, Fed. Reg.
, (Sept., ) (Hearing Notice); Tr. at - (attached to Order of the Secretary (Setting Deadline for Proposed Transcript Corrections) (Oct., ) (unpublished) (as amended by Order of the Secretary (Adopting Transcript Corrections and Admitting Revised Exhibit) (Nov.,
) (unpublished))).


1 See Kairos Power LLC; Construction Permit Application; Notice of Hearing, Fed. Reg.
BACKGROUND A.
, (Sept., ) (Hearing Notice); Tr. at - (attached to Order of the Secretary (Setting Deadline for Proposed Transcript Corrections) (Oct., ) (unpublished) (as amended by Order of the Secretary (Adopting Transcript Corrections and Admitting Revised Exhibit) (Nov.,
Proposed Action The construction permit would allow construction of a -megawatt thermal test reactor on an approximately -acre brownfield site in Oak Ridge, Tennessee.2 The Hermes test reactor will use a combination of tri-structural isotropic (TRISO) fuel particles and a molten fluoride salt coolant known as Flibe. The non-power reactor will serve as a scaled demonstration plant to test and demonstrate key technical elements, design features, safety functions, and equipment performance for Kaiross salt-cooled, fluoride high temperature reactor technology.3 Kairos expects to complete construction by the end of and then to operate for four years.4 Before submitting its construction permit application in,5 Kairos engaged in extensive preapplication activities with the Staff, including the development of topical reports and participation in public meetings and audits.6 Topical reports cover safety-related topics that apply to multiple nuclear reactors and increase the efficiency of the licensing process by minimizing the time and resources that both applicants and the Staff spend on multiple reviews of the same topic. Kairos submitted eleven topical reports for the Staffs review and approval, 2 Ex. KRS-, Applicants Pre-Filed Testimony of Peter Hastings; Kairos Power LLC; Evidentiary Hearing (Sept., ), at, (Kairos Testimony).
) (unpublished))).
 
BACKGROUND
 
A. Proposed Action
 
The construction permit would allow construction of a -megawatt thermal test reactor
 
on an approximately -acre brownfield site in Oak Ridge, Tennessee. 2 The Hermes test
 
reactor will use a combination of tri-structural isotropic (TRISO) fuel particles and a molten
 
fluoride salt coolant known as Flibe. The non-power reactor will serve as a scaled
 
demonstration plant to test and demonstrate key technical elements, design features, safety
 
functions, and equipment performance for Kaiross salt-cooled, fluoride high temperature reactor
 
technology.3 Kairos expects to complete construction by the end of and then to operate for
 
four years.4
 
Before submitting its construction permit application in,5 Kairos engaged in
 
extensive preapplication activities with the Staff, including the development of topical reports
 
and participation in public meetings and audits. 6 Topical reports cover safety-related topics that
 
apply to multiple nuclear reactors and increase the efficiency of the licensing process by
 
minimizing the time and resources that both applicants and the Staff spend on multiple reviews
 
of the same topic. Kairos submitted eleven topical reports for the Staffs review and approval,
 
2 Ex. KRS-, Applicants Pre-Filed Testimony of Peter Hastings; Kairos Power LLC; Evidentiary Hearing (Sept., ), at, (Kairos Testimony).
 
3 Id. at.
3 Id. at.
4 Id. at, ; Ex. NRC-, Safety Evaluation Related to the Kairos Power LLC Construction Permit Application for the Hermes Test Reactor (June, ), at -, - (Safety Evaluation).
4 Id. at, ; Ex. NRC-, Safety Evaluation Related to the Kairos Power LLC Construction Permit Application for the Hermes Test Reactor (June, ), at -, - (Safety Evaluation).
5 The public version of the application can be found in Exhibits NRC-A through NRC-E in this proceeding.
5 The public version of the application can be found in Exhibits NRC-A through NRC-E in this proceeding.
 
6 Ex. NRC-, Staffs Statement in Support of the Uncontested Hearing for Issuance of a Construction Permit for the Kairos Hermes Test Reactor, Commission Paper SECY--
6 Ex. NRC-, Staffs Statement in Support of the Uncontested Hearing for Issuance of a Construction Permit for the Kairos Hermes Test Reactor, Commission Paper SECY- -
(Aug., ), at (Staff Information Paper). The topics covered by the topical reports, preapplication meetings, and preapplication audits are listed in the Staff Information Paper. Id.
(Aug., ), at (Staff Information Paper). The topics covered by the topical reports, preapplication meetings, and preapplication audits are listed in the Staff Information Paper. Id.
at -.
at -.  
 
eight of which were referenced in its application. 7 Kairos supplemented its application and
 
provided clarifications through timely responses to several hundred Staff questions during audit
 
meetings and in docketed correspondence. 8 The Staff also issued three requests for additional
 
information and one request for confirmation of information. 9 Kairos and the Staff used
 
regulatory guidance in NUREG-in the preparation and review of the construction permit
 
application.10 Kairos did not request, and the Staff did not grant, any exemptions from NRC
 
regulations.11
 
The Staff conducted a safety review of the application to determine whether it complies
 
with the Atomic Energy Act of, as amended (AEA), and the NRCs regulations. 12 The
 
Advisory Committee on Reactor Safeguards (ACRS), a committee of technical experts charged
 
with reviewing and reporting on safety studies and applications for construction permits and
 
facility operating licenses, provided an independent assessment of the safety aspects of the


7 Id. The Staff prepared a safety evaluation for each of the topical reports, and any condition or limitation on the use of a topical report is provided in the approved version of the report. Id. at.
eight of which were referenced in its application.7 Kairos supplemented its application and provided clarifications through timely responses to several hundred Staff questions during audit meetings and in docketed correspondence.8 The Staff also issued three requests for additional information and one request for confirmation of information.9 Kairos and the Staff used regulatory guidance in NUREG-in the preparation and review of the construction permit application.10 Kairos did not request, and the Staff did not grant, any exemptions from NRC regulations.11 The Staff conducted a safety review of the application to determine whether it complies with the Atomic Energy Act of, as amended (AEA), and the NRCs regulations.12 The Advisory Committee on Reactor Safeguards (ACRS), a committee of technical experts charged with reviewing and reporting on safety studies and applications for construction permits and facility operating licenses, provided an independent assessment of the safety aspects of the 7 Id. The Staff prepared a safety evaluation for each of the topical reports, and any condition or limitation on the use of a topical report is provided in the approved version of the report. Id. at.
The Staffs review of the construction permit application confirmed that the conditions or limitations for the topical reports referenced in the application were satisfied or could reasonably be left for the operating license application. Id.
The Staffs review of the construction permit application confirmed that the conditions or limitations for the topical reports referenced in the application were satisfied or could reasonably be left for the operating license application. Id.
8 Ex. KRS-, Kairos Testimony, at.
8 Ex. KRS-, Kairos Testimony, at.
9 Id.
9 Id.
 
10 See id. at (citing Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors: Format and Content, NUREG-, pt. (Feb. ) (ADAMS accession no. ML); Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors: Standard Review Plan and Acceptance Criteria, NUREG-, pt.
10 See id. at (citing Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors: Format and Content, NUREG-, pt. (Feb. ) (ADAMS accession no. ML ); Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors: Standard Review Plan and Acceptance Criteria, NUREG-, pt.
(Feb. ) (ML)); Ex. NRC-, Staff Information Paper, at -.
(Feb. ) (ML )); Ex. NRC-, Staff Information Paper, at -.
 
11 Ex. NRC-, Staff Information Paper, at.
11 Ex. NRC-, Staff Information Paper, at.
12 See Ex. NRC-, Safety Evaluation.


12 See Ex. NRC-, Safety Evaluation.
application.13 The ACRS recommended that the construction permit be issued.14 The Staff also performed an environmental review, in accordance with the National Environmental Policy Act of (NEPA),15 that evaluated the environmental impacts of constructing, operating, and decommissioning the Hermes test reactor.16 Based on its safety and environmental reviews, the Staff recommended that the Commission issue the construction permit to Kairos once the National Historic Preservation Act of (NHPA) section consultation process is complete.17 B.
 
Review Standards Section a. of the AEA requires that we hold a hearing on an application to construct a testing facility.18 The Staff published a notice of hearing in the Federal Register and provided an opportunity for interested members of the public to petition for leave to intervene.19 No petitions to intervene were filed. Therefore, there was no separate contested hearing.
application.13 The ACRS recommended that the construction permit be issued. 14 The Staff also
We issued a second notice that set the time and place for the uncontested hearing and outlined the standards for our review.20 These standards track the two major areas of focus for 13 See Letter from Joy L. Rempe, ACRS, Chairman, to Christopher T. Hanson, Chair, NRC, Kairos Non-Power Reactor Hermes Construction Permit Application (May, )
 
(MLA) (ACRS Letter).
performed an environmental review, in accordance wi th the National Environmental Policy Act of
 
(NEPA),15 that evaluated the environmental impacts of constructing, operating, and
 
decommissioning the Hermes test reactor. 16 Based on its safety and environmental reviews, the
 
Staff recommended that the Commission issue the construction permit to Kairos once the
 
National Historic Preservation Act of (NHPA) section consultation process is
 
complete.17
 
B. Review Standards
 
Section a. of the AEA requires that we hold a hearing on an application to construct a
 
testing facility.18 The Staff published a notice of hearing in the Federal Register and provided an
 
opportunity for interested members of the public to petition for leave to intervene. 19 No petitions
 
to intervene were filed. Therefore, there was no separate contested hearing.
 
We issued a second notice that set the time and place for the uncontested hearing and
 
outlined the standards for our review. 20 These standards track the two major areas of focus for
 
13 See Letter from Joy L. Rempe, ACRS, Chairman, to Christopher T. Hanson, Chair, NRC, Kairos Non-Power Reactor Hermes Construction Permit Application (May, )
(ML A ) (ACRS Letter).
 
14 Id. at.
14 Id. at.
15 U.S.C. § et seq.
15 U.S.C. § et seq.
16 See Ex. NRC-, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Final Report), NUREG- (Aug. ) (FEIS).
16 See Ex. NRC-, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Final Report), NUREG- (Aug. ) (FEIS).
17 Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Regan). At the time of the hearing, the Staff had not yet completed the section consultation process.
17 Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Regan). At the time of the hearing, the Staff had not yet completed the section consultation process.
18 AEA § a., U.S.C. § (a) (The Commission shall hold a hearing... on any application under section c. for a construction permit for a testing facility.).
18 AEA § a., U.S.C. § (a) (The Commission shall hold a hearing... on any application under section c. for a construction permit for a testing facility.).
19 Kairos Power, LLC; Construction Permit Application; Opportunity to Request a Hearing and Petition for Leave to Intervene; Order Imposing Procedures, Fed. Reg. (Feb., ).
19 Kairos Power, LLC; Construction Permit Application; Opportunity to Request a Hearing and Petition for Leave to Intervene; Order Imposing Procedures, Fed. Reg. (Feb., ).
20 Hearing Notice, Fed. Reg. at,-.


20 Hearing Notice, Fed. Reg. at,-.
the review of a construction permit application: the Staffs safety and environmental reviews. For the safety review, we must determine whether:
 
the applicant has described the proposed design of the facility, including, but not limited to, the principal architectural and engineering criteria for the design, and has identified the major features or components incorporated therein for the protection of the health and safety of the public; such further technical or design information as may be required to complete the safety analysis, and which can reasonably be left for later consideration, will be supplied in the final safety analysis report; safety features or components, if any, which require research and development have been described by the applicant and the applicant has identified, and there will be conducted, a research and development program reasonably designed to resolve any safety questions associated with such features or components; and on the basis of the foregoing, there is reasonable assurance that (i) such safety questions will be satisfactorily resolved at or before the latest date stated in the application for completion of construction of the proposed facility, and (ii) taking into consideration the site criteria contained in C.F.R. Part, the proposed facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.21 In making these findings, we are guided by the additional considerations in C.F.R.  
the review of a construction permit application: the Staffs safety and environmental reviews. For
 
the safety review, we must determine whether:
 
. the applicant has described the proposed design of the facility, including, but not limited to, the principal architectural and engineering criteria for the design, and has identified the major features or components incorporated therein for the protection of the health and safety of the public;
 
. such further technical or design information as may be required to complete the safety analysis, and which can reasonably be left for later consideration, will be supplied in the final safety analysis report;
 
. safety features or components, if any, which require research and development have been described by the applicant and the applicant has identified, and there will be conducted, a research and development program reasonably designed to resolve any safety questions associated with such features or components; and
 
. on the basis of the foregoing, there is reasonable assurance that (i) such safety questions will be satisfactorily resolved at or before the latest date stated in the application for completion of construction of the proposed facility, and (ii) taking into consideration the site criteria contained in C.F.R. Part, the proposed facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public. 21
 
In making these findings, we are guided by the additional considerations in C.F.R.
 
§.. We consider whether:
§.. We consider whether:
the processes to be performed, the operating procedures, the facility and equipment, the use of the facility, and other technical specifications, or the proposals, in regard to any of the foregoing collectively provide reasonable assurance that the applicant will comply with NRC regulations, including the regulations in C.F.R. Part,22 and that the health and safety of the public will not be endangered; 21 C.F.R. §.(a); Hearing Notice, Fed. Reg. at,-.
22 The regulations in Part apply to persons licensed by the Commission to receive, possess, use, transfer, or dispose of byproduct, source, or special nuclear material or to operate a production or utilization facility. C.F.R. §.. Kairos has neither requested approval of design information nor has applied for a license to receive, possess, use, transfer, or dispose of byproduct, source, or special nuclear material at the facility. Ex. NRC-, Safety Evaluation, at -. Therefore, the [S]taff did not evaluate whether requirements in CFR Part would be met for the construction of the Hermes reactor. Instead, the [S]taff assessed whether Kairos had identified the relevant requirements for an operating facility and provided descriptions of the preliminary facility design and provisions for protecting the health and safety of the public, workers, and the environment in sufficient detail to determine whether the [preliminary safety analysis report] provides an acceptable basis for the development of the radiation protection programs and radioactive waste management, and whether there is reasonable assurance that


. the processes to be performed, the operating procedures, the facility and equipment, the use of the facility, and other technical specifications, or the proposals, in regard to any of the foregoing collectively provide reasonable assurance that the applicant will comply with NRC regulations, including the regulations in C.F.R. Part, 22 and that the health and safety of the public will not be endangered;
the applicant is technically and financially qualified to engage in the proposed activities; the issuance of the construction permit will not be inimical to the common defense and security or to the health and safety of the public; and any applicable requirements of Subpart A of C.F.R. Part have been satisfied.23 Overlapping this last consideration are the environmental findings that we must make to support issuance of the construction permit.24 The findings reflect our agencys obligations under NEPA, a statute that requires us to consider the impacts of NRC actions on environmental values.25 To ensure that these obligations are fulfilled for this construction permit proceeding, we must:
 
determine whether the requirements of NEPA Sections ()(A), (C), and (E),26 and the applicable regulations in C.F.R. Part, have been met; independently consider the final balance among conflicting factors contained in the record of the proceeding with a view to determining the appropriate action to be taken; determine, after weighing the environmental, economic, technical, and other benefits against environmental and other costs, and considering reasonable alternatives, whether the construction permit should be issued, denied, or appropriately conditioned to protect environmental values; and Kairos will comply with the regulations in CFR Part during operation of the Hermes facility. Id. We agree that the Staffs approach meets C.F.R. §.(a).
21 C.F.R. §. (a); Hearing Notice, Fed. Reg. at, -.
23 C.F.R. §.(a)-(d).
 
24 See, e.g., id. §.(a).
22 The regulations in Part apply to persons licensed by the Commission to receive, possess, use, transfer, or dispose of byproduct, source, or special nuclear material or to operate a production or utilization facility. C.F.R. §.. Kairos has neither requested approval of design information nor has applied for a license to receive, possess, use, transfer, or dispose of byproduct, source, or special nuclear material at the facility. Ex. NRC-, Safety Evaluation, at -. Therefore, the [S]taff did not evaluate whether requirements in CFR Part would be met for the construction of the Hermes reactor. Instead, the [S]taff assessed whether Kairos had identified the relevant requirements for an operating facility and provided descriptions of the preliminary facility design and provisions for protecting the health and safety of the public, workers, and the environment in sufficient detail to determine whether the [preliminary safety analysis report] provides an acceptable basis fo r the development of the radiation protection programs and radioactive waste management, and whether there is reasonable assurance that
25 NEPA § (), U.S.C. § (); see C.F.R. §..
 
. the applicant is technically and financially qualified to engage in the proposed activities;
 
. the issuance of the construction permit will not be inimical to the common defense and security or to the health and safety of the public; and
 
. any applicable requirements of Subpart A of C.F.R. Part have been satisfied.23
 
Overlapping this last consideration are the environmental findings that we must make to
 
support issuance of the construction permit. 24 The findings reflect our agencys obligations
 
under NEPA, a statute that requires us to consider the impacts of NRC actions on
 
environmental values.25 To ensure that these obligations are fulfilled for this construction permit
 
proceeding, we must:
 
. determine whether the requirements of NEPA Sections ( )(A), (C), and (E),26 and the applicable regulations in C.F.R. Part, have been met;
 
. independently consider the final balance among conflicting factors contained in the record of the proceeding with a view to determining the appropriate action to be taken;
 
. determine, after weighing the environmental, economic, technical, and other benefits against environmental and other costs, and considering reasonable alternatives, whether the construction permit should be issued, denied, or appropriately conditioned to protect environmental values; and
 
Kairos will comply with the regulations in CFR Part during operation of the Hermes facility. Id. We agree that the Staffs approach meets C.F.R. §. (a).
 
23 C.F.R. §. (a)-(d).
 
24 See, e.g., id. §. (a).
 
25 NEPA § ( ), U.S.C. § ( ); see C.F.R. §..
 
26 On June 3, 2023, President Biden signed into law the Fiscal Responsibility Act of 2023.
26 On June 3, 2023, President Biden signed into law the Fiscal Responsibility Act of 2023.
Pub. L. No. 118-5, 137 Stat. 10. In addition to increasing the debt ceiling and addressing other matters related to federal spending, the Ac t, in section 321, included amendments to NEPA.
Pub. L. No. 118-5, 137 Stat. 10. In addition to increasing the debt ceiling and addressing other matters related to federal spending, the Act, in section 321, included amendments to NEPA.
The amendments added new sections (D), (E), and (F) to section 102(2); as a result, the section 102(2)(E) referred to in 10 C.F.R. § 51.105(a)(1) is now section 102(2)(H), but the substance of the provision remains the same.
The amendments added new sections (D), (E), and (F) to section 102(2); as a result, the section 102(2)(E) referred to in 10 C.F.R. § 51.105(a)(1) is now section 102(2)(H), but the substance of the provision remains the same.  
 
. determine whether the NEPA review conducted by the NRC Staff has been adequate.27
 
If we determine that the application meets the standards and requirements of the AEA and the
 
NRCs regulations and that any notifications to other agencies or bodies have been duly made,
 
we will issue a construction permit in such form and containing such conditions and limitations
 
that we deem appropriate and necessary. 28
 
We do not review Kaiross application de novo; rather, we consider the sufficiency of the
 
Staffs review of the application on both safety and environmental matters. 29 In other words, we
 
consider whether the safety and environmental record is adequate to support issuance of the
 
construction permit and whether the Staffs findings are reasonably supported in logic and fact. 30
 
Under our regulations, we must reach our own independent determination on certain
 
environmental findingsi.e., whether the relevant NEPA requirements have been met, what is
 
the appropriate final balance among conflicting factors, and whether the construction permit
 
should be issued, denied[,] or appropriately conditioned. 31 But we will not second-guess [the
 
Staffs] underlying technical or factual findings unless we find the Staffs review incomplete or
 
inadequate or its findings insufficiently explained in the record. 32
 
27 C.F.R. §. (a)( )-( ); Hearing Notice, Fed. Reg. at,. Because this is an uncontested proceeding, C.F.R. §. (a)( ), which concerns only contested proceedings, does not apply.


determine whether the NEPA review conducted by the NRC Staff has been adequate.27 If we determine that the application meets the standards and requirements of the AEA and the NRCs regulations and that any notifications to other agencies or bodies have been duly made, we will issue a construction permit in such form and containing such conditions and limitations that we deem appropriate and necessary.28 We do not review Kaiross application de novo; rather, we consider the sufficiency of the Staffs review of the application on both safety and environmental matters.29 In other words, we consider whether the safety and environmental record is adequate to support issuance of the construction permit and whether the Staffs findings are reasonably supported in logic and fact.30 Under our regulations, we must reach our own independent determination on certain environmental findingsi.e., whether the relevant NEPA requirements have been met, what is the appropriate final balance among conflicting factors, and whether the construction permit should be issued, denied[,] or appropriately conditioned.31 But we will not second-guess [the Staffs] underlying technical or factual findings unless we find the Staffs review incomplete or inadequate or its findings insufficiently explained in the record.32 27 C.F.R. §.(a)()-(); Hearing Notice, Fed. Reg. at,. Because this is an uncontested proceeding, C.F.R. §.(a)(), which concerns only contested proceedings, does not apply.
28 C.F.R. §..
28 C.F.R. §..
 
29 See Exelon Generation Co. (Early Site Permit for Clinton ESP Site), CLI--, NRC,,  
29 See Exelon Generation Co. (Early Site Permit for Clinton ESP Site), CLI- -, NRC,,
- ().
- ().
30 See id. at.
30 See id. at.
31 Id. at (quoting C.F.R. §.(a)()-()).
32 Id.


31 Id. at (quoting C.F.R. §. (a)( )-( )).
C.
 
The Hearing Process The Staff completed its safety review of the Hermes application in June, with the publication of the Safety Evaluation, and its environmental review in August, with the issuance of the Final Environmental Impact Statement (FEIS).33 Shortly after publication of the FEIS we received the Staffs information paper, which serves as the Staffs pre-filed testimony for the uncontested hearing.34 Pre-Hearing Activities The notice of hearing set a schedule for pre-hearing filings.35 We issued twenty-eight questions on environmental and safety-related topics for the Staff and Kairos to answer in writing in advance of the hearing. The questions addressed a variety of topics including functional containment, temperature monitoring of the safety-related decay heat removal system, how to address the new NEPA requirements enacted in June, and whether the cumulative impacts of the proposed Hermes facility are analyzed in the FEIS.36 We also invited interested states, local government bodies, and federally recognized Indian tribes to provide statements for us to consider as part of the uncontested proceeding.37 In response, we received a statement from the City of Oak Ridge, Tennessee.38 The letter from the 33 See Ex. NRC-, Safety Evaluation; Ex. NRC-, FEIS.
32 Id.
 
C. The Hearing Process
 
The Staff completed its safety review of the Hermes application in June, with the
 
publication of the Safety Evaluation, and its environmental review in August, with the
 
issuance of the Final Environmental Impact Statement (FEIS). 33 Shortly after publication of the
 
FEIS we received the Staffs information paper, which serves as the Staffs pre-filed testimony
 
for the uncontested hearing. 34
 
. Pre-Hearing Activities
 
The notice of hearing set a schedule for pre-hearing filings. 35 We issued twenty-eight
 
questions on environmental and safety-related topics for the Staff and Kairos to answer in
 
writing in advance of the hearing. The questions addressed a variety of topics including
 
functional containment, temperature monitori ng of the safety-related decay heat removal
 
system, how to address the new NEPA requirements enacted in June, and whether the
 
cumulative impacts of the proposed Hermes facility are analyzed in the FEIS. 36
 
We also invited interested states, local government bodies, and federally recognized
 
Indian tribes to provide statements for us to consider as part of the uncontested proceeding. 37 In
 
response, we received a statement from the City of Oak Ridge, Tennessee. 38 The letter from the
 
33 See Ex. NRC-, Safety Evaluation; Ex. NRC-, FEIS.
 
34 See Ex. NRC-, Staff Information Paper.
34 See Ex. NRC-, Staff Information Paper.
35 Hearing Notice, Fed. Reg. at,.
35 Hearing Notice, Fed. Reg. at,.
36 See Order of the Secretary (Transmitting Pre-Hearing Questions) (Sept., )
36 See Order of the Secretary (Transmitting Pre-Hearing Questions) (Sept., )
(unpublished), at - (Pre-Hearing Questions Order).
(unpublished), at - (Pre-Hearing Questions Order).
37 See Hearing Notice, Fed. Reg. at,.
37 See Hearing Notice, Fed. Reg. at,.
38 See Letter from Jack Suggs, Interim City Manager, City of Oak Ridge, Tennessee, to NRC Document Control Desk (Sept., ) (MLA).


38 See Letter from Jack Suggs, Interim City Manager, City of Oak Ridge, Tennessee, to NRC Document Control Desk (Sept., ) (ML A ).
City of Oak Ridge expressed its continued support for the Kairos project and described the positive interaction with Kairos during the Citys zoning approval process.39 The Hearing We set the topics for and the order of presentations at the hearing.40 In the first panel, witnesses for Kairos provided an overview of the Hermes test reactor project and the Hermes construction permit application.41 In the second panel, witnesses for the Staff provided an overview of the construction permit review process and a summary of the Staffs review and regulatory findings.42 The third panel focused on safety-related issues, and the fourth panel focused on environmental issues.43 The Staff made available thirty-two witnesses at the hearing.44 Thirteen of these witnesses were scheduled panelists; the remainder stood by to answer questions on topics related to their areas of expertise.45 A total of twenty-one Kairos 39 Id. at -.
 
City of Oak Ridge expressed its continued support for the Kairos project and described the
 
positive interaction with Kairos during the Citys zoning approval process. 39
 
. The Hearing
 
We set the topics for and the order of presentations at the hearing. 40 In the first panel,
 
witnesses for Kairos provided an overview of the Hermes test reactor project and the Hermes
 
construction permit application. 41 In the second panel, witnesses for the Staff provided an
 
overview of the construction permit review process and a summary of the Staffs review and
 
regulatory findings.42 The third panel focused on safety-related issues, and the fourth panel
 
focused on environmental issues. 43 The Staff made available thirty-two witnesses at the
 
hearing.44 Thirteen of these witnesses were scheduled panelists; the remainder stood by to
 
answer questions on topics related to their areas of expertise. 45 A total of twenty-one Kairos
 
39 Id. at -.
 
40 See Memorandum from Brooke P. Clark, Secretary of the Commission, to Counsel for Applicant and Staff (Oct., ), Encl. (MLA) (Scheduling Note).
40 See Memorandum from Brooke P. Clark, Secretary of the Commission, to Counsel for Applicant and Staff (Oct., ), Encl. (MLA) (Scheduling Note).
41 Ex. KRS-, Hermes Mandatory HearingOverview Panel (Oct., ) (Kairos Overview Panel Presentation).
41 Ex. KRS-, Hermes Mandatory HearingOverview Panel (Oct., ) (Kairos Overview Panel Presentation).
 
42 Ex. NRC--R, Kairos Hermes Mandatory Hearing Construction Permit Application Review:
42 Ex. NRC- -R, Kairos Hermes Mandatory Hearing Construction Permit Application Review:
Overview of Review Methodology and Summary of Key Regulatory Findings (Oct., )
Overview of Review Methodology and Summary of Key Regulatory Findings (Oct., )
(Staff Overview Panel Presentation).
(Staff Overview Panel Presentation).
43 See Ex. KRS-, Hermes Mandatory HearingSafety Panel (Oct., ) (Kairos Safety Panel Presentation); Ex. NRC-, Kairos Hermes Mandatory Hearing Construction Permit Application Review: Safety Panel (Oct., ) (Staff Safety Panel Presentation);
43 See Ex. KRS-, Hermes Mandatory HearingSafety Panel (Oct., ) (Kairos Safety Panel Presentation); Ex. NRC-, Kairos Hermes Mandatory Hearing Construction Permit Application Review: Safety Panel (Oct., ) (Staff Safety Panel Presentation);
Ex. KRS-, Hermes Mandatory HearingEnvironmental Panel (Oct., ) (Kairos Environmental Panel Presentation); Ex. NRC-, Kairos Hermes Mandatory Hearing Construction Permit Application Review (Oct., ) (Staff Environmental Panel Presentation).
Ex. KRS-, Hermes Mandatory HearingEnvironmental Panel (Oct., ) (Kairos Environmental Panel Presentation); Ex. NRC-, Kairos Hermes Mandatory Hearing Construction Permit Application Review (Oct., ) (Staff Environmental Panel Presentation).
44 See Tr. at - (Ms. Wright); see also NRC Staff Witness List (Sep., ), Attach.
(MLA).
45 See Ex. NRC--R, Staff Overview Panel Presentation, at ; Ex. NRC-, Staff Safety Panel Presentation, at (MLA) (Staff Safety Panel Presentation); Ex. NRC-, Staff Environmental Panel Presentation, at.


44 See Tr. a t - (Ms. Wright); see also NRC Staff Witness List (Sep., ), Attach.
witnesses attended the hearing, four of whom offered testimony on behalf of Kairos on panels at the hearing and in pre-filed written testimony.46
(MLA ).
: a.
 
Summary of the Overview Panels Mike Laufer, Chief Executive Officer; Ed Blandford, Chief Technology Officer; Per Peterson, Chief Nuclear Officer; and Peter Hastings, Vice President, Regulatory Affairs and Quality of Kairos Power LLC, provided testimony for the Kairos overview panel.47 Dr. Laufer provided information on the background and mission of Kairos.48 Dr. Peterson provided testimony on technical aspects and the objectives for the Hermes reactor project.49 Dr. Laufer, Dr. Peterson, and Mr. Hastings also answered questions regarding the effectiveness of Kaiross interactions with the Staff during its review, the interactions with the community around Oak Ridge, Tennessee, and the public more generally, and the purpose of the mandatory hearing process.50 Robert Taylor, Deputy Director of the Office of Nuclear Reactor Regulation (NRR);
45 See Ex. NRC- -R, Staff Overview Panel Presentation, at ; Ex. NRC-, Staff Safety Panel Presentation, at (ML A ) (Staff Safety Panel Presentation); Ex. NRC-, Staff Environmental Panel Presentation, at.
Mohamed Shams, Director, Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU), NRR; Jeremy Bowen, Deputy Director, DANU, NRR; and Christopher Regan, Director, Division of Rulemaking, Environmental, and Financial Support (REFS), Office of Nuclear Material Safety and Safeguards (NMSS), presented the Staffs overview panel and provided testimony on the Staffs review of the Kairos construction permit 46 See List of Anticipated Witnesses for Kairos Power, LLC for the Hearing on Uncontested Issues (Sep., ), at -; Tr. at - (Mr. Lighty); Ex. KRS-, Kairos Testimony; Ex. KRS-, Kairos Overview Panel Presentation, at ; Ex. KRS-, Kairos Safety Panel Presentation, at ; Ex. KRS-, Kairos Environmental Panel Presentation, at.
 
47 Tr. at - (Dr. Laufer, Dr. Peterson); Scheduling Note, Encl. at.
witnesses attended the hearing, four of whom offered testimony on behalf of Kairos on panels at
48 Tr. at - (Dr. Laufer).
 
the hearing and in pre-filed written testimony. 46
: a. Summary of the Overview Panels
 
Mike Laufer, Chief Executive Officer; Ed Blandford, Chief Technology Officer; Per
 
Peterson, Chief Nuclear Officer; and Peter Hastings, Vice President, Regulatory Affairs and
 
Quality of Kairos Power LLC, provided testimony for the Kairos overview panel. 47 Dr. Laufer
 
provided information on the background and mission of Kairos. 48 Dr. Peterson provided
 
testimony on technical aspects and the objectives for the Hermes reactor project. 49 Dr. Laufer,
 
Dr. Peterson, and Mr. Hastings also answered questions regarding the effectiveness of Kaiross
 
interactions with the Staff during its review, the interactions with the community around Oak
 
Ridge, Tennessee, and the public more generally, and the purpose of the mandatory hearing
 
process.50
 
Robert Taylor, Deputy Director of the Office of Nuclear Reactor Regulation (NRR);
 
Mohamed Shams, Director, Division of Advanced Reactors and Non-Power Production and
 
Utilization Facilities (DANU), NRR; Jeremy Bowen, Deputy Director, DANU, NRR; and
 
Christopher Regan, Director, Division of Rulemaking, Environmental, and Financial Support
 
(REFS), Office of Nuclear Material Safety and Safeguards (NMSS), presented the Staffs
 
overview panel and provided testimony on the Staf fs review of the Kairos construction permit
 
46 See List of Anticipated Witnesses for Kairos Power, LLC for the Hearing on Uncontested Issues (Sep., ), at - ; Tr. at - (Mr. Lighty); Ex. KRS-, Kairos Testimony; Ex. KRS-, Kairos Overview Panel Presentation, at ; Ex. KRS-, Kairos Safety Panel Presentation, at ; Ex. KRS-, Kairos Environmental Panel Presentation, at.
 
47 Tr. a t - (Dr. Laufer, Dr. Peterson); Scheduling Note, Encl. at.
 
48 Tr. a t - (Dr. Laufer).
 
49 Id. at - (Dr. Peterson).
49 Id. at - (Dr. Peterson).
50 Id. at - (Dr. Laufer, Dr. Peterson, Mr. Hastings).


50 Id. at - (Dr. Laufer, Dr. Peterson, Mr. Hastings).
application.51 Mr. Taylor provided an overview of the Kairos construction permit application.52 Mr. Shams described the pre-application engagement with Kairos, regulatory standards governing the construction permit application review, and public engagement during the review.53 Mr. Bowen provided insights into the Staffs safety review.54 Mr. Regan provided an overview of the Staffs environmental review and findings in support of issuance of the construction permit.55 Mr. Shams, Mr. Taylor, and Mr. Bowen answered questions relating to the applicants construction permit application, research activities, pre-application engagement, the use of topical reports in the construction permit application review, knowledge management for future advanced reactor applications, and lessons learned from the Staffs review of this construction permit application that can be applied to the Hermes construction permit application.56
 
: b.
application.51 Mr. Taylor provided an overview of the Kairos construction permit application. 52
Summary of the Safety Panel The safety panel discussed the Kairos construction permit application and Staff conclusions from the Safety Evaluation, focusing on unique features of the facility and novel issues, including TRISO fuel, molten salt coolant, high-temperature materials, functional containment, and passive accident response.57 Ed Blandford, Chief Technology Officer, Kairos 51 Id. at - (Mr. Taylor, Mr. Shams, Mr. Bowen, Mr. Regan); Scheduling Note, Encl. at.
 
Mr. Shams described the pre-application engagement with Kairos, regulatory standards
 
governing the construction permit application review, and public engagement during the
 
review.53 Mr. Bowen provided insights into the Staffs safety review. 54 Mr. Regan provided an
 
overview of the Staffs environmental review and findings in support of issuance of the
 
construction permit.55 Mr. Shams, Mr. Taylor, and Mr. Bowen answered questions relating to the
 
applicants construction permit application, research activities, pre-application engagement, the
 
use of topical reports in the construction permit application review, knowledge management for
 
future advanced reactor applications, and lessons learned from the Staffs review of this
 
construction permit application that can be applied to the Hermes construction permit
 
application.56
: b. Summary of the Safety Panel
 
The safety panel discussed the Kairos construction permit application and Staff
 
conclusions from the Safety Evaluation, focusing on unique features of the facility and novel
 
issues, including TRISO fuel, molten salt coolant, high-temperature materials, functional
 
containment, and passive accident response. 57 Ed Blandford, Chief Technology Officer, Kairos
 
51 Id. at - (Mr. Taylor, Mr. Shams, Mr. Bowen, Mr. Regan); Scheduling Note, Encl. at.
 
52 Id. at - (Mr. Taylor).
52 Id. at - (Mr. Taylor).
53 Id. at - (Mr. Shams).
53 Id. at - (Mr. Shams).
54 Id. at - (Mr. Bowen).
54 Id. at - (Mr. Bowen).
55 Id. at - (Mr. Regan).
55 Id. at - (Mr. Regan).
56 Id. at - (Mr. Shams, Mr. Taylor, Mr. Bowen).
56 Id. at - (Mr. Shams, Mr. Taylor, Mr. Bowen).
57 Id. at - (Mr. Blandford, Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy); Ex. KRS-, Kairos Safety Panel Presentation, at -; Ex. NRC-, Staff Safety Panel Presentation, at -.


57 Id. at - (Mr. Blandford, Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy); Ex. KRS-, Kairos Safety Panel Presentation, at - ; Ex. NRC-, Staff Safety Panel Presentation, at -.
Power LLC, served as the witness for Kairos.58 William Jessup, Chief, Advanced Reactor Licensing Branch, DANU, NRR; Edward Helvenston, Project Manager, DANU, NRR; Chris Van Wert, Senior Technical Advisor for Reactor Fuel, Division of Safety Systems, NRR; Alexander Chereskin, Materials Engineer, DANU, NRR; Michelle Hart, Senior Reactor Engineer, DANU, NRR; and Alexandra Siwy, Senior Nuclear Engineer, DANU, NRR, testified for the Staff.59 Kaiross testimony focused on the inherent safety features of the Hermes test reactor, including how the TRISO fuel and the Flibe coolant allow for the use of functional containment in making Kaiross safety case.60 The Staffs testimony addressed the regulatory requirements for issuing a construction permit and covered novel technical issues presented by the Hermes test reactor, including the TRISO fuel, molten salt coolant, high temperature materials, functional containment, and passive accident response.61 Following the safety panel presentations, we posed questions to witnesses for both Kairos and the Staff.
 
58 Tr. at - (Mr. Blandford); Scheduling Note, Encl. at.
Power LLC, served as the witness for Kairos. 58 William Jessup, Chief, Advanced Reactor
 
Licensing Branch, DANU, NRR; Edward Helvenston, Project Manager, DANU, NRR; Chris Van
 
Wert, Senior Technical Advisor for Reactor Fuel, Division of Safety Systems, NRR; Alexander
 
Chereskin, Materials Engineer, DANU, NRR; Michelle Hart, Senior Reactor Engineer, DANU,
 
NRR; and Alexandra Siwy, Senior Nuclear Engineer, DANU, NRR, testified for the Staff. 59
 
Kaiross testimony focused on the inherent safety features of the Hermes test reactor,
 
including how the TRISO fuel and the Flibe coolant allow for the use of functional containment in
 
making Kaiross safety case. 60 The Staffs testimony addressed the regulatory requirements for
 
issuing a construction permit and covered novel technical issues presented by the Hermes test
 
reactor, including the TRISO fuel, molten salt coolant, high temperature materials, functional
 
containment, and passive accident response. 61 Following the safety panel presentations, we
 
posed questions to witnesses for both Kairos and the Staff.
 
58 Tr. a t - (Mr. Blandford); Scheduling Note, Encl. at.
 
59 Id. at - (Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy);
59 Id. at - (Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy);
Scheduling Note, Encl. at.
Scheduling Note, Encl. at.
 
60 Tr. at - (Mr. Blandford).
60 Tr. a t - (Mr. Blandford).
 
61 Id. at - (Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy).
61 Id. at - (Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy).
: c. Summary of the Environmental Panel
: c.
 
Summary of the Environmental Panel The environmental panel focused on the FEIS, including the proposed federal action, purpose and need for the project, the environmental review process and public outreach, NEPA findings, and alternatives to the proposed action.62 Peter Hastings, Vice President, Regulatory Affairs and Quality, represented Kairos.63 Kenneth Erwin, Branch Chief, New Reactor Environmental Review Branch, REFS, NMSS; Tamsen Dozier, Project Manager, REFS, NMSS; and Peyton Doub, Environmental Scientist, REFS, NMSS, testified on behalf of the Staff.64 Mr. Hastings discussed the environmental report, the site-selection process, and characteristics of the Hermes test reactor site.65 The Staff described the proposed federal action, its environmental review process, evaluation of alternatives to the proposed action, consultation with other agencies and tribes, public outreach, and consideration of and conclusions on environmental impacts.66 Following the environmental panel presentations, we posed questions to witnesses for both Kairos and the Staff.
The environmental panel focused on the FEIS, including the proposed federal action,
Post-Hearing Activities After the hearing, we adopted corrections to the hearing transcript and admitted a revised Staff exhibit.67 We held the record open because the Staff had not yet completed its 62 Id. at - (Mr. Hastings, Mr. Erwin, Ms. Dozier, Mr. Doub); Scheduling Note, Encl. at ;
 
purpose and need for the project, the environmental review process and public outreach, NEPA
 
findings, and alternatives to the proposed action. 62 Peter Hastings, Vice President, Regulatory
 
Affairs and Quality, represented Kairos. 63 Kenneth Erwin, Branch Chief, New Reactor
 
Environmental Review Branch, REFS, NMSS; Tamsen Dozier, Project Manager, REFS, NMSS;
 
and Peyton Doub, Environmental Scientist, REFS, NMSS, testified on behalf of the Staff. 64
 
Mr. Hastings discussed the environmental report, the site-selection process, and characteristics
 
of the Hermes test reactor site. 65 The Staff described the proposed federal action, its
 
environmental review process, evaluation of alternatives to the proposed action, consultation
 
with other agencies and tribes, public outreach, and consideration of and conclusions on
 
environmental impacts.66 Following the environmental panel presentations, we posed questions
 
to witnesses for both Kairos and the Staff.
 
. Post-Hearing Activities
 
After the hearing, we adopted corrections to the hearing transcript and admitted a
 
revised Staff exhibit.67 We held the record open because the Staff had not yet completed its
 
62 Id. at - (Mr. Hastings, Mr. Erwin, Ms. Dozier, Mr. Doub); Scheduling Note, Encl. at ;
Ex. KRS-, Kairos Environmental Panel Presentation, at -; Ex. NRC-, Staff Environmental Panel Presentation, at -.
Ex. KRS-, Kairos Environmental Panel Presentation, at -; Ex. NRC-, Staff Environmental Panel Presentation, at -.
 
63 Tr. at - (Mr. Hastings); Scheduling Note, Encl. at.
63 Tr. a t - (Mr. Hastings); Scheduling Note, Encl. at.
 
64 Id. at - (Mr. Erwin, Ms. Dozier, Mr. Doub); Scheduling Note, Encl. at.
64 Id. at - (Mr. Erwin, Ms. Dozier, Mr. Doub); Scheduling Note, Encl. at.
 
65 Tr. at - (Mr. Hastings).
65 Tr. a t - (Mr. Hastings).
 
66 Id. at - (Mr. Erwin, Ms. Dozier, Mr. Doub).
66 Id. at - (Mr. Erwin, Ms. Dozier, Mr. Doub).
67 Order of the Secretary (Adopting Transcript Corrections and Admitting Revised Exhibit)
67 Order of the Secretary (Adopting Transcript Corrections and Admitting Revised Exhibit)
(Nov., ) (unpublished).
(Nov., ) (unpublished).  
 
consultation activities under the NHPA. 68 On December, the Staff filed revisions to two
 
exhibits: NRC-, the draft construction permit, and NRC-, the draft record of decision. 69 In
 
the revised draft construction permit, the Staff made several non-substantive edits and replaced
 
placeholder language relating to NHPA section with a requirement that Kairos implement its
 
Archaeological Resource Monitoring and Unanticipated Discovery Plan. 70 In the revised draft
 
record of decision, the Staff documented completion of the NHPA section process for this


licensing action. 71 Kairos does not object to the admission of these exhibits. 72 Accordingly, we
consultation activities under the NHPA.68 On December, the Staff filed revisions to two exhibits: NRC-, the draft construction permit, and NRC-, the draft record of decision.69 In the revised draft construction permit, the Staff made several non-substantive edits and replaced placeholder language relating to NHPA section with a requirement that Kairos implement its Archaeological Resource Monitoring and Unanticipated Discovery Plan.70 In the revised draft record of decision, the Staff documented completion of the NHPA section process for this licensing action.71 Kairos does not object to the admission of these exhibits.72 Accordingly, we strike exhibits NRC-and NRC-, admit exhibits NRC--R and NRC--R, and close the evidentiary record.
 
DISCUSSION As discussed in Section II.E, we find that Kaiross application meets our regulatory requirements for issuance of a construction permit. Although we authorize issuance of a construction permit, our decision does not constitute approval of the design.73 Kairos has represented that it will apply for an operating license and submit with that application a final 68 Id. at.
strike exhibits NRC-and NRC-, admit exhibits NRC--R and NRC--R, and close
69 NRC Staff Exhibit List (Dec., ) (Staff Revised Exhibit List), at ; see Ex. NRC--R, Kairos Power LLC, Docket No. -, Hermes Test Reactor Construction Permit (Oct.,  
 
) (Draft Construction Permit); Ex. NRC--R, Draft Summary Record of Decision, U.S.
the evidentiary record.
 
DISCUSSION
 
As discussed in Section II.E, we find that Kaiross application meets our regulatory
 
requirements for issuance of a construction permit. Although we authorize issuance of a
 
construction permit, our decision does not constitute approval of the design. 73 Kairos has
 
represented that it will apply for an operating license and submit with that application a final
 
68 Id. at.
 
69 NRC Staff Exhibit List (Dec., ) (Staff Revised Exhibit List), at ; see Ex. NRC--R, Kairos Power LLC, Docket No. -, Hermes Test Reactor Construction Permit (Oct.,
) (Draft Construction Permit); Ex. NRC--R, Draft Summary Record of Decision, U.S.
Nuclear Regulatory Commission, Docket No. -, Construction Permit Application for the Kairos Hermes Test Reactor (Nov., ) (Draft Record of Decision).
Nuclear Regulatory Commission, Docket No. -, Construction Permit Application for the Kairos Hermes Test Reactor (Nov., ) (Draft Record of Decision).
 
70 See Staff Revised Exhibit List at -; Ex. NRC--R, Draft Construction Permit, app. A, at A-.
70 See Staff Revised Exhibit List at - ; Ex. NRC- -R, Draft Construction Permit, app. A, at A-.
 
71 Staff Revised Exhibit List at ; Ex. NRC--R, Draft Record of Decision, at,.
71 Staff Revised Exhibit List at ; Ex. NRC--R, Draft Record of Decision, at,.
72 Staff Revised Exhibit List at.
72 Staff Revised Exhibit List at.
73 See C.F.R. §.(b) (A construction permit will constitute authorization to the applicant to proceed with construction but will not constitute Commission approval of the safety of any design feature or specification unless the applicant specifically requests such approval and such approval is incorporated into the permit.). Kairos did not request such approval.


73 See C.F.R. §. (b) (A construction permit will constitute authorization to the applicant to proceed with construction but will not constitute Commission approval of the safety of any design feature or specification unless the applicant specifically requests such approval and such approval is incorporated into the permit.). Kairos did not request such approval.
safety analysis report, which will contain the final detailed design.74 The discussion that follows provides a survey of the key facts that support our findings and certain novel issues in the Staffs safety review. We do not discuss every aspect of Kaiross construction permit application, the Staffs review, or our sufficiency review. Our decision to authorize issuance of the construction permit, however, is based on the record in its entirety.
 
A.
safety analysis report, which will contain the final detailed design. 74 The discussion that follows
The Proposed Design Kaiross Hermes reactor will be configured as a pebble bed with a chemically stable, low-pressure molten fluoride salt coolant known as Flibe.75 The pairing of high-temperature-tolerant TRISO fuel and low-pressure, single-phase, chemically stable reactor coolant reduces the number of potential fuel-damage scenarios, thus simplifying the reactor design and reducing the number of required safety systems.76 For example, low-leakage, pressure retaining containment structures are not necessary due to the low pressure of the reactor and associated piping in combination with the fission product retention provided by the TRISO fuel.77 The Hermes design further relies on passive decay heat removal and does not require an emergency core cooling system for decay heat removal or replacement of coolant inventory.78 The Hermes reactor has three major plant systems: the reactor system, the primary heat transport system, and the decay heat removal system.79 The facility includes engineered safety 74 See, e.g., Ex. KRS-, Kairos Testimony, at.
 
provides a survey of the key facts that support our findings and certain novel issues in the
 
Staffs safety review. We do not discuss every aspect of Kaiross construction permit application,
 
the Staffs review, or our sufficiency review. Our decision to authorize issuance of the
 
construction permit, however, is based on the record in its entirety.
 
A. The Proposed Design
 
Kaiross Hermes reactor will be configured as a pebble bed with a chemically stable,
 
low-pressure molten fluoride salt coolant known as Flibe. 75 The pairing of high-temperature-
 
tolerant TRISO fuel and low-pressure, single-phase, chemically stable reactor coolant reduces
 
the number of potential fuel-damage scenarios, thus simplifying the reactor design and reducing
 
the number of required safety systems. 76 For example, low-leakage, pressure retaining
 
containment structures are not necessary due to the low pressure of the reactor and associated
 
piping in combination with the fission product retention provided by the TRISO fuel. 77 The
 
Hermes design further relies on passive decay heat removal and does not require an
 
emergency core cooling system for decay heat re moval or replacement of coolant inventory. 78
 
The Hermes reactor has three major plant systems: the reactor system, the primary heat
 
transport system, and the decay heat removal system. 79 The facility includes engineered safety
 
74 See, e.g., Ex. KRS-, Kairos Testimony, at.
 
75 Ex. NRC-, Safety Evaluation, at -.
75 Ex. NRC-, Safety Evaluation, at -.
76 Ex. KRS-, Kairos Testimony, at.
76 Ex. KRS-, Kairos Testimony, at.
77 Id.; Tr. at (Dr. Peterson).
77 Id.; Tr. at (Dr. Peterson).
78 Ex. KRS-, Kairos Testimony, at.
78 Ex. KRS-, Kairos Testimony, at.
79 Id.


79 Id.
features that provide functional containment and decay heat removalthese features are credited for mitigation of the consequences of postulated events.80 Kairos uses a definition of safety-related structures, systems, and components that differs from the definition found in C.F.R. §. to establish those structures, systems, and components that are classified as safety related for the Hermes reactor. Specifically, in lieu of using the integrity of the reactor coolant pressure boundary terminology in C.F.R. §.,
 
Kairos's definition reads: the integrity of the portions of the reactor coolant boundary relied upon to maintain coolant level above the active core.81 Kairos uses this definition because the Hermes reactor does not rely on the functional capability of the primary heat transport system to remove decay heat from the reactor core, and the Staff found this definition acceptable for the proposed facility.82 TRISO Fuel Hermes will use TRISO fuel particles embedded in a carbon matrix pebble.83 The pebbles are roughly the size of golf balls, and the TRISO particles are roughly the size of poppy seeds.84 The fuel particle is composed of a uranium oxycarbide fuel kernel encased in coating layers to limit fission product releases.85 The fuel particles will contain high assay low enriched 80 See Ex. KRS-, Kairos Testimony, at.
features that provide functional containment and decay heat removalthese features are
81 Ex. NRC-, Safety Evaluation, at - (emphasis added). The Staff found that the C.F.R.  
 
credited for mitigation of the consequences of postulated events. 80
 
Kairos uses a definition of safety-related structures, systems, and components that
 
differs from the definition found in C.F.R. §. to establish those structures, systems, and
 
components that are classified as safety related for the Hermes reactor. Specifically, in lieu of
 
using the integrity of the reactor coolant pressure boundary terminology in C.F.R. §.,
 
Kairos's definition reads: the integrity of the portions of the reactor coolant boundary relied
 
upon to maintain coolant level above the active core.81 Kairos uses this definition because the
 
Hermes reactor does not rely on the functional capability of the primary heat transport system to
 
remove decay heat from the reactor core, and the Staff found this definition acceptable for the
 
proposed facility.82
 
. TRISO Fuel
 
Hermes will use TRISO fuel particles embedded in a carbon matrix pebble. 83 The
 
pebbles are roughly the size of golf balls, and the TRISO particles are roughly the size of poppy
 
seeds.84 The fuel particle is composed of a uranium oxycarbide fuel kernel encased in coating
 
layers to limit fission product releases. 85 The fuel particles will contain high assay low enriched
 
80 See Ex. KRS-, Kairos Testimony, at.
 
81 Ex. NRC-, Safety Evaluation, at - (emphasis added). The Staff found that the C.F.R.
§. definition of safety-related structures, systems, and components is not applicable to the Hermes facility. Id.; Ex. NRC-, NRC Staff Responses to Commission Pre-Hearing Questions (Sept., ), at (Staff Pre-Hearing Responses).
§. definition of safety-related structures, systems, and components is not applicable to the Hermes facility. Id.; Ex. NRC-, NRC Staff Responses to Commission Pre-Hearing Questions (Sept., ), at (Staff Pre-Hearing Responses).
82 Ex. NRC-, Safety Evaluation, at -, - to -.
82 Ex. NRC-, Safety Evaluation, at -, - to -.
83 Ex. NRC-, Staff Safety Panel Presentation, at.
83 Ex. NRC-, Staff Safety Panel Presentation, at.
84 Tr. at (Mr. Van Wert).
85 Ex. NRC-, Staff Information Paper, at.


84 Tr. a t (Mr. Van Wert).
uranium.86 The coating layers are composed of pyrolytic carbon and silicon carbide.87 In addition, there is a carbon buffer layer between the kernel and the inner pyrolytic carbon layer that serves to accommodate fission gases and limit pressure buildup.88 The TRISO particles are arranged in a fuel annulus near the outer surface of the pebble surrounding a low-density graphite core.89 In addition to fuel pebbles, the reactor also contains moderator pebbles, which have the same diameter as the fuel pebbles but contain no uranium and are made of graphite material.90 Both the fuel and moderator pebbles are designed to maintain positive buoyancy under normal operation and postulated events.91 Pebbles are buoyant in Flibe and travel upward through the core.92 The TRISO particle specification is based on the U.S. Department of Energy (DOE)
 
Advanced Gas Reactor program.93 The TRISO fuel is similar to that developed for high temperature gas-cooled reactors, and the coatings on the particle fuel have demonstrated retention of fission products to temperatures above,°C.94 In comparison, the Hermes test reactor normal operating temperature is up to °C.95 86 Ex. NRC-, Safety Evaluation, at ii.
85 Ex. NRC-, Staff Information Paper, at.
 
uranium.86 The coating layers are composed of pyrolytic carbon and silicon carbide. 87 In
 
addition, there is a carbon buffer layer between the kernel and the inner pyrolytic carbon layer
 
that serves to accommodate fission gases and limit pressure buildup. 88 The TRISO particles are
 
arranged in a fuel annulus near the outer surface of the pebble surrounding a low-density
 
graphite core.89 In addition to fuel pebbles, the reactor also contains moderator pebbles, which
 
have the same diameter as the fuel pebbles but contain no uranium and are made of graphite
 
material.90 Both the fuel and moderator pebbles are designed to maintain positive buoyancy
 
under normal operation and postulated events. 91 Pebbles are buoyant in Flibe and travel
 
upward through the core.92
 
The TRISO particle specification is based on the U.S. Department of Energy (DOE)
 
Advanced Gas Reactor program. 93 The TRISO fuel is similar to that developed for high
 
temperature gas-cooled reactors, and the coatings on the particle fuel have demonstrated
 
retention of fission products to temperatures above,°C. 94 In comparison, the Hermes test
 
reactor normal operating temperature is up to °C.95
 
86 Ex. NRC-, Safety Evaluation, at ii.
 
87 Ex. NRC-, Staff Information Paper, at.
87 Ex. NRC-, Staff Information Paper, at.
88 Id.
88 Id.
89 Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Van Wert); Ex. NRC-, Staff Safety Panel Presentation, at.
89 Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Van Wert); Ex. NRC-, Staff Safety Panel Presentation, at.
90 Ex. NRC-, Safety Evaluation, at -.
90 Ex. NRC-, Safety Evaluation, at -.
91 Id.
91 Id.
92 Id. at -.
92 Id. at -.
93 Ex. NRC-, Staff Information Paper, at.
93 Ex. NRC-, Staff Information Paper, at.
94 Id. at ; Ex. NRC-, Safety Evaluation, at - to -; Tr. at - (Dr. Peterson).
95 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.


94 Id. at ; Ex. NRC-, Safety Evaluation, at - to - ; Tr. at - (Dr. Peterson).
The Staff evaluated the Kairos fuel qualification program as described in the topical report and concluded that it meets the applicable regulatory requirements.96 Tribology testing will be conducted on fuel pebbles in two separate environments: () Flibe with an argon cover gas, and () an argon only environment.97 The coefficient of friction and wear rates will be determined during tribology tests in both of these environments.98 In its preliminary safety analysis report, Kairos provided the relevant principal design criteria, a design description of the TRISO particle and corresponding fuel elements (pebbles), and a preliminary analysis and evaluation of the fuel element demonstrating the margins of safety during normal operations and transient conditions anticipated during the life of the facility.99 The Staff concluded that the information was sufficient to conform to the applicable guidance and meet the regulatory requirements of C.F.R. §§. and..100 Both fuel and moderator pebbles will be inspected by the pebble handling and storage system as they are removed from the core.101 Therefore, neither the fuel nor moderator pebbles are expected to produce debris or dust in the reactor coolant that could inhibit the removal of heat from the core.102 96 Id.; see Final Safety Evaluation for Topical Report KP-TR-, Revision, Fuel Qualification Methodology for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor (KP-FHR),
 
(Mar., ) (MLA).
95 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.
 
The Staff evaluated the Kairos fuel qualification program as described in the topical
 
report and concluded that it meets the applicable regulatory requirements. 96 Tribology testing
 
will be conducted on fuel pebbles in two separate environments: ( ) Flibe with an argon cover
 
gas, and ( ) an argon only environment. 97 The coefficient of friction and wear rates will be
 
determined during tribology tests in both of these environments. 98 In its preliminary safety
 
analysis report, Kairos provided the relevant principal design criteria, a design description of the
 
TRISO particle and corresponding fuel elements (pebbles), and a preliminary analysis and
 
evaluation of the fuel element demonstrating the margins of safety during normal operations and
 
transient conditions anticipated during the life of the facility. 99 The Staff concluded that the
 
information was sufficient to conform to the applicable guidance and meet the regulatory
 
requirements of C.F.R. §§. and.. 100
 
Both fuel and moderator pebbles will be inspected by the pebble handling and storage
 
system as they are removed from the core. 101 Therefore, neither the fuel nor moderator pebbles
 
are expected to produce debris or dust in the reactor coolant that could inhibit the removal of
 
heat from the core.102
 
96 Id.; see Final Safety Evaluation for Topical Report KP-TR-, Revision, Fuel Qualification Methodology for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor (KP-FHR),
(Mar., ) (ML A ).
 
97 Ex. KRS-, Kairos Power LLCs Responses to Commissions Pre-hearing Questions (Oct., ), at (Kairos Pre-Hearing Responses).
97 Ex. KRS-, Kairos Power LLCs Responses to Commissions Pre-hearing Questions (Oct., ), at (Kairos Pre-Hearing Responses).
98 Id.
98 Id.
99 Ex. NRC-, Staff Information Paper, at.
99 Ex. NRC-, Staff Information Paper, at.
100 Id.
100 Id.
 
101 Ex. NRC-, Safety Evaluation, at -; Ex. KRS-, Kairos Pre-Hearing Responses, at.
101 Ex. NRC-, Safety Evaluation, at - ; Ex. KRS-, Kairos Pre-Hearing Responses, at.
 
102 Ex. KRS-, Kairos Pre-Hearing Responses, at ; Ex. NRC-, Safety Evaluation, at -
102 Ex. KRS-, Kairos Pre-Hearing Responses, at ; Ex. NRC-, Safety Evaluation, at -
to -; see also Ex. NRC-, Staff Pre-Hearing Responses, at.
to -; see also Ex. NRC-, Staff Pre-Hearing Responses, at.  
 
. Molten Salt Coolant
 
Flibe is a lithium fluoride-beryllium fluoride mixture ( LiF-BeF ).103 In the Hermes design,
 
the Flibe coolant is credited with supporting reactivity control and serving as a fission product
 
barrier.104 Flibe is able to retain radionuclides and prevent radionuclide release to the
 
environment during normal operations and postulated events. 105 The Staff reviewed the
 
capabilities of Flibe to retain fission products in its review of Karioss topical report on
 
mechanistic source term. 106
 
Flibe has advantageous heat transfer properties and is thermally and radiolytically stable
 
at high temperatures.107 But Flibe contains beryllium, which requires controls to mitigate
 
potential worker exposure, and the transmutation of lithium will generate tritium, which will also
 
need to be managed.108 The Staff will evaluate the potential beryllium hazard and its ability to
 
impact operations or accident response and the methods and systems to control tritium during
 
the operating license review. 109 During reactor operations, the Flibe coolant is expected to
 
accumulate impurities, which may affect the corrosion of primary system components, create
 
some circulating activity in the primary system, af fect reactivity characteristics, and potentially
 
affect thermophysical properties. 110 To ensure that the Flibe coolant maintains the properties
 
needed for natural circulation heat transfer, Kairos must monitor, and potentially correct, the salt
 
103 Ex. KRS-, Kairos Safety Panel Presentation, at.


Molten Salt Coolant Flibe is a lithium fluoride-beryllium fluoride mixture (LiF-BeF).103 In the Hermes design, the Flibe coolant is credited with supporting reactivity control and serving as a fission product barrier.104 Flibe is able to retain radionuclides and prevent radionuclide release to the environment during normal operations and postulated events.105 The Staff reviewed the capabilities of Flibe to retain fission products in its review of Karioss topical report on mechanistic source term.106 Flibe has advantageous heat transfer properties and is thermally and radiolytically stable at high temperatures.107 But Flibe contains beryllium, which requires controls to mitigate potential worker exposure, and the transmutation of lithium will generate tritium, which will also need to be managed.108 The Staff will evaluate the potential beryllium hazard and its ability to impact operations or accident response and the methods and systems to control tritium during the operating license review.109 During reactor operations, the Flibe coolant is expected to accumulate impurities, which may affect the corrosion of primary system components, create some circulating activity in the primary system, affect reactivity characteristics, and potentially affect thermophysical properties.110 To ensure that the Flibe coolant maintains the properties needed for natural circulation heat transfer, Kairos must monitor, and potentially correct, the salt 103 Ex. KRS-, Kairos Safety Panel Presentation, at.
104 Ex. NRC-, Staff Information Paper, at.
104 Ex. NRC-, Staff Information Paper, at.
105 Ex. KRS-, Kairos Testimony, at.
105 Ex. KRS-, Kairos Testimony, at.
 
106 Tr. at (Mr. Chereskin).
106 Tr. a t (Mr. Chereskin).
 
107 Ex. NRC-, Staff Information Paper, at.
107 Ex. NRC-, Staff Information Paper, at.
 
108 Tr. at (Mr. Chereskin).
108 Tr. a t (Mr. Chereskin).
 
109 Id.
109 Id.
110 Ex. NRC-, Staff Information Paper, at.


110 Ex. NRC-, Staff Information Paper, at.
composition.111 Kairos expects to include a limiting condition of operation to maintain the reactor coolant composition within allowable limits as part of the technical specifications in its operating license application.112 High-Temperature Materials The Hermes test reactor design operates at higher temperatures than light-water reactors.113 Therefore, the primary system components must be qualified for these high temperatures as well as for the Flibe coolant environment.114 This construction permit application is the first to reference American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section III, Division, High Temperature Materials, which was endorsed in NRC Regulatory Guide., Revision.115 Kairos will use H stainless steel and ER--- weld filler material for safety-related metallic components and ET-for graphite reflector components.116 ASME Boiler and Pressure Vessel Code Section III, Division provides an approach to ensure the mechanical and structural integrity of components that operate in high-temperature environments. It specifies material properties, such as allowable stresses based on creep damage for the metallic materials at the times and temperatures the Hermes reactor 111 Id.
 
composition.111 Kairos expects to include a limiting condition of operation to maintain the reactor
 
coolant composition within allowable limits as part of the technical specifications in its operating
 
license application.112
 
. High-Temperature Materials
 
The Hermes test reactor design operates at higher temperatures than light-water
 
reactors.113 Therefore, the primary system components must be qualified for these high
 
temperatures as well as for the Flibe coolant environment. 114 This construction permit
 
application is the first to reference American Society of Mechanical Engineers (ASME) Boiler
 
and Pressure Vessel Code Section III, Division, High Temperature Materials, which was
 
endorsed in NRC Regulatory Guide., Revision.115 Kairos will use H stainless steel and
 
ER-- - weld filler material for safety-related metallic components and ET-for graphite
 
reflector components.116
 
ASME Boiler and Pressure Vessel Code Section III, Division provides an approach to
 
ensure the mechanical and structural integrity of components that operate in high-temperature
 
environments. It specifies material properties, such as allowable stresses based on creep
 
damage for the metallic materials at the times and temperatures the Hermes reactor
 
111 Id.
 
112 See Ex. NRC-, Safety Evaluation, at -.
112 See Ex. NRC-, Safety Evaluation, at -.
113 Ex. NRC-, Staff Information Paper, at.
113 Ex. NRC-, Staff Information Paper, at.
114 Id.
114 Id.
115 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Chereskin).
115 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Chereskin).
116 Tr. at - (Mr. Chereskin); Ex. NRC-, Staff Safety Panel Presentation, at -;
Ex. NRC-, Staff Information Paper, at.


116 Tr. a t - (Mr. Chereskin); Ex. NRC-, Staff Safety Panel Presentation, at - ;
components will experience.117 The use of Section III, Division also provides rules for aspects related to structural and mechanical integrity for the use of H stainless steel.118 ASME Boiler and Pressure Vessel Code Section III, Division does not address the interactions between the Flibe environment and metallic structural materials.119 Therefore, Kairos submitted a topical report describing its qualification plan for metallic structural materials used in Flibe-wetted areas for safety-related high-temperature components of its reactor designs, including the Hermes test reactor.120 The qualification plan includes extensive testing to quantify degradation mechanisms in normal and postulated accident conditions, and the Staffs evaluation of the topical report concluded that the Kairos qualification program for metallic materials satisfies the regulatory requirements related to the qualification of H stainless steel in the Flibe environment.121 The Hermes test reactor uses graphite reflector blocks to moderate and reflect neutrons back into the reactor core and protect the reactor vessel from the effects of neutron fluence.122 The reflector blocks provide a heat sink for the core and form coolant flow channels, the pebble defueling chute, and channels for the insertion and withdrawal of reactivity control and shutdown elements.123 For graphite components, Kairos cited an approved topical report for the 117 Tr. at (Mr. Chereskin).
Ex. NRC-, Staff Information Paper, at.
 
components will experience. 117 The use of Section III, Division also provides rules for aspects
 
related to structural and mechanical integrity for the use of H stainless steel. 118
 
ASME Boiler and Pressure Vessel Code Section III, Division does not address the
 
interactions between the Flibe environment and metallic structural materials. 119 Therefore,
 
Kairos submitted a topical report describing its qualification plan for metallic structural materials
 
used in Flibe-wetted areas for safety-related high-temperature components of its reactor
 
designs, including the Hermes test reactor. 120 The qualification plan includes extensive testing to
 
quantify degradation mechanisms in normal and postulated accident conditions, and the Staffs
 
evaluation of the topical report concluded that the Kairos qualification program for metallic
 
materials satisfies the regulatory requirements related to the qualification of H stainless steel
 
in the Flibe environment. 121
 
The Hermes test reactor uses graphite reflector blocks to moderate and reflect neutrons
 
back into the reactor core and protect the reactor vessel from the effects of neutron fluence. 122
 
The reflector blocks provide a heat sink for the core and form coolant flow channels, the pebble
 
defueling chute, and channels for the insertion and withdrawal of reactivity control and shutdown
 
elements.123 For graphite components, Kairos cited an approved topical report for the
 
117 Tr. a t (Mr. Chereskin).
 
118 Id.
118 Id.
 
119 Tr. at (Mr. Chereskin).
119 Tr. a t (Mr. Chereskin).
120 See Metallic Material Qualification for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor, KP-TR--NP-A, Revision (Sept. ) (MLA).
 
120 See Metallic Material Qualification for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor, KP-TR- -NP-A, Revision (Sept. ) (ML A ).
 
121 Ex. NRC-, Staff Information Paper, at.
121 Ex. NRC-, Staff Information Paper, at.
122 Id.
122 Id.
123 Id.; Ex. NRC-, Safety Evaluation, at -.


123 Id.; Ex. NRC-, Safety Evaluation, at -.
qualification of the material.124 In its evaluation of the topical report on graphite qualification, the Staff concluded that the methodology is acceptable because it is generally consistent with applicable portions of ASME Boiler and Pressure Vessel Code, Section III, Division, with departures related to graphite material qualification.125 The behavior of graphite as a function of fluence and temperature is an important design consideration to ensure graphite components maintain their integrity and perform their design functions.126 Functional Containment The safety case for the Hermes reactor is based on the concept of functional containment, which is a barrier, or a set of barriers taken together, that effectively limits the physical transport of radioactive materials to the environment.127 For the Hermes test reactor, functional containment consists of physical barriers, operating conditions, coolant design, and fuel form.128 We previously approved the concept of functional containment in SRM-SECY--.129 Instead of using the event categorization scheme described in SECY--, Kairos identified anticipated operational occurrences, design-basis events, and beyond-design-basis-events, consistent with a maximum hypothetical accident (MHA) 124 See Graphite Material Qualification for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor, KP-TR--NP-A, Revision (Sept. ) (MLA).
 
qualification of the material. 124 In its evaluation of the topical report on graphite qualification, the
 
Staff concluded that the methodology is acceptable because it is generally consistent with
 
applicable portions of ASME Boiler and Pressure Vessel Code, Section III, Division, with
 
departures related to graphite material qualification. 125 The behavior of graphite as a function of
 
fluence and temperature is an important design consideration to ensure graphite components
 
maintain their integrity and perform their design functions. 126
 
. Functional Containment
 
The safety case for the Hermes reactor is based on the concept of functional
 
containment, which is a barrier, or a set of barriers taken together, that effectively limits the
 
physical transport of radioactive materials to the environment. 127 For the Hermes test reactor,
 
functional containment consists of physical barriers, operating conditions, coolant design, and
 
fuel form.128 We previously approved the concept of functional containment in
 
SRM-SECY--.129 Instead of using the event categorization scheme described in
 
SECY--, Kairos identified anticipated operational occurrences, design-basis events, and
 
beyond-design-basis-events, consistent with a maximum hypothetical accident (MHA)
 
124 See Graphite Material Qualification for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor, KP-TR- -NP-A, Revision (Sept. ) (ML A ).
 
125 Ex. NRC-, Staff Information Paper, at.
125 Ex. NRC-, Staff Information Paper, at.
 
126 Id.; see Tr. at - (Mr. Chereskin).
126 Id.; see Tr. a t - (Mr. Chereskin).
127 See Ex. KRS-, Kairos Safety Panel Presentation, at ; Ex. NRC-, Staff Safety Panel Presentation, at (citing SECY--, Functional Containment Performance Criteria for Non-Light-Water-Reactors, (MLA)).
 
127 See Ex. KRS-, Kairos Safety Panel Presentation, at ; Ex. NRC-, Staff Safety Panel Presentation, at (citing SECY- -, Functional Containment Performance Criteria for Non-Light-Water-Reactors, (MLA)).
 
128 Ex. NRC-, Safety Evaluation, at -.
128 Ex. NRC-, Safety Evaluation, at -.
129 Staff RequirementsSECY--Functional Containment Performance Criteria for Non-Light-Water-Reactors (Dec., ) (MLA).


129 Staff RequirementsSECY-- Functional Containment Performance Criteria for Non-Light-Water-Reactors (Dec., ) (ML A).
approach.130 The MHA is intended to bound all postulated events in terms of dose consequences, consistent with the guidance for non-power reactors in NUREG-.131 To establish the MHA, Kairos considered a broad range of event categories, including insertion of reactivity, salt spills, loss of forced circulation, malfunction of the pebble handling and storage system, radioactive releases from a subsystem or component, general challenges to normal operation, internal hazards (fire and flood), and external hazards (seismic, wind, and flood).132 The Staff concluded that Kaiross MHA analysis demonstrates that the dose consequences of the MHA are within the accident dose criteria of C.F.R. §.(a).133 Even with conservative estimates for releases from TRISO fuel, tritium in graphite structures, and argon-from activation of the cover gas, the MHA results in radiological doses at the site boundary that are well below the siting criteria of rem and also below the U.S. Environmental Protection Agency Protective Action Guides.134 The safety case for the Hermes reactor does not rely on traditional containment barriers like reactor coolant piping or the reactor building due to the effectiveness of the TRISO fuel particle and the Flibe coolant at retaining radionuclides.135 The fuel particle forms four of the five fission product barriers credited for functional containment: the fuel kernel, an inner pyrolytic carbon layer, a silicon carbide layer, and an outer pyrolytic carbon layer.136 Additionally, the fuel 130 Ex. NRC-, Staff Information Paper, at.
 
approach.130 The MHA is intended to bound all postulated events in terms of dose
 
consequences, consistent with the guidanc e for non-power reactors in NUREG-.131
 
To establish the MHA, Kairos considered a broad range of event categories, including
 
insertion of reactivity, salt spills, loss of forced circulation, malfunction of the pebble handling
 
and storage system, radioactive releases from a subsystem or component, general challenges
 
to normal operation, internal hazards (fire and flood), and external hazards (seismic, wind, and
 
flood).132 The Staff concluded that Kaiross MHA analysis demonstrates that the dose
 
consequences of the MHA are within the accident dose criteria of C.F.R. §.(a). 133 Even
 
with conservative estimates for releases from TRISO fuel, tritium in graphite structures, and
 
argon-from activation of the cover gas, the MHA results in radiological doses at the site
 
boundary that are well below the siting criteria of rem and also below the U.S. Environmental
 
Protection Agency Protective Action Guides. 134
 
The safety case for the Hermes reactor does not rely on traditional containment barriers
 
like reactor coolant piping or the reactor building due to the effectiveness of the TRISO fuel
 
particle and the Flibe coolant at retaining radionuclides. 135 The fuel particle forms four of the five
 
fission product barriers credited for functional containment: the fuel kernel, an inner pyrolytic
 
carbon layer, a silicon carbide layer, and an outer pyrolytic carbon layer. 136 Additionally, the fuel
 
130 Ex. NRC-, Staff Information Paper, at.
 
131 See Ex. KRS-, Kairos Pre-Hearing Responses, at.
131 See Ex. KRS-, Kairos Pre-Hearing Responses, at.
132 ACRS Letter at.
132 ACRS Letter at.
133 Ex. NRC-, Staff Information Paper, at.
133 Ex. NRC-, Staff Information Paper, at.
134 ACRS Letter at. The dose consequences of the MHA are less than rem at the site boundary. Ex. KRS-, Kairos Safety Panel Presentation, at.
134 ACRS Letter at. The dose consequences of the MHA are less than rem at the site boundary. Ex. KRS-, Kairos Safety Panel Presentation, at.
135 See Ex. KRS-, Kairos Safety Panel Presentation, at.
135 See Ex. KRS-, Kairos Safety Panel Presentation, at.
136 Ex. NRC-, Staff Information Paper, at.


136 Ex. NRC-, Staff Information Paper, at.
particles are embedded in an annular shell arrangement inside a spherical pebble, which provides physical protection against mechanical damage.137 The majority of radioactive material at risk for release is held within the TRISO fuel, and the Flibe coolant serves as an additional barrier for release of radionuclides for submerged fuel pebbles.138 Because the TRISO fuel and Flibe coolant effectively contain fission products such as cesium and iodine, the MHAs dose driving elements are mobile activation products, such as argon-and tritium, rather than fission products.139 Kairos described the components and operating conditions that define the Hermes test reactor functional containment in its preliminary safety analysis report.140 Kairos also identified key performance criteria on specific structures, systems, and components to ensure that the MHA remains bounding: () specified acceptable system radionuclide release design limits for the fuel and () circulating activity limits for the Flibe coolant.141 Passive Accident Response The reactor vessel system contains the reactor core and provides for circulation of reactor coolant and pebbles as well as insertion of the reactivity control and shutdown system elements in the reactor core.142 The Hermes test reactor is designed with three safety-related shutdown elements, only two of which are needed to shut down the reactor and maintain it in a 137 Ex. NRC-, Safety Evaluation, at -.
 
particles are embedded in an annular shell arrangement inside a spherical pebble, which
 
provides physical protection against mechanical damage. 137 The majority of radioactive material
 
at risk for release is held within the TRISO fuel, and the Flibe coolant serves as an additional
 
barrier for release of radionuclides for submerged fuel pebbles. 138 Because the TRISO fuel and
 
Flibe coolant effectively contain fission products such as cesium and iodine, the MHAs dose
 
driving elements are mobile activation products, such as argon-and tritium, rather than fission
 
products.139
 
Kairos described the components and operating conditions that define the Hermes test
 
reactor functional containment in its preliminary safety analysis report. 140 Kairos also identified
 
key performance criteria on specific structures, systems, and components to ensure that the
 
MHA remains bounding: () specified acceptable system radionuclide release design limits for
 
the fuel and ( ) circulating activity limits for the Flibe coolant. 141
 
. Passive Accident Response
 
The reactor vessel system contains the reactor core and provides for circulation of
 
reactor coolant and pebbles as well as insertion of the reactivity control and shutdown system
 
elements in the reactor core. 142 The Hermes test reactor is designed with three safety-related
 
shutdown elements, only two of which are needed to shut down the reactor and maintain it in a
 
137 Ex. NRC-, Safety Evaluation, at -.
 
138 See Ex. KRS-, Kairos Safety Panel Presentation, at.
138 See Ex. KRS-, Kairos Safety Panel Presentation, at.
139 Ex. KRS-, Kairos Pre-Hearing Responses, at ; ACRS Letter at.
139 Ex. KRS-, Kairos Pre-Hearing Responses, at ; ACRS Letter at.
140 Ex. NRC-, Staff Information Paper, at.
140 Ex. NRC-, Staff Information Paper, at.
141 Id.
141 Id.
142 Ex. NRC-, Safety Evaluation, at -.


142 Ex. NRC-, Safety Evaluation, at -.
safe condition.143 These elements have two positionsfully withdrawn or fully inserted.144 The shutdown elements accomplish a safe shutdown (reactor trip) through gravity insertion on a reactor trip signal or on a loss of normal electrical power, after a short delay to mitigate spurious trips.145 The reactor trip signal removes power from an electromagnetic clutch, which causes the shutdown elements to fall into the core by gravity and shut down the reactor.146 The reactor relies on passive decay heat removal and does not need an active emergency core cooling system for decay heat removal or replacement of coolant inventory.147 The decay heat removal system removes residual decay heat from the reactor core through the reactor vessel wall during both normal and off-normal conditions.148 In postulated events where the normal heat rejection system is unavailable, the decay heat removal system, along with natural circulation flow within the core, provides heat removal from fuel in the reactor core via thermal radiation and convection without the need for external sources of electrical power or operator intervention.149 Natural circulation and the passive decay heat removal system reject residual heat from the reactor core to the atmosphere.150 The decay heat removal system and 143 See Ex. NRC-, Staff Pre-Hearing Responses, at.
 
safe condition.143 These elements have two positionsfully withdrawn or fully inserted. 144 The
 
shutdown elements accomplish a safe shutdown (reactor trip) through gravity insertion on a
 
reactor trip signal or on a loss of normal electrical power, after a short delay to mitigate spurious
 
trips.145 The reactor trip signal removes power from an electromagnetic clutch, which causes the
 
shutdown elements to fall into the core by gravity and shut down the reactor. 146
 
The reactor relies on passive decay heat removal and does not need an active
 
emergency core cooling system for decay heat re moval or replacement of coolant inventory. 147
 
The decay heat removal system removes residual decay heat from the reactor core through the
 
reactor vessel wall during both normal and off-normal conditions. 148 In postulated events where
 
the normal heat rejection system is unavailable, the decay heat removal system, along with
 
natural circulation flow within the core, provides heat removal from fuel in the reactor core via
 
thermal radiation and convection without the need for external sources of electrical power or
 
operator intervention.149 Natural circulation and the passive decay heat removal system reject
 
residual heat from the reactor core to the atmosphere. 150 The decay heat removal system and
 
143 See Ex. NRC-, Staff Pre-Hearing Responses, at.
 
144 Ex. NRC-, Staff Information Paper, at.
144 Ex. NRC-, Staff Information Paper, at.
145 Id.; Ex. NRC-, Safety Evaluation, at -.
145 Id.; Ex. NRC-, Safety Evaluation, at -.
146 Ex. NRC-, Staff Safety Panel Presentation, at.
146 Ex. NRC-, Staff Safety Panel Presentation, at.
 
147 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Overview Panel Presentation, at. Active emergency replacement of coolant inventory is not required based on the results of the maximum Flibe spill event. See Ex. NRC-, Safety Evaluation, - to  
147 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Overview Panel Presentation, at. Active emergency replacement of coolant inventory is not required based on the results of the maximum Flibe spill event. See Ex. NRC-, Safety Evaluation, - to
-. The evaluation determined that, without active emergency makeup, sufficient inventory was maintained to support adequate invessel natural circulation, to ensure the fuel remains covered, and to limit the heat up and radionuclide release. Additionally, the Staff determined that a Flibe salt spill beyond that assumed in the analysis is not expected to occur. Id. at -.
-. The evaluation determined that, without active emergency makeup, sufficient inventory was maintained to support adequate invessel natural circulation, to ensure the fuel remains covered, and to limit the heat up and radionuclide release. Additionally, the Staff determined that a Flibe salt spill beyond that assumed in the analysis is not expected to occur. Id. at -.
148 Ex. NRC-, Staff Information Paper, at.
148 Ex. NRC-, Staff Information Paper, at.
149 Ex. KRS-, Kairos Testimony, at.
149 Ex. KRS-, Kairos Testimony, at.
150 See Ex. KRS-, Kairos Safety Panel Presentation, at.


150 See Ex. KRS-, Kairos Safety Panel Presentation, at.
natural circulation together provide adequate heat removal to ensure that the vessel temperature remains below design limits and that the fuel integrity is not challenged.151 The decay heat removal system is made up of four independent trains to provide redundancy in the event of a single failure.152 The decay heat removal system has sufficient inventory in the thermosyphons to operate for up to seven days to mitigate a postulated event where normal cooling systems are unavailable.153 The fluidic diodes, which are part of the reactor internals and enable natural circulation when forced circulation is lost, will be subject to planned qualification testing and inspection.154 The Staff concluded that there is reasonable assurance that the reactor vessel system will perform its safety functions of maintaining structural integrity, geometry, and coolant inventory to ensure sufficient heat removal.155 B.
 
The Proposed Site The site is located in an industrial area of Oak Ridge, Tennessee. The property is at the site of former Buildings K-and K-of the DOE gaseous diffusion plant, where uranium enrichment occurred between the mid-s and mid-s.156 The site boundary encompasses acres, of which about acres would be permanently disturbed for operations of the facility.157 The site is adjacent to Poplar Creek and. mile (. kilometer) from the Clinch River arm of the Watts Bar Reservoir.158 151 Ex. KRS-, Kairos Testimony, at.
natural circulation together provide adequate heat removal to ensure that the vessel
 
temperature remains below design limits and that the fuel integrity is not challenged. 151
 
The decay heat removal system is made up of four independent trains to provide
 
redundancy in the event of a single failure. 152 The decay heat removal system has sufficient
 
inventory in the thermosyphons to operate for up to seven days to mitigate a postulated event
 
where normal cooling systems are unavailable. 153 The fluidic diodes, which are part of the
 
reactor internals and enable natural circulation when forced circulation is lost, will be subject to
 
planned qualification testing and inspection. 154 The Staff concluded that there is reasonable
 
assurance that the reactor vessel system will perform its safety functions of maintaining
 
structural integrity, geometry, and coolant inventory to ensure sufficient heat removal. 155
 
B. The Proposed Site
 
The site is located in an industrial area of Oak Ridge, Tennessee. The property is at the
 
site of former Buildings K-and K-of the DOE gaseous diffusion plant, where uranium
 
enrichment occurred between the mid-s and mid-s.156 The site boundary encompasses
 
acres, of which about acres would be permanently disturbed for operations of the
 
facility.157 The site is adjacent to Poplar Creek and. mile (. kilometer) from the Clinch River
 
arm of the Watts Bar Reservoir.158
 
151 Ex. KRS-, Kairos Testimony, at.
 
152 Id.
152 Id.
153 Ex. NRC-, Staff Information Paper, at.
153 Ex. NRC-, Staff Information Paper, at.
154 Id.; Ex. NRC-, Safety Evaluation, at -.
154 Id.; Ex. NRC-, Safety Evaluation, at -.
155 Ex. NRC-, Staff Information Paper, at -.
155 Ex. NRC-, Staff Information Paper, at -.
156 Id. at ; Ex. KRS-, Kairos Testimony, at.
156 Id. at ; Ex. KRS-, Kairos Testimony, at.
157 Ex. KRS-, Kairos Overview Panel Presentation, at.
157 Ex. KRS-, Kairos Overview Panel Presentation, at.
158 Ex. KRS-, Kairos Testimony, at.


158 Ex. KRS-, Kairos Testimony, at.
The Staff considered the relevant siting criteria in Part and guidance in NUREG-and concluded that the Hermes facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.159 The Staff considered site characteristics such as geography and demography; nearby industrial, transportation, and military facilities; meteorology; hydrology; and geology, seismology, and geotechnical engineering.160 In addition, the Staff evaluated structures, systems, and components and equipment designed to ensure safe operation, performance, and shutdown when subjected to extreme weather, floods, seismic events, missiles (including aircraft impacts), chemical and radiological releases, and loss of offsite power.161 As stated earlier, Kairos plans to operate the reactor for four years. When the Staff assessed flooding hazards from potential dam failures, it relied on this limited operating lifetime to approve the acceptability of the site.162 Therefore, an operating license, if issued, would include a license term that would be limited to ensure the validity of assumptions and conclusions in the safety analysis for the final design of the Hermes facility.163 The Staff verified that the Hermes emergency planning zone size is appropriate and consistent with guidance based on the preliminary MHA calculations, which indicate that accident doses at the emergency planning zone boundary would not exceed the doses recommended by the U.S. Environmental Protection Agency protective action guidelines of rem total effective dose equivalent or rem projected child thyroid dose.164 The Staff will 159 See C.F.R. §.(a)()(ii).
 
The Staff considered the relevant siting criteria in Part and guidance in NUREG-  
 
and concluded that the Hermes facility can be constructed and operated at the proposed
 
location without undue risk to the health and safety of the public. 159 The Staff considered site
 
characteristics such as geography and demogr aphy; nearby industrial, transportation, and
 
military facilities; meteorology; hydrology; and geology, seismology, and geotechnical
 
engineering.160 In addition, the Staff evaluated structures, systems, and components and
 
equipment designed to ensure safe operation, performance, and shutdown when subjected to
 
extreme weather, floods, seismic events, missile s (including aircraft impacts), chemical and
 
radiological releases, and loss of offsite power. 161 As stated earlier, Kairos plans to operate the
 
reactor for four years. When the Staff assessed flooding hazards from potential dam failures, it
 
relied on this limited operating lifetime to approve the acceptability of the site. 162 Therefore, an
 
operating license, if issued, would include a lice nse term that would be limited to ensure the
 
validity of assumptions and conclusions in the safety analysis for the final design of the Hermes
 
facility.163
 
The Staff verified that the Hermes emergency planning zone size is appropriate and
 
consistent with guidance based on the preliminary MHA calculations, which indicate that
 
accident doses at the emergency planning zone boundary would not exceed the doses
 
recommended by the U.S. Environmental Protection Agency protective action guidelines of
 
rem total effective dose equivalent or rem projected child thyroid dose. 164 The Staff will
 
159 See C.F.R. §. (a)( )(ii).
 
160 Ex. NRC-, Safety Evaluation, at - to -.
160 Ex. NRC-, Safety Evaluation, at - to -.
161 Id.
161 Id.
162 Ex. NRC-, Staff Pre-Hearing Responses, at -.
162 Ex. NRC-, Staff Pre-Hearing Responses, at -.
163 Id. at.
163 Id. at.
164 Ex. NRC-, Safety Evaluation, at -; Ex. NRC-, Staff Pre-Hearing Responses, at -.


164 Ex. NRC-, Safety Evaluation, at - ; Ex. NRC-, Staff Pre-Hearing Responses, at -.
review the final justification for the emergency planning zone size based on more detailed plant design information during review of the operating license application.165 In pre-hearing questions, we inquired into potential hazards associated with the proposed Oak Ridge Airport. Kairos used DOE guidelines and methodologies in its evaluation of crash frequencies related to the proposed airport in its preliminary safety analysis report.166 Kairos will design the safety-related portion of the reactor building to withstand the impact of general aviation aircraft associated with operations at the proposed airport.167 Based on information in the environmental assessment prepared by DOE for the proposed Oak Ridge Airport, the Staff expects that the Beechcraft King Air i likely bounds the other types of general aviation aircraft that would use the airport.168 Additionally, Kairos stated that any proposed configuration of the airport runways is not anticipated to change the need to design for aircraft impact.169 C.
 
Technical and Design Information for Later Consideration Kairos has described the principal design features and the technology that it plans to use, but Kairos will supply further technical and design information in the final safety analysis report filed as part of the operating license application in accordance with C.F.R.  
review the final justification for the emergency planning zone size based on more detailed plant
§.(a)(). The construction permit will not constitute approval of the safety of any design feature or specification.170 Because Kairos did not request approval of any design features or 165 Ex. NRC-, Staff Pre-Hearing Responses, at.
 
design information during review of the operating license application. 165
 
In pre-hearing questions, we inquired into potential hazards associated with the
 
proposed Oak Ridge Airport. Kairos used DOE guidelines and methodologies in its evaluation of
 
crash frequencies related to the proposed airport in its preliminary safety analysis report. 166
 
Kairos will design the safety-related portion of the reactor building to withstand the impact of
 
general aviation aircraft associated with operations at the proposed airport. 167 Based on
 
information in the environmental assessment prepared by DOE for the proposed Oak Ridge
 
Airport, the Staff expects that the Beechcraft King Air i likely bounds the other types of
 
general aviation aircraft that would use the airport. 168 Additionally, Kairos stated that any
 
proposed configuration of the airport runways is not anticipated to change the need to design for
 
aircraft impact.169
 
C. Technical and Design Information for Later Consideration
 
Kairos has described the principal design features and the technology that it plans to
 
use, but Kairos will supply further technical and design information in the final safety analysis
 
report filed as part of the operating license application in accordance with C.F.R.
 
§. (a)( ). The construction permit will not constitute approval of the safety of any design
 
feature or specification.170 Because Kairos did not request approval of any design features or
 
165 Ex. NRC-, Staff Pre-Hearing Responses, at.
 
166 Ex. KRS-, Kairos Pre-Hearing Responses, at.
166 Ex. KRS-, Kairos Pre-Hearing Responses, at.
 
167 Id. at -; see Ex. NRC-, Staff Pre-Hearing Responses, at.
167 Id. at - ; see Ex. NRC-, Staff Pre-Hearing Responses, at.
 
168 Ex. NRC-, Staff Pre-Hearing Responses, at.
168 Ex. NRC-, Staff Pre-Hearing Responses, at.
169 Ex. KRS-, Kairos Pre-Hearing Responses, at.
169 Ex. KRS-, Kairos Pre-Hearing Responses, at.
170 Ex. NRC-, Staff Information Paper, at ; Ex. NRC-, Staff Safety Panel Presentation, at.


170 Ex. NRC-, Staff Information Paper, at ; Ex. NRC-, Staff Safety Panel Presentation, at.
specifications to be included in the construction permit, the Staff did not make any findings regarding the safety of any Part design feature or specification.171 The Staff identified two conditions to include in the construction permitone relating to site characteristics and one relating to quality assurance. The first condition directs Kairos to confirm the condition of bedrock supporting the facility and provides for examination of excavations by the Staff, if necessary.172 The second requires Kairos to implement its quality assurance program for design, procurement, and construction of the Hermes reactor.173 By including this condition, the construction permit will have an explicit requirement comparable to C.F.R. §.(f)(). This condition will allow Kairos to make changes to the program without prior NRC approval that do not reduce commitments in the program description previously approved by the NRC, consistent with C.F.R. §.(f)().174 Without this license condition, the Staff would need to approve a license amendment request from Kairos to make any changes to the quality assurance plan regardless of whether the change would reduce a commitment.175 As it finalizes the design of its facility, Kairos will need to complete the following research and development activities: () perform a laboratory testing program to confirm fuel pebble behavior; () develop a high-temperature material surveillance sampling program for the reactor vessel and internals; () perform testing of high-temperature material to qualify Alloy H and ER---; () perform an analysis related to potential oxidation in certain postulated events for 171 Ex. NRC-, Staff Information Paper, at ; Ex. NRC-, Staff Pre-Hearing Responses, at.
 
specifications to be included in the construction permit, the Staff did not make any findings
 
regarding the safety of any Part design feature or specification. 171
 
The Staff identified two conditions to include in the construction permitone relating to
 
site characteristics and one relating to quality assurance. The first condition directs Kairos to
 
confirm the condition of bedrock supporting the facility and provides for examination of
 
excavations by the Staff, if necessary. 172 The second requires Kairos to implement its quality
 
assurance program for design, procurement, and construction of the Hermes reactor. 173 By
 
including this condition, the construction permit will have an explicit requirement comparable to
 
C.F.R. §. (f)( ). This condition will allow Kairos to make changes to the program without
 
prior NRC approval that do not reduce commitments in the program description previously
 
approved by the NRC, consistent with C.F.R. §. (f)( ).174 Without this license condition,
 
the Staff would need to approve a license amendment request from Kairos to make any
 
changes to the quality assurance plan regardless of whether the change would reduce a
 
commitment.175
 
As it finalizes the design of its facility, Kairos will need to complete the following research
 
and development activities: () perform a laboratory testing program to confirm fuel pebble
 
behavior; ( ) develop a high-temperature material surveillance sampling program for the reactor
 
vessel and internals; ( ) perform testing of high-temperature material to qualify Alloy H and
 
ER-- - ; ( ) perform an analysis related to potential oxidation in certain postulated events for
 
171 Ex. NRC-, Staff Information Paper, at ; Ex. NRC-, Staff Pre-Hearing Responses, at.
 
172 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.
172 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.
173 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.
173 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.
174 Ex. KRS-, Kairos Pre-Hearing Responses, at.
174 Ex. KRS-, Kairos Pre-Hearing Responses, at.
175 Id.


175 Id.
the qualification of the graphite used in the reflector structure; () develop and validate computer codes for core design and analysis methodology; () develop a fluidic diode device to ensure proper circulation during normal operation and passive cooling by natural circulation; () justify thermodynamic data and associated vapor pressure correlations of representative species;
 
() develop process sensor technology for key reactor process variables; and () develop the reactor coolant chemical monitoring instrumentation.176 The Staff listed these activities in Appendix A, Section A. of the Safety Evaluation and will verify that they are completed prior to the completion of construction, which Kairos projects to be December.177 The Staff will also track several other items listed in Appendix A, Section A. of the Safety Evaluation that Kairos must address in its operating license application.178 This list contains elements of design, analysis, and administration that are not necessary for issuance of a construction permit but need additional development or resolution before issuance of an operating license.
the qualification of the graphite used in the reflector structure; ( ) develop and validate computer
After reviewing the construction permit application, the ACRS recommended that Kairos address three topics in the operating license application: () combustible gas generation,
 
() tritium release levels, and () management of airborne tritium and beryllium in the facility.179 In response to the ACRS review, the Staff stated that it will consider the identified topics in its review of the operating license application.180 In response to our pre-hearing questions, Kairos stated that the specific instrumentation of the tritium management system and its capabilities to 176 Ex. NRC-, Staff Information Paper, at -; Ex. KRS-, Kairos Testimony, at.
codes for core design and analysis methodology; ( ) develop a fluidic diode device to ensure
 
proper circulation during normal operation and passive cooling by natural circulation; ( ) justify
 
thermodynamic data and associated vapor pressu re correlations of representative species;
 
( ) develop process sensor technology for key reactor process variables; and ( ) develop the
 
reactor coolant chemical monitoring instrumentation. 176 The Staff listed these activities in
 
Appendix A, Section A. of the Safety Evaluation and will verify that they are completed prior to
 
the completion of construction, which Kairos projects to be December. 177
 
The Staff will also track several other items listed in Appendix A, Section A. of the
 
Safety Evaluation that Kairos must address in its operating license application. 178 This list
 
contains elements of design, analysis, and administration that are not necessary for issuance of
 
a construction permit but need additional development or resolution before issuance of an
 
operating license.
 
After reviewing the construction permit application, the ACRS recommended that Kairos
 
address three topics in the operating license application: ( ) combustible gas generation,
 
( ) tritium release levels, and ( ) management of airborne tritium and beryllium in the facility. 179
 
In response to the ACRS review, the Staff stated that it will consider the identified topics in its
 
review of the operating license application. 180 In response to our pre-hearing questions, Kairos
 
stated that the specific instrumentation of the tritium management system and its capabilities to
 
176 Ex. NRC-, Staff Information Paper, at - ; Ex. KRS-, Kairos Testimony, at.
 
177 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at -; see also Ex. NRC--R, Draft Construction Permit, at.
177 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at -; see also Ex. NRC--R, Draft Construction Permit, at.
178 See Ex. KRS-, Kairos Testimony, at.
178 See Ex. KRS-, Kairos Testimony, at.
179 Ex. NRC-, Staff Safety Panel Presentation, at, ; Tr. at (Mr. Chereskin).
179 Ex. NRC-, Staff Safety Panel Presentation, at, ; Tr. at (Mr. Chereskin).
180 See Letter from Robert Taylor on behalf of Andrea D. Veil, NRR, to Joy L. Rempe, ACRS (June, ) (MLA).


180 See Letter from Robert Taylor on behalf of Andrea D. Veil, NRR, to Joy L. Rempe, ACRS (June, ) (ML A).
measure tritium, for comparison with limits derived from the MHA, will be discussed in further detail in the final safety analysis report.181 D.
 
The Staffs Environmental Review As required by our regulations, the Staff prepared an environmental impact statement (EIS) for the Hermes construction permit application.182 Although the Staffs safety review was limited to the findings necessary for issuance of the construction permit, the Staffs environmental review was broader in scope. In addition to evaluating the environmental impacts of facility construction, the Staff evaluated the impacts of facility operation and decommissioning to the extent that information was available for these activities.183 In its review of the Hermes project, the Staff made effective use of existing resources, such as the recently completed EIS for the Tennessee Valley Authoritys early site permit application for the Clinch River small modular reactor project, which would be situated approximately two miles south of where the Hermes reactor would be constructed.184 The Staff issued the draft EIS (DEIS) in September and the FEIS in August  
measure tritium, for comparison with limits deriv ed from the MHA, will be discussed in further
.185 After publishing a notice of its intent to prepare an EIS, the Staff conducted a virtual joint public outreach and scoping meeting in March.186 The Staff received public comments 181 Ex. KRS-, Kairos Pre-Hearing Responses, at -; Ex. NRC-, Staff Pre-Hearing Responses, at -.
 
182 See C.F.R. §.(b)() (requiring EIS for issuance of a permit to construct a nuclear testing facility); Ex. NRC-, FEIS, at xiii, -.
detail in the final safety analysis report. 181
 
D. The Staffs Environmental Review
 
As required by our regulations, the Staff prepared an environmental impact statement
 
(EIS) for the Hermes construction permit application. 182 Although the Staffs safety review was
 
limited to the findings necessary for issuance of the construction permit, the Staffs
 
environmental review was broader in scope. In addition to evaluating the environmental impacts
 
of facility construction, the Staff evaluated the impacts of facility operation and decommissioning
 
to the extent that information was available for these activities. 183 In its review of the Hermes
 
project, the Staff made effective use of existing resources, such as the recently completed EIS
 
for the Tennessee Valley Authoritys early site permit application for the Clinch River small
 
modular reactor project, which would be situated approximately two miles south of where the
 
Hermes reactor would be constructed. 184
 
The Staff issued the draft EIS (DEIS) in September and the FEIS in August
 
. 185 After publishing a notice of its intent to prepare an EIS, the Staff conducted a virtual
 
joint public outreach and scoping meeting in March. 186 The Staff received public comments
 
181 Ex. KRS-, Kairos Pre-Hearing Responses, at - ; Ex. NRC-, Staff Pre-Hearing Responses, at -.
 
182 See C.F.R. §. (b)( ) (requiring EIS for issuance of a permit to construct a nuclear testing facility); Ex. NRC-, FEIS, at xiii, -.
 
183 Ex. NRC-, FEIS, at -, -. The Staff would perform separate environmental reviews for any subsequent licensing actions, such as an operating license application, operating license renewal, and decommissioning.
183 Ex. NRC-, FEIS, at -, -. The Staff would perform separate environmental reviews for any subsequent licensing actions, such as an operating license application, operating license renewal, and decommissioning.
184 See id. at -.
184 See id. at -.
185 Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Draft Report for Comment), NUREG- (MLA); Ex. NRC-, FEIS.
186 Ex. NRC-, FEIS, at -. The Staffs decision to conduct a virtual meeting was based on high Covid-transmission rates in the Oak Ridge area at that time. Id. at G-.


185 Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Draft Report for Comment), NUREG- (ML A); Ex. NRC-, FEIS.
during a sixty-day scoping process in early. The Staff also conducted a virtual environmental audit in March to verify information in the Kairos environmental report and discuss information needs with Kairos staff and their contractors.187 The DEIS was issued for public comment, and the comments received were addressed by the Staff in the FEIS.188 As discussed above, the proposed site for the Hermes project is a -acre site in the Heritage Center Industrial Park of the East Tennessee Technology Park, located within the corporate limits of the City of Oak Ridge, Tennessee.189 The industrial park was established on land formerly owned by DOE, and the site proposed for the Hermes project was previously the site of two buildings that formed part of the Oak Ridge Gaseous Diffusion Plant. These buildings were razed after the gaseous diffusion plant ceased operations in the s, and the site was environmentally remediated and released for industrial reuse, subject to certain restrictions.190 Most of the -acre site consists of developed land and herbaceous grassland, with bands of forested land in perimeter areas between previously developed land and adjacent waterways.191 The site is bounded on the south and east by Poplar Creek, and the Clinch River arm of the Watts Bar Reservoir lies near the western border of the site boundary.192 The Hermes project would make use of existing industrial infrastructure, with the exception of additional roads and 187 Id. at -.
 
186 Ex. NRC-, FEIS, at -. The Staffs decision to conduct a virtual meeting was based on high Covid-transmission rates in the Oak Ridge area at that time. Id. at G-.
 
during a sixty-day scoping process in early. The Staff also conducted a virtual
 
environmental audit in March to verify information in the Kairos environmental report and
 
discuss information needs with Kairos staff and their contractors. 187 The DEIS was issued for
 
public comment, and the comments received were addressed by the Staff in the FEIS. 188
 
As discussed above, the proposed site for the Hermes project is a -acre site in the
 
Heritage Center Industrial Park of the East Tennessee Technology Park, located within the
 
corporate limits of the City of Oak Ridge, Tennessee. 189 The industrial park was established on
 
land formerly owned by DOE, and the site proposed for the Hermes project was previously the
 
site of two buildings that formed part of the Oak Ridge Gaseous Diffusion Plant. These buildings
 
were razed after the gaseous diffusion plant ceased operations in the s, and the site was
 
environmentally remediated and released for industrial reuse, subject to certain restrictions. 190
 
Most of the -acre site consists of developed land and herbaceous grassland, with bands of
 
forested land in perimeter areas between previously developed land and adjacent waterways. 191
 
The site is bounded on the south and east by Poplar Creek, and the Clinch River arm of the
 
Watts Bar Reservoir lies near the western border of the site boundary. 192 The Hermes project
 
would make use of existing industrial infrastruc ture, with the exception of additional roads and
 
187 Id. at -.
 
188 Id., app. G.
188 Id., app. G.
189 Id. at -.
189 Id. at -.
190 Id. at -, G-to G-. These restrictions pertain to the use of and occupational exposure to contaminated groundwater and at the site. See id. at G-to G-.
190 Id. at -, G-to G-. These restrictions pertain to the use of and occupational exposure to contaminated groundwater and at the site. See id. at G-to G-.
191 Id. at -.
191 Id. at -.
192 Id. at - fig. -, -. The only wetland on or adjacent to the Hermes site occurs in the forested perimeter lands adjoining Poplar Creek. Id. at - to -.


192 Id. at - fig. -, -. The only wetland on or adjacent to the Hermes site occurs in the forested perimeter lands adjoining Poplar Creek. Id. at - to -.
parking lots that would be constructed to service the -acre portion of the site on which the reactor and its auxiliary buildings would be situated.193 The Staff evaluated the environmental impacts of constructing, operating, and decommissioning the Hermes reactor across a variety of resource areas: land use and visual resources; air quality and noise; hydrogeology and water resources; ecological resources; historic and cultural resources; socioeconomics and environmental justice; human health; nonradiological waste management; uranium fuel cycle and radiological waste management; transportation; accidents; and climate change.194 The Staff also analyzed the cumulative environmental impacts of other projects proposed in the Oak Ridge region in conjunction with the Hermes project for each resource area considered.195 The Staff found that the direct and indirect impacts of the proposed action in each of these areas would be small.196 Impacts are considered small if they are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resource.197 In July, Kairos submitted a construction permit application for the Hermes project, a two-unit fluoride salt-cooled, high temperature test reactor that would be situated adjacent to the Hermes test reactor. We asked the Staff whether the analysis in the FEIS accounted for the cumulative impacts of the applicants new proposed project. The Staff 193 See id. at -.
 
parking lots that would be constructed to service the -acre portion of the site on which the
 
reactor and its auxiliary buildings would be situated. 193
 
The Staff evaluated the environmental impacts of constructing, operating, and
 
decommissioning the Hermes reactor across a variety of resource areas: land use and visual
 
resources; air quality and noise; hydrogeology and water resources; ecological resources;
 
historic and cultural resources; socioec onomics and environmental justice; human health;
 
nonradiological waste management; uranium fuel cycle and radiological waste management;
 
transportation; accidents; and climate change. 194 The Staff also analyzed the cumulative
 
environmental impacts of other projects proposed in the Oak Ridge region in conjunction with
 
the Hermes project for each resource area considered. 195 The Staff found that the direct and
 
indirect impacts of the proposed action in each of these areas would be small. 196 Impacts are
 
considered small if they are not detectable or are so minor that they will neither destabilize
 
nor noticeably alter any important attribute of the resource. 197
 
In July, Kairos submitted a construction permit application for the Hermes  
 
project, a two-unit fluoride salt-cooled, high temperature test reactor that would be situated
 
adjacent to the Hermes test reactor. We asked the Staff whether the analysis in the FEIS
 
accounted for the cumulative impacts of the applicants new proposed project. The Staff
 
193 See id. at -.
 
194 Id. at - tbl. -.
194 Id. at - tbl. -.
195 Id. at -. These included continuing DOE operations at Oak Ridge National Laboratory and the Y-site; industrial development in the East Tennessee Technology Park; the Ultra Safe Nuclear Corporation Pilot Fuel Manufacturing Facility; the Sequoyah and Watts Bar nuclear plants; and future projects such as the construction and operation of small modular reactors at the Clinch River Nuclear site; the applicants plan to construct and operate the Kairos Atlas Fuel Fabrication Facility at the Hermes site; the planned TRISO-X fuel fabrication facility; and development of a general aviation airport to the south of the Hermes site. Id. at -.
195 Id. at -. These included continuing DOE operations at Oak Ridge National Laboratory and the Y-site; industrial development in the East Tennessee Technology Park; the Ultra Safe Nuclear Corporation Pilot Fuel Manufacturing Facility; the Sequoyah and Watts Bar nuclear plants; and future projects such as the construction and operation of small modular reactors at the Clinch River Nuclear site; the applicants plan to construct and operate the Kairos Atlas Fuel Fabrication Facility at the Hermes site; the planned TRISO-X fuel fabrication facility; and development of a general aviation airport to the south of the Hermes site. Id. at -.
196 Id. at - tbl. -.
196 Id. at - tbl. -.
197 Id. at -.


197 Id. at -.
explained that the FEIS was published too soon after submission of the Hermes application to account for these impacts in the Hermes FEIS, but that an evaluation was performed to determine the significance of the Hermes project on the FEISs cumulative impacts analysis.198 The Staff concluded in this evaluation that the proposed Hermes project would not alter the conclusion in the FEIS that the cumulative impacts from the Hermes reactor and other past, present, and reasonably foreseeable actions would be SMALL for all environmental resources.199 Accordingly, the Staff determined that information in the Hermes application did not require preparation of a supplement to the Hermes FEIS.200 To fulfill its obligations under section of the Endangered Species Act of, the Staff compiled a table of federally listed endangered species using databases maintained by the U.S.
 
Fish and Wildlife Service (FWS) and the Tennessee Department of Environment and Conservation, and the information in Kaiross environmental report.201 The Staff defined the action area for the purposes of this review as the -acre Hermes site, which consists of lands previously disturbed by DOEs operations but also includes, for conservatism, slivers of riparian forested land on the site bordering Poplar Creek that might be affected by project-related 198 Ex. NRC-, Staff Pre-Hearing Responses, at -.
explained that the FEIS was published too soon after submission of the Hermes application to
199 Memorandum from Christopher M. Regan, Director, Division of Rulemaking, Environmental, and Financial Support, NMSS, to John W. Lubinski, Director, NMSS, Consideration of New Information Regarding Potential Cumulative Impacts from the Proposed Kairos Hermes Test Reactor on the Kairos Hermes Construction Permit Review (Sept., ), Encl. at (MLA (package)).
 
account for these impacts in the Hermes FEIS, but that an evaluation was performed to
 
determine the significance of the Hermes project on the FEISs cumulative impacts
 
analysis.198 The Staff concluded in this evaluation that the proposed Hermes project would
 
not alter the conclusion in the FEIS that the cumulative impacts from the Hermes reactor and
 
other past, present, and reasonably foreseeable ac tions would be SMALL for all environmental
 
resources.199 Accordingly, the Staff determined that information in the Hermes application did
 
not require preparation of a supplement to the Hermes FEIS. 200
 
To fulfill its obligations under section of the Endangered Species Act of, the Staff
 
compiled a table of federally listed endangered species using databases maintained by the U.S.
 
Fish and Wildlife Service (FWS) and the Tennessee Department of Environment and
 
Conservation, and the information in Kaiross environmental report. 201 The Staff defined the
 
action area for the purposes of this review as the -acre Hermes site, which consists of lands
 
previously disturbed by DOEs operations but also includes, for conservatism, slivers of riparian
 
forested land on the site bordering Poplar Creek that might be affected by project-related
 
198 Ex. NRC-, Staff Pre-Hearing Responses, at -.
 
199 Memorandum from Christopher M. Regan, Director, Division of Rulemaking, Environmental, and Financial Support, NMSS, to John W. Lubinski, Director, NMSS, Consideration of New Information Regarding Potential Cumulative Impacts from the Proposed Kairos Hermes Te s t Reactor on the Kairos Hermes Construction Permit Review (Sept., ), Encl. at (ML A (package)).
 
200 Id.
200 Id.
201 Ex. NRC-, FEIS, at -, -. Section of the Endangered Species Act requires an agency, in consultation with the Secretary of the Interior or the Secretary of Commerce (as appropriate), to ensure that any action authorized, funded, or carried out by such an agency...
201 Ex. NRC-, FEIS, at -, -. Section of the Endangered Species Act requires an agency, in consultation with the Secretary of the Interior or the Secretary of Commerce (as appropriate), to ensure that any action authorized, funded, or carried out by such an agency...
is not likely to jeopardize the continued existence of any endangered species or threatened species or result in the destruction or adverse modification of [critical] habitat of such species.
is not likely to jeopardize the continued existence of any endangered species or threatened species or result in the destruction or adverse modification of [critical] habitat of such species.
Endangered Species Act § (a)( ), U.S.C. § (a)( ). The Fish and Wildlife Service (under the Department of the Interior) and the National Marine Fisheries Service (under the Department of Commerce) jointly administer the Act.
Endangered Species Act § (a)(), U.S.C. § (a)(). The Fish and Wildlife Service (under the Department of the Interior) and the National Marine Fisheries Service (under the Department of Commerce) jointly administer the Act.  
 
noise.202 The Staff identified the potential for four federally listed engendered species, four
 
federally listed threatened species, and one federal candidate species to occur at the site. 203 At
 
the request of the FWS, the Staff included in the FEIS a biological evaluation addressing the
 
potential impacts from the Hermes project on these species. 204 Because of historical
 
disturbances to the affected site and the lack of disturbance to forest and other natural
 
vegetation, wetlands, or aquatic habitat from construction activities, the Staff found that effects
 
on terrestrial wildlife habitats would be minimal, and the potential ecological impacts of the
 
proposed action would be small. 205 The Staff determined that the Hermes project may affect, but
 
is not likely to adversely affect (or would not affect), any of these endangered species. 206 On
 
January,, the FWS concurred with the Staffs conclusions in its biological evaluation,
 
which completed the NRCs responsibilities under section of the Endangered Species Act.207
 
The Staff originally proposed to include a condition in the Environmental Protection Plan
 
(EPP), which is incorporated into the constructi on permit, that Kairos must request a license
 
amendment to incorporate the requirements of any Terms and Conditions set forth in the
 
Incidental Take Statement of Biological Opinions issued subsequent to the effective date of this
 
EPP.208 However, the Staff did not engage in formal consultation with FWS and, as a result, did
 
202 Ex. NRC-, FEIS, at -.


noise.202 The Staff identified the potential for four federally listed engendered species, four federally listed threatened species, and one federal candidate species to occur at the site.203 At the request of the FWS, the Staff included in the FEIS a biological evaluation addressing the potential impacts from the Hermes project on these species.204 Because of historical disturbances to the affected site and the lack of disturbance to forest and other natural vegetation, wetlands, or aquatic habitat from construction activities, the Staff found that effects on terrestrial wildlife habitats would be minimal, and the potential ecological impacts of the proposed action would be small.205 The Staff determined that the Hermes project may affect, but is not likely to adversely affect (or would not affect), any of these endangered species.206 On January,, the FWS concurred with the Staffs conclusions in its biological evaluation, which completed the NRCs responsibilities under section of the Endangered Species Act.207 The Staff originally proposed to include a condition in the Environmental Protection Plan (EPP), which is incorporated into the construction permit, that Kairos must request a license amendment to incorporate the requirements of any Terms and Conditions set forth in the Incidental Take Statement of Biological Opinions issued subsequent to the effective date of this EPP.208 However, the Staff did not engage in formal consultation with FWS and, as a result, did 202 Ex. NRC-, FEIS, at -.
203 Id. at -. The endangered species are the gray bat, the Indiana bat, and two freshwater clam speciesthe finerayed pigtoe and shiny pigtoe. The threatened species are the northern long-eared bat, the spotfin chub, and two plant speciesthe Virginia spiraea and white fringeless orchid. The federal candidate species is the monarch butterfly. The Staff did not identify the presence of critical habitat within the action area. Id. at - to -.
203 Id. at -. The endangered species are the gray bat, the Indiana bat, and two freshwater clam speciesthe finerayed pigtoe and shiny pigtoe. The threatened species are the northern long-eared bat, the spotfin chub, and two plant speciesthe Virginia spiraea and white fringeless orchid. The federal candidate species is the monarch butterfly. The Staff did not identify the presence of critical habitat within the action area. Id. at - to -.
 
204 Id. at -; see id. at - to - & tbl. -.
204 Id. at - ; see id. at - to - & tbl. -.
 
205 Id. at -.
205 Id. at -.
206 Id. at -.
206 Id. at -.
207 Id. at -.
207 Id. at -.
208 See Ex. NRC--R, Draft Construction Permit, app. A, Environmental Protection Plan.


208 See Ex. NRC--R, Draft Construction Permit, app. A, Environmental Protection Plan.
not receive from FWS a biological opinion containing an Incidental Take Statement with Terms and Conditions.209 In response to our pre-hearing question asking about the necessity of this condition, the Staff elected to remove this condition from the construction permit and noted that it will consider whether the condition should be added at the operating license stage.210 Section of the NHPA requires federal agencies to consider the effects of their undertakings on historic properties listed or eligible for listing on the National Register of Historic Places.211 The section process must be completed prior to the issuance of any license.212 The Staff considered the direct effects of the construction and operation of the Hermes facility on the -acre Hermes site, as well as the indirect effects of these activities on a.-mile area around the site.213 Relying on an environmental assessment prepared in by DOE for the East Tennessee Technology Park, the Staff initially concluded that there are likely no intact archaeological sites or prehistorical archaeological resources to be found within the APE due to extensive prior cut and fill excavation activities associated with construction of the former DOE facilities and their subsequent decontamination, demolition, and decommissioning.214 However, in response to a comment on the DEIS from a consulting tribe, the Staff gathered additional 209 See Ex. NRC-, Staff Pre-Hearing Responses, at.
 
not receive from FWS a biological opinion containing an Incidental Take Statement with Terms
 
and Conditions.209 In response to our pre-hearing question asking about the necessity of this
 
condition, the Staff elected to remove this condition from the construction permit and noted that
 
it will consider whether the condition should be added at the operating license stage. 210
 
Section of the NHPA requires federal agencies to consider the effects of their
 
undertakings on historic properties listed or eligible for listing on the National Register of Historic
 
Places.211 The section process must be completed prior to the issuance of any license. 212
 
The Staff considered the direct effects of the construction and operation of the Hermes facility
 
on the -acre Hermes site, as well as the indirect effects of these activities on a. -mile area
 
around the site.213 Relying on an environmental assessment prepared in by DOE for the
 
East Tennessee Technology Park, the Staff initially concluded that there are likely no intact
 
archaeological sites or prehistor ical archaeological resources to be found within the APE due to
 
extensive prior cut and fill excavation activities associated with construction of the former DOE
 
facilities and their subsequent decontamination, demolition, and decommissioning. 214 However,
 
in response to a comment on the DEIS from a consulting tribe, the Staff gathered additional
 
209 See Ex. NRC-, Staff Pre-Hearing Responses, at.
 
210 Id.
210 Id.
211 Section of the NHPA requires federal agencies to consider the effects of their undertakings on historic properties listed or eligible for listing on the National Register of Historic Places. NHPA §, U.S.C. §. The NRCs undertaking is the issuance of a construction permit to Kairos that allows for the construction of the proposed Kairos Hermes project. Ex. NRC-, FEIS, at -.
211 Section of the NHPA requires federal agencies to consider the effects of their undertakings on historic properties listed or eligible for listing on the National Register of Historic Places. NHPA §, U.S.C. §. The NRCs undertaking is the issuance of a construction permit to Kairos that allows for the construction of the proposed Kairos Hermes project. Ex. NRC-, FEIS, at -.
 
212 C.F.R. §.(c).
212 C.F.R. §. (c).
 
213 Ex. NRC-, FEIS, at -. Together, these areas constitute the area of potential effects (APE) for the NRCs section review. See generally id. at - to -.
213 Ex. NRC-, FEIS, at -. Together, these areas constitute the area of potential effects (APE) for the NRCs section review. See generally id. at - to -.
214 See DEIS at -, -. The Staff also reviewed information held by the Tennessee Historical Commission and determined that there are no extant architectural resources within the direct-effects APE. Id.


214 See DEIS at -, -. The Staff also reviewed information held by the Tennessee Historical Commission and determined that there are no extant architectural resources within the direct-effects APE. Id.
information from DOE related to the geology and geomorphology of the site, as well as the total area and depth of prior disturbance at the former DOE facility locations.215 Based on this new information and a discussion with DOE, the Staff determined that there is a potential for deeply buried archaeological deposits to occur within the APE.216 To satisfy its consultation responsibilities under the NHPA, the Staff contacted the Tennessee Historical Commission, the Advisory Council on Historic Preservation, the National Park Service, and eighteen federally recognized Indian tribes.217 The Tennessee Historical Commission advised that the Kairos project would not adversely affect the Manhattan Project National Historic Park, the only property located within the APE that is eligible for listing on the National Register of Historic Places.218 In December, after publication of the DEIS, one Tribe initiated government-to-government consultation, requested consulting party status, and requested that a cultural resources survey be conducted for the proposed project.219 The Staff met with Kairos several times between February and April to discuss information needs to support the Staffs consultations with the Tribe. In April, the Staff forwarded additional information Kairos provided to the consulting Tribe for review and comment. Between June and the publication of the FEIS in August, the Staff met with the Tribe and Kairos to discuss the Tribes request for an additional reconnaissance field investigation, updates to the 215 Ex. NRC-, FEIS, at -, see id. at G-to G-.
 
information from DOE related to the geology and geomorphology of the site, as well as the total
 
area and depth of prior disturbance at the former DOE facility locations. 215 Based on this new
 
information and a discussion with DOE, the Staff determined that there is a potential for deeply
 
buried archaeological deposits to occur within the APE. 216
 
To satisfy its consultation responsibilities under the NHPA, the Staff contacted the
 
Tennessee Historical Commission, the Advisory Council on Historic Preservation, the National
 
Park Service, and eighteen federally recognized Indian tribes. 217 The Tennessee Historical
 
Commission advised that the Kairos project would not adversely affect the Manhattan Project
 
National Historic Park, the only property located within the APE that is eligible for listing on the
 
National Register of Historic Places. 218 In December, after publication of the DEIS, one
 
Tribe initiated government-to-government consultation, requested consulting party status, and
 
requested that a cultural resources survey be conducted for the proposed project. 219 The Staff
 
met with Kairos several times between February and April to discuss information needs to
 
support the Staffs consultations with the Tribe. In April, the Staff forwarded additional
 
information Kairos provided to the consulting Tribe for review and comment. Between June and
 
the publication of the FEIS in August, the Staff met with the Tribe and Kairos to discuss the
 
Tribes request for an additional reconnaissance field investigation, updates to the
 
215 Ex. NRC-, FEIS, at -, see id. at G-to G-.
 
216 Id. at -.
216 Id. at -.
217 Id. at -.
217 Id. at -.
218 Id. at -, -. The Manhattan Project National Historical Park, which is jointly administered by DOE and the National Park Service, includes the K-History Center, which opened in and focuses on the men and women who built and operated the K-Gaseous Diffusion Plant during the Manhattan Project and Cold War. Id. at -; see National Park Service, K-History Center, https://www.nps.gov/places/k--history-center.htm (last visited Nov., ).
219 Ex. NRC-, FEIS, at -, G-to G-.


218 Id. at -, -. The Manhattan Project National Historical Park, which is jointly administered by DOE and the National Park Service, includes the K-History Center, which opened in and focuses on the men and women who built and operated the K-Gaseous Diffusion Plant during the Manhattan Project and Cold War. Id. at -; see National Park Service, K-History Center, https://www.nps.gov/places/k- -history-center.htm (last visited Nov., ).
archaeological resource monitoring and unanticipated discovery plan, and a path forward to support NHPA section consultation closure.220 The Staffs section consultation efforts were still in progress when we held the hearing on Kaiross construction permit application. Prior to the hearing, we asked the Staff to clarify the purpose of the additional reconnaissance field investigation and the basis for the Staffs conclusions regarding impacts to historic and cultural resources from the Hermes project.221 At the hearing, the Staff informed us that Kairos had completed the requested field investigation, had used the resulting information to update its monitoring plan, and had incorporated the Staffs and Tribes input into the plan.222 After the hearing, the Staff provided notice of consultation closure in a revised draft record of decision.223 The draft record of decision explained that after Kairos submitted the updated monitoring plan and Geoarchaeological Reconnaissance Survey Report, the Staff sent the monitoring plan and Kaiross report to the Tennessee Historical Commission and the consulting Tribe.224 The Tennessee Historical Commission responded that it had no objections to the project proceeding as proposed. Likewise, the consulting Tribe stated that it had no objections to the project proceeding, provided the NRC agrees to notify the consulting Tribe of changes to project activities on the site and to any unanticipated discoveries.225 The Staff noted that these stipulations were previously discussed and agreed upon between the consulting 220 Id. at - to -; Ex. NRC-, Staff Information Paper, at, ; Ex. NRC-, Staff Pre-Hearing Responses, at.
 
219 Ex. NRC-, FEIS, at -, G-to G-.
 
archaeological resource monitoring and unanticipated discovery plan, and a path forward to
 
support NHPA section consultation closure. 220
 
The Staffs section consultation efforts were still in progress when we held the
 
hearing on Kaiross construction permit application. Prior to the hearing, we asked the Staff to
 
clarify the purpose of the additional reconnaissance field investigation and the basis for the
 
Staffs conclusions regarding impacts to historic and cultural resources from the Hermes
 
project.221 At the hearing, the Staff informed us that Kairos had completed the requested field
 
investigation, had used the resulting information to update its monitoring plan, and had
 
incorporated the Staffs and Tribes input into the plan. 222
 
After the hearing, the Staff provided notice of consultation closure in a revised draft
 
record of decision.223 The draft record of decision explained that after Kairos submitted the
 
updated monitoring plan and Geoarchaeological Reconnaissance Survey Report, the Staff sent
 
the monitoring plan and Kaiross report to the Tennessee Historical Commission and the
 
consulting Tribe.224 The Tennessee Historical Commission responded that it had no objections
 
to the project proceeding as proposed. Likewise, the consulting Tribe stated that it had no
 
objections to the project proceeding, provided th e NRC agrees to notify the consulting Tribe of
 
changes to project activities on the site and to any unanticipated discoveries. 225 The Staff noted
 
that these stipulations were previously discussed and agreed upon between the consulting
 
220 Id. at - to -; Ex. NRC-, Staff Information Paper, at, ; Ex. NRC-, Staff Pre-Hearing Responses, at.
 
221 See Pre-Hearing Questions Order at -.
221 See Pre-Hearing Questions Order at -.
 
222 See Tr. at (Mr. Regan); see also Ex. NRC--R, Draft Record of Decision, at (stating that the reconnaissance field investigation was completed in August ).
222 See Tr. a t (Mr. Regan); see also Ex. NRC--R, Draft Record of Decision, at (stating that the reconnaissance field investigation was completed in August ).
 
223 See Staff Revised Exhibit List at ; Ex. NRC--R, Draft Record of Decision, at.
223 See Staff Revised Exhibit List at ; Ex. NRC--R, Draft Record of Decision, at.
224 Ex. NRC--R, Draft Record of Decision, at.
225 Id.


224 Ex. NRC- -R, Draft Record of Decision, at.
parties and that the NRCs process for implementing these stipulations had been documented in a memorandum to the NRCs Federal Preservation Officer.226 Because there are no known historic properties on the proposed Hermes site and mitigation measures will be in place to protect any undiscovered resources, the Staff determined under the NHPA that there would be no adverse effects to historic properties from the proposed undertaking.227 For the same reason, the Staff concluded for the purposes of NEPA that the potential environmental impacts on cultural and historic resources from constructing, operating, and decommissioning the Hermes project would be small.228 In its environmental review of the Hermes project, the Staff also analyzed alternatives to the proposed action.229 This review included consideration of the no-action alternative and one alternative site.230 For the no-action alternative, i.e., if the construction permit were to be denied, the Staff found that the environmental effects described in the FEIS would not occur, but because these effects were found to be small, any environmental benefit from selecting the no-action alternative would be minimal.231 Moreover, the proposed site would remain available for other government or private industrial development projects, which might lead to similar 226 Id. (citing Memorandum from Tamsen Dozier, NRC, to Christopher M. Regan, NRC, Implementation of Provisions from Consultations Under Section of the National Historic Preservation Act on the Kairos Hermes Test Reactor Construction Permit Review (Nov.,  
 
) (MLA).
225 Id.
 
parties and that the NRCs process for implementing these stipulations had been documented in
 
a memorandum to the NRCs Federal Preservation Officer. 226
 
Because there are no known historic properties on the proposed Hermes site and
 
mitigation measures will be in place to protect any undiscovered resources, the Staff determined
 
under the NHPA that there would be no adverse effects to historic properties from the proposed
 
undertaking.227 For the same reason, the Staff concluded for the purposes of NEPA that the
 
potential environmental impacts on cultural and historic resources from constructing, operating,
 
and decommissioning the Hermes project would be small. 228
 
In its environmental review of the Hermes project, the Staff also analyzed alternatives to
 
the proposed action.229 This review included consideration of the no-action alternative and one
 
alternative site.230 For the no-action alternative, i.e., if the construction permit were to be denied,
 
the Staff found that the environmental effects described in the FEIS would not occur, but
 
because these effects were found to be small, any environmental benefit from selecting the
 
no-action alternative would be minimal. 231 Moreover, the proposed site would remain available
 
for other government or private industrial development projects, which might lead to similar
 
226 Id. (citing Memorandum from Tamsen Dozier, NRC, to Christopher M. Regan, NRC, Implementation of Provisions from Consultations Under Section of the National Historic Preservation Act on the Kairos Hermes Test Reactor Construction Permit Review (Nov.,
) (ML A).
 
227 See id. at, ; Ex. NRC-, Staff Pre-Hearing Responses, at -; Ex. NRC-, FEIS, at - to -.
227 See id. at, ; Ex. NRC-, Staff Pre-Hearing Responses, at -; Ex. NRC-, FEIS, at - to -.
 
228 See Ex. NRC--R, Draft Record of Decision, at,, ; Ex. NRC-, Staff Pre-Hearing Responses, at -; Ex. NRC-, FEIS, at - to -.
228 See Ex. NRC- -R, Draft Record of Decision, at,, ; Ex. NRC-, Staff Pre-Hearing Responses, at -; Ex. NRC-, FEIS, at - to -.
 
229 Ex. NRC-, FEIS, ch..
229 Ex. NRC-, FEIS, ch..
230 Id. at -.
230 Id. at -.
231 Id.


231 Id.
environmental effects as the proposed project.232 In addition, this alternative would not meet the purpose of the proposed actionto demonstrate key elements of the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor technology for possible future commercial deployment.233 After reviewing the applicants systematic site-selection process and finding it to have been reasonable, the Staff examined an alternative site on federal land approximately twenty miles west of Idaho Falls, Idaho, termed the Eagle Rock site.234 The Staff compared the environmental costs and benefits of the proposed action at the Eagle Rock site with the costs and benefits of the proposed action at the Oak Ridge site. The Staff found that the impacts at the Eagle Rock site would be small for all resource areas except for visual, ecological, and cultural resources, which would experience moderate impacts from construction, reflecting the Staffs determination that building the Hermes facilities at the Eagle Rock site could be visually intrusive in that rural setting and would require disturbance of soils supporting natural vegetation and potentially containing subsurface archaeological resources.235 With the Oak Ridge site presenting only small environmental impacts, as contrasted with the Eagle Rock site, the Staff concluded that the Oak Ridge site was the environmentally preferable alternative.236 On the basis of its environmental review, the Staff recommended issuing the construction permit to Kairos.237 At the operating license stage, the Staff will prepare a 232 Id.
 
environmental effects as the proposed project. 232 In addition, this alternative would not meet the
 
purpose of the proposed actionto demonstrate key elements of the Kairos Power Fluoride
 
Salt-Cooled, High Temperature Reactor technology for possible future commercial
 
deployment.233
 
After reviewing the applicants systematic site-selection process and finding it to have
 
been reasonable, the Staff examined an alternative site on federal land approximately twenty
 
miles west of Idaho Falls, Idaho, termed the Eagle Rock site. 234 The Staff compared the
 
environmental costs and benefits of the proposed action at the Eagle Rock site with the costs
 
and benefits of the proposed action at the Oak Ridge site. The Staff found that the impacts at
 
the Eagle Rock site would be small for all res ource areas except for visual, ecological, and
 
cultural resources, which would experience moder ate impacts from construction, reflecting the
 
Staffs determination that building the Hermes facilities at the Eagle Rock site could be visually
 
intrusive in that rural setting and would require disturbance of soils supporting natural
 
vegetation and potentially containing subsurface archaeological resources. 235 With the Oak
 
Ridge site presenting only small environmental impacts, as contrasted with the Eagle Rock site,
 
the Staff concluded that the Oak Ridge site was the environmentally preferable alternative. 236
 
On the basis of its environmental review, the Staff recommended issuing the
 
construction permit to Kairos.237 At the operating license stage, the Staff will prepare a
 
232 Id.
 
233 Id. at -; see id. at -. For the same reason, Kairos and the Staff did not consider alternative technologies for the Hermes reactor. Id. at -.
233 Id. at -; see id. at -. For the same reason, Kairos and the Staff did not consider alternative technologies for the Hermes reactor. Id. at -.
234 Id. at -.
234 Id. at -.
235 Id. at - to -, - & tbl. -.
235 Id. at - to -, - & tbl. -.
236 Id. at - to -.
236 Id. at - to -.
237 Id. at -. The Staff conditioned its recommendation on completion of the NHPA section process, which was not yet complete at the time the FEIS was issued. Id.


237 Id. at -. The Staff conditioned its recommendation on completion of the NHPA section process, which was not yet complete at the time the FEIS was issued. Id.
supplement to the FEIS to address any new and significant information that was not available during its review of the construction permit application.238 E.
 
Findings We have conducted an independent review of the sufficiency of the Staffs safety findings, with particular attention to the topics discussed above. Our findings, however, are based on the record as a whole.
supplement to the FEIS to address any new and si gnificant information that was not available
Safety Findings Based on the evidence presented in the uncontested hearing, including the Staffs review documents and the testimony provided, we find that Kairos has described the proposed design of the facility, including, but not limited to, the principal architectural and engineering criteria for the design, and it has identified major features or components incorporated therein for the protection of the health and safety of the public.239 Further technical or design information as may be required to complete the safety analysis has reasonably been left for later consideration and will be supplied in the final safety analysis report. Kairos has described the safety features or components that require research and development and has identified and will establish a research and development program reasonably designed to resolve any safety questions associated with these features or components. On the basis of the foregoing, we find that there is reasonable assurance that open safety questions will be resolved satisfactorily at or before the latest date stated in the application for completion of construction of the proposed facility. Taking into consideration the site criteria in C.F.R. Part, the proposed facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.
 
238 See C.F.R. §.(b); Ex. NRC-, FEIS, at -; Tr. at (Mr. Doub) (stating that the Staff would supplement the EIS and update the analysis for later life cycle stages should the applicant apply for future licenses for Hermes).
during its review of the construction permit application. 238
239 See Ex. KRS-, Kairos Pre-Hearing Responses, at -.  
 
E. Findings
 
We have conducted an independent review of the sufficiency of the Staffs safety
 
findings, with particular attention to the topics discussed above. Our findings, however, are
 
based on the record as a whole.
 
. Safety Findings


Based on the evidence presented in the uncontested hearing, including the Staffs
In making these findings, we also conclude that: () there is reasonable assurance that construction of the facility will not endanger the health and safety of the public, and the authorized activities can be conducted in compliance with the NRCs regulations, including the requirements in C.F.R. Part ; () Kairos is technically and financially qualified to engage in the activities authorized;240 () issuance of the construction permit will not be inimical to the common defense and security or to the health and safety of the public; and () Kaiross application meets the standards and requirements of the AEA and the NRCs regulations.
 
Required notifications to other agencies have been duly made.241 Additionally, we find that the Staffs proposed permit conditions are appropriately drawn and sufficient to provide reasonable assurance of adequate protection of public health and safety.242 Environmental Findings We also conducted an independent review of the Staffs environmental analysis in the FEIS, taking into account the particular requirements of NEPA. NEPA section ()(A) requires agencies to use a systematic, interdisciplinary approach which will ensure the integrated use of the natural and social sciences and the environmental design arts in decision making that may impact the environment.243 We find that the environmental review team used the systematic, interdisciplinary approach that NEPA requires.244 The environmental review team consisted of 240 Ex. NRC-, Safety Evaluation, chs., ; Ex. NRC-, Staff Information Paper, at ;
review documents and the testimony provided, we find that Kairos has described the proposed
 
design of the facility, including, but not limited to, the principal architectural and engineering
 
criteria for the design, and it has identified major features or components incorporated therein
 
for the protection of the health and safety of the public. 239 Further technical or design information
 
as may be required to complete the safety analysis has reasonably been left for later
 
consideration and will be supplied in the final safety analysis report. Kairos has described the
 
safety features or components that require research and development and has identified and
 
will establish a research and development program reasonably designed to resolve any safety
 
questions associated with these features or components. On the basis of the foregoing, we find
 
that there is reasonable assurance that open safety questions will be resolved satisfactorily at or
 
before the latest date stated in the application for completion of construction of the proposed
 
facility. Taking into consideration the site criteria in C.F.R. Part, the proposed facility can
 
be constructed and operated at the proposed location without undue risk to the health and
 
safety of the public.
 
238 See C.F.R. §. (b); Ex. NRC-, FEIS, at - ; Tr. at (Mr. Doub) (stating that the Staff would supplement the EIS and update the analysis for later life cycle stages should the applicant apply for future licenses for Hermes).
 
239 See Ex. KRS-, Kairos Pre-Hearing Responses, at -.
 
In making these findings, we also conclude that: () there is reasonable assurance that
 
construction of the facility will not endanger the health and safety of the public, and the
 
authorized activities can be conducted in compliance with the NRCs regulations, including the
 
requirements in C.F.R. Part ; ( ) Kairos is technically and financially qualified to engage in
 
the activities authorized;240 ( ) issuance of the construction permit will not be inimical to the
 
common defense and security or to the health and safety of the public; and ( ) Kaiross
 
application meets the standards and requirements of the AEA and the NRCs regulations.
 
Required notifications to other agencies have been duly made. 241 Additionally, we find that the
 
Staffs proposed permit conditions are appropriately drawn and sufficient to provide reasonable
 
assurance of adequate protection of public health and safety. 242
 
. Environmental Findings
 
We also conducted an independent review of the Staffs environmental analysis in the
 
FEIS, taking into account the particular requirements of NEPA. NEPA section ( )(A) requires
 
agencies to use a systematic, interdisciplinary approach which will ensure the integrated use of
 
the natural and social sciences and the environment al design arts in decision making that may
 
impact the environment.243 We find that the environmental review team used the systematic,
 
interdisciplinary approach that NEPA requires. 244 The environmental review team consisted of
 
240 Ex. NRC-, Safety Evaluation, chs., ; Ex. NRC-, Staff Information Paper, at ;
Ex. KRS-, Kairos Testimony, at -.
Ex. KRS-, Kairos Testimony, at -.
241 See, e.g., C.F.R. §.(a); Ex. NRC-, Staff Pre-Hearing Responses, at ;
241 See, e.g., C.F.R. §.(a); Ex. NRC-, Staff Pre-Hearing Responses, at ;
Ex. NRC-, FEIS, app. B.
Ex. NRC-, FEIS, app. B.
 
242 See C.F.R. §§.(b),.; Ex. NRC--R, Draft Construction Permit, at -.
242 See C.F.R. §§. (b),. ; Ex. NRC--R, Draft Construction Permit, at -.
 
243 NEPA § 102(2)(A), 42 U.S.C. § 4332(2)(A), as amended.
243 NEPA § 102(2)(A), 42 U.S.C. § 4332(2)(A), as amended.
244 See, e.g., Tr. at - (Mr. Erwin, Ms. Dozier, Mr. Doub) (providing an overview of the Staffs environmental review methodology and findings); Ex. NRC-, Staff Environmental Panel Presentation, at -.


244 See, e.g., Tr. at - (Mr. Erwin, Ms. Dozier, Mr. Doub) (providing an overview of the Staffs environmental review methodology and findings); Ex. NRC-, Staff Environmental Panel Presentation, at -.
over two dozen individuals with expertise in disciplines including ecology, geology, hydrology, human health, socioeconomics, and cultural resources.245 In addition to the general requirement that an EIS address the reasonably foreseeable environmental effects of a proposed action, NEPA section ()(C) requires federal agencies to describe () any reasonably foreseeable adverse environmental effects which cannot be avoided should the proposal be implemented; () a reasonable range of alternatives to the proposed agency action, including an analysis of any negative environmental impacts of not implementing the proposed agency action in the case of a no action alternative, that are technically and economically feasible, and meet the purpose and need of the proposal; () the relationship between local short-term uses and long-term productivity of the environment; and
 
() any irreversible and irretrievable commitments of federal resources associated with the proposed agency action.246 The Staffs evaluation of alternatives is in chapter of the FEIS and summarized in chapter ; the other enumerated items are discussed under the heading of resource commitments in chapter.
over two dozen individuals with expertise in disciplines including ecology, geology, hydrology,
Because the Staff issued the FEIS shortly after Congress amended section ()(C),
 
we asked the Staff to provide additional information explaining how its environmental review satisfied these standards, as amended by the Fiscal Responsibility Act.247 The Staff stated that 245 See Ex. NRC-, FEIS, app. A tbl. A- (listing contributors from the NRC and Pacific Northwest National Laboratory).
human health, socioeconomics, and cultural resources. 245
 
In addition to the general requirement that an EIS address the reasonably foreseeable
 
environmental effects of a proposed action, NEPA section ( )(C) requires federal agencies to
 
describe ( ) any reasonably foreseeable adverse environmental effects which cannot be
 
avoided should the proposal be implemented; ( ) a reasonable range of alternatives to the
 
proposed agency action, including an analysis of any negative environmental impacts of not
 
implementing the proposed agency action in the case of a no action alternative, that are
 
technically and economically feasible, and meet the purpose and need of the proposal; ( ) the
 
relationship between local short-term uses and long-term productivity of the environment; and
 
( ) any irreversible and irretrievable commitments of federal resources associated with the
 
proposed agency action. 246 The Staffs evaluation of alternatives is in chapter of the FEIS and
 
summarized in chapter ; the other enumerated items are discussed under the heading of
 
resource commitments in chapter.
 
Because the Staff issued the FEIS shortly after Congress amended section ( )(C),
 
we asked the Staff to provide additional inform ation explaining how its environmental review
 
satisfied these standards, as amended by the Fiscal Responsibility Act. 247 The Staff stated that
 
245 See Ex. NRC-, FEIS, app. A tbl. A- (listing contributors from the NRC and Pacific Northwest National Laboratory).
 
246 NEPA § 102(2)(C)(i)-(v), 42 U.S.C. § 4332(2)(C)(i)-(v), as amended.
246 NEPA § 102(2)(C)(i)-(v), 42 U.S.C. § 4332(2)(C)(i)-(v), as amended.
247 See Pre-Hearing Questions Order at 13, 15-16; Tr. at 150-51 (Commissioner Wright). As noted above, pursuant to 10 C.F.R. § 51.105(a), we must determine whether the requirements of NEPA Sections 102(2)(A), (C), and (E) have been met, and determine as a general matter whether the NEPA review conducted by the NRC Staff has been adequate. The amendments to NEPA which became effective upon enactment of the Fiscal Responsibility Act substantively affect the requirements in NEPA section 102(2)(C). For example, section 102(2)(C)(iii) has been amended to specify that the alternatives analysis must include a discussion of the negative impacts of not implementing the proposed action, and section 102(2)(C)(v) now requires an analysis of any irreversible and irretrievable commitment of federal resources, as opposed to the broader analysis of resources typically performed by the Staff to satisfy this requirement.


247 See Pre-Hearing Questions Order at 13, 15 -16; Tr. at 150-51 (Commissioner Wright). As noted above, pursuant to 10 C.F.R. § 51.105(a), we must determine whether the requirements of NEPA Sections 102(2)(A), (C), and (E) have been met, and determine as a general matter whether the NEPA review conducted by the NRC Staff has been adequate. The amendments to NEPA which became effective upon enactment of the Fiscal Responsibility Act substantively affect the requirements in NEPA section 102(2)(C ). For example, section 102(2)(C)(iii) has been amended to specify that the alternatives analysis must include a discussion of the negative impacts of not implementing the proposed action, and section 102(2)(C)(v) now requires an analysis of any irreversible and irretrievable commitment of federal resources, as opposed to the broader analysis of resources typically performed by the Staff to satisfy this requirement.
prior to issuing the FEIS, the Staff reviewed the Fiscal Responsibility Act and the amendments to NEPA, and found that the FEIS was consistent with the Staffs current understanding of these new requirements and that it had made all the findings necessary in the FEIS to support issuance of the construction permit.248 In response to our question, the Staff revised the record of decision to reflect this determination.249 In further questions to the Staff before and during the hearing, we asked the Staff to clarify whether the FEIS considered the irreversible and irretrievable commitment of exclusively federal resources involved in issuing a construction permit to Kairos, commensurate with the more specific analysis required by amended NEPA section ()(C)(v).250 The Staff explained that its comprehensive analysis of irreversible and irretrievable resources in the FEIS accounted for federal resources as well.251
 
: a.
prior to issuing the FEIS, the Staff review ed the Fiscal Responsibility Act and the amendments
Resource Commitments Chapter of the FEIS includes a table of the unavoidable adverse environmental impacts anticipated from construction, operation, and decommissioning, along with actions to mitigate those impacts.252 As noted above, the Staff concluded that the impacts of the proposed action in all resource areas would be small, despite the potential unavoidable adverse impacts presented in this table. To address these unavoidable impacts, the Staff identified mitigation and control measures that Kairos could implement to lessen some of these potential adverse effects.253 Examples of such mitigation measures include instituting best management practices to control dust and manage stormwater runoff, developing an Archaeological Resources 248 Ex. NRC-, Staff Pre-Hearing Responses, at -; Tr. at (Mr. Regan).
 
to NEPA, and found that the FEIS was consistent with the Staffs current understanding of these
 
new requirements and that it had made all the findings necessary in the FEIS to support
 
issuance of the construction permit. 248 In response to our question, the Staff revised the record
 
of decision to reflect this determination. 249 In further questions to the Staff before and during the
 
hearing, we asked the Staff to clarify whether the FEIS considered the irreversible and
 
irretrievable commitment of exclusively federal resources involved in issuing a construction
 
permit to Kairos, commensurate with the more specific analysis required by amended NEPA
 
section ( )(C)(v).250 The Staff explained that its comprehensive analysis of irreversible and
 
irretrievable resources in the FEIS accounted for federal resources as well. 251
: a. Resource Commitments
 
Chapter of the FEIS includes a table of the unavoidable adverse environmental
 
impacts anticipated from construction, operation, and decommissioning, along with actions to
 
mitigate those impacts.252 As noted above, the Staff concluded that the impacts of the proposed
 
action in all resource areas would be small, despite the potential unavoidable adverse impacts
 
presented in this table. To address these unavoidable impacts, the Staff identified mitigation and
 
control measures that Kairos could implement to lessen some of these potential adverse
 
effects.253 Examples of such mitigation measures include instituting best management practices
 
to control dust and manage stormwater runoff, developing an Archaeological Resources
 
248 Ex. NRC-, Staff Pre-Hearing Responses, at -; Tr. at (Mr. Regan).
 
249 Ex. NRC-, Staff Pre-Hearing Responses, at -.
249 Ex. NRC-, Staff Pre-Hearing Responses, at -.
250 See Pre-Hearing Questions Order at -; Tr. at - (Commissioner Wright).
250 See Pre-Hearing Questions Order at -; Tr. at - (Commissioner Wright).
251 See Ex. NRC-, Staff Pre-Hearing Responses, at ; Tr. at (Mr. Doub).
251 See Ex. NRC-, Staff Pre-Hearing Responses, at ; Tr. at (Mr. Doub).
252 Ex. NRC-, FEIS, at - to - tbl. -.
252 Ex. NRC-, FEIS, at - to - tbl. -.
253 Id. at -.


253 Id. at -.
Monitoring and Unanticipated Discovery Plan to address unexpected discoveries of human remains and archaeological materials, and restoring temporarily disturbed lands with native plants or landscaping when no longer needed for construction or decommissioning activities.254 Concerning irreversible and irretrievable commitments of federal resources, the Staff found that construction of the Hermes facility would irretrievably commit capital, energy, labor, and material resources, some of which are expended by the NRC during its review of the Hermes application and would thus constitute federal resources.255 Although the Staff did not separately analyze federal resources in the FEIS, the Staff clarified that the FEIS analysis considered the totality of resources, including but not limited to federal resources, and therefore adequately addressed the requirements of the Fiscal Responsibility Act.256 With respect to other resources, the Staff concluded that construction of the Hermes facility would irretrievably consume energy, water, chemicals, fossil fuels, as well as construction materials, unless Kairos recycles them during decommissioning.257 Historic and cultural resources buried beneath the surface or in deeply buried paleosoils are nonrenewable and may be disturbed by construction, but impacts to any such resources would be mitigated by implementation of Kaiross Archaeological Resources Monitoring and Unanticipated Discovery Plan.258 During operations, uranium used in TRISO fuel pebbles would be irreversibly and irretrievably committed, and nonradiololgical irreversible impacts on occupational human health could occur but are expected to be comparable to potential hazards at any industrial construction site.259 254 Id. at - to - tbl. -.
 
255 Id. at -; Ex. NRC-, Staff Pre-Hearing Responses, at ; see also Tr. at (Mr. Regan).
Monitoring and Unanticipated Discovery Plan to address unexpected discoveries of human
256 Tr. at (Mr. Erwin, Mr. Doub).
 
remains and archaeological materials, and restori ng temporarily disturbed lands with native
 
plants or landscaping when no longer needed for construction or decommissioning activities. 254
 
Concerning irreversible and irretrievable commitments of federal resources, the Staff
 
found that construction of the Hermes facility would irretrievably commit capital, energy, labor,
 
and material resources, some of which are expended by the NRC during its review of the
 
Hermes application and would thus constitute federal resources. 255 Although the Staff did not
 
separately analyze federal resources in the FEIS, the Staff clarified that the FEIS analysis
 
considered the totality of resources, including but not limited to federal resources, and therefore
 
adequately addressed the requirements of the Fiscal Responsibility Act. 256 With respect to other
 
resources, the Staff concluded that construction of the Hermes facility would irretrievably
 
consume energy, water, chemicals, fossil fuels, as well as construction materials, unless Kairos
 
recycles them during decommissioning. 257 Historic and cultural resources buried beneath the
 
surface or in deeply buried paleosoils are nonrenewable and may be disturbed by
 
construction, but impacts to any such resources would be mitigated by implementation of
 
Kaiross Archaeological Resources Monitoring and Unanticipated Discovery Plan. 258 During
 
operations, uranium used in TRISO fuel pebbles would be irreversibly and irretrievably
 
committed, and nonradiololgical irreversible impacts on occupational human health could occur
 
but are expected to be comparable to potential hazards at any industrial construction site. 259
 
254 Id. at - to - tbl. -.
 
255 Id. at - ; Ex. NRC-, Staff Pre-Hearing Responses, at ; see also Tr. a t (Mr. Regan).
 
256 Tr. a t (Mr. Erwin, Mr. Doub).
 
257 Ex. NRC-, FEIS, at -.
257 Ex. NRC-, FEIS, at -.
258 Id.
258 Id.
259 Id. at - to -.


259 Id. at - to -.
Finally, with respect to the relationship between local short-term uses and long-term productivity of the environment, the Staff found that the short-term uses of the environment construction, operation, and decommissioning of the Hermes facilitywould commit acres of previously used industrial land over the life of the project and up to acres of land during construction and decommissioning. Use of the entire -acre Hermes site would also be limited during operation due to its designation as the exclusion area.260 Further short-term uses of the environment would include consumption of small quantities of water supplied by municipal or commercial sources, small increases in demand for housing and services in the local community, an increase in the volume of traffic on local roads, and energy consumption.261 The Staff noted that management and disposal of wasteradioactive, hazardous, and nonhazardouswould consume space at treatment, storage, or disposal facilities, and the use of land to meet waste disposal needs would reduce the long-term productivity of the land, but Hermes would contribute only a minimal amount to these reductions.262 In addition, in the short term, the project would bring increased employment, expenditures, and tax revenues that would directly benefit local, regional, and State economies.263 As compared to the minimal impacts of the project over the short term, the Staff found substantial potential long-term benefits from the Hermes project, including demonstrating the commercial viability of its fluoride salt-cooled, high temperature reactor technology, generating data helpful in future commercial deployment of the technology, and helping the nation meet its climate change objectives with less reliance on more land-intensive energy generation processes.264 260 Id. at -.
 
Finally, with respect to the relationship between local short-term uses and long-term
 
productivity of the environment, the Staff found that the short-term uses of the environment
 
construction, operation, and decommissioning of the Hermes facilitywould commit acres of
 
previously used industrial land over the life of the project and up to acres of land during
 
construction and decommissioning. Use of the entire -acre Hermes site would also be limited
 
during operation due to its designation as the exclusion area. 260 Further short-term uses of the
 
environment would include consumption of small quantities of water supplied by municipal or
 
commercial sources, small increases in demand for housing and services in the local
 
community, an increase in the volume of traffic on local roads, and energy consumption. 261 The
 
Staff noted that management and disposal of wasteradioactive, hazardous, and
 
nonhazardouswould consume space at treatment, storage, or disposal facilities, and the use
 
of land to meet waste disposal needs would reduce the long-term productivity of the land, but
 
Hermes would contribute only a minimal amount to these reductions. 262 In addition, in the short
 
term, the project would bring increased employ ment, expenditures, and tax revenues that would
 
directly benefit local, regional, and State economies. 263 As compared to the minimal impacts of
 
the project over the short term, the Staff found substantial potential long-term benefits from the
 
Hermes project, including demonstrating the commercial viability of its fluoride salt-cooled, high
 
temperature reactor technology, generating data helpful in future commercial deployment of the
 
technology, and helping the nation meet its climate change objectives with less reliance on more
 
land-intensive energy generation processes. 264
 
260 Id. at -.
 
261 Id. at -.
261 Id. at -.
262 Id.
262 Id.
263 Id.
263 Id.
264 Id.


264 Id.
Having considered the unavoidable adverse environmental impacts and resource commitmentsthe environmental costs of the projectas well as the projects benefits as summarized above, we agree with the Staffs conclusion that the benefits of the project outweigh the costs.265
 
: b.
Having considered the unavoidable adverse environmental impacts and resource
Alternatives The alternatives analysis is the heart of the environmental impact statement.266 NEPA section ()(H), formerly section ()(E), calls for agencies to study, develop, and describe appropriate alternatives to recommended courses of action in any proposal which involves unresolved conflicts involving alternative uses of available resources.267 Further, section
 
()(C) requires consideration of a reasonable range of alternatives to the proposed agency action that are technically and economically feasible, and meet the purpose and need of the proposed action. Where the alternatives considered include taking no action on the proposal, the analysis must consider any negative environmental impacts of not implementing the proposed agency action.268 Based on the Staffs testimony at the hearing, as well as the discussion in the FEIS, we find that the environmental review identified an appropriate range of alternatives with respect to the no-action alternative and the alternative Eagle Rock site, and adequately described the environmental impacts of both alternatives. The Staffs decision not to consider alternative technologies was reasonable in light of the purpose and need of the proposed project, which is to demonstrate and test its reactor technologies.269 265 Cf. C.F.R. §.(a); see Ex. NRC-, FEIS, at -.
commitmentsthe environmental costs of the projectas well as the projects benefits as
 
summarized above, we agree with the Staffs conclusion that the benefits of the project
 
outweigh the costs.265
: b. Alternatives
 
The alternatives analysis is the heart of the environmental impact statement. 266 NEPA
 
section ( )(H), formerly section ( )(E), calls for agencies to study, develop, and describe
 
appropriate alternatives to recommended courses of action in any proposal which involves
 
unresolved conflicts involving alternative uses of available resources. 267 Further, section
 
( )(C) requires consideration of a reasonable range of alternatives to the proposed agency
 
action that are technically and economically feasible, and meet the purpose and need of the
 
proposed action. Where the alternatives considered include taking no action on the proposal,
 
the analysis must consider any negative environmental impacts of not implementing the
 
proposed agency action.268 Based on the Staffs testimony at the hearing, as well as the
 
discussion in the FEIS, we find that the environmental review identified an appropriate range of
 
alternatives with respect to the no-action alternative and the alternative Eagle Rock site, and
 
adequately described the environmental impacts of both alternatives. The Staffs decision not to
 
consider alternative technologies was reasonable in light of the purpose and need of the
 
proposed project, which is to demonstrate and test its reactor technologies. 269
 
265 Cf. C.F.R. §. (a); see Ex. NRC-, FEIS, at -.
 
266 C.F.R. pt., subpt. A, app. A, §.
266 C.F.R. pt., subpt. A, app. A, §.
267 NEPA § 102(2)(H), 42 U.S.C. § 4332(2)(H). In its review of the potential impacts associated with the proposed action, the Staff did not identify any unresolved conflicts concerning alternative uses of available resources. Ex. NRC-, FEIS, at -.
267 NEPA § 102(2)(H), 42 U.S.C. § 4332(2)(H). In its review of the potential impacts associated with the proposed action, the Staff did not identify any unresolved conflicts concerning alternative uses of available resources. Ex. NRC-, FEIS, at -.
268 NEPA § 102(2)(C)(iii), 42 U.S.C. § 4332(2)(C)(iii), as amended.
268 NEPA § 102(2)(C)(iii), 42 U.S.C. § 4332(2)(C)(iii), as amended.
269 See Ex. NRC-, FEIS, at -, -.


269 See Ex. NRC-, FEIS, at -, -.
We also find that the Staff adequately considered the negative impacts of not implementing the proposed action. For example, the Staff found that under the no-action alternative, Kairos could not build the proposed Hermes reactor, and therefore would not have an opportunity to test its technologies, design features, and safety functions at a reduced scale relative to a potential commercial power reactor. The Staff noted that forgoing the opportunity provided by Hermes may not necessarily preclude future development of reactors using the salt-cooled, fluoride high temperature reactor technologies but anticipated that it could slow or impede safe and efficient development of the technologies.270 The Staff also identified that any environmental benefits from implementing the proposed action would not be realized if the action is not approved, and additionally, the proposed site would remain available for other development projects, potentially giving rise to environmental impacts from land disturbance and construction from those projects in the future.271 In sum, we find reasonable the Staffs conclusion that, because there are no environmentally preferable alternatives that meet the purpose and need of the proposed action,  
 
... there are no obviously superior alternatives to the proposed action from an environmental perspective.272
We also find that the Staff adequately considered the negative impacts of not
: c.
 
Commission Determination For each of the topics discussed at the hearing and in todays decision, we find that the Staffs review was reasonably supported in logic and fact and sufficient to support the Staffs conclusions. Based on our review of the FEIS, we also find that the remainder of the FEIS was reasonably supported and sufficient to support the Staffs conclusions. Therefore, as a result of our review of the FEIS, and in accordance with the notice of hearing for this uncontested 270 Id. at -.
implementing the proposed action. For example, the Staff found that under the no-action
 
alternative, Kairos could not build the proposed Hermes reactor, and therefore would not have
 
an opportunity to test its technologies, design features, and safety functions at a reduced scale
 
relative to a potential commercial power reactor. The Staff noted that forgoing the opportunity
 
provided by Hermes may not necessarily preclude future development of reactors using the salt-
 
cooled, fluoride high temperature reactor technologies but anticipated that it could slow or
 
impede safe and efficient development of the technologies. 270 The Staff also identified that any
 
environmental benefits from implementing the proposed action would not be realized if the
 
action is not approved, and additionally, the proposed site would remain available for other
 
development projects, potentially giving rise to environmental impacts from land disturbance
 
and construction from those projects in the future. 271
 
In sum, we find reasonable the Staffs conclusion that, because there are no
 
environmentally preferable alternatives that meet the purpose and need of the proposed action,
 
... there are no obviously superior alternatives to the proposed action from an environmental
 
perspective.272
: c. Commission Determination
 
For each of the topics discussed at the hearing and in todays decision, we find that the
 
Staffs review was reasonably supported in logic and fact and sufficient to support the Staffs
 
conclusions. Based on our review of the FEIS, we also find that the remainder of the FEIS was
 
reasonably supported and sufficient to support the Staffs conclusions. Therefore, as a result of
 
our review of the FEIS, and in accordance with the notice of hearing for this uncontested
 
270 Id. at -.
 
271 Id.; see also id. at G-.
271 Id.; see also id. at G-.
272 Id. at -; see also id. at -.
272 Id. at -; see also id. at -.
- 49 -
proceeding, we find that the relevant requirements of NEPA section 102(2), and the applicable regulations in 10 C.F.R: Part 51, have been satisfied with respect to the construction permit application.273 We independently considered the final balance among conflicting factors contained in the record of this proceeding. We find, after weighing the environmental, economic, technical, and other benefits against environmental and other costs, and considering reasonable alternatives, that the construction permit should be issued.
 
JII.
proceeding, we find that the relevant requirements of NEPA section 102(2), and the applicable
CONCLUSION We find that, with respect to the safety and environmental issues before us, the Staff's review ofKairos's construction permit application was sufficient to support issuance of the construction permit. We authorize the 'Director of the Office of Nuclear Reactor Regulation to issue the permit for the construction of the Hermes Test Reactor. Additionally, we authorize the Staff to issue the record of decision.
 
regulations in 10 C.F.R: Part 51, have been satisfied with respect to the construction permit
 
application.273 We independently considered the final balance among conflicting factors
 
contained in the record of this proceeding. We find, after weighing the environmental, economic,
 
technical, and other benefits against environmental and other costs, and considering reasonable
 
alternatives, that the construction permit should be issued.
JII. CONCLUSION
 
We find that, with respect to the safety and environmental issues before us, the Staff's
 
review ofKairos's construction permit application was sufficient to support issuance of the
 
construction permit. We authorize the 'Director of the Office of Nuclear Reactor Regulation to
 
issue the permit for the construction of the Hermes Test Reactor. Additionally, we authorize the
 
Staff to issue the record of decision.
 
IT IS SO ORDERED.
IT IS SO ORDERED.
For the Commission
~a0 C. ll-vr..~
Tomas E. Herrera Acting Secretary of the Commission
Dated at Rockville, Maryland, this 12th day of December 2023.
Dated at Rockville, Maryland, this 12th day of December 2023.
273 See supra note 26.
For the Commission
~a0 C. ll-vr..~
Tomas E. Herrera Acting Secretary of the Commission


273 See supra note 26.

/i255/9/10 /i255/7/4/3/8/3/7/i255/5/4/3/2/1/0 /8/11/4 /12/i255/8/13/2
   
/4/15/0 /14/12/i255/12/8/4/14/13/0/1 /3/9/12 /16/8/13/9/i255/11/11/2 /7/2/9/1 /i255/7
      
/i255

/11 /i255 /20 /19 /18 /i255 /17 /24 /i255/i255/i255/i255/i255/25 /i255/23/2/i255/22/20/18/18/21
 
/i255/i255 /i255/i255/i255/i255/i255/25 /i255

/12/9/7/2 /8 /26 /27/9/28/4 /12/i255/13 /i255/i255 /i255 /i255/i255 /25 /i255/i255 /5 /23/14/14/i255/29 /13 /35 /38 /37 /33 /36 /35 /34 /33 /i255 /32 /23 /1 /i255 /18 /20 /31 /30 /i255 /27

/i255 /25

/25 /i255/i255 /i255 /i255/i255 /25 /i255/22/23/22/41/20 /42/18/20/30/40/21/39/20/12/i255/18/42/20/3/i255

/i255/i255 /i255/i255/i255/i255/i255/25}}







    





 !"#$!%&# 

'()** 










' +,(-.


 
 
 / 
0,-,1-*.-.34556776485954:;8<=5;8<4:<9:
>3?6@AB@CDEF0*F+G1HHI-.1**0,H-)-J. 
 GH .GH, ))-**-
- ))-**-11HH+KG+--
-H1L #%MN&&
*-. O"!!!#"""%
#)-HL)-H *GP.F
 GH .GH, ))-**-
-, ))-**-
-H1L #%MN&&
*-. O"!!!#"""%
#)-HL-.+P.F
 GH .GH, ))-**-
-H G*H
-H1# #%QQQ
*-. O"!!!#"""%
-*#0
F-+ 
G*/-*
R),G
-H-N,+
.-()1
N-IHH
#)-HL-.*0P.F
+F-+ P.F
*G* F-*P.F
-H- 0,+P.F
K), IGP.F
..- )1P.F
0- IHHP.F
G*H-*I 
.I-*SN-G* 
%%%%*,HF-F
*-. O"""Q
,-.,
HJH*,
#)-HL, H-.,P).HI-* )

HJ 1H*,P).HI-* )



TTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTT
-, ))-**-
+ F-HH ,H+
-*%O+,)0O"O&
UVWXWZ[\\]VW
^_`_aWVVbc_`defgbUVWXWZ[
\\]VW
^Waehijik[li[liljhlmhlj
njmo jjo}}

Revision as of 07:31, 25 November 2024

Commission Memorandum and Order (CLI-23-05)
ML23346A068
Person / Time
Site: Hermes File:Kairos Power icon.png
Issue date: 12/12/2023
From: Thi Herrera
NRC/SECY
To:
NRC/OCM
SECY RAS
References
Construction Permit Mndtry Hrg, RAS 56874, Kairos Power, Hermes-M 50-7513-CP, 50-7513-CP, CLI-23-05
Download: ML23346A068 (50)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION COMMISSIONERS:

Christopher T. Hanson, Chair David A. Wright Annie Caputo Bradley R. Crowell In the Matter of KAIROS POWER LLC (Hermes Test Reactor)

Docket No. --CP CLI--

MEMORANDUM AND ORDER On October,, we held a hearing on the application of Kairos Power LLC (Kairos) for a construction permit for the Hermes non-power test reactor.1 In this uncontested proceeding, we consider the sufficiency of the NRC Staffs review of Kaiross application. As discussed below, we find that the Staffs review was sufficient to support the regulatory findings.

We authorize issuance of the construction permit.

1 See Kairos Power LLC; Construction Permit Application; Notice of Hearing, Fed. Reg.

, (Sept., ) (Hearing Notice); Tr. at - (attached to Order of the Secretary (Setting Deadline for Proposed Transcript Corrections) (Oct., ) (unpublished) (as amended by Order of the Secretary (Adopting Transcript Corrections and Admitting Revised Exhibit) (Nov.,

) (unpublished))).

BACKGROUND A.

Proposed Action The construction permit would allow construction of a -megawatt thermal test reactor on an approximately -acre brownfield site in Oak Ridge, Tennessee.2 The Hermes test reactor will use a combination of tri-structural isotropic (TRISO) fuel particles and a molten fluoride salt coolant known as Flibe. The non-power reactor will serve as a scaled demonstration plant to test and demonstrate key technical elements, design features, safety functions, and equipment performance for Kaiross salt-cooled, fluoride high temperature reactor technology.3 Kairos expects to complete construction by the end of and then to operate for four years.4 Before submitting its construction permit application in,5 Kairos engaged in extensive preapplication activities with the Staff, including the development of topical reports and participation in public meetings and audits.6 Topical reports cover safety-related topics that apply to multiple nuclear reactors and increase the efficiency of the licensing process by minimizing the time and resources that both applicants and the Staff spend on multiple reviews of the same topic. Kairos submitted eleven topical reports for the Staffs review and approval, 2 Ex. KRS-, Applicants Pre-Filed Testimony of Peter Hastings; Kairos Power LLC; Evidentiary Hearing (Sept., ), at, (Kairos Testimony).

3 Id. at.

4 Id. at, ; Ex. NRC-, Safety Evaluation Related to the Kairos Power LLC Construction Permit Application for the Hermes Test Reactor (June, ), at -, - (Safety Evaluation).

5 The public version of the application can be found in Exhibits NRC-A through NRC-E in this proceeding.

6 Ex. NRC-, Staffs Statement in Support of the Uncontested Hearing for Issuance of a Construction Permit for the Kairos Hermes Test Reactor, Commission Paper SECY--

(Aug., ), at (Staff Information Paper). The topics covered by the topical reports, preapplication meetings, and preapplication audits are listed in the Staff Information Paper. Id.

at -.

eight of which were referenced in its application.7 Kairos supplemented its application and provided clarifications through timely responses to several hundred Staff questions during audit meetings and in docketed correspondence.8 The Staff also issued three requests for additional information and one request for confirmation of information.9 Kairos and the Staff used regulatory guidance in NUREG-in the preparation and review of the construction permit application.10 Kairos did not request, and the Staff did not grant, any exemptions from NRC regulations.11 The Staff conducted a safety review of the application to determine whether it complies with the Atomic Energy Act of, as amended (AEA), and the NRCs regulations.12 The Advisory Committee on Reactor Safeguards (ACRS), a committee of technical experts charged with reviewing and reporting on safety studies and applications for construction permits and facility operating licenses, provided an independent assessment of the safety aspects of the 7 Id. The Staff prepared a safety evaluation for each of the topical reports, and any condition or limitation on the use of a topical report is provided in the approved version of the report. Id. at.

The Staffs review of the construction permit application confirmed that the conditions or limitations for the topical reports referenced in the application were satisfied or could reasonably be left for the operating license application. Id.

8 Ex. KRS-, Kairos Testimony, at.

9 Id.

10 See id. at (citing Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors: Format and Content, NUREG-, pt. (Feb. ) (ADAMS accession no. ML); Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors: Standard Review Plan and Acceptance Criteria, NUREG-, pt.

(Feb. ) (ML)); Ex. NRC-, Staff Information Paper, at -.

11 Ex. NRC-, Staff Information Paper, at.

12 See Ex. NRC-, Safety Evaluation.

application.13 The ACRS recommended that the construction permit be issued.14 The Staff also performed an environmental review, in accordance with the National Environmental Policy Act of (NEPA),15 that evaluated the environmental impacts of constructing, operating, and decommissioning the Hermes test reactor.16 Based on its safety and environmental reviews, the Staff recommended that the Commission issue the construction permit to Kairos once the National Historic Preservation Act of (NHPA) section consultation process is complete.17 B.

Review Standards Section a. of the AEA requires that we hold a hearing on an application to construct a testing facility.18 The Staff published a notice of hearing in the Federal Register and provided an opportunity for interested members of the public to petition for leave to intervene.19 No petitions to intervene were filed. Therefore, there was no separate contested hearing.

We issued a second notice that set the time and place for the uncontested hearing and outlined the standards for our review.20 These standards track the two major areas of focus for 13 See Letter from Joy L. Rempe, ACRS, Chairman, to Christopher T. Hanson, Chair, NRC, Kairos Non-Power Reactor Hermes Construction Permit Application (May, )

(MLA) (ACRS Letter).

14 Id. at.

15 U.S.C. § et seq.

16 See Ex. NRC-, Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Final Report), NUREG- (Aug. ) (FEIS).

17 Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Regan). At the time of the hearing, the Staff had not yet completed the section consultation process.

18 AEA § a., U.S.C. § (a) (The Commission shall hold a hearing... on any application under section c. for a construction permit for a testing facility.).

19 Kairos Power, LLC; Construction Permit Application; Opportunity to Request a Hearing and Petition for Leave to Intervene; Order Imposing Procedures, Fed. Reg. (Feb., ).

20 Hearing Notice, Fed. Reg. at,-.

the review of a construction permit application: the Staffs safety and environmental reviews. For the safety review, we must determine whether:

the applicant has described the proposed design of the facility, including, but not limited to, the principal architectural and engineering criteria for the design, and has identified the major features or components incorporated therein for the protection of the health and safety of the public; such further technical or design information as may be required to complete the safety analysis, and which can reasonably be left for later consideration, will be supplied in the final safety analysis report; safety features or components, if any, which require research and development have been described by the applicant and the applicant has identified, and there will be conducted, a research and development program reasonably designed to resolve any safety questions associated with such features or components; and on the basis of the foregoing, there is reasonable assurance that (i) such safety questions will be satisfactorily resolved at or before the latest date stated in the application for completion of construction of the proposed facility, and (ii) taking into consideration the site criteria contained in C.F.R. Part, the proposed facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.21 In making these findings, we are guided by the additional considerations in C.F.R.

§.. We consider whether:

the processes to be performed, the operating procedures, the facility and equipment, the use of the facility, and other technical specifications, or the proposals, in regard to any of the foregoing collectively provide reasonable assurance that the applicant will comply with NRC regulations, including the regulations in C.F.R. Part,22 and that the health and safety of the public will not be endangered; 21 C.F.R. §.(a); Hearing Notice, Fed. Reg. at,-.

22 The regulations in Part apply to persons licensed by the Commission to receive, possess, use, transfer, or dispose of byproduct, source, or special nuclear material or to operate a production or utilization facility. C.F.R. §.. Kairos has neither requested approval of design information nor has applied for a license to receive, possess, use, transfer, or dispose of byproduct, source, or special nuclear material at the facility. Ex. NRC-, Safety Evaluation, at -. Therefore, the [S]taff did not evaluate whether requirements in CFR Part would be met for the construction of the Hermes reactor. Instead, the [S]taff assessed whether Kairos had identified the relevant requirements for an operating facility and provided descriptions of the preliminary facility design and provisions for protecting the health and safety of the public, workers, and the environment in sufficient detail to determine whether the [preliminary safety analysis report] provides an acceptable basis for the development of the radiation protection programs and radioactive waste management, and whether there is reasonable assurance that

the applicant is technically and financially qualified to engage in the proposed activities; the issuance of the construction permit will not be inimical to the common defense and security or to the health and safety of the public; and any applicable requirements of Subpart A of C.F.R. Part have been satisfied.23 Overlapping this last consideration are the environmental findings that we must make to support issuance of the construction permit.24 The findings reflect our agencys obligations under NEPA, a statute that requires us to consider the impacts of NRC actions on environmental values.25 To ensure that these obligations are fulfilled for this construction permit proceeding, we must:

determine whether the requirements of NEPA Sections ()(A), (C), and (E),26 and the applicable regulations in C.F.R. Part, have been met; independently consider the final balance among conflicting factors contained in the record of the proceeding with a view to determining the appropriate action to be taken; determine, after weighing the environmental, economic, technical, and other benefits against environmental and other costs, and considering reasonable alternatives, whether the construction permit should be issued, denied, or appropriately conditioned to protect environmental values; and Kairos will comply with the regulations in CFR Part during operation of the Hermes facility. Id. We agree that the Staffs approach meets C.F.R. §.(a).

23 C.F.R. §.(a)-(d).

24 See, e.g., id. §.(a).

25 NEPA § (), U.S.C. § (); see C.F.R. §..

26 On June 3, 2023, President Biden signed into law the Fiscal Responsibility Act of 2023.

Pub. L. No. 118-5, 137 Stat. 10. In addition to increasing the debt ceiling and addressing other matters related to federal spending, the Act, in section 321, included amendments to NEPA.

The amendments added new sections (D), (E), and (F) to section 102(2); as a result, the section 102(2)(E) referred to in 10 C.F.R. § 51.105(a)(1) is now section 102(2)(H), but the substance of the provision remains the same.

determine whether the NEPA review conducted by the NRC Staff has been adequate.27 If we determine that the application meets the standards and requirements of the AEA and the NRCs regulations and that any notifications to other agencies or bodies have been duly made, we will issue a construction permit in such form and containing such conditions and limitations that we deem appropriate and necessary.28 We do not review Kaiross application de novo; rather, we consider the sufficiency of the Staffs review of the application on both safety and environmental matters.29 In other words, we consider whether the safety and environmental record is adequate to support issuance of the construction permit and whether the Staffs findings are reasonably supported in logic and fact.30 Under our regulations, we must reach our own independent determination on certain environmental findingsi.e., whether the relevant NEPA requirements have been met, what is the appropriate final balance among conflicting factors, and whether the construction permit should be issued, denied[,] or appropriately conditioned.31 But we will not second-guess [the Staffs] underlying technical or factual findings unless we find the Staffs review incomplete or inadequate or its findings insufficiently explained in the record.32 27 C.F.R. §.(a)()-(); Hearing Notice, Fed. Reg. at,. Because this is an uncontested proceeding, C.F.R. §.(a)(), which concerns only contested proceedings, does not apply.

28 C.F.R. §..

29 See Exelon Generation Co. (Early Site Permit for Clinton ESP Site), CLI--, NRC,,

- ().

30 See id. at.

31 Id. at (quoting C.F.R. §.(a)()-()).

32 Id.

C.

The Hearing Process The Staff completed its safety review of the Hermes application in June, with the publication of the Safety Evaluation, and its environmental review in August, with the issuance of the Final Environmental Impact Statement (FEIS).33 Shortly after publication of the FEIS we received the Staffs information paper, which serves as the Staffs pre-filed testimony for the uncontested hearing.34 Pre-Hearing Activities The notice of hearing set a schedule for pre-hearing filings.35 We issued twenty-eight questions on environmental and safety-related topics for the Staff and Kairos to answer in writing in advance of the hearing. The questions addressed a variety of topics including functional containment, temperature monitoring of the safety-related decay heat removal system, how to address the new NEPA requirements enacted in June, and whether the cumulative impacts of the proposed Hermes facility are analyzed in the FEIS.36 We also invited interested states, local government bodies, and federally recognized Indian tribes to provide statements for us to consider as part of the uncontested proceeding.37 In response, we received a statement from the City of Oak Ridge, Tennessee.38 The letter from the 33 See Ex. NRC-, Safety Evaluation; Ex. NRC-, FEIS.

34 See Ex. NRC-, Staff Information Paper.

35 Hearing Notice, Fed. Reg. at,.

36 See Order of the Secretary (Transmitting Pre-Hearing Questions) (Sept., )

(unpublished), at - (Pre-Hearing Questions Order).

37 See Hearing Notice, Fed. Reg. at,.

38 See Letter from Jack Suggs, Interim City Manager, City of Oak Ridge, Tennessee, to NRC Document Control Desk (Sept., ) (MLA).

City of Oak Ridge expressed its continued support for the Kairos project and described the positive interaction with Kairos during the Citys zoning approval process.39 The Hearing We set the topics for and the order of presentations at the hearing.40 In the first panel, witnesses for Kairos provided an overview of the Hermes test reactor project and the Hermes construction permit application.41 In the second panel, witnesses for the Staff provided an overview of the construction permit review process and a summary of the Staffs review and regulatory findings.42 The third panel focused on safety-related issues, and the fourth panel focused on environmental issues.43 The Staff made available thirty-two witnesses at the hearing.44 Thirteen of these witnesses were scheduled panelists; the remainder stood by to answer questions on topics related to their areas of expertise.45 A total of twenty-one Kairos 39 Id. at -.

40 See Memorandum from Brooke P. Clark, Secretary of the Commission, to Counsel for Applicant and Staff (Oct., ), Encl. (MLA) (Scheduling Note).

41 Ex. KRS-, Hermes Mandatory HearingOverview Panel (Oct., ) (Kairos Overview Panel Presentation).

42 Ex. NRC--R, Kairos Hermes Mandatory Hearing Construction Permit Application Review:

Overview of Review Methodology and Summary of Key Regulatory Findings (Oct., )

(Staff Overview Panel Presentation).

43 See Ex. KRS-, Hermes Mandatory HearingSafety Panel (Oct., ) (Kairos Safety Panel Presentation); Ex. NRC-, Kairos Hermes Mandatory Hearing Construction Permit Application Review: Safety Panel (Oct., ) (Staff Safety Panel Presentation);

Ex. KRS-, Hermes Mandatory HearingEnvironmental Panel (Oct., ) (Kairos Environmental Panel Presentation); Ex. NRC-, Kairos Hermes Mandatory Hearing Construction Permit Application Review (Oct., ) (Staff Environmental Panel Presentation).

44 See Tr. at - (Ms. Wright); see also NRC Staff Witness List (Sep., ), Attach.

(MLA).

45 See Ex. NRC--R, Staff Overview Panel Presentation, at ; Ex. NRC-, Staff Safety Panel Presentation, at (MLA) (Staff Safety Panel Presentation); Ex. NRC-, Staff Environmental Panel Presentation, at.

witnesses attended the hearing, four of whom offered testimony on behalf of Kairos on panels at the hearing and in pre-filed written testimony.46

a.

Summary of the Overview Panels Mike Laufer, Chief Executive Officer; Ed Blandford, Chief Technology Officer; Per Peterson, Chief Nuclear Officer; and Peter Hastings, Vice President, Regulatory Affairs and Quality of Kairos Power LLC, provided testimony for the Kairos overview panel.47 Dr. Laufer provided information on the background and mission of Kairos.48 Dr. Peterson provided testimony on technical aspects and the objectives for the Hermes reactor project.49 Dr. Laufer, Dr. Peterson, and Mr. Hastings also answered questions regarding the effectiveness of Kaiross interactions with the Staff during its review, the interactions with the community around Oak Ridge, Tennessee, and the public more generally, and the purpose of the mandatory hearing process.50 Robert Taylor, Deputy Director of the Office of Nuclear Reactor Regulation (NRR);

Mohamed Shams, Director, Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU), NRR; Jeremy Bowen, Deputy Director, DANU, NRR; and Christopher Regan, Director, Division of Rulemaking, Environmental, and Financial Support (REFS), Office of Nuclear Material Safety and Safeguards (NMSS), presented the Staffs overview panel and provided testimony on the Staffs review of the Kairos construction permit 46 See List of Anticipated Witnesses for Kairos Power, LLC for the Hearing on Uncontested Issues (Sep., ), at -; Tr. at - (Mr. Lighty); Ex. KRS-, Kairos Testimony; Ex. KRS-, Kairos Overview Panel Presentation, at ; Ex. KRS-, Kairos Safety Panel Presentation, at ; Ex. KRS-, Kairos Environmental Panel Presentation, at.

47 Tr. at - (Dr. Laufer, Dr. Peterson); Scheduling Note, Encl. at.

48 Tr. at - (Dr. Laufer).

49 Id. at - (Dr. Peterson).

50 Id. at - (Dr. Laufer, Dr. Peterson, Mr. Hastings).

application.51 Mr. Taylor provided an overview of the Kairos construction permit application.52 Mr. Shams described the pre-application engagement with Kairos, regulatory standards governing the construction permit application review, and public engagement during the review.53 Mr. Bowen provided insights into the Staffs safety review.54 Mr. Regan provided an overview of the Staffs environmental review and findings in support of issuance of the construction permit.55 Mr. Shams, Mr. Taylor, and Mr. Bowen answered questions relating to the applicants construction permit application, research activities, pre-application engagement, the use of topical reports in the construction permit application review, knowledge management for future advanced reactor applications, and lessons learned from the Staffs review of this construction permit application that can be applied to the Hermes construction permit application.56

b.

Summary of the Safety Panel The safety panel discussed the Kairos construction permit application and Staff conclusions from the Safety Evaluation, focusing on unique features of the facility and novel issues, including TRISO fuel, molten salt coolant, high-temperature materials, functional containment, and passive accident response.57 Ed Blandford, Chief Technology Officer, Kairos 51 Id. at - (Mr. Taylor, Mr. Shams, Mr. Bowen, Mr. Regan); Scheduling Note, Encl. at.

52 Id. at - (Mr. Taylor).

53 Id. at - (Mr. Shams).

54 Id. at - (Mr. Bowen).

55 Id. at - (Mr. Regan).

56 Id. at - (Mr. Shams, Mr. Taylor, Mr. Bowen).

57 Id. at - (Mr. Blandford, Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy); Ex. KRS-, Kairos Safety Panel Presentation, at -; Ex. NRC-, Staff Safety Panel Presentation, at -.

Power LLC, served as the witness for Kairos.58 William Jessup, Chief, Advanced Reactor Licensing Branch, DANU, NRR; Edward Helvenston, Project Manager, DANU, NRR; Chris Van Wert, Senior Technical Advisor for Reactor Fuel, Division of Safety Systems, NRR; Alexander Chereskin, Materials Engineer, DANU, NRR; Michelle Hart, Senior Reactor Engineer, DANU, NRR; and Alexandra Siwy, Senior Nuclear Engineer, DANU, NRR, testified for the Staff.59 Kaiross testimony focused on the inherent safety features of the Hermes test reactor, including how the TRISO fuel and the Flibe coolant allow for the use of functional containment in making Kaiross safety case.60 The Staffs testimony addressed the regulatory requirements for issuing a construction permit and covered novel technical issues presented by the Hermes test reactor, including the TRISO fuel, molten salt coolant, high temperature materials, functional containment, and passive accident response.61 Following the safety panel presentations, we posed questions to witnesses for both Kairos and the Staff.

58 Tr. at - (Mr. Blandford); Scheduling Note, Encl. at.

59 Id. at - (Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy);

Scheduling Note, Encl. at.

60 Tr. at - (Mr. Blandford).

61 Id. at - (Mr. Jessup, Mr. Helvenston, Mr. Van Wert, Mr. Chereskin, Ms. Hart, Ms. Siwy).

c.

Summary of the Environmental Panel The environmental panel focused on the FEIS, including the proposed federal action, purpose and need for the project, the environmental review process and public outreach, NEPA findings, and alternatives to the proposed action.62 Peter Hastings, Vice President, Regulatory Affairs and Quality, represented Kairos.63 Kenneth Erwin, Branch Chief, New Reactor Environmental Review Branch, REFS, NMSS; Tamsen Dozier, Project Manager, REFS, NMSS; and Peyton Doub, Environmental Scientist, REFS, NMSS, testified on behalf of the Staff.64 Mr. Hastings discussed the environmental report, the site-selection process, and characteristics of the Hermes test reactor site.65 The Staff described the proposed federal action, its environmental review process, evaluation of alternatives to the proposed action, consultation with other agencies and tribes, public outreach, and consideration of and conclusions on environmental impacts.66 Following the environmental panel presentations, we posed questions to witnesses for both Kairos and the Staff.

Post-Hearing Activities After the hearing, we adopted corrections to the hearing transcript and admitted a revised Staff exhibit.67 We held the record open because the Staff had not yet completed its 62 Id. at - (Mr. Hastings, Mr. Erwin, Ms. Dozier, Mr. Doub); Scheduling Note, Encl. at ;

Ex. KRS-, Kairos Environmental Panel Presentation, at -; Ex. NRC-, Staff Environmental Panel Presentation, at -.

63 Tr. at - (Mr. Hastings); Scheduling Note, Encl. at.

64 Id. at - (Mr. Erwin, Ms. Dozier, Mr. Doub); Scheduling Note, Encl. at.

65 Tr. at - (Mr. Hastings).

66 Id. at - (Mr. Erwin, Ms. Dozier, Mr. Doub).

67 Order of the Secretary (Adopting Transcript Corrections and Admitting Revised Exhibit)

(Nov., ) (unpublished).

consultation activities under the NHPA.68 On December, the Staff filed revisions to two exhibits: NRC-, the draft construction permit, and NRC-, the draft record of decision.69 In the revised draft construction permit, the Staff made several non-substantive edits and replaced placeholder language relating to NHPA section with a requirement that Kairos implement its Archaeological Resource Monitoring and Unanticipated Discovery Plan.70 In the revised draft record of decision, the Staff documented completion of the NHPA section process for this licensing action.71 Kairos does not object to the admission of these exhibits.72 Accordingly, we strike exhibits NRC-and NRC-, admit exhibits NRC--R and NRC--R, and close the evidentiary record.

DISCUSSION As discussed in Section II.E, we find that Kaiross application meets our regulatory requirements for issuance of a construction permit. Although we authorize issuance of a construction permit, our decision does not constitute approval of the design.73 Kairos has represented that it will apply for an operating license and submit with that application a final 68 Id. at.

69 NRC Staff Exhibit List (Dec., ) (Staff Revised Exhibit List), at ; see Ex. NRC--R, Kairos Power LLC, Docket No. -, Hermes Test Reactor Construction Permit (Oct.,

) (Draft Construction Permit); Ex. NRC--R, Draft Summary Record of Decision, U.S.

Nuclear Regulatory Commission, Docket No. -, Construction Permit Application for the Kairos Hermes Test Reactor (Nov., ) (Draft Record of Decision).

70 See Staff Revised Exhibit List at -; Ex. NRC--R, Draft Construction Permit, app. A, at A-.

71 Staff Revised Exhibit List at ; Ex. NRC--R, Draft Record of Decision, at,.

72 Staff Revised Exhibit List at.

73 See C.F.R. §.(b) (A construction permit will constitute authorization to the applicant to proceed with construction but will not constitute Commission approval of the safety of any design feature or specification unless the applicant specifically requests such approval and such approval is incorporated into the permit.). Kairos did not request such approval.

safety analysis report, which will contain the final detailed design.74 The discussion that follows provides a survey of the key facts that support our findings and certain novel issues in the Staffs safety review. We do not discuss every aspect of Kaiross construction permit application, the Staffs review, or our sufficiency review. Our decision to authorize issuance of the construction permit, however, is based on the record in its entirety.

A.

The Proposed Design Kaiross Hermes reactor will be configured as a pebble bed with a chemically stable, low-pressure molten fluoride salt coolant known as Flibe.75 The pairing of high-temperature-tolerant TRISO fuel and low-pressure, single-phase, chemically stable reactor coolant reduces the number of potential fuel-damage scenarios, thus simplifying the reactor design and reducing the number of required safety systems.76 For example, low-leakage, pressure retaining containment structures are not necessary due to the low pressure of the reactor and associated piping in combination with the fission product retention provided by the TRISO fuel.77 The Hermes design further relies on passive decay heat removal and does not require an emergency core cooling system for decay heat removal or replacement of coolant inventory.78 The Hermes reactor has three major plant systems: the reactor system, the primary heat transport system, and the decay heat removal system.79 The facility includes engineered safety 74 See, e.g., Ex. KRS-, Kairos Testimony, at.

75 Ex. NRC-, Safety Evaluation, at -.

76 Ex. KRS-, Kairos Testimony, at.

77 Id.; Tr. at (Dr. Peterson).

78 Ex. KRS-, Kairos Testimony, at.

79 Id.

features that provide functional containment and decay heat removalthese features are credited for mitigation of the consequences of postulated events.80 Kairos uses a definition of safety-related structures, systems, and components that differs from the definition found in C.F.R. §. to establish those structures, systems, and components that are classified as safety related for the Hermes reactor. Specifically, in lieu of using the integrity of the reactor coolant pressure boundary terminology in C.F.R. §.,

Kairos's definition reads: the integrity of the portions of the reactor coolant boundary relied upon to maintain coolant level above the active core.81 Kairos uses this definition because the Hermes reactor does not rely on the functional capability of the primary heat transport system to remove decay heat from the reactor core, and the Staff found this definition acceptable for the proposed facility.82 TRISO Fuel Hermes will use TRISO fuel particles embedded in a carbon matrix pebble.83 The pebbles are roughly the size of golf balls, and the TRISO particles are roughly the size of poppy seeds.84 The fuel particle is composed of a uranium oxycarbide fuel kernel encased in coating layers to limit fission product releases.85 The fuel particles will contain high assay low enriched 80 See Ex. KRS-, Kairos Testimony, at.

81 Ex. NRC-, Safety Evaluation, at - (emphasis added). The Staff found that the C.F.R.

§. definition of safety-related structures, systems, and components is not applicable to the Hermes facility. Id.; Ex. NRC-, NRC Staff Responses to Commission Pre-Hearing Questions (Sept., ), at (Staff Pre-Hearing Responses).

82 Ex. NRC-, Safety Evaluation, at -, - to -.

83 Ex. NRC-, Staff Safety Panel Presentation, at.

84 Tr. at (Mr. Van Wert).

85 Ex. NRC-, Staff Information Paper, at.

uranium.86 The coating layers are composed of pyrolytic carbon and silicon carbide.87 In addition, there is a carbon buffer layer between the kernel and the inner pyrolytic carbon layer that serves to accommodate fission gases and limit pressure buildup.88 The TRISO particles are arranged in a fuel annulus near the outer surface of the pebble surrounding a low-density graphite core.89 In addition to fuel pebbles, the reactor also contains moderator pebbles, which have the same diameter as the fuel pebbles but contain no uranium and are made of graphite material.90 Both the fuel and moderator pebbles are designed to maintain positive buoyancy under normal operation and postulated events.91 Pebbles are buoyant in Flibe and travel upward through the core.92 The TRISO particle specification is based on the U.S. Department of Energy (DOE)

Advanced Gas Reactor program.93 The TRISO fuel is similar to that developed for high temperature gas-cooled reactors, and the coatings on the particle fuel have demonstrated retention of fission products to temperatures above,°C.94 In comparison, the Hermes test reactor normal operating temperature is up to °C.95 86 Ex. NRC-, Safety Evaluation, at ii.

87 Ex. NRC-, Staff Information Paper, at.

88 Id.

89 Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Van Wert); Ex. NRC-, Staff Safety Panel Presentation, at.

90 Ex. NRC-, Safety Evaluation, at -.

91 Id.

92 Id. at -.

93 Ex. NRC-, Staff Information Paper, at.

94 Id. at ; Ex. NRC-, Safety Evaluation, at - to -; Tr. at - (Dr. Peterson).

95 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.

The Staff evaluated the Kairos fuel qualification program as described in the topical report and concluded that it meets the applicable regulatory requirements.96 Tribology testing will be conducted on fuel pebbles in two separate environments: () Flibe with an argon cover gas, and () an argon only environment.97 The coefficient of friction and wear rates will be determined during tribology tests in both of these environments.98 In its preliminary safety analysis report, Kairos provided the relevant principal design criteria, a design description of the TRISO particle and corresponding fuel elements (pebbles), and a preliminary analysis and evaluation of the fuel element demonstrating the margins of safety during normal operations and transient conditions anticipated during the life of the facility.99 The Staff concluded that the information was sufficient to conform to the applicable guidance and meet the regulatory requirements of C.F.R. §§. and..100 Both fuel and moderator pebbles will be inspected by the pebble handling and storage system as they are removed from the core.101 Therefore, neither the fuel nor moderator pebbles are expected to produce debris or dust in the reactor coolant that could inhibit the removal of heat from the core.102 96 Id.; see Final Safety Evaluation for Topical Report KP-TR-, Revision, Fuel Qualification Methodology for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor (KP-FHR),

(Mar., ) (MLA).

97 Ex. KRS-, Kairos Power LLCs Responses to Commissions Pre-hearing Questions (Oct., ), at (Kairos Pre-Hearing Responses).

98 Id.

99 Ex. NRC-, Staff Information Paper, at.

100 Id.

101 Ex. NRC-, Safety Evaluation, at -; Ex. KRS-, Kairos Pre-Hearing Responses, at.

102 Ex. KRS-, Kairos Pre-Hearing Responses, at ; Ex. NRC-, Safety Evaluation, at -

to -; see also Ex. NRC-, Staff Pre-Hearing Responses, at.

Molten Salt Coolant Flibe is a lithium fluoride-beryllium fluoride mixture (LiF-BeF).103 In the Hermes design, the Flibe coolant is credited with supporting reactivity control and serving as a fission product barrier.104 Flibe is able to retain radionuclides and prevent radionuclide release to the environment during normal operations and postulated events.105 The Staff reviewed the capabilities of Flibe to retain fission products in its review of Karioss topical report on mechanistic source term.106 Flibe has advantageous heat transfer properties and is thermally and radiolytically stable at high temperatures.107 But Flibe contains beryllium, which requires controls to mitigate potential worker exposure, and the transmutation of lithium will generate tritium, which will also need to be managed.108 The Staff will evaluate the potential beryllium hazard and its ability to impact operations or accident response and the methods and systems to control tritium during the operating license review.109 During reactor operations, the Flibe coolant is expected to accumulate impurities, which may affect the corrosion of primary system components, create some circulating activity in the primary system, affect reactivity characteristics, and potentially affect thermophysical properties.110 To ensure that the Flibe coolant maintains the properties needed for natural circulation heat transfer, Kairos must monitor, and potentially correct, the salt 103 Ex. KRS-, Kairos Safety Panel Presentation, at.

104 Ex. NRC-, Staff Information Paper, at.

105 Ex. KRS-, Kairos Testimony, at.

106 Tr. at (Mr. Chereskin).

107 Ex. NRC-, Staff Information Paper, at.

108 Tr. at (Mr. Chereskin).

109 Id.

110 Ex. NRC-, Staff Information Paper, at.

composition.111 Kairos expects to include a limiting condition of operation to maintain the reactor coolant composition within allowable limits as part of the technical specifications in its operating license application.112 High-Temperature Materials The Hermes test reactor design operates at higher temperatures than light-water reactors.113 Therefore, the primary system components must be qualified for these high temperatures as well as for the Flibe coolant environment.114 This construction permit application is the first to reference American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section III, Division, High Temperature Materials, which was endorsed in NRC Regulatory Guide., Revision.115 Kairos will use H stainless steel and ER--- weld filler material for safety-related metallic components and ET-for graphite reflector components.116 ASME Boiler and Pressure Vessel Code Section III, Division provides an approach to ensure the mechanical and structural integrity of components that operate in high-temperature environments. It specifies material properties, such as allowable stresses based on creep damage for the metallic materials at the times and temperatures the Hermes reactor 111 Id.

112 See Ex. NRC-, Safety Evaluation, at -.

113 Ex. NRC-, Staff Information Paper, at.

114 Id.

115 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Tr. at (Mr. Chereskin).

116 Tr. at - (Mr. Chereskin); Ex. NRC-, Staff Safety Panel Presentation, at -;

Ex. NRC-, Staff Information Paper, at.

components will experience.117 The use of Section III, Division also provides rules for aspects related to structural and mechanical integrity for the use of H stainless steel.118 ASME Boiler and Pressure Vessel Code Section III, Division does not address the interactions between the Flibe environment and metallic structural materials.119 Therefore, Kairos submitted a topical report describing its qualification plan for metallic structural materials used in Flibe-wetted areas for safety-related high-temperature components of its reactor designs, including the Hermes test reactor.120 The qualification plan includes extensive testing to quantify degradation mechanisms in normal and postulated accident conditions, and the Staffs evaluation of the topical report concluded that the Kairos qualification program for metallic materials satisfies the regulatory requirements related to the qualification of H stainless steel in the Flibe environment.121 The Hermes test reactor uses graphite reflector blocks to moderate and reflect neutrons back into the reactor core and protect the reactor vessel from the effects of neutron fluence.122 The reflector blocks provide a heat sink for the core and form coolant flow channels, the pebble defueling chute, and channels for the insertion and withdrawal of reactivity control and shutdown elements.123 For graphite components, Kairos cited an approved topical report for the 117 Tr. at (Mr. Chereskin).

118 Id.

119 Tr. at (Mr. Chereskin).

120 See Metallic Material Qualification for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor, KP-TR--NP-A, Revision (Sept. ) (MLA).

121 Ex. NRC-, Staff Information Paper, at.

122 Id.

123 Id.; Ex. NRC-, Safety Evaluation, at -.

qualification of the material.124 In its evaluation of the topical report on graphite qualification, the Staff concluded that the methodology is acceptable because it is generally consistent with applicable portions of ASME Boiler and Pressure Vessel Code,Section III, Division, with departures related to graphite material qualification.125 The behavior of graphite as a function of fluence and temperature is an important design consideration to ensure graphite components maintain their integrity and perform their design functions.126 Functional Containment The safety case for the Hermes reactor is based on the concept of functional containment, which is a barrier, or a set of barriers taken together, that effectively limits the physical transport of radioactive materials to the environment.127 For the Hermes test reactor, functional containment consists of physical barriers, operating conditions, coolant design, and fuel form.128 We previously approved the concept of functional containment in SRM-SECY--.129 Instead of using the event categorization scheme described in SECY--, Kairos identified anticipated operational occurrences, design-basis events, and beyond-design-basis-events, consistent with a maximum hypothetical accident (MHA) 124 See Graphite Material Qualification for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor, KP-TR--NP-A, Revision (Sept. ) (MLA).

125 Ex. NRC-, Staff Information Paper, at.

126 Id.; see Tr. at - (Mr. Chereskin).

127 See Ex. KRS-, Kairos Safety Panel Presentation, at ; Ex. NRC-, Staff Safety Panel Presentation, at (citing SECY--, Functional Containment Performance Criteria for Non-Light-Water-Reactors, (MLA)).

128 Ex. NRC-, Safety Evaluation, at -.

129 Staff RequirementsSECY--Functional Containment Performance Criteria for Non-Light-Water-Reactors (Dec., ) (MLA).

approach.130 The MHA is intended to bound all postulated events in terms of dose consequences, consistent with the guidance for non-power reactors in NUREG-.131 To establish the MHA, Kairos considered a broad range of event categories, including insertion of reactivity, salt spills, loss of forced circulation, malfunction of the pebble handling and storage system, radioactive releases from a subsystem or component, general challenges to normal operation, internal hazards (fire and flood), and external hazards (seismic, wind, and flood).132 The Staff concluded that Kaiross MHA analysis demonstrates that the dose consequences of the MHA are within the accident dose criteria of C.F.R. §.(a).133 Even with conservative estimates for releases from TRISO fuel, tritium in graphite structures, and argon-from activation of the cover gas, the MHA results in radiological doses at the site boundary that are well below the siting criteria of rem and also below the U.S. Environmental Protection Agency Protective Action Guides.134 The safety case for the Hermes reactor does not rely on traditional containment barriers like reactor coolant piping or the reactor building due to the effectiveness of the TRISO fuel particle and the Flibe coolant at retaining radionuclides.135 The fuel particle forms four of the five fission product barriers credited for functional containment: the fuel kernel, an inner pyrolytic carbon layer, a silicon carbide layer, and an outer pyrolytic carbon layer.136 Additionally, the fuel 130 Ex. NRC-, Staff Information Paper, at.

131 See Ex. KRS-, Kairos Pre-Hearing Responses, at.

132 ACRS Letter at.

133 Ex. NRC-, Staff Information Paper, at.

134 ACRS Letter at. The dose consequences of the MHA are less than rem at the site boundary. Ex. KRS-, Kairos Safety Panel Presentation, at.

135 See Ex. KRS-, Kairos Safety Panel Presentation, at.

136 Ex. NRC-, Staff Information Paper, at.

particles are embedded in an annular shell arrangement inside a spherical pebble, which provides physical protection against mechanical damage.137 The majority of radioactive material at risk for release is held within the TRISO fuel, and the Flibe coolant serves as an additional barrier for release of radionuclides for submerged fuel pebbles.138 Because the TRISO fuel and Flibe coolant effectively contain fission products such as cesium and iodine, the MHAs dose driving elements are mobile activation products, such as argon-and tritium, rather than fission products.139 Kairos described the components and operating conditions that define the Hermes test reactor functional containment in its preliminary safety analysis report.140 Kairos also identified key performance criteria on specific structures, systems, and components to ensure that the MHA remains bounding: () specified acceptable system radionuclide release design limits for the fuel and () circulating activity limits for the Flibe coolant.141 Passive Accident Response The reactor vessel system contains the reactor core and provides for circulation of reactor coolant and pebbles as well as insertion of the reactivity control and shutdown system elements in the reactor core.142 The Hermes test reactor is designed with three safety-related shutdown elements, only two of which are needed to shut down the reactor and maintain it in a 137 Ex. NRC-, Safety Evaluation, at -.

138 See Ex. KRS-, Kairos Safety Panel Presentation, at.

139 Ex. KRS-, Kairos Pre-Hearing Responses, at ; ACRS Letter at.

140 Ex. NRC-, Staff Information Paper, at.

141 Id.

142 Ex. NRC-, Safety Evaluation, at -.

safe condition.143 These elements have two positionsfully withdrawn or fully inserted.144 The shutdown elements accomplish a safe shutdown (reactor trip) through gravity insertion on a reactor trip signal or on a loss of normal electrical power, after a short delay to mitigate spurious trips.145 The reactor trip signal removes power from an electromagnetic clutch, which causes the shutdown elements to fall into the core by gravity and shut down the reactor.146 The reactor relies on passive decay heat removal and does not need an active emergency core cooling system for decay heat removal or replacement of coolant inventory.147 The decay heat removal system removes residual decay heat from the reactor core through the reactor vessel wall during both normal and off-normal conditions.148 In postulated events where the normal heat rejection system is unavailable, the decay heat removal system, along with natural circulation flow within the core, provides heat removal from fuel in the reactor core via thermal radiation and convection without the need for external sources of electrical power or operator intervention.149 Natural circulation and the passive decay heat removal system reject residual heat from the reactor core to the atmosphere.150 The decay heat removal system and 143 See Ex. NRC-, Staff Pre-Hearing Responses, at.

144 Ex. NRC-, Staff Information Paper, at.

145 Id.; Ex. NRC-, Safety Evaluation, at -.

146 Ex. NRC-, Staff Safety Panel Presentation, at.

147 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Overview Panel Presentation, at. Active emergency replacement of coolant inventory is not required based on the results of the maximum Flibe spill event. See Ex. NRC-, Safety Evaluation, - to

-. The evaluation determined that, without active emergency makeup, sufficient inventory was maintained to support adequate invessel natural circulation, to ensure the fuel remains covered, and to limit the heat up and radionuclide release. Additionally, the Staff determined that a Flibe salt spill beyond that assumed in the analysis is not expected to occur. Id. at -.

148 Ex. NRC-, Staff Information Paper, at.

149 Ex. KRS-, Kairos Testimony, at.

150 See Ex. KRS-, Kairos Safety Panel Presentation, at.

natural circulation together provide adequate heat removal to ensure that the vessel temperature remains below design limits and that the fuel integrity is not challenged.151 The decay heat removal system is made up of four independent trains to provide redundancy in the event of a single failure.152 The decay heat removal system has sufficient inventory in the thermosyphons to operate for up to seven days to mitigate a postulated event where normal cooling systems are unavailable.153 The fluidic diodes, which are part of the reactor internals and enable natural circulation when forced circulation is lost, will be subject to planned qualification testing and inspection.154 The Staff concluded that there is reasonable assurance that the reactor vessel system will perform its safety functions of maintaining structural integrity, geometry, and coolant inventory to ensure sufficient heat removal.155 B.

The Proposed Site The site is located in an industrial area of Oak Ridge, Tennessee. The property is at the site of former Buildings K-and K-of the DOE gaseous diffusion plant, where uranium enrichment occurred between the mid-s and mid-s.156 The site boundary encompasses acres, of which about acres would be permanently disturbed for operations of the facility.157 The site is adjacent to Poplar Creek and. mile (. kilometer) from the Clinch River arm of the Watts Bar Reservoir.158 151 Ex. KRS-, Kairos Testimony, at.

152 Id.

153 Ex. NRC-, Staff Information Paper, at.

154 Id.; Ex. NRC-, Safety Evaluation, at -.

155 Ex. NRC-, Staff Information Paper, at -.

156 Id. at ; Ex. KRS-, Kairos Testimony, at.

157 Ex. KRS-, Kairos Overview Panel Presentation, at.

158 Ex. KRS-, Kairos Testimony, at.

The Staff considered the relevant siting criteria in Part and guidance in NUREG-and concluded that the Hermes facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.159 The Staff considered site characteristics such as geography and demography; nearby industrial, transportation, and military facilities; meteorology; hydrology; and geology, seismology, and geotechnical engineering.160 In addition, the Staff evaluated structures, systems, and components and equipment designed to ensure safe operation, performance, and shutdown when subjected to extreme weather, floods, seismic events, missiles (including aircraft impacts), chemical and radiological releases, and loss of offsite power.161 As stated earlier, Kairos plans to operate the reactor for four years. When the Staff assessed flooding hazards from potential dam failures, it relied on this limited operating lifetime to approve the acceptability of the site.162 Therefore, an operating license, if issued, would include a license term that would be limited to ensure the validity of assumptions and conclusions in the safety analysis for the final design of the Hermes facility.163 The Staff verified that the Hermes emergency planning zone size is appropriate and consistent with guidance based on the preliminary MHA calculations, which indicate that accident doses at the emergency planning zone boundary would not exceed the doses recommended by the U.S. Environmental Protection Agency protective action guidelines of rem total effective dose equivalent or rem projected child thyroid dose.164 The Staff will 159 See C.F.R. §.(a)()(ii).

160 Ex. NRC-, Safety Evaluation, at - to -.

161 Id.

162 Ex. NRC-, Staff Pre-Hearing Responses, at -.

163 Id. at.

164 Ex. NRC-, Safety Evaluation, at -; Ex. NRC-, Staff Pre-Hearing Responses, at -.

review the final justification for the emergency planning zone size based on more detailed plant design information during review of the operating license application.165 In pre-hearing questions, we inquired into potential hazards associated with the proposed Oak Ridge Airport. Kairos used DOE guidelines and methodologies in its evaluation of crash frequencies related to the proposed airport in its preliminary safety analysis report.166 Kairos will design the safety-related portion of the reactor building to withstand the impact of general aviation aircraft associated with operations at the proposed airport.167 Based on information in the environmental assessment prepared by DOE for the proposed Oak Ridge Airport, the Staff expects that the Beechcraft King Air i likely bounds the other types of general aviation aircraft that would use the airport.168 Additionally, Kairos stated that any proposed configuration of the airport runways is not anticipated to change the need to design for aircraft impact.169 C.

Technical and Design Information for Later Consideration Kairos has described the principal design features and the technology that it plans to use, but Kairos will supply further technical and design information in the final safety analysis report filed as part of the operating license application in accordance with C.F.R.

§.(a)(). The construction permit will not constitute approval of the safety of any design feature or specification.170 Because Kairos did not request approval of any design features or 165 Ex. NRC-, Staff Pre-Hearing Responses, at.

166 Ex. KRS-, Kairos Pre-Hearing Responses, at.

167 Id. at -; see Ex. NRC-, Staff Pre-Hearing Responses, at.

168 Ex. NRC-, Staff Pre-Hearing Responses, at.

169 Ex. KRS-, Kairos Pre-Hearing Responses, at.

170 Ex. NRC-, Staff Information Paper, at ; Ex. NRC-, Staff Safety Panel Presentation, at.

specifications to be included in the construction permit, the Staff did not make any findings regarding the safety of any Part design feature or specification.171 The Staff identified two conditions to include in the construction permitone relating to site characteristics and one relating to quality assurance. The first condition directs Kairos to confirm the condition of bedrock supporting the facility and provides for examination of excavations by the Staff, if necessary.172 The second requires Kairos to implement its quality assurance program for design, procurement, and construction of the Hermes reactor.173 By including this condition, the construction permit will have an explicit requirement comparable to C.F.R. §.(f)(). This condition will allow Kairos to make changes to the program without prior NRC approval that do not reduce commitments in the program description previously approved by the NRC, consistent with C.F.R. §.(f)().174 Without this license condition, the Staff would need to approve a license amendment request from Kairos to make any changes to the quality assurance plan regardless of whether the change would reduce a commitment.175 As it finalizes the design of its facility, Kairos will need to complete the following research and development activities: () perform a laboratory testing program to confirm fuel pebble behavior; () develop a high-temperature material surveillance sampling program for the reactor vessel and internals; () perform testing of high-temperature material to qualify Alloy H and ER---; () perform an analysis related to potential oxidation in certain postulated events for 171 Ex. NRC-, Staff Information Paper, at ; Ex. NRC-, Staff Pre-Hearing Responses, at.

172 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.

173 Ex. NRC-, Staff Safety Panel Presentation, at ; Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at.

174 Ex. KRS-, Kairos Pre-Hearing Responses, at.

175 Id.

the qualification of the graphite used in the reflector structure; () develop and validate computer codes for core design and analysis methodology; () develop a fluidic diode device to ensure proper circulation during normal operation and passive cooling by natural circulation; () justify thermodynamic data and associated vapor pressure correlations of representative species;

() develop process sensor technology for key reactor process variables; and () develop the reactor coolant chemical monitoring instrumentation.176 The Staff listed these activities in Appendix A, Section A. of the Safety Evaluation and will verify that they are completed prior to the completion of construction, which Kairos projects to be December.177 The Staff will also track several other items listed in Appendix A, Section A. of the Safety Evaluation that Kairos must address in its operating license application.178 This list contains elements of design, analysis, and administration that are not necessary for issuance of a construction permit but need additional development or resolution before issuance of an operating license.

After reviewing the construction permit application, the ACRS recommended that Kairos address three topics in the operating license application: () combustible gas generation,

() tritium release levels, and () management of airborne tritium and beryllium in the facility.179 In response to the ACRS review, the Staff stated that it will consider the identified topics in its review of the operating license application.180 In response to our pre-hearing questions, Kairos stated that the specific instrumentation of the tritium management system and its capabilities to 176 Ex. NRC-, Staff Information Paper, at -; Ex. KRS-, Kairos Testimony, at.

177 Ex. NRC-, Staff Information Paper, at ; Ex. KRS-, Kairos Testimony, at -; see also Ex. NRC--R, Draft Construction Permit, at.

178 See Ex. KRS-, Kairos Testimony, at.

179 Ex. NRC-, Staff Safety Panel Presentation, at, ; Tr. at (Mr. Chereskin).

180 See Letter from Robert Taylor on behalf of Andrea D. Veil, NRR, to Joy L. Rempe, ACRS (June, ) (MLA).

measure tritium, for comparison with limits derived from the MHA, will be discussed in further detail in the final safety analysis report.181 D.

The Staffs Environmental Review As required by our regulations, the Staff prepared an environmental impact statement (EIS) for the Hermes construction permit application.182 Although the Staffs safety review was limited to the findings necessary for issuance of the construction permit, the Staffs environmental review was broader in scope. In addition to evaluating the environmental impacts of facility construction, the Staff evaluated the impacts of facility operation and decommissioning to the extent that information was available for these activities.183 In its review of the Hermes project, the Staff made effective use of existing resources, such as the recently completed EIS for the Tennessee Valley Authoritys early site permit application for the Clinch River small modular reactor project, which would be situated approximately two miles south of where the Hermes reactor would be constructed.184 The Staff issued the draft EIS (DEIS) in September and the FEIS in August

.185 After publishing a notice of its intent to prepare an EIS, the Staff conducted a virtual joint public outreach and scoping meeting in March.186 The Staff received public comments 181 Ex. KRS-, Kairos Pre-Hearing Responses, at -; Ex. NRC-, Staff Pre-Hearing Responses, at -.

182 See C.F.R. §.(b)() (requiring EIS for issuance of a permit to construct a nuclear testing facility); Ex. NRC-, FEIS, at xiii, -.

183 Ex. NRC-, FEIS, at -, -. The Staff would perform separate environmental reviews for any subsequent licensing actions, such as an operating license application, operating license renewal, and decommissioning.

184 See id. at -.

185 Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor (Draft Report for Comment), NUREG- (MLA); Ex. NRC-, FEIS.

186 Ex. NRC-, FEIS, at -. The Staffs decision to conduct a virtual meeting was based on high Covid-transmission rates in the Oak Ridge area at that time. Id. at G-.

during a sixty-day scoping process in early. The Staff also conducted a virtual environmental audit in March to verify information in the Kairos environmental report and discuss information needs with Kairos staff and their contractors.187 The DEIS was issued for public comment, and the comments received were addressed by the Staff in the FEIS.188 As discussed above, the proposed site for the Hermes project is a -acre site in the Heritage Center Industrial Park of the East Tennessee Technology Park, located within the corporate limits of the City of Oak Ridge, Tennessee.189 The industrial park was established on land formerly owned by DOE, and the site proposed for the Hermes project was previously the site of two buildings that formed part of the Oak Ridge Gaseous Diffusion Plant. These buildings were razed after the gaseous diffusion plant ceased operations in the s, and the site was environmentally remediated and released for industrial reuse, subject to certain restrictions.190 Most of the -acre site consists of developed land and herbaceous grassland, with bands of forested land in perimeter areas between previously developed land and adjacent waterways.191 The site is bounded on the south and east by Poplar Creek, and the Clinch River arm of the Watts Bar Reservoir lies near the western border of the site boundary.192 The Hermes project would make use of existing industrial infrastructure, with the exception of additional roads and 187 Id. at -.

188 Id., app. G.

189 Id. at -.

190 Id. at -, G-to G-. These restrictions pertain to the use of and occupational exposure to contaminated groundwater and at the site. See id. at G-to G-.

191 Id. at -.

192 Id. at - fig. -, -. The only wetland on or adjacent to the Hermes site occurs in the forested perimeter lands adjoining Poplar Creek. Id. at - to -.

parking lots that would be constructed to service the -acre portion of the site on which the reactor and its auxiliary buildings would be situated.193 The Staff evaluated the environmental impacts of constructing, operating, and decommissioning the Hermes reactor across a variety of resource areas: land use and visual resources; air quality and noise; hydrogeology and water resources; ecological resources; historic and cultural resources; socioeconomics and environmental justice; human health; nonradiological waste management; uranium fuel cycle and radiological waste management; transportation; accidents; and climate change.194 The Staff also analyzed the cumulative environmental impacts of other projects proposed in the Oak Ridge region in conjunction with the Hermes project for each resource area considered.195 The Staff found that the direct and indirect impacts of the proposed action in each of these areas would be small.196 Impacts are considered small if they are not detectable or are so minor that they will neither destabilize nor noticeably alter any important attribute of the resource.197 In July, Kairos submitted a construction permit application for the Hermes project, a two-unit fluoride salt-cooled, high temperature test reactor that would be situated adjacent to the Hermes test reactor. We asked the Staff whether the analysis in the FEIS accounted for the cumulative impacts of the applicants new proposed project. The Staff 193 See id. at -.

194 Id. at - tbl. -.

195 Id. at -. These included continuing DOE operations at Oak Ridge National Laboratory and the Y-site; industrial development in the East Tennessee Technology Park; the Ultra Safe Nuclear Corporation Pilot Fuel Manufacturing Facility; the Sequoyah and Watts Bar nuclear plants; and future projects such as the construction and operation of small modular reactors at the Clinch River Nuclear site; the applicants plan to construct and operate the Kairos Atlas Fuel Fabrication Facility at the Hermes site; the planned TRISO-X fuel fabrication facility; and development of a general aviation airport to the south of the Hermes site. Id. at -.

196 Id. at - tbl. -.

197 Id. at -.

explained that the FEIS was published too soon after submission of the Hermes application to account for these impacts in the Hermes FEIS, but that an evaluation was performed to determine the significance of the Hermes project on the FEISs cumulative impacts analysis.198 The Staff concluded in this evaluation that the proposed Hermes project would not alter the conclusion in the FEIS that the cumulative impacts from the Hermes reactor and other past, present, and reasonably foreseeable actions would be SMALL for all environmental resources.199 Accordingly, the Staff determined that information in the Hermes application did not require preparation of a supplement to the Hermes FEIS.200 To fulfill its obligations under section of the Endangered Species Act of, the Staff compiled a table of federally listed endangered species using databases maintained by the U.S.

Fish and Wildlife Service (FWS) and the Tennessee Department of Environment and Conservation, and the information in Kaiross environmental report.201 The Staff defined the action area for the purposes of this review as the -acre Hermes site, which consists of lands previously disturbed by DOEs operations but also includes, for conservatism, slivers of riparian forested land on the site bordering Poplar Creek that might be affected by project-related 198 Ex. NRC-, Staff Pre-Hearing Responses, at -.

199 Memorandum from Christopher M. Regan, Director, Division of Rulemaking, Environmental, and Financial Support, NMSS, to John W. Lubinski, Director, NMSS, Consideration of New Information Regarding Potential Cumulative Impacts from the Proposed Kairos Hermes Test Reactor on the Kairos Hermes Construction Permit Review (Sept., ), Encl. at (MLA (package)).

200 Id.

201 Ex. NRC-, FEIS, at -, -. Section of the Endangered Species Act requires an agency, in consultation with the Secretary of the Interior or the Secretary of Commerce (as appropriate), to ensure that any action authorized, funded, or carried out by such an agency...

is not likely to jeopardize the continued existence of any endangered species or threatened species or result in the destruction or adverse modification of [critical] habitat of such species.

Endangered Species Act § (a)(), U.S.C. § (a)(). The Fish and Wildlife Service (under the Department of the Interior) and the National Marine Fisheries Service (under the Department of Commerce) jointly administer the Act.

noise.202 The Staff identified the potential for four federally listed engendered species, four federally listed threatened species, and one federal candidate species to occur at the site.203 At the request of the FWS, the Staff included in the FEIS a biological evaluation addressing the potential impacts from the Hermes project on these species.204 Because of historical disturbances to the affected site and the lack of disturbance to forest and other natural vegetation, wetlands, or aquatic habitat from construction activities, the Staff found that effects on terrestrial wildlife habitats would be minimal, and the potential ecological impacts of the proposed action would be small.205 The Staff determined that the Hermes project may affect, but is not likely to adversely affect (or would not affect), any of these endangered species.206 On January,, the FWS concurred with the Staffs conclusions in its biological evaluation, which completed the NRCs responsibilities under section of the Endangered Species Act.207 The Staff originally proposed to include a condition in the Environmental Protection Plan (EPP), which is incorporated into the construction permit, that Kairos must request a license amendment to incorporate the requirements of any Terms and Conditions set forth in the Incidental Take Statement of Biological Opinions issued subsequent to the effective date of this EPP.208 However, the Staff did not engage in formal consultation with FWS and, as a result, did 202 Ex. NRC-, FEIS, at -.

203 Id. at -. The endangered species are the gray bat, the Indiana bat, and two freshwater clam speciesthe finerayed pigtoe and shiny pigtoe. The threatened species are the northern long-eared bat, the spotfin chub, and two plant speciesthe Virginia spiraea and white fringeless orchid. The federal candidate species is the monarch butterfly. The Staff did not identify the presence of critical habitat within the action area. Id. at - to -.

204 Id. at -; see id. at - to - & tbl. -.

205 Id. at -.

206 Id. at -.

207 Id. at -.

208 See Ex. NRC--R, Draft Construction Permit, app. A, Environmental Protection Plan.

not receive from FWS a biological opinion containing an Incidental Take Statement with Terms and Conditions.209 In response to our pre-hearing question asking about the necessity of this condition, the Staff elected to remove this condition from the construction permit and noted that it will consider whether the condition should be added at the operating license stage.210 Section of the NHPA requires federal agencies to consider the effects of their undertakings on historic properties listed or eligible for listing on the National Register of Historic Places.211 The section process must be completed prior to the issuance of any license.212 The Staff considered the direct effects of the construction and operation of the Hermes facility on the -acre Hermes site, as well as the indirect effects of these activities on a.-mile area around the site.213 Relying on an environmental assessment prepared in by DOE for the East Tennessee Technology Park, the Staff initially concluded that there are likely no intact archaeological sites or prehistorical archaeological resources to be found within the APE due to extensive prior cut and fill excavation activities associated with construction of the former DOE facilities and their subsequent decontamination, demolition, and decommissioning.214 However, in response to a comment on the DEIS from a consulting tribe, the Staff gathered additional 209 See Ex. NRC-, Staff Pre-Hearing Responses, at.

210 Id.

211 Section of the NHPA requires federal agencies to consider the effects of their undertakings on historic properties listed or eligible for listing on the National Register of Historic Places. NHPA §, U.S.C. §. The NRCs undertaking is the issuance of a construction permit to Kairos that allows for the construction of the proposed Kairos Hermes project. Ex. NRC-, FEIS, at -.

212 C.F.R. §.(c).

213 Ex. NRC-, FEIS, at -. Together, these areas constitute the area of potential effects (APE) for the NRCs section review. See generally id. at - to -.

214 See DEIS at -, -. The Staff also reviewed information held by the Tennessee Historical Commission and determined that there are no extant architectural resources within the direct-effects APE. Id.

information from DOE related to the geology and geomorphology of the site, as well as the total area and depth of prior disturbance at the former DOE facility locations.215 Based on this new information and a discussion with DOE, the Staff determined that there is a potential for deeply buried archaeological deposits to occur within the APE.216 To satisfy its consultation responsibilities under the NHPA, the Staff contacted the Tennessee Historical Commission, the Advisory Council on Historic Preservation, the National Park Service, and eighteen federally recognized Indian tribes.217 The Tennessee Historical Commission advised that the Kairos project would not adversely affect the Manhattan Project National Historic Park, the only property located within the APE that is eligible for listing on the National Register of Historic Places.218 In December, after publication of the DEIS, one Tribe initiated government-to-government consultation, requested consulting party status, and requested that a cultural resources survey be conducted for the proposed project.219 The Staff met with Kairos several times between February and April to discuss information needs to support the Staffs consultations with the Tribe. In April, the Staff forwarded additional information Kairos provided to the consulting Tribe for review and comment. Between June and the publication of the FEIS in August, the Staff met with the Tribe and Kairos to discuss the Tribes request for an additional reconnaissance field investigation, updates to the 215 Ex. NRC-, FEIS, at -, see id. at G-to G-.

216 Id. at -.

217 Id. at -.

218 Id. at -, -. The Manhattan Project National Historical Park, which is jointly administered by DOE and the National Park Service, includes the K-History Center, which opened in and focuses on the men and women who built and operated the K-Gaseous Diffusion Plant during the Manhattan Project and Cold War. Id. at -; see National Park Service, K-History Center, https://www.nps.gov/places/k--history-center.htm (last visited Nov., ).

219 Ex. NRC-, FEIS, at -, G-to G-.

archaeological resource monitoring and unanticipated discovery plan, and a path forward to support NHPA section consultation closure.220 The Staffs section consultation efforts were still in progress when we held the hearing on Kaiross construction permit application. Prior to the hearing, we asked the Staff to clarify the purpose of the additional reconnaissance field investigation and the basis for the Staffs conclusions regarding impacts to historic and cultural resources from the Hermes project.221 At the hearing, the Staff informed us that Kairos had completed the requested field investigation, had used the resulting information to update its monitoring plan, and had incorporated the Staffs and Tribes input into the plan.222 After the hearing, the Staff provided notice of consultation closure in a revised draft record of decision.223 The draft record of decision explained that after Kairos submitted the updated monitoring plan and Geoarchaeological Reconnaissance Survey Report, the Staff sent the monitoring plan and Kaiross report to the Tennessee Historical Commission and the consulting Tribe.224 The Tennessee Historical Commission responded that it had no objections to the project proceeding as proposed. Likewise, the consulting Tribe stated that it had no objections to the project proceeding, provided the NRC agrees to notify the consulting Tribe of changes to project activities on the site and to any unanticipated discoveries.225 The Staff noted that these stipulations were previously discussed and agreed upon between the consulting 220 Id. at - to -; Ex. NRC-, Staff Information Paper, at, ; Ex. NRC-, Staff Pre-Hearing Responses, at.

221 See Pre-Hearing Questions Order at -.

222 See Tr. at (Mr. Regan); see also Ex. NRC--R, Draft Record of Decision, at (stating that the reconnaissance field investigation was completed in August ).

223 See Staff Revised Exhibit List at ; Ex. NRC--R, Draft Record of Decision, at.

224 Ex. NRC--R, Draft Record of Decision, at.

225 Id.

parties and that the NRCs process for implementing these stipulations had been documented in a memorandum to the NRCs Federal Preservation Officer.226 Because there are no known historic properties on the proposed Hermes site and mitigation measures will be in place to protect any undiscovered resources, the Staff determined under the NHPA that there would be no adverse effects to historic properties from the proposed undertaking.227 For the same reason, the Staff concluded for the purposes of NEPA that the potential environmental impacts on cultural and historic resources from constructing, operating, and decommissioning the Hermes project would be small.228 In its environmental review of the Hermes project, the Staff also analyzed alternatives to the proposed action.229 This review included consideration of the no-action alternative and one alternative site.230 For the no-action alternative, i.e., if the construction permit were to be denied, the Staff found that the environmental effects described in the FEIS would not occur, but because these effects were found to be small, any environmental benefit from selecting the no-action alternative would be minimal.231 Moreover, the proposed site would remain available for other government or private industrial development projects, which might lead to similar 226 Id. (citing Memorandum from Tamsen Dozier, NRC, to Christopher M. Regan, NRC, Implementation of Provisions from Consultations Under Section of the National Historic Preservation Act on the Kairos Hermes Test Reactor Construction Permit Review (Nov.,

) (MLA).

227 See id. at, ; Ex. NRC-, Staff Pre-Hearing Responses, at -; Ex. NRC-, FEIS, at - to -.

228 See Ex. NRC--R, Draft Record of Decision, at,, ; Ex. NRC-, Staff Pre-Hearing Responses, at -; Ex. NRC-, FEIS, at - to -.

229 Ex. NRC-, FEIS, ch..

230 Id. at -.

231 Id.

environmental effects as the proposed project.232 In addition, this alternative would not meet the purpose of the proposed actionto demonstrate key elements of the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor technology for possible future commercial deployment.233 After reviewing the applicants systematic site-selection process and finding it to have been reasonable, the Staff examined an alternative site on federal land approximately twenty miles west of Idaho Falls, Idaho, termed the Eagle Rock site.234 The Staff compared the environmental costs and benefits of the proposed action at the Eagle Rock site with the costs and benefits of the proposed action at the Oak Ridge site. The Staff found that the impacts at the Eagle Rock site would be small for all resource areas except for visual, ecological, and cultural resources, which would experience moderate impacts from construction, reflecting the Staffs determination that building the Hermes facilities at the Eagle Rock site could be visually intrusive in that rural setting and would require disturbance of soils supporting natural vegetation and potentially containing subsurface archaeological resources.235 With the Oak Ridge site presenting only small environmental impacts, as contrasted with the Eagle Rock site, the Staff concluded that the Oak Ridge site was the environmentally preferable alternative.236 On the basis of its environmental review, the Staff recommended issuing the construction permit to Kairos.237 At the operating license stage, the Staff will prepare a 232 Id.

233 Id. at -; see id. at -. For the same reason, Kairos and the Staff did not consider alternative technologies for the Hermes reactor. Id. at -.

234 Id. at -.

235 Id. at - to -, - & tbl. -.

236 Id. at - to -.

237 Id. at -. The Staff conditioned its recommendation on completion of the NHPA section process, which was not yet complete at the time the FEIS was issued. Id.

supplement to the FEIS to address any new and significant information that was not available during its review of the construction permit application.238 E.

Findings We have conducted an independent review of the sufficiency of the Staffs safety findings, with particular attention to the topics discussed above. Our findings, however, are based on the record as a whole.

Safety Findings Based on the evidence presented in the uncontested hearing, including the Staffs review documents and the testimony provided, we find that Kairos has described the proposed design of the facility, including, but not limited to, the principal architectural and engineering criteria for the design, and it has identified major features or components incorporated therein for the protection of the health and safety of the public.239 Further technical or design information as may be required to complete the safety analysis has reasonably been left for later consideration and will be supplied in the final safety analysis report. Kairos has described the safety features or components that require research and development and has identified and will establish a research and development program reasonably designed to resolve any safety questions associated with these features or components. On the basis of the foregoing, we find that there is reasonable assurance that open safety questions will be resolved satisfactorily at or before the latest date stated in the application for completion of construction of the proposed facility. Taking into consideration the site criteria in C.F.R. Part, the proposed facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.

238 See C.F.R. §.(b); Ex. NRC-, FEIS, at -; Tr. at (Mr. Doub) (stating that the Staff would supplement the EIS and update the analysis for later life cycle stages should the applicant apply for future licenses for Hermes).

239 See Ex. KRS-, Kairos Pre-Hearing Responses, at -.

In making these findings, we also conclude that: () there is reasonable assurance that construction of the facility will not endanger the health and safety of the public, and the authorized activities can be conducted in compliance with the NRCs regulations, including the requirements in C.F.R. Part ; () Kairos is technically and financially qualified to engage in the activities authorized;240 () issuance of the construction permit will not be inimical to the common defense and security or to the health and safety of the public; and () Kaiross application meets the standards and requirements of the AEA and the NRCs regulations.

Required notifications to other agencies have been duly made.241 Additionally, we find that the Staffs proposed permit conditions are appropriately drawn and sufficient to provide reasonable assurance of adequate protection of public health and safety.242 Environmental Findings We also conducted an independent review of the Staffs environmental analysis in the FEIS, taking into account the particular requirements of NEPA. NEPA section ()(A) requires agencies to use a systematic, interdisciplinary approach which will ensure the integrated use of the natural and social sciences and the environmental design arts in decision making that may impact the environment.243 We find that the environmental review team used the systematic, interdisciplinary approach that NEPA requires.244 The environmental review team consisted of 240 Ex. NRC-, Safety Evaluation, chs., ; Ex. NRC-, Staff Information Paper, at ;

Ex. KRS-, Kairos Testimony, at -.

241 See, e.g., C.F.R. §.(a); Ex. NRC-, Staff Pre-Hearing Responses, at ;

Ex. NRC-, FEIS, app. B.

242 See C.F.R. §§.(b),.; Ex. NRC--R, Draft Construction Permit, at -.

243 NEPA § 102(2)(A), 42 U.S.C. § 4332(2)(A), as amended.

244 See, e.g., Tr. at - (Mr. Erwin, Ms. Dozier, Mr. Doub) (providing an overview of the Staffs environmental review methodology and findings); Ex. NRC-, Staff Environmental Panel Presentation, at -.

over two dozen individuals with expertise in disciplines including ecology, geology, hydrology, human health, socioeconomics, and cultural resources.245 In addition to the general requirement that an EIS address the reasonably foreseeable environmental effects of a proposed action, NEPA section ()(C) requires federal agencies to describe () any reasonably foreseeable adverse environmental effects which cannot be avoided should the proposal be implemented; () a reasonable range of alternatives to the proposed agency action, including an analysis of any negative environmental impacts of not implementing the proposed agency action in the case of a no action alternative, that are technically and economically feasible, and meet the purpose and need of the proposal; () the relationship between local short-term uses and long-term productivity of the environment; and

() any irreversible and irretrievable commitments of federal resources associated with the proposed agency action.246 The Staffs evaluation of alternatives is in chapter of the FEIS and summarized in chapter ; the other enumerated items are discussed under the heading of resource commitments in chapter.

Because the Staff issued the FEIS shortly after Congress amended section ()(C),

we asked the Staff to provide additional information explaining how its environmental review satisfied these standards, as amended by the Fiscal Responsibility Act.247 The Staff stated that 245 See Ex. NRC-, FEIS, app. A tbl. A- (listing contributors from the NRC and Pacific Northwest National Laboratory).

246 NEPA § 102(2)(C)(i)-(v), 42 U.S.C. § 4332(2)(C)(i)-(v), as amended.

247 See Pre-Hearing Questions Order at 13, 15-16; Tr. at 150-51 (Commissioner Wright). As noted above, pursuant to 10 C.F.R. § 51.105(a), we must determine whether the requirements of NEPA Sections 102(2)(A), (C), and (E) have been met, and determine as a general matter whether the NEPA review conducted by the NRC Staff has been adequate. The amendments to NEPA which became effective upon enactment of the Fiscal Responsibility Act substantively affect the requirements in NEPA section 102(2)(C). For example, section 102(2)(C)(iii) has been amended to specify that the alternatives analysis must include a discussion of the negative impacts of not implementing the proposed action, and section 102(2)(C)(v) now requires an analysis of any irreversible and irretrievable commitment of federal resources, as opposed to the broader analysis of resources typically performed by the Staff to satisfy this requirement.

prior to issuing the FEIS, the Staff reviewed the Fiscal Responsibility Act and the amendments to NEPA, and found that the FEIS was consistent with the Staffs current understanding of these new requirements and that it had made all the findings necessary in the FEIS to support issuance of the construction permit.248 In response to our question, the Staff revised the record of decision to reflect this determination.249 In further questions to the Staff before and during the hearing, we asked the Staff to clarify whether the FEIS considered the irreversible and irretrievable commitment of exclusively federal resources involved in issuing a construction permit to Kairos, commensurate with the more specific analysis required by amended NEPA section ()(C)(v).250 The Staff explained that its comprehensive analysis of irreversible and irretrievable resources in the FEIS accounted for federal resources as well.251

a.

Resource Commitments Chapter of the FEIS includes a table of the unavoidable adverse environmental impacts anticipated from construction, operation, and decommissioning, along with actions to mitigate those impacts.252 As noted above, the Staff concluded that the impacts of the proposed action in all resource areas would be small, despite the potential unavoidable adverse impacts presented in this table. To address these unavoidable impacts, the Staff identified mitigation and control measures that Kairos could implement to lessen some of these potential adverse effects.253 Examples of such mitigation measures include instituting best management practices to control dust and manage stormwater runoff, developing an Archaeological Resources 248 Ex. NRC-, Staff Pre-Hearing Responses, at -; Tr. at (Mr. Regan).

249 Ex. NRC-, Staff Pre-Hearing Responses, at -.

250 See Pre-Hearing Questions Order at -; Tr. at - (Commissioner Wright).

251 See Ex. NRC-, Staff Pre-Hearing Responses, at ; Tr. at (Mr. Doub).

252 Ex. NRC-, FEIS, at - to - tbl. -.

253 Id. at -.

Monitoring and Unanticipated Discovery Plan to address unexpected discoveries of human remains and archaeological materials, and restoring temporarily disturbed lands with native plants or landscaping when no longer needed for construction or decommissioning activities.254 Concerning irreversible and irretrievable commitments of federal resources, the Staff found that construction of the Hermes facility would irretrievably commit capital, energy, labor, and material resources, some of which are expended by the NRC during its review of the Hermes application and would thus constitute federal resources.255 Although the Staff did not separately analyze federal resources in the FEIS, the Staff clarified that the FEIS analysis considered the totality of resources, including but not limited to federal resources, and therefore adequately addressed the requirements of the Fiscal Responsibility Act.256 With respect to other resources, the Staff concluded that construction of the Hermes facility would irretrievably consume energy, water, chemicals, fossil fuels, as well as construction materials, unless Kairos recycles them during decommissioning.257 Historic and cultural resources buried beneath the surface or in deeply buried paleosoils are nonrenewable and may be disturbed by construction, but impacts to any such resources would be mitigated by implementation of Kaiross Archaeological Resources Monitoring and Unanticipated Discovery Plan.258 During operations, uranium used in TRISO fuel pebbles would be irreversibly and irretrievably committed, and nonradiololgical irreversible impacts on occupational human health could occur but are expected to be comparable to potential hazards at any industrial construction site.259 254 Id. at - to - tbl. -.

255 Id. at -; Ex. NRC-, Staff Pre-Hearing Responses, at ; see also Tr. at (Mr. Regan).

256 Tr. at (Mr. Erwin, Mr. Doub).

257 Ex. NRC-, FEIS, at -.

258 Id.

259 Id. at - to -.

Finally, with respect to the relationship between local short-term uses and long-term productivity of the environment, the Staff found that the short-term uses of the environment construction, operation, and decommissioning of the Hermes facilitywould commit acres of previously used industrial land over the life of the project and up to acres of land during construction and decommissioning. Use of the entire -acre Hermes site would also be limited during operation due to its designation as the exclusion area.260 Further short-term uses of the environment would include consumption of small quantities of water supplied by municipal or commercial sources, small increases in demand for housing and services in the local community, an increase in the volume of traffic on local roads, and energy consumption.261 The Staff noted that management and disposal of wasteradioactive, hazardous, and nonhazardouswould consume space at treatment, storage, or disposal facilities, and the use of land to meet waste disposal needs would reduce the long-term productivity of the land, but Hermes would contribute only a minimal amount to these reductions.262 In addition, in the short term, the project would bring increased employment, expenditures, and tax revenues that would directly benefit local, regional, and State economies.263 As compared to the minimal impacts of the project over the short term, the Staff found substantial potential long-term benefits from the Hermes project, including demonstrating the commercial viability of its fluoride salt-cooled, high temperature reactor technology, generating data helpful in future commercial deployment of the technology, and helping the nation meet its climate change objectives with less reliance on more land-intensive energy generation processes.264 260 Id. at -.

261 Id. at -.

262 Id.

263 Id.

264 Id.

Having considered the unavoidable adverse environmental impacts and resource commitmentsthe environmental costs of the projectas well as the projects benefits as summarized above, we agree with the Staffs conclusion that the benefits of the project outweigh the costs.265

b.

Alternatives The alternatives analysis is the heart of the environmental impact statement.266 NEPA section ()(H), formerly section ()(E), calls for agencies to study, develop, and describe appropriate alternatives to recommended courses of action in any proposal which involves unresolved conflicts involving alternative uses of available resources.267 Further, section

()(C) requires consideration of a reasonable range of alternatives to the proposed agency action that are technically and economically feasible, and meet the purpose and need of the proposed action. Where the alternatives considered include taking no action on the proposal, the analysis must consider any negative environmental impacts of not implementing the proposed agency action.268 Based on the Staffs testimony at the hearing, as well as the discussion in the FEIS, we find that the environmental review identified an appropriate range of alternatives with respect to the no-action alternative and the alternative Eagle Rock site, and adequately described the environmental impacts of both alternatives. The Staffs decision not to consider alternative technologies was reasonable in light of the purpose and need of the proposed project, which is to demonstrate and test its reactor technologies.269 265 Cf. C.F.R. §.(a); see Ex. NRC-, FEIS, at -.

266 C.F.R. pt., subpt. A, app. A, §.

267 NEPA § 102(2)(H), 42 U.S.C. § 4332(2)(H). In its review of the potential impacts associated with the proposed action, the Staff did not identify any unresolved conflicts concerning alternative uses of available resources. Ex. NRC-, FEIS, at -.

268 NEPA § 102(2)(C)(iii), 42 U.S.C. § 4332(2)(C)(iii), as amended.

269 See Ex. NRC-, FEIS, at -, -.

We also find that the Staff adequately considered the negative impacts of not implementing the proposed action. For example, the Staff found that under the no-action alternative, Kairos could not build the proposed Hermes reactor, and therefore would not have an opportunity to test its technologies, design features, and safety functions at a reduced scale relative to a potential commercial power reactor. The Staff noted that forgoing the opportunity provided by Hermes may not necessarily preclude future development of reactors using the salt-cooled, fluoride high temperature reactor technologies but anticipated that it could slow or impede safe and efficient development of the technologies.270 The Staff also identified that any environmental benefits from implementing the proposed action would not be realized if the action is not approved, and additionally, the proposed site would remain available for other development projects, potentially giving rise to environmental impacts from land disturbance and construction from those projects in the future.271 In sum, we find reasonable the Staffs conclusion that, because there are no environmentally preferable alternatives that meet the purpose and need of the proposed action,

... there are no obviously superior alternatives to the proposed action from an environmental perspective.272

c.

Commission Determination For each of the topics discussed at the hearing and in todays decision, we find that the Staffs review was reasonably supported in logic and fact and sufficient to support the Staffs conclusions. Based on our review of the FEIS, we also find that the remainder of the FEIS was reasonably supported and sufficient to support the Staffs conclusions. Therefore, as a result of our review of the FEIS, and in accordance with the notice of hearing for this uncontested 270 Id. at -.

271 Id.; see also id. at G-.

272 Id. at -; see also id. at -.

proceeding, we find that the relevant requirements of NEPA section 102(2), and the applicable regulations in 10 C.F.R: Part 51, have been satisfied with respect to the construction permit application.273 We independently considered the final balance among conflicting factors contained in the record of this proceeding. We find, after weighing the environmental, economic, technical, and other benefits against environmental and other costs, and considering reasonable alternatives, that the construction permit should be issued.

JII.

CONCLUSION We find that, with respect to the safety and environmental issues before us, the Staff's review ofKairos's construction permit application was sufficient to support issuance of the construction permit. We authorize the 'Director of the Office of Nuclear Reactor Regulation to issue the permit for the construction of the Hermes Test Reactor. Additionally, we authorize the Staff to issue the record of decision.

IT IS SO ORDERED.

Dated at Rockville, Maryland, this 12th day of December 2023.

273 See supra note 26.

For the Commission

~a0 C. ll-vr..~

Tomas E. Herrera Acting Secretary of the Commission



   

      



 























    











 !"#$!%&# 



'()** 





















' +,(-.





 

 

 / 

0,-,1-*.-.34556776485954:;8<=5;8<4:<9:

>3?6@AB@CDEF0*F+G1HHI-.1**0,H-)-J. 

 GH .GH, ))-**-

- ))-**-11HH+KG+--

-H1L #%MN&&

*-. O"!!!#"""%

#)-HL)-H *GP.F

 GH .GH, ))-**-

-, ))-**-

-H1L #%MN&&

*-. O"!!!#"""%

#)-HL-.+P.F

 GH .GH, ))-**-

-H G*H

-H1# #%QQQ

*-. O"!!!#"""%

-*#0

F-+ 

G*/-*

R),G

-H-N,+

.-()1

N-IHH

#)-HL-.*0P.F

+F-+ P.F

  • G* F-*P.F

-H- 0,+P.F

K), IGP.F

..- )1P.F

0- IHHP.F

G*H-*I 

.I-*SN-G* 

%%%%*,HF-F

*-. O"""Q

,-.,

HJH*,

#)-HL, H-.,P).HI-* )



HJ 1H*,P).HI-* )







TTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTT

-, ))-**-

+ F-HH ,H+

-*%O+,)0O"O&

UVWXWZ[\\]VW

^_`_aWVVbc_`defgbUVWXWZ[

\\]VW

^Waehijik[li[liljhlmhlj

njmo jjo