{{#Wiki_filter:ConstructionStatusUpdateRyderThompson SouthCarolinaElectric&Gas VCSUnits2&3SafelyConstructVCSUnits2&3inaccordancewiththeApprovedDesignandLicenseRequirements.
{{#Wiki_filter:Construction Status Update Ryder Thompson South Carolina Electric & Gas
VCSUnits2&3ConstructionMilestones-Completed
 
*Unit2FNC,3/11/13 7000cubicyardsofconcrete*Unit2CR10set 4/3/13*Unit2ContainmentVesselBottomHeadplaced,5/22/13*Unit3FNC,11/4/13*Switchyardenergized*CoolingTower2Astructureerected*Unit2TurbineBuildingBasemat&BasementWallsplaced*Unit2Condensersset12/30/13*Unit2CH80&CH82steelset VCSUnits2&3ConstructionMilestones-Upcoming*2014FirstQuarter-SetUnit2CA20AuxiliaryBuildingModule-CompleteUnit3CR10CVBHSupportModule-SetUnit2ContainmentVesselRing1-BeginBackfillAdjacenttoAux.Building*2014SecondQuarter-SetUnit3ContainmentVesselBottomHead-SetCA05Module VCS Units 2 & 3 -Site Overview Site Overview VCS Unit 3 FNC Pour Site Overview VCS Unit 3 CR 10 Installation Site Overview VCS Unit 2 Auxiliary Building Wall Construction Site Overview VCS Unit 2 Containment Vessel Ring 1 Site Overview VCS Unit 3 Containment Vessel Bottom Head Site Overview VCS Unit 3 Containment Vessel Ring 1 Site Overview 12 Units2&3Accumulator Tanks Unit3CoreMakeupTanks Units2TurbineWaterbox Unit2TurbineStator 13VCS Unit 2 Turbine Building Condensers Set ConstructionInspectionLessons*ShareLessonsLearnedwithVogtle*OpenCommunicationwithVogtle,WECandCB&I*RobustConstructionOversightwithFocusonITAAC*StrongCorrectiveActionProgramwithDetailedITAACScreening Questions?}}
VCS Units 2 & 3 Safely Construct VCS Units 2 & 3 in accordance with the Approved Design and License Requirements.
 
VCS Units 2 & 3 Construction Milestones - Completed
* Unit 2 FNC, 3/11/13
* Switchyard energized 7000 cubic yards of
* Cooling Tower 2A structure concrete                    erected
* Unit 2 CR10 set
* Unit 2 Turbine Building 4/3/13                     Basemat & Basement Walls
* Unit 2 Containment Vessel  placed Bottom Head placed,
* Unit 2 Condensers set 5/22/13                     12/30/13
* Unit 3 FNC, 11/4/13
* Unit 2 CH80 & CH82 steel set
 
VCS Units 2 & 3 Construction Milestones - Upcoming
* 2014 First Quarter
  - Set Unit 2 CA20 Auxiliary Building Module
  - Complete Unit 3 CR10 CVBH Support Module
  - Set Unit 2 Containment Vessel Ring 1
  - Begin Backfill Adjacent to Aux. Building
* 2014 Second Quarter
  - Set Unit 3 Containment Vessel Bottom Head
  - Set CA05 Module
 
VCS Units 2 & 3 - Site Overview Site Overview
 
VCS Unit 3 FNC Pour Site Overview
 
VCS Unit 3 CR 10 Installation Site Overview
 
VCS Unit 2 Auxiliary Building Wall Construction Site Overview
 
VCS Unit 2 Containment Vessel Ring 1 Site Overview
 
VCS Unit 3 Containment Vessel Bottom Head Site Overview
 
VCS Unit 3 Containment Vessel Ring 1 Site Overview
 
Unit 3 Core Makeup Tanks Units 2 & 3 Accumulator Tanks Unit 2 Turbine Stator    Units 2 Turbine Waterbox 12
 
VCS Unit 2 Turbine Building Condensers Set 13
 
Construction Inspection Lessons
* Share Lessons Learned with Vogtle
* Open Communication with Vogtle, WEC and CB&I
* Robust Construction Oversight with Focus on ITAAC
* Strong Corrective Action Program with Detailed ITAAC Screening
 
Questions?}}

Revision as of 07:48, 4 November 2019

Public Meeting 2/27/2014 VCS Construction Update
ML14057A420
Person / Time
Site: Summer, Vogtle  South Carolina Electric & Gas Company icon.png
Issue date: 02/27/2014
From: Thompson R
South Carolina Electric & Gas Co
To:
Division of Construction Inspection and Operational Programs
Bloom S
References
Download: ML14057A420 (15)


Text

Construction Status Update Ryder Thompson South Carolina Electric & Gas

VCS Units 2 & 3 Safely Construct VCS Units 2 & 3 in accordance with the Approved Design and License Requirements.

VCS Units 2 & 3 Construction Milestones - Completed

  • Unit 2 FNC, 3/11/13
  • Unit 2 CR10 set
  • Unit 2 Turbine Building 4/3/13 Basemat & Basement Walls
  • Unit 2 Containment Vessel placed Bottom Head placed,
  • Unit 2 Condensers set 5/22/13 12/30/13
  • Unit 3 FNC, 11/4/13
  • Unit 2 CH80 & CH82 steel set

VCS Units 2 & 3 Construction Milestones - Upcoming

  • 2014 First Quarter

- Set Unit 2 CA20 Auxiliary Building Module

- Complete Unit 3 CR10 CVBH Support Module

- Set Unit 2 Containment Vessel Ring 1

- Begin Backfill Adjacent to Aux. Building

  • 2014 Second Quarter

- Set Unit 3 Containment Vessel Bottom Head

- Set CA05 Module

VCS Units 2 & 3 - Site Overview Site Overview

VCS Unit 3 FNC Pour Site Overview

VCS Unit 3 CR 10 Installation Site Overview

VCS Unit 2 Auxiliary Building Wall Construction Site Overview

VCS Unit 2 Containment Vessel Ring 1 Site Overview

VCS Unit 3 Containment Vessel Bottom Head Site Overview

VCS Unit 3 Containment Vessel Ring 1 Site Overview

Unit 3 Core Makeup Tanks Units 2 & 3 Accumulator Tanks Unit 2 Turbine Stator Units 2 Turbine Waterbox 12

VCS Unit 2 Turbine Building Condensers Set 13

Construction Inspection Lessons

  • Share Lessons Learned with Vogtle
  • Open Communication with Vogtle, WEC and CB&I
  • Robust Construction Oversight with Focus on ITAAC
  • Strong Corrective Action Program with Detailed ITAAC Screening

Questions?