{{#Wiki_filter:NRC Preparations to License Accident Tolerant Fuel Agenda
{{#Wiki_filter:NRC Preparations to License Accident Tolerant Fuel Andrew Proffitt February, 2019
 
Agenda I. ATF Project Plan implementation II. Cr-coated cladding PIRT/ISG III. Upcoming NRC meetings on ATF 2


I. ATF Project Plan Implementation
I. ATF Project Plan Implementation
* NRCs ATF Project Plan issued in September 2018 (ML18261A414)
* Heightened stakeholder engagement
  - Fuel vendors
  - Public
  - DOE
  - Industry
* Actively modifying NRC analysis capability to model near-term ATF concepts 3


Draft ATF Regulatory Issue Summary Issued
Draft ATF Regulatory Issue Summary Issued
* Pre-application Communication and Scheduling for Accident Tolerant Fuel Submittals (ML18270A019)
* Inform budget and resource planning
    - Scheduling
    - Necessary knowledge and skillsets
* Begin addressing questions with NRC staff today
* Responses are voluntary 4
Confirmatory Tool Updates
* Identifying data gaps / code updates needed to support near-term ATF concepts
* Near-term focus:
  -  Doped fuels
  -  Coated claddings
  -  FeCrAl
  -  Phase 1 (~67 GWd/mtU) burnup extension
* Completed activities:
  - Material library updates (available data)
  - Oxidation kinetics for FeCrAl
  - Assessment on doped fuel behavior
* Engaged with fuel vendors and DOE/CASL on ATF modeling efforts and plans 5
II. Chrome Coated Cladding
* Initiated phenomena identification and ranking (PIRT) exercise for chrome coated zirconium alloy cladding
* Preliminary report available in ADAMS (ML19036A716)
* Provided to experts in advance of panel discussions
* PIRT panel to be held at PNNL April 23-25, 2019 6
Preliminary Cr-Coated PIRT Report
* Overview of coating concepts and techniques
* Cr-Zr Phase Diagram
* Potential changes to Safety Analysis Codes, Methods and Safety Limits
  - Cladding base material property correlations + impacts
  - Impact of coating on SAFDLs
  - Changes to existing codes and methodologies
* Current publicly available data
  - In-reactor
  - Ex-reactor
  - Data gaps and performance concerns 7
Developing Interim Staff Guidance for Predictable and Efficient Reviews
* NRR Office Instruction on Interim Staff Guidance (ISG):
Purpose: Provide temporary guidance to staff until more durable guidance is incorporated into established NRC regulatory processes
* Useful in facilitating expedited resolution of emerging technical or licensing issues
* Provide staff guidance concerning issues not currently addressed within established NRC regulatory processes
* PIRT results will be used to develop ISG that supplements standard review plan (SRP) chapters 4.2 and 15 (as necessary)
* Provide guidance to both staff and industry:
  - Industry: Understand staff expectations for submittals
  - Staff: Supplement the standard review plan with concept specific review criteria 8


Confirmatory Tool Updates II. Chrome Coated Cladding
Cr-Coated Cladding PIRT/ISG Timeline
* April 2019: PIRT panel
* July 2019: Final PIRT report
* July 2019: Initial draft ISG publicly available
* August 2019: Public meeting on initial draft ISG
* September 2019: Potential ACRS subcommittee meeting on draft ISG
* September 2019: ISG published in Federal Register for public comment
* December 2019: Public meeting to discuss resolution of comments
* December 2019: Final issuance of ISG 9


Preliminary Cr-Coated PIRT Report Developing Interim Staff Guidance for Predictable and Efficient Reviews Cr-Coated Cladding PIRT/ISG Timeline III. Upcoming NRC ATF Meetings}}
III. Upcoming NRC ATF Meetings
* Public portion at beginning of all vendor meetings
  - February 27, 2019: GNF
  - February 27-28, 2019: Framatome
  - February 28, 2019: Westinghouse
* March 14, 2019 - RIC Session
  - Accident Tolerant Fuels: Preparations to License
  - Panelists: DOE, NEA, NEI, & NRC
* April 23-25, 2019 - Cr-coated PIRT Panel
  - Richland, WA (PNNL)
  - meeting notice
* July 2019 - Public meeting on Cr-coated interim staff guidance
  - Initial draft to be made available prior to meeting 10}}

Revision as of 01:09, 20 October 2019

Update on NRC Accident Tolerant Fuel (ATF) Activities, February 2019
ML19057A131
Person / Time
Issue date: 02/26/2019
From: Proffitt J
NRC/NRR/DLP/PLPB
To:
Proffitt J
References
Download: ML19057A131 (10)


Text

NRC Preparations to License Accident Tolerant Fuel Andrew Proffitt February, 2019

Agenda I. ATF Project Plan implementation II. Cr-coated cladding PIRT/ISG III. Upcoming NRC meetings on ATF 2

I. ATF Project Plan Implementation

  • Heightened stakeholder engagement

- Fuel vendors

- Public

- DOE

- Industry

  • Actively modifying NRC analysis capability to model near-term ATF concepts 3

Draft ATF Regulatory Issue Summary Issued

  • Inform budget and resource planning

- Scheduling

- Necessary knowledge and skillsets

  • Begin addressing questions with NRC staff today
  • Responses are voluntary 4

Confirmatory Tool Updates

  • Identifying data gaps / code updates needed to support near-term ATF concepts
  • Near-term focus:

- Doped fuels

- Coated claddings

- FeCrAl

- Phase 1 (~67 GWd/mtU) burnup extension

  • Completed activities:

- Material library updates (available data)

- Oxidation kinetics for FeCrAl

- Assessment on doped fuel behavior

  • Engaged with fuel vendors and DOE/CASL on ATF modeling efforts and plans 5

II. Chrome Coated Cladding

  • Initiated phenomena identification and ranking (PIRT) exercise for chrome coated zirconium alloy cladding
  • Provided to experts in advance of panel discussions
  • PIRT panel to be held at PNNL April 23-25, 2019 6

Preliminary Cr-Coated PIRT Report

  • Overview of coating concepts and techniques
  • Cr-Zr Phase Diagram
  • Potential changes to Safety Analysis Codes, Methods and Safety Limits

- Cladding base material property correlations + impacts

- Impact of coating on SAFDLs

- Changes to existing codes and methodologies

  • Current publicly available data

- In-reactor

- Ex-reactor

- Data gaps and performance concerns 7

Developing Interim Staff Guidance for Predictable and Efficient Reviews

  • NRR Office Instruction on Interim Staff Guidance (ISG):

Purpose: Provide temporary guidance to staff until more durable guidance is incorporated into established NRC regulatory processes

  • Useful in facilitating expedited resolution of emerging technical or licensing issues
  • Provide staff guidance concerning issues not currently addressed within established NRC regulatory processes
  • PIRT results will be used to develop ISG that supplements standard review plan (SRP) chapters 4.2 and 15 (as necessary)
  • Provide guidance to both staff and industry:

- Industry: Understand staff expectations for submittals

- Staff: Supplement the standard review plan with concept specific review criteria 8

Cr-Coated Cladding PIRT/ISG Timeline

  • April 2019: PIRT panel
  • July 2019: Final PIRT report
  • July 2019: Initial draft ISG publicly available
  • August 2019: Public meeting on initial draft ISG
  • September 2019: Potential ACRS subcommittee meeting on draft ISG
  • September 2019: ISG published in Federal Register for public comment
  • December 2019: Public meeting to discuss resolution of comments
  • December 2019: Final issuance of ISG 9

III. Upcoming NRC ATF Meetings

  • Public portion at beginning of all vendor meetings

- February 27, 2019: GNF

- February 27-28, 2019: Framatome

- February 28, 2019: Westinghouse

  • March 14, 2019 - RIC Session

- Accident Tolerant Fuels: Preparations to License

- Panelists: DOE, NEA, NEI, & NRC

  • April 23-25, 2019 - Cr-coated PIRT Panel

- Richland, WA (PNNL)

- meeting notice

  • July 2019 - Public meeting on Cr-coated interim staff guidance

- Initial draft to be made available prior to meeting 10