ML20155A291: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot insert
 
StriderTol Bot change
Line 1: Line 1:
#REDIRECT [[IR 05000333/1988010]]
{{Adams
| number = ML20155A291
| issue date = 09/27/1988
| title = Ack Receipt of 880831 Ltr Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-333/88-10
| author name = Bellamy R
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
| addressee name = Converse R
| addressee affiliation = POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
| docket = 05000333
| license number =
| contact person =
| document report number = NUDOCS 8810050271
| document type = CORRESPONDENCE-LETTERS, NRC TO UTILITY, OUTGOING CORRESPONDENCE
| page count = 2
}}
See also: [[see also::IR 05000333/1988010]]
 
=Text=
{{#Wiki_filter:_ _ _ - _ _ .
        ___
t    e
            .-
  ,,
                                                                                  SEP 2 7 gggy
                          &
              Docket No. 50-333
              Power Authority of the State of New York
              James A. FitzPatrick Nuclear Power Plant
              ATTN: Mr. Radford J. Converse
                        Resident Manager
              P. O. Box 41
              Lycoming, New York 13093
              Gentlemen:
              Subject:      Inspection No. 50-333/88-10
              This refers to your letter dated August 31, 1988, in response to our letter
              dated August 8, 1988.
              Thank you for informing us of the corrective and preventive actions documented
              in your letter. These actions will be examined during a future inspection of
              your licensed program.
              Your cooperation with us is appreciated.
                                                              Sincerely,
                                                                Cridnot signed By:
                                                                Rcnald R. Scitamy
                                                              Ronald R. Bellamy, Chief
                                                              Facilities Radiological Safety
                                                                and Safeguards Branch
                                                              Division of Radiation Safety
                                                                and Safeguards
              cc w/ encl:
              J. Phillip Bayne, President
              Mr. Jol.n C. Brons, Executive Vice President
    "
              A. Klause nn, Senior Vice President - Appraisal and Compliance Services
              R. L. Patch, Quality Assurance Superintendent
              George M. Wilverding, Manager Nuclear Safety Evaluation
n            Gerald C. Goldstein, Assistant General Counsel
gg            R. E. Beedle, Vice President Nuclear Support
Non.          S. S. Zulla. Vice President Nuclear Engineering
go            R. Burns, Vice President Nuclear Operation
gh            Dept. of Public Service, State of New York
              State of New York, Department of Law
4              Licensing Project Manager, NRR
No            Public Document Room (POR)                                                f "*    p
$@
g
              Local Public Document Room (LPOR)
              Nuclear Safety Information Center (NSIC)
                                                                                          7f*
                                                                                        C h.
- ce          NRC Resident Inspector                                                              b3J  J
$$c          State of New York
                                                                                                    \\
                                            OFFICIAL RECORD COPY          RL NYPA 88-10 - 0001.0.0
                                                                          09/23/88
                                                          _ .
                                                                                            -
 
                          . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
..  o
      *
  .
        Power Authority of the                                                  2              SEP 2 7 ;ggg
            State of New York
        bec w/ encl:
        Region I Docket Room (with concurrences)
        Management Assistant, DRMA (w/o encl)
        Section Chief, DRP
        Robert J. Bores, DRSS
        B, Clayton, EDO
                d                                                          OMS
        RI.DRSS          RI:DRSYM                                      RI:DRSS
        Davidson        O sciak                                        Bellamy
        9/s.//88        9h 3/88                                        9/W/88
                                                                  0FFICIAL RECORD COPY RL NYPA 88-10 - 0002,0.0
                                                                                        09/23/88
                        -                                                                                        J
 
  --
    b      *
                        James A. Fit: Patrick
              **
      ,
        *
                        Nuclear Power Plant
                        P O. Bcx 41
    !                  Lycommg. New Yom 13093
                        315 342 3840
                          *
                                                  .
              #> NewWrkPower
              4# Authority
                AUGUST 31, 1988
                JAFP 88- 0824
                UNITED STATES NUCLEAR REGULATORY COMMISSION
                Mail Station Pl-137
                Washington, D.C.
                Attention: Document Control Desk
                SUBJECT:        James A. FitzPatrick Nuclear Power Plant
                                  Docket No. 50-333
                                  Inspection No. 88-10 - Radioactive Effluents Control Program
                Dear Sirst
                In accordance with 10CFR2.201, the Authority is submitting its response to
                Appendix A, Notice of Violation. This Notice was transmitted to the Authority
                August 8, 1988. The inspection was conducted by B. S. Davidson of Region I
                office on June 6-10, 1988 at the FitzPatrick Nuclear Power Plant.
                                                    Notice of biolation
                As a result of the inspection conducted on June 6-10, 1988 and in accordance
                with the "General Statement of Policy and Procedure for NRC Enforcement
                Actions," 10 CFR Part 2, Appendix C (Enforcement ?olicy) (1988), the following
                violation was identified:
                      Technical Specification 6.5.2.8 of Appendix A to Facility Operating License
                      No. DPR-59, Technical Spacifications, requires audits of the conformance of
                      the facility operation to provisions contained within the Technical
                      Specifications (TS) and applicable license < .inditions at least once per 12
                      months; and audits of the Radiological Ervironmental Monitoring Program
                      (REMP) and results at least once per l' months.
                      Contrary to the above requirements, sn audit of the liquid and caseous
                      radioactive effluent portions of the TS and the REMP was not p,rformed
                      within the 12 month interval as required. The last stioit of the radioac-
                      tive effluents petion of the TS and the RD:P was conducted in November,
                      1986.
                      This is a Severity Level V Violation (Supplement 1) .
.
!
          O f % O l '1 e l ) {              fl i)
l
          ov ii/vi            -
                                              i ;- *
[
 
  *
t...    ..'.
        . - .
    ,,,
4
              United States Nuclear Requiatory Commission                          August 31, 1988
              Attention: Document Control Desk                                    JAFP 88- 0824
              SUBJB7F      INSPECTION'NO. 88-10                                  Page 2 of 2
                                                                                                      1
                                                                                                      1
                                          Response to Notice of Violation A
              The Authority agrees with the finding specified in the violation.                      l
              CAUSE - The Site Quality Assurance Organization has historically received tech-
              nical support f rom the Corporate Appraisal and Compliance Services Department's
              Operational Appraisal Group. This group was in the process of performing the
              required Technical Specification Radiological and Environmental audits when they
              were 41= banded as 4 result of a corporate reorganization. The Site QA
              Organization then requested, through the Director of Quality Assurance, that the
              Safety Review Committee (SRC) provide the necessary technical stipport for the
              Site Quality Assurance Department to perform these audits. Communications bet-
              ween the Chairman of the SRC and the Site QA Superintendent with regard to the
              scope of these audits and specific manpower needs further delayed the audit per-
              formance and resulted in this Technical Specification violation.
              CORRECTIVE ACTIONS -
              1)    Immediate - The Site Qualilty Assurance Organization has contracted for the
                    necessary technical assistance and is in the process of performing the
                    liquid and gaseous portions of the Technical Specifications and REMP
                    audits.    It is expected that these audits will be completed by September
                    30, 1988.
              2)    The Site Quality Assurance Superintendent has been counseled on the impor-
                    tance of meeting the Technical Specification Audit commitments and the need
                    to escalate manpower requests to whatever appropriate levels of management
                    may be necessary to resolve any potential schedule delays.
              LONG TERM CORRECTIVE ACTION - Funding has been established in the Quality
              Assurance Department's annual budget for the purpose of ensuring that any
              necessary technical expertise needed te support the variouc Technical
              Specification Audit commitments is provided.
                              /
                            $Wl%W
              RADPORD CONVERSE
              RESIDENT MANAGER
              RJC RLPacep
              cc    Sr. Resident Inspector                Records Center - WPO
                    Director of Licensing                  D. C. C.
                    Superintendent of Power
                    G. Wilverding                          R. bellamy
                    F. Pesce                              Nuclear Regulatory Commission
                    A. Klausmann                          Region 1
                    E. Mulcahey                            475 Allendale Road
                                                            King of Prussia. PA 19406
                                                                                                    ]
}}

Revision as of 14:05, 2 January 2021

Ack Receipt of 880831 Ltr Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-333/88-10
ML20155A291
Person / Time
Site: FitzPatrick 
Issue date: 09/27/1988
From: Ronald Bellamy
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Radford Converse
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
References
NUDOCS 8810050271
Download: ML20155A291 (2)


See also: IR 05000333/1988010

Text

_ _ _ - _ _ .

___

t e

.-

,,

SEP 2 7 gggy

&

Docket No. 50-333

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN: Mr. Radford J. Converse

Resident Manager

P. O. Box 41

Lycoming, New York 13093

Gentlemen:

Subject: Inspection No. 50-333/88-10

This refers to your letter dated August 31, 1988, in response to our letter

dated August 8, 1988.

Thank you for informing us of the corrective and preventive actions documented

in your letter. These actions will be examined during a future inspection of

your licensed program.

Your cooperation with us is appreciated.

Sincerely,

Cridnot signed By:

Rcnald R. Scitamy

Ronald R. Bellamy, Chief

Facilities Radiological Safety

and Safeguards Branch

Division of Radiation Safety

and Safeguards

cc w/ encl:

J. Phillip Bayne, President

Mr. Jol.n C. Brons, Executive Vice President

"

A. Klause nn, Senior Vice President - Appraisal and Compliance Services

R. L. Patch, Quality Assurance Superintendent

George M. Wilverding, Manager Nuclear Safety Evaluation

n Gerald C. Goldstein, Assistant General Counsel

gg R. E. Beedle, Vice President Nuclear Support

Non. S. S. Zulla. Vice President Nuclear Engineering

go R. Burns, Vice President Nuclear Operation

gh Dept. of Public Service, State of New York

State of New York, Department of Law

4 Licensing Project Manager, NRR

No Public Document Room (POR) f "* p

$@

g

Local Public Document Room (LPOR)

Nuclear Safety Information Center (NSIC)

7f*

C h.

- ce NRC Resident Inspector b3J J

$$c State of New York

\\

OFFICIAL RECORD COPY RL NYPA 88-10 - 0001.0.0

09/23/88

_ .

-

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.. o

.

Power Authority of the 2 SEP 2 7 ;ggg

State of New York

bec w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

Section Chief, DRP

Robert J. Bores, DRSS

B, Clayton, EDO

d OMS

RI.DRSS RI:DRSYM RI:DRSS

Davidson O sciak Bellamy

9/s.//88 9h 3/88 9/W/88

0FFICIAL RECORD COPY RL NYPA 88-10 - 0002,0.0

09/23/88

- J

--

b *

James A. Fit: Patrick

,

Nuclear Power Plant

P O. Bcx 41

! Lycommg. New Yom 13093

315 342 3840

.

  1. > NewWrkPower

4# Authority

AUGUST 31, 1988

JAFP 88- 0824

UNITED STATES NUCLEAR REGULATORY COMMISSION

Mail Station Pl-137

Washington, D.C.

Attention: Document Control Desk

SUBJECT: James A. FitzPatrick Nuclear Power Plant

Docket No. 50-333

Inspection No. 88-10 - Radioactive Effluents Control Program

Dear Sirst

In accordance with 10CFR2.201, the Authority is submitting its response to

Appendix A, Notice of Violation. This Notice was transmitted to the Authority

August 8, 1988. The inspection was conducted by B. S. Davidson of Region I

office on June 6-10, 1988 at the FitzPatrick Nuclear Power Plant.

Notice of biolation

As a result of the inspection conducted on June 6-10, 1988 and in accordance

with the "General Statement of Policy and Procedure for NRC Enforcement

Actions," 10 CFR Part 2, Appendix C (Enforcement ?olicy) (1988), the following

violation was identified:

Technical Specification 6.5.2.8 of Appendix A to Facility Operating License

No. DPR-59, Technical Spacifications, requires audits of the conformance of

the facility operation to provisions contained within the Technical

Specifications (TS) and applicable license < .inditions at least once per 12

months; and audits of the Radiological Ervironmental Monitoring Program

(REMP) and results at least once per l' months.

Contrary to the above requirements, sn audit of the liquid and caseous

radioactive effluent portions of the TS and the REMP was not p,rformed

within the 12 month interval as required. The last stioit of the radioac-

tive effluents petion of the TS and the RD:P was conducted in November,

1986.

This is a Severity Level V Violation (Supplement 1) .

.

!

O f % O l '1 e l ) { fl i)

l

ov ii/vi -

i ;- *

[

t... ..'.

. - .

,,,

4

United States Nuclear Requiatory Commission August 31, 1988

Attention: Document Control Desk JAFP 88- 0824

SUBJB7F INSPECTION'NO. 88-10 Page 2 of 2

1

1

Response to Notice of Violation A

The Authority agrees with the finding specified in the violation. l

CAUSE - The Site Quality Assurance Organization has historically received tech-

nical support f rom the Corporate Appraisal and Compliance Services Department's

Operational Appraisal Group. This group was in the process of performing the

required Technical Specification Radiological and Environmental audits when they

were 41= banded as 4 result of a corporate reorganization. The Site QA

Organization then requested, through the Director of Quality Assurance, that the

Safety Review Committee (SRC) provide the necessary technical stipport for the

Site Quality Assurance Department to perform these audits. Communications bet-

ween the Chairman of the SRC and the Site QA Superintendent with regard to the

scope of these audits and specific manpower needs further delayed the audit per-

formance and resulted in this Technical Specification violation.

CORRECTIVE ACTIONS -

1) Immediate - The Site Qualilty Assurance Organization has contracted for the

necessary technical assistance and is in the process of performing the

liquid and gaseous portions of the Technical Specifications and REMP

audits. It is expected that these audits will be completed by September

30, 1988.

2) The Site Quality Assurance Superintendent has been counseled on the impor-

tance of meeting the Technical Specification Audit commitments and the need

to escalate manpower requests to whatever appropriate levels of management

may be necessary to resolve any potential schedule delays.

LONG TERM CORRECTIVE ACTION - Funding has been established in the Quality

Assurance Department's annual budget for the purpose of ensuring that any

necessary technical expertise needed te support the variouc Technical

Specification Audit commitments is provided.

/

$Wl%W

RADPORD CONVERSE

RESIDENT MANAGER

RJC RLPacep

cc Sr. Resident Inspector Records Center - WPO

Director of Licensing D. C. C.

Superintendent of Power

G. Wilverding R. bellamy

F. Pesce Nuclear Regulatory Commission

A. Klausmann Region 1

E. Mulcahey 475 Allendale Road

King of Prussia. PA 19406

]