{{#Wiki_filter:Page 1 of 1 | {{#Wiki_filter:Page 1 of 1 As of: 3/3/17 11:41 AM Received: February 28, 2017 Status: Pending_Post PUBLIC SUBMISSION Tracking No. lkl-8uzq-4ars Comments Due: February 28, 2017 Submission Type: Web Docket: NRC-2016-0224 Restart of a Nuclear Power Plant Shut Down by a Seismic Event 11P/~1~ | ||
February 28, 2017 Status: Pending_Post Tracking No. lkl-8uzq-4ars Comments Due: February 28, 2017 Submission Type: Web Guidance: | Comment On: NRC-2016-0224-0003 ~;r;:_/'(,? ~::; | ||
Restart of a Nuclear Power Plant Shut Down by a Seismic Event | Guidance: Restart of a Nuclear Power Plant Shut Down by a Seismic Event Document: NRC-2016-0224-DRAFT-0005 Comment on FR Doc# 2016-30895 | ||
NRC-2016-0224-DRAFT-0005 Comment on FR Doc# 2016-30895 | --.-, | ||
https://www.fdms.gov/fdms/getcontent?objectld=09000064824dfc4b&format=xml&showorig=false 03/03/2017 . I}} | _).. _) | ||
eJ '.f ~ ::C1 Submitter Information .-*n | |||
_.., | |||
...... | |||
.... | |||
' | |||
'.../ | |||
r-- | |||
r" rr Cf; | |||
)"* :-.J | |||
.., ! | |||
Name: T. Stewart t i w ', .. | |||
-*-*.. | |||
**--- | |||
-._,, | |||
-i-1 | |||
-- | |||
=r.-;: | |||
: | |||
-'- ~ | |||
-..., | |||
--* | |||
~- | |||
'- , | |||
--, :--i General Comment :.,_.,...,) | |||
w (0 | |||
--::*- | |||
r*r~1 | |||
(_;') | |||
Virgil C. Summer Nuclear Station (VCSNS) Unit 1 revised its station procedures concerning earthquake | |||
~esponse and incorporated guidance provided in Regulatory Guide (RG) 1.167 Revision 0 and EPRI NP-6695, "Guidance for Nuclear Power Plan Response to an Earthquake," in addressing INPO IER L2 12-12, "Greater than D~sign Basis Earthquake Results in a Loss of Off Site Power and Reactor SCRAM" and INPO IER L4 13-3, "Recovering froma Beyond-Design-Basis Natural Event - Lessons Learned." VCSNS J]nit 1 requests that the NRC does not approve any imposition or backfitting of the guidance provided in RG 1.167 Revision 1 for existing licensees who have incorporated previous guidance into their earthquake response. | |||
) | |||
SUNSI Review Complete Template = ADM - 013 E-RIDS= ADM-03 Add= ;D-f)~(:.;Xo) https://www.fdms.gov/fdms/getcontent?objectld=09000064824dfc4b&format=xml&showorig=false 03/03/2017 | |||
. I}} |
Revision as of 06:59, 30 October 2019
ML17067A114 | |
Person / Time | |
---|---|
Site: | Summer ![]() |
Issue date: | 02/28/2017 |
From: | Stewart T South Carolina Electric & Gas Co |
To: | Rules, Announcements, and Directives Branch |
References | |
81FR76633 00005, NRC-2016-0224 | |
Download: ML17067A114 (1) | |
Text
Page 1 of 1 As of: 3/3/17 11:41 AM Received: February 28, 2017 Status: Pending_Post PUBLIC SUBMISSION Tracking No. lkl-8uzq-4ars Comments Due: February 28, 2017 Submission Type: Web Docket: NRC-2016-0224 Restart of a Nuclear Power Plant Shut Down by a Seismic Event 11P/~1~
Comment On: NRC-2016-0224-0003 ~;r;:_/'(,? ~::;
Guidance: Restart of a Nuclear Power Plant Shut Down by a Seismic Event Document: NRC-2016-0224-DRAFT-0005 Comment on FR Doc# 2016-30895
--.-,
_).. _)
eJ '.f ~ ::C1 Submitter Information .-*n
_..,
......
....
'
'.../
r--
r" rr Cf;
)"* :-.J
.., !
Name: T. Stewart t i w ', ..
-*-*..
- ---
-._,,
-i-1
--
=r.-;:
-'- ~
-...,
--*
~-
'- ,
--, :--i General Comment :.,_.,...,)
w (0
--::*-
r*r~1
(_;')
Virgil C. Summer Nuclear Station (VCSNS) Unit 1 revised its station procedures concerning earthquake
~esponse and incorporated guidance provided in Regulatory Guide (RG) 1.167 Revision 0 and EPRI NP-6695, "Guidance for Nuclear Power Plan Response to an Earthquake," in addressing INPO IER L2 12-12, "Greater than D~sign Basis Earthquake Results in a Loss of Off Site Power and Reactor SCRAM" and INPO IER L4 13-3, "Recovering froma Beyond-Design-Basis Natural Event - Lessons Learned." VCSNS J]nit 1 requests that the NRC does not approve any imposition or backfitting of the guidance provided in RG 1.167 Revision 1 for existing licensees who have incorporated previous guidance into their earthquake response.
)
SUNSI Review Complete Template = ADM - 013 E-RIDS= ADM-03 Add= ;D-f)~(:.;Xo) https://www.fdms.gov/fdms/getcontent?objectld=09000064824dfc4b&format=xml&showorig=false 03/03/2017