{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 16, 2012 | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 16, 2012 CAL No. 3-10-001 Mr. Barry Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760 | ||
CAL No. 3-10-001 | |||
Mr. Barry Allen Site Vice President | |||
FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 | |||
5501 North State Route 2 | |||
Oak Harbor, OH 43449-9760 | |||
==SUBJECT:== | ==SUBJECT:== | ||
COMPLETION OF COMMITMENTS OF CONFIRMATORY ACTION LETTER NO. 3-10-001 | COMPLETION OF COMMITMENTS OF CONFIRMATORY ACTION LETTER NO. 3-10-001 | ||
==Dear Mr. Allen:== | ==Dear Mr. Allen:== | ||
This letter is in response to your November 7, 2011, letter informing the U.S. Nuclear Regulatory Commission (NRC) that | This letter is in response to your November 7, 2011, letter informing the U.S. Nuclear Regulatory Commission (NRC) that FirstEnergy Nuclear Operating Company (FENOC) had completed all actions required by the June 23, 2010, Confirmatory Action Letter (CAL) issued to the Davis-Besse Nuclear Power Station. The CAL (ML101740519) confirmed the following commitments by FENOC to the NRC: | ||
: 1. Provide to the NRC, in writing, the results of the Reinspection Years calculation for Operating Cycle 17 performed in accordance with American Society of Mechanical Engineers (ASME) Code Case N-729-1 based on calculated RPV Head temperatures. | : 1. Provide to the NRC, in writing, the results of the Reinspection Years calculation for Operating Cycle 17 performed in accordance with American Society of Mechanical Engineers (ASME) Code Case N-729-1 based on calculated RPV Head temperatures. | ||
Due prior to plant restart (Mode 2). | Due prior to plant restart (Mode 2). | ||
: 2. Upon completion of destructive examination of the control rod drive mechanism nozzle ring samples removed from nozzles #4 and #10, quarantine one untested minimum full-length 90 degree sample and turn over ownership to the NRC. Quarantine the sample immediately until arrangements can be made to transport the sample to an independent laboratory selected by the NRC. | : 2. Upon completion of destructive examination of the control rod drive mechanism nozzle ring samples removed from nozzles #4 and #10, quarantine one untested minimum full-length 90 degree sample and turn over ownership to the NRC. Quarantine the sample immediately until arrangements can be made to transport the sample to an independent laboratory selected by the NRC. | ||
: 3. Beginning with reactor startup (Mode 2) and until reactor pressure vessel (RPV) head replacement, upon reaching Action Level 3 of EN-DP-01171, "Engineering Implementation of the reactor coolant system (RCS) Integrated Leakage Program," the plant shall be shut down in 30 days if RPV Head leakage cannot be ruled out. During subsequent shutdown as part of the containment inspection for RCS leakage, if RPV Head leakage cannot be ruled out, a bare metal visual examination of the RPV head will be performed per applicable ASME Code Case and 10 CFR 50.55a(g)(6)(ii)(D). | : 3. Beginning with reactor startup (Mode 2) and until reactor pressure vessel (RPV) head replacement, upon reaching Action Level 3 of EN-DP-01171, "Engineering Implementation of the reactor coolant system (RCS) Integrated Leakage Program," the plant shall be shut down in 30 days if RPV Head leakage cannot be ruled out. During subsequent shutdown as part of the containment inspection for RCS leakage, if RPV Head leakage cannot be ruled out, a bare metal visual examination of the RPV head will be performed per applicable ASME Code Case and 10 CFR 50.55a(g)(6)(ii)(D). | ||
: 4. The licensee has voluntarily elected to shut down the unit no later than October 1, 2011, and replace the RPV head. | : 4. The licensee has voluntarily elected to shut down the unit no later than October 1, 2011, and replace the RPV head. | ||
On July 7, 2010, the NRC issued a letter (ML101880308) that closed Commitment No. 1 of CAL 3-10-001. Commitments No. 2 through 4 were assessed in Section 4OA5.4 of Inspection Report 05000346/2011004 (ML112991544). Based on our review of the CAL commitments and the results of our inspections, we consider Commitments No. 2 through 4 of the CAL to be closed and, therefore, conclude that FENOC has met all of the commitments contained in the June 23, 2010, CAL issued to Davis-Besse Nuclear Power Station. | B. Allen On July 7, 2010, the NRC issued a letter (ML101880308) that closed Commitment No. 1 of CAL 3-10-001. Commitments No. 2 through 4 were assessed in Section 4OA5.4 of Inspection Report 05000346/2011004 (ML112991544). Based on our review of the CAL commitments and the results of our inspections, we consider Commitments No. 2 through 4 of the CAL to be closed and, therefore, conclude that FENOC has met all of the commitments contained in the June 23, 2010, CAL issued to Davis-Besse Nuclear Power Station. | ||
In accordance with 10 CFR 2.390 of the | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), | ||
accessible from the NRC Web Site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ | |||
Cynthia D. Pederson Acting Regional Administrator Docket No. 50-346 License No. NPF-3 cc: Distribution via ListServ | |||
available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of | B. Allen On July 7, 2010, the NRC issued a letter (ML101880308) that closed Commitment No. 1 of CAL 3-10-001. Commitments No. 2 through 4 were assessed in Section 4OA5.4 of Inspection Report 05000346/2011004 (ML112991544). Based on our review of the CAL commitments and the results of our inspections, we consider Commitments No. 2 through 4 of the CAL to be closed and, therefore, conclude that FENOC has met all of the commitments contained in the June 23, 2010, CAL issued to Davis-Besse Nuclear Power Station. | ||
Sincerely, | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), | ||
accessible from the NRC Web Site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Cynthia D. Pederson | Sincerely, | ||
/RA/ | |||
Cynthia D. Pederson Acting Regional Administrator Docket No. 50-346 License No. NPF-3 cc: Distribution via ListServ DOCUMENT NAME: Davis-Besse CAL 3-10-001 Closure Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME PSmagacz:dtp JCameron DHills SReynolds DATE 03/06/12 03/09/12 03/09/12 03/09/12 OFFICE RIII RIII NRR RIII NAME GShear for SWest SOrth TMcGinty CPederson (for BBoger) for ELeeds DATE 03/13/12 03/13/12 03/09/12 03/16/12 OFFICIAL RECORD COPY | |||
Letter to B. Allen from C. Pederson dated March 16, 2012 | |||
==SUBJECT:== | ==SUBJECT:== | ||
COMPLETION OF COMMITMENTS OF CONFIRMATORY ACTION LETTER NO. 3-10-001 | COMPLETION OF COMMITMENTS OF CONFIRMATORY ACTION LETTER NO. 3-10-001 DISTRIBUTION: | ||
RidsNrrDorlLpl3-2 Resource Breeda Reilly RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Jennifer Uhle Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports.Resource@nrc.gov}} | |||
DISTRIBUTION: | |||
RidsNrrDorlLpl3-2 Resource | |||
Breeda Reilly | |||
RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson | |||
Jennifer Uhle Steven Orth Jared Heck Allan Barker | |||
Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports.Resource@nrc.gov}} | |||
Revision as of 06:43, 12 November 2019
| ML12076A170 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 03/16/2012 |
| From: | Pederson C Region 3 Administrator |
| To: | Allen B FirstEnergy Nuclear Operating Co |
| References | |
| CAL 3-10-001 | |
| Download: ML12076A170 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 16, 2012 CAL No. 3-10-001 Mr. Barry Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
COMPLETION OF COMMITMENTS OF CONFIRMATORY ACTION LETTER NO. 3-10-001
Dear Mr. Allen:
This letter is in response to your November 7, 2011, letter informing the U.S. Nuclear Regulatory Commission (NRC) that FirstEnergy Nuclear Operating Company (FENOC) had completed all actions required by the June 23, 2010, Confirmatory Action Letter (CAL) issued to the Davis-Besse Nuclear Power Station. The CAL (ML101740519) confirmed the following commitments by FENOC to the NRC:
- 1. Provide to the NRC, in writing, the results of the Reinspection Years calculation for Operating Cycle 17 performed in accordance with American Society of Mechanical Engineers (ASME) Code Case N-729-1 based on calculated RPV Head temperatures.
Due prior to plant restart (Mode 2).
- 2. Upon completion of destructive examination of the control rod drive mechanism nozzle ring samples removed from nozzles #4 and #10, quarantine one untested minimum full-length 90 degree sample and turn over ownership to the NRC. Quarantine the sample immediately until arrangements can be made to transport the sample to an independent laboratory selected by the NRC.
- 3. Beginning with reactor startup (Mode 2) and until reactor pressure vessel (RPV) head replacement, upon reaching Action Level 3 of EN-DP-01171, "Engineering Implementation of the reactor coolant system (RCS) Integrated Leakage Program," the plant shall be shut down in 30 days if RPV Head leakage cannot be ruled out. During subsequent shutdown as part of the containment inspection for RCS leakage, if RPV Head leakage cannot be ruled out, a bare metal visual examination of the RPV head will be performed per applicable ASME Code Case and 10 CFR 50.55a(g)(6)(ii)(D).
- 4. The licensee has voluntarily elected to shut down the unit no later than October 1, 2011, and replace the RPV head.
B. Allen On July 7, 2010, the NRC issued a letter (ML101880308) that closed Commitment No. 1 of CAL 3-10-001. Commitments No. 2 through 4 were assessed in Section 4OA5.4 of Inspection Report 05000346/2011004 (ML112991544). Based on our review of the CAL commitments and the results of our inspections, we consider Commitments No. 2 through 4 of the CAL to be closed and, therefore, conclude that FENOC has met all of the commitments contained in the June 23, 2010, CAL issued to Davis-Besse Nuclear Power Station.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS),
accessible from the NRC Web Site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Cynthia D. Pederson Acting Regional Administrator Docket No. 50-346 License No. NPF-3 cc: Distribution via ListServ
B. Allen On July 7, 2010, the NRC issued a letter (ML101880308) that closed Commitment No. 1 of CAL 3-10-001. Commitments No. 2 through 4 were assessed in Section 4OA5.4 of Inspection Report 05000346/2011004 (ML112991544). Based on our review of the CAL commitments and the results of our inspections, we consider Commitments No. 2 through 4 of the CAL to be closed and, therefore, conclude that FENOC has met all of the commitments contained in the June 23, 2010, CAL issued to Davis-Besse Nuclear Power Station.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS),
accessible from the NRC Web Site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Cynthia D. Pederson Acting Regional Administrator Docket No. 50-346 License No. NPF-3 cc: Distribution via ListServ DOCUMENT NAME: Davis-Besse CAL 3-10-001 Closure Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME PSmagacz:dtp JCameron DHills SReynolds DATE 03/06/12 03/09/12 03/09/12 03/09/12 OFFICE RIII RIII NRR RIII NAME GShear for SWest SOrth TMcGinty CPederson (for BBoger) for ELeeds DATE 03/13/12 03/13/12 03/09/12 03/16/12 OFFICIAL RECORD COPY
Letter to B. Allen from C. Pederson dated March 16, 2012
SUBJECT:
COMPLETION OF COMMITMENTS OF CONFIRMATORY ACTION LETTER NO. 3-10-001 DISTRIBUTION:
RidsNrrDorlLpl3-2 Resource Breeda Reilly RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Jennifer Uhle Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports.Resource@nrc.gov