{{#Wiki_filter:Post Office Box 2000, Decatur, Alabama 35609-2000 March 23, 2021 10 CFR 21.21(a)(2) 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296
 
==Subject:==
Interim Report of a Deviation or Failure to Comply In accordance with Title 10 of the Code of Federal Regulations 21.21(a)(2), the Tennessee Valley Authority is submitting this interim report for Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. On January 22, 2021, a safety-related time-delay relay procured from Nutherm International, part number ETR14D3DNM015, was found to be unable to change state during a calibration bench test prior to its installation. BFN is submitting this Interim Report since this condition was entered into the BFN Corrective Action Program, but the evaluation of this condition is not expected to be complete within 60 days.
Nutherm International has agreed to take responsibility for the failure analysis and any further Part 21 reporting required by the results of their findings. Nutherm International has not determined the completion date for their failure analysis. This condition is being tracked in the BFN Corrective Action Program as Condition Report 1676419. The relay was returned to Nutherm International under Return Authorization Number 102962.
There are no new regulatory commitments contained within this letter. If you have any questions, please contact J. L. Paul at (256) 729-2636.
Respectfully, Respectf  tffully, Matthew Rasmussen Site Vice President
 
U.S. Nuclear Regulatory Commission Page 2 March 23, 2021 cc:
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant}}

Latest revision as of 18:05, 19 January 2022

Interim Report of a Deviation or Failure to Comply
ML21082A116
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 03/23/2021
From: Rasmussen M
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML21082A116 (2)


Text

Post Office Box 2000, Decatur, Alabama 35609-2000 March 23, 2021 10 CFR 21.21(a)(2) 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296

Subject:

Interim Report of a Deviation or Failure to Comply In accordance with Title 10 of the Code of Federal Regulations 21.21(a)(2), the Tennessee Valley Authority is submitting this interim report for Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. On January 22, 2021, a safety-related time-delay relay procured from Nutherm International, part number ETR14D3DNM015, was found to be unable to change state during a calibration bench test prior to its installation. BFN is submitting this Interim Report since this condition was entered into the BFN Corrective Action Program, but the evaluation of this condition is not expected to be complete within 60 days.

Nutherm International has agreed to take responsibility for the failure analysis and any further Part 21 reporting required by the results of their findings. Nutherm International has not determined the completion date for their failure analysis. This condition is being tracked in the BFN Corrective Action Program as Condition Report 1676419. The relay was returned to Nutherm International under Return Authorization Number 102962.

There are no new regulatory commitments contained within this letter. If you have any questions, please contact J. L. Paul at (256) 729-2636.

Respectfully, Respectf tffully, Matthew Rasmussen Site Vice President

U.S. Nuclear Regulatory Commission Page 2 March 23, 2021 cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant