ML12109A071: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 2: Line 2:
| number = ML12109A071
| number = ML12109A071
| issue date = 04/16/2012
| issue date = 04/16/2012
| title = 2012/04/16 - Diablo Canyon - April 2012 Hearing File Update
| title = Diablo Canyon - April 2012 Hearing File Update
| author name = Subin L
| author name = Subin L
| author affiliation = NRC/OGC
| author affiliation = NRC/OGC

Latest revision as of 21:21, 5 December 2019

Diablo Canyon - April 2012 Hearing File Update
ML12109A071
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/16/2012
From: Subin L
NRC/OGC
To: Curran D, Repka D, Sisco C, Tanya Smith, Zamek J
Atomic Safety and Licensing Board Panel, Harmon, Curran, Harmon, Curran, Spielberg & Eisenberg, LLP, San Luis Obispo Mothers for Peace, Winston & Strawn, LLP
Subin L
References
50-275-LR, 50-323-LR
Download: ML12109A071 (3)


Text

April 16, 2012 David A. Repka, Esq. Diane Curran, Esq.

Tyson Smith, Esq. Harmon, Curran, Spielberg, and Eisenberg Carlos Sisco 1726 M Street NW Winston & Strawn LLP Washington, DC 20036 101 California Street Suite 600 San Francisco, CA 94111-5802 E-mail: dcurran@harmoncurran.com E-mail: drepka@winston.com trsmith@winston.com CSisco@winston.com Jill ZamEk, Esq.

San Luis Obispo Mothers for Peace 1123 Flora Road Arroyo Grande, CA 93420 E-mail: jzk@charter.net In the Matter of Pacific Gas and Electric Company (Diablo Canyon Nuclear Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR

Dear Parties:

Pursuant to the Licensing Board's Memorandum and Order dated September 15, 2010, the Staff will monthly provide the parties an index identifying the hearing file and mandatory disclosures in accordance with 10 C.F.R. §§ 2.1203 and 2.336. For purposes of producing the mandatory disclosures and hearing file, and considering any document as privileged or protected, the Staff treated documents created by agents and contractors of the NRC the same as if those documents were created by the Staff. Accordingly, the Staff did not produce any documents to be disclosed since the last mandatory disclosure and therefore there is no index.

Attached is the Affidavit of Elaine M. Keegan, as required by 10 C.F.R. § 2.336(c).

Respectfully submitted,

/signed (electronically) by/

Lloyd B. Subin Counsel for the NRC Staff : Affidavit of Elaine M. Keegan

In the Matter of PACIFIC GAS & ELECTRIC COMPANY (Diablo Canyon Nuclear Power Plant, Units 1 and 2)

Docket Nos. SO-27S-LR and SO-323-LR NRC Staff Transmittal Letter dated April 16, 2012 Attachment 1 Affidavit of Elaine M. Keegan

April 16, 2012 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

PACIFIC GAS & ELECTRIC COMPANY ) Docket Nos. SO-27S-LRI SO-323-LR

)

(Diablo Canyon Nuclear Power Plant )

Units 1 and 2)

AFFIDAVIT OF ELAINE KEEGAN CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(b)

I, Elaine M. Keegan, do hereby state as follows:

1. I am employed as a Project Manager in the Division of License Renewal in the U.S. Nuclear Regulatory Commission's ("NRC") Office of Nuclear Reactor Regulation. I serve as a project manager for the Diablo Canyon Nuclear Power Plant, Units 1 and 2 license renewal application ("LRA"). Among other things, I am managing the preparation of the hearing file and mandatory disclosures in connection with the LRA at issue in this proceeding.
2. I hereby certify that all relevant materials related to the issues in connection with the LRA that are required to be disclosed pursuant to 10 C.F.R. § 2.336 (b) and (c) in the captioned proceeding have been disclosed, and that the disclosures are accurate and complete for documents identified by the Staff as of April 16, 2012.
3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information and belief.

Executed in Rockville, Maryland this 16th day of April, 2012