ENOC-14-00004, Completion of Change to the Entergy Quality Assurance Manual Per Confirmatory Order EA-11-096: Difference between revisions
StriderTol (talk | contribs) Created page by program invented by StriderTol |
StriderTol (talk | contribs) Created page by program invented by StriderTol |
||
| Line 3: | Line 3: | ||
| issue date = 02/26/2014 | | issue date = 02/26/2014 | ||
| title = Completion of Change to the Entergy Quality Assurance Manual Per Confirmatory Order EA-11-096 | | title = Completion of Change to the Entergy Quality Assurance Manual Per Confirmatory Order EA-11-096 | ||
| author name = | | author name = Mccann J | ||
| author affiliation = Entergy Nuclear Operations, Inc, Entergy Operations, Inc | | author affiliation = Entergy Nuclear Operations, Inc, Entergy Operations, Inc | ||
| addressee name = Zimmerman R | | addressee name = Zimmerman R | ||
| addressee affiliation = NRC/OE | | addressee affiliation = NRC/OE | ||
| docket = 05000155, 05000247, 05000255, 05000271, 05000286, 05000293, 05000313, 05000333, 05000368, 05000382, 05000416, 05000458 | | docket = 05000155, 05000247, 05000255, 05000271, 05000286, 05000293, 05000313, 05000333, 05000368, 05000382, 05000416, 05000458 | ||
Revision as of 15:44, 21 June 2019
| ML14063A270 | |
| Person / Time | |
|---|---|
| Site: | Palisades, Indian Point, Grand Gulf, Pilgrim, Arkansas Nuclear, River Bend, Vermont Yankee, Waterford, Big Rock Point, FitzPatrick File:Consumers Energy icon.png |
| Issue date: | 02/26/2014 |
| From: | Mccann J Entergy Nuclear Operations, Entergy Operations |
| To: | Zimmerman R NRC/OE |
| References | |
| CNRO-2014-00001, EA-11-096, ENOC-14-00004 | |
| Download: ML14063A270 (2) | |
Text
.//Aft.manormw Enteigy Entergy Operations, Inc.Entergy Nuclear Operations, Inc.440 Hamilton Avenue White Plains, NY 10601 John F. McCann Vice President, Regulatory Assurance Tel. (914) 272-3370 CNRO-2014-00001 ENOC-14-00004 February 26, 2014 Mr. Roy P. Zimmerman Director, Office of Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555
SUBJECT:
Completion of Change to the Entergy Quality Assurance Program Manual with regards to Confirmatory Order EA-1 1-096 Arkansas Nuclear One Indian Point Nuclear Generating Station Unit One Unit Two Unit 2 Unit 3 Docket 05000313 Docket 05000368 Docket 05000247 Docket 05000286 License DRP-51 License NPF-6 License DPR-26 License DPR-64 Grand Gulf Nuclear Station James A. FitzPatrick Nuclear Power Plant Docket 05000416 Docket 05000333 License NPF-29 License DPR-59 River Bend Station Palisades Nuclear Plant Docket 05000458 Docket 05000255 License NPF-47 License DPR-20 Waterford Steam Electric Station -Unit 3 Pilgrim Nuclear Power Station Docket 05000382 Docket 05000293 License NPF-38 License DPR-35 Big Rock Point Nuclear Plant -ISFSI Vermont Yankee Nuclear Power Station Docket 05000155 Docket 05000271 License DPR-6 License DPR-28
REFERENCES:
- 1. Entergy Letter to NRC, NRC Confirmatory Order EA-11-096, Planned Reorganization of Quality Control Reporting Relationship, dated November 14, 2011 (ADAMS Accession No. ML11335A045)
- 2. Entergy Letter to NRC, Planned Modification of the Entergy Quality Assurance Program Manual (QAPM), dated November 4, 2013 (ADAMS Accession No. ML14002A120)
Dear Mr. Zimmerman:
Entergy Operations, Inc. and Entergy Nuclear Operations, Inc. (Entergy) in Reference 2 identified additional actions that would be taken in associated with the actions discussed in Reference
- 1. Entergy confirms the completion of the actions discussed in Reference 2./.- 5501 CNRO-2014-00001 ENOC-14-00004 Page 2 of 2 If you have any questions or require additional information, please contact Bryan Ford at (601) 368-5516.This letter contains no new regulatory commitments.
SincereIyj 14 J'JFM/ghd/aye cc: NRC Document Control Desk
Text
.//Aft.manormw Enteigy Entergy Operations, Inc.Entergy Nuclear Operations, Inc.440 Hamilton Avenue White Plains, NY 10601 John F. McCann Vice President, Regulatory Assurance Tel. (914) 272-3370 CNRO-2014-00001 ENOC-14-00004 February 26, 2014 Mr. Roy P. Zimmerman Director, Office of Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555
SUBJECT:
Completion of Change to the Entergy Quality Assurance Program Manual with regards to Confirmatory Order EA-1 1-096 Arkansas Nuclear One Indian Point Nuclear Generating Station Unit One Unit Two Unit 2 Unit 3 Docket 05000313 Docket 05000368 Docket 05000247 Docket 05000286 License DRP-51 License NPF-6 License DPR-26 License DPR-64 Grand Gulf Nuclear Station James A. FitzPatrick Nuclear Power Plant Docket 05000416 Docket 05000333 License NPF-29 License DPR-59 River Bend Station Palisades Nuclear Plant Docket 05000458 Docket 05000255 License NPF-47 License DPR-20 Waterford Steam Electric Station -Unit 3 Pilgrim Nuclear Power Station Docket 05000382 Docket 05000293 License NPF-38 License DPR-35 Big Rock Point Nuclear Plant -ISFSI Vermont Yankee Nuclear Power Station Docket 05000155 Docket 05000271 License DPR-6 License DPR-28
REFERENCES:
- 1. Entergy Letter to NRC, NRC Confirmatory Order EA-11-096, Planned Reorganization of Quality Control Reporting Relationship, dated November 14, 2011 (ADAMS Accession No. ML11335A045)
- 2. Entergy Letter to NRC, Planned Modification of the Entergy Quality Assurance Program Manual (QAPM), dated November 4, 2013 (ADAMS Accession No. ML14002A120)
Dear Mr. Zimmerman:
Entergy Operations, Inc. and Entergy Nuclear Operations, Inc. (Entergy) in Reference 2 identified additional actions that would be taken in associated with the actions discussed in Reference
- 1. Entergy confirms the completion of the actions discussed in Reference 2./.- 5501 CNRO-2014-00001 ENOC-14-00004 Page 2 of 2 If you have any questions or require additional information, please contact Bryan Ford at (601) 368-5516.This letter contains no new regulatory commitments.
SincereIyj 14 J'JFM/ghd/aye cc: NRC Document Control Desk