| title = Response to Oig'S Special Inquiry Into the Nrc'S Oversight of the Auxiliary Feedwater System at Diablo Canyon (OIG Case No. 20-025)
| title = Response to OIGs Special Inquiry Into the NRCs Oversight of the Auxiliary Feedwater System at Diablo Canyon (OIG Case No. 20-025)
| release date = 05/03/2022
| release date = 05/03/2022
| package contents = {{Adams package content
| package contents = {{Adams package content
| number = ML22109A179
| number = ML22109A179
| issue date = 05/03/2022
| issue date = 05/03/2022
| title = Response OIG Special Inquiry Into Nrc'S Oversight AFW at Diablo Canyon (OIG Case No. 20-025)
| title = Response OIG Special Inquiry Into NRCs Oversight AFW at Diablo Canyon (OIG Case No. 20-025)
| author name = Dorman D
| author name = Dorman D
| author affiliation = NRC/EDO
| author affiliation = NRC/EDO
Line 20: Line 20:
| number = ML22108A167
| number = ML22108A167
| issue date = 05/03/2022
| issue date = 05/03/2022
| title = Staff Assessment of OIG Event Inquiry Into the Nrc'S Oversight AFW at Diablo Canyon (OIG Case No. 20-025)
| title = Staff Assessment of OIG Event Inquiry Into the NRCs Oversight AFW at Diablo Canyon (OIG Case No. 20-025)
| author name = Veil A
| author name = Veil A
| author affiliation = NRC/NRR
| author affiliation = NRC/NRR

Latest revision as of 04:20, 20 September 2024

Response to OIGs Special Inquiry Into the NRCs Oversight of the Auxiliary Feedwater System at Diablo Canyon (OIG Case No.20-025)
Date released: 05/03/2022 Download: ML22123A188


Response OIG Special Inquiry Into NRCs Oversight AFW at Diablo Canyon (OIG Case No.20-025)
ML22109A179
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/03/2022
From: Dan Dorman
NRC/EDO
To: Feitel R J
NRC/OGC
Zachary Hollcraft NRR/DRO/IRIB 415-0504
References
Download: ML22109A179 (3)
Staff Assessment of OIG Event Inquiry Into the NRCs Oversight AFW at Diablo Canyon (OIG Case No.20-025)
ML22108A167
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/03/2022
From: Andrea Veil
Office of Nuclear Reactor Regulation
To: Dorman D H
NRC/EDO
Zachary Hollcraft NRR/DRO/IRIB 415-0504
References
Download: ML22108A167 (2)
Enclosure 1 - Assessment Event Inquiry Into the Nuclear Regulatory Commission Oversight of the Auxiliary Feedwater System at Diablo Canyon Nuclear
ML22108A166
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/03/2022
From:
Office of Nuclear Reactor Regulation
To:
Zachary Hollcraft NRR/DRO/IRIB 415-0504
References
Download: ML22108A166 (10)
Enclosure 2 - Timeline of Event
ML22108A165
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/03/2022
From:
Office of Nuclear Reactor Regulation
To:
Zachary Hollcraft NRR/DRO/IRIB 415-0504
References
Download: ML22108A165 (2)