Line 11: |
Line 11: |
| | contact person = | | | contact person = |
| | case reference number = NL-10-102 | | | case reference number = NL-10-102 |
| | document type = Letter | | | document type = Letter type:NL |
| | page count = 2 | | | page count = 2 |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:}} | | {{#Wiki_filter:Entergy Nuclear Northeast Indian Point Energy Center*450 Broadway, GSB fP.O. Box 249 Buchanan, N.Y. 10511-0249 Tel (914) 734-6710 Robert Walpole Manager Licensing Tel (914) 734-6710 NL-1 0-102 October 6, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 |
| | |
| | ==Subject:== |
| | Indian Point Energy Center Installation of Plant Integrated Computer System (PICS) in Unit 3 Simulation Facility Prior to Installation in the Unit 3 Nuclear Power Plant Control Room Indian Point, Unit 3 Docket No. 50-286 License No. DPR-64 |
| | |
| | ==Dear Sir or Madam;The purpose of this letter is to notify the NRC of Entergy Nuclear Operations,== |
| | Inc. (Entergy)revision to the Indian Point Energy Center (IPEC) Unit 3 plant Simulation Facility prior to installation of the modification for the Plant Integrated Computer System (PICS) into the Unit 3 plant Control Room.An IPEC Engineering Change will replace the existing IPEC Unit 3 plant process computer, also known as the Critical Function Monitoring System (CFMS), with a new updated Plant Integrated Computer System (PICS) in the plant-reference simulator prior to this Engineering Change being installed in the Unit 3 plant. The primary reason for the replacement is equipment obsolescence, including outdated hardware and software. |
| | The primary function of the plant computer is to aid the operator in acquiring plant data and presenting it to the operator in a useful and meaningful way.The new Unit 3 computer processors will be located in the Unit 2 Computer Room which will become the Computer Room for both Unit 2 and Unit 3 Plant Computers. |
| | The new Unit 3 plant process computer workstations will be located in the Unit 3 Control Room (same locations as the existing CFMS workstations). |
| | 10 CFR 55.45(13)(b)(1) requires that the operating test will be administered in a plant walkthrough and in either a simulation facility that the Commission has approved for use after application has been made by the facility licensee under 55.46(b) or a plant-referenced simulator (55.46(c)). |
| | Under 10 CFR 55.46(c)(1)(i) plant-referenced simulators must be sufficient in scope and fidelity to allow conduct of the evolutions listed in 55.45(a)(1) through (13) and applicable to the design of the reference plant, and (c)(2)(ii) |
| | Facility licensees that propose to use a plant-referenced simulator to meet the control manipulation requirements must ensure that Simulator fidelity has been demonstrated so the significant control manipulations are completed without procedural exceptions, simulator performance exceptions, or deviation from the approved training scenario sequence. |
| | ATOoI Indian Point Unit 3 Docket Nos. 50-286 License No. DPR-64 NL-10-102 Page 2 of 2 Entergy elected to install the Unit 3 PICS System in the plant Simulator prior to installation in the plant to facilitate testing, training, and human factors considerations in the Simulator before the Operators would be called upon to use the system in the plant. The decision to install the PICS System in the Simulator prior to the plant was to have the PICS installation in the Simulator complete so the Operators have a chance to become familiar with the system before it is installed in the plant. As the existing plant computer and the new PICS computer can not be run simultaneously, there would be no time for the Operators to learn the new computer system in-an on-the-job setting. Installing the new PICS computer in the Simulator will allow time for the Operators to become familiar with and learn the new computer system before required use in the plant. This will allow training for the Operators during the last quarter of 2010 and the first cycle in 2011 will be available for Operator simulator evaluations to verify the Operators were comfortable with the system in a transient |
| | / stress environment. |
| | The installation of PICS in the Simulator prior to the plant will occur during the cycle of Licensed Operator Requalification training immediately following the Annual Operating Exams being administered for Unit 3 with the exception of the pilot team. The pilot team was rescheduled due to the Unit 2 and 3 forced outages and will be examined after Unit 3 PICS is installed in the Simulator. |
| | In order to accommodate this, the warranty load, which is the previous training load without PICS will be used to examine the pilot team. The next Annual Operating Exams on Unit 3 are scheduled well after PICS being installed in both the plant and Simulator. |
| | Entergy is making no new commitments in this letter. Should you have any questions regarding this matter, please contact Mr. John Ferrick, Manager Training and Development, at Indian Point Energy Center at (914) 788-2611.Sincerely yours, RW/as cc: NRC Resident Inspector's Office Mr. John Boska, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region 1 Mr. Francis J. Murray, Jr., President and CEO, NYSERDA Mr. Paul Eddy, New York State Dept. of Public Service Mr. Larry Vick, NRC NRR DIRS IOLB}} |
|
---|
Category:Letter type:NL
MONTHYEARNL-21-034, Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals2021-05-26026 May 2021 Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary NL-21-033, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2021-05-11011 May 2021 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-21-032, Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center2021-05-11011 May 2021 Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center NL-21-005, Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions2021-05-11011 May 2021 Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions NL-21-030, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0606 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NL-21-027, Registration of Spent Fuel Cask Use2021-04-20020 April 2021 Registration of Spent Fuel Cask Use NL-21-021, Registration of Spent Fuel Cask Use2021-04-19019 April 2021 Registration of Spent Fuel Cask Use NL-21-017, Pre-Notice of Disbursement from Decommissioning Trusts2021-04-0808 April 2021 Pre-Notice of Disbursement from Decommissioning Trusts NL-21-010, Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2021-02-17017 February 2021 Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-082, Notice of Planned Transfer of Decommissioning Funds2020-12-14014 December 2020 Notice of Planned Transfer of Decommissioning Funds NL-20-081, Pre-Notice of Disbursement from Decommissioning Trusts2020-12-0909 December 2020 Pre-Notice of Disbursement from Decommissioning Trusts NL-20-080, Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-93212020-11-19019 November 2020 Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-9321 NL-20-079, (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-12012 November 2020 (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-076, Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal2020-11-0202 November 2020 Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal NL-20-069, One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-10-0808 October 2020 One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-067, Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-09-16016 September 2020 Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-064, 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments2020-09-0101 September 2020 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments NL-20-060, Status of Remaining Actions for Generic Letter 2004-022020-08-11011 August 2020 Status of Remaining Actions for Generic Letter 2004-02 NL-20-057, Cancellation of Commitment Related to Large Break LOCA Reanalysis2020-07-30030 July 2020 Cancellation of Commitment Related to Large Break LOCA Reanalysis NL-20-0851, 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-07-22022 July 2020 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material NL-20-051, Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center2020-07-0707 July 2020 Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center NL-20-052, Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results2020-07-0707 July 2020 Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-041, Registration of Unit 3 Spent Fuel Cask Use2020-05-13013 May 2020 Registration of Unit 3 Spent Fuel Cask Use NL-20-042, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2020-05-12012 May 2020 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-20-033, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2020-04-28028 April 2020 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-20-038, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-04-23023 April 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-035, Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-16016 April 2020 Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-034, Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-13013 April 2020 Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-020, Submittal of 2019 Annual Fitness for Duty Performance Data Report Update2020-02-26026 February 2020 Submittal of 2019 Annual Fitness for Duty Performance Data Report Update NL-20-015, Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2020-02-10010 February 2020 Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-20-008, Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane2020-01-0606 January 2020 Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane NL-19-094, 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2019-12-16016 December 2019 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-092, Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-11-20020 November 2019 Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-043, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122019-10-22022 October 2019 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-078, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-10-22022 October 2019 Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-091, Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use2019-10-17017 October 2019 Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use NL-19-090, Registration of Unit 2 Spent Fuel Cask Use2019-10-0909 October 2019 Registration of Unit 2 Spent Fuel Cask Use NL-19-079, 50.59(d)(2) Summary Report of Changes, Tests and Experiments2019-09-26026 September 2019 50.59(d)(2) Summary Report of Changes, Tests and Experiments 2021-05-06
[Table view] |
Text
Entergy Nuclear Northeast Indian Point Energy Center*450 Broadway, GSB fP.O. Box 249 Buchanan, N.Y. 10511-0249 Tel (914) 734-6710 Robert Walpole Manager Licensing Tel (914) 734-6710 NL-1 0-102 October 6, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Indian Point Energy Center Installation of Plant Integrated Computer System (PICS) in Unit 3 Simulation Facility Prior to Installation in the Unit 3 Nuclear Power Plant Control Room Indian Point, Unit 3 Docket No. 50-286 License No. DPR-64
Dear Sir or Madam;The purpose of this letter is to notify the NRC of Entergy Nuclear Operations,
Inc. (Entergy)revision to the Indian Point Energy Center (IPEC) Unit 3 plant Simulation Facility prior to installation of the modification for the Plant Integrated Computer System (PICS) into the Unit 3 plant Control Room.An IPEC Engineering Change will replace the existing IPEC Unit 3 plant process computer, also known as the Critical Function Monitoring System (CFMS), with a new updated Plant Integrated Computer System (PICS) in the plant-reference simulator prior to this Engineering Change being installed in the Unit 3 plant. The primary reason for the replacement is equipment obsolescence, including outdated hardware and software.
The primary function of the plant computer is to aid the operator in acquiring plant data and presenting it to the operator in a useful and meaningful way.The new Unit 3 computer processors will be located in the Unit 2 Computer Room which will become the Computer Room for both Unit 2 and Unit 3 Plant Computers.
The new Unit 3 plant process computer workstations will be located in the Unit 3 Control Room (same locations as the existing CFMS workstations).
10 CFR 55.45(13)(b)(1) requires that the operating test will be administered in a plant walkthrough and in either a simulation facility that the Commission has approved for use after application has been made by the facility licensee under 55.46(b) or a plant-referenced simulator (55.46(c)).
Under 10 CFR 55.46(c)(1)(i) plant-referenced simulators must be sufficient in scope and fidelity to allow conduct of the evolutions listed in 55.45(a)(1) through (13) and applicable to the design of the reference plant, and (c)(2)(ii)
Facility licensees that propose to use a plant-referenced simulator to meet the control manipulation requirements must ensure that Simulator fidelity has been demonstrated so the significant control manipulations are completed without procedural exceptions, simulator performance exceptions, or deviation from the approved training scenario sequence.
ATOoI Indian Point Unit 3 Docket Nos. 50-286 License No. DPR-64 NL-10-102 Page 2 of 2 Entergy elected to install the Unit 3 PICS System in the plant Simulator prior to installation in the plant to facilitate testing, training, and human factors considerations in the Simulator before the Operators would be called upon to use the system in the plant. The decision to install the PICS System in the Simulator prior to the plant was to have the PICS installation in the Simulator complete so the Operators have a chance to become familiar with the system before it is installed in the plant. As the existing plant computer and the new PICS computer can not be run simultaneously, there would be no time for the Operators to learn the new computer system in-an on-the-job setting. Installing the new PICS computer in the Simulator will allow time for the Operators to become familiar with and learn the new computer system before required use in the plant. This will allow training for the Operators during the last quarter of 2010 and the first cycle in 2011 will be available for Operator simulator evaluations to verify the Operators were comfortable with the system in a transient
/ stress environment.
The installation of PICS in the Simulator prior to the plant will occur during the cycle of Licensed Operator Requalification training immediately following the Annual Operating Exams being administered for Unit 3 with the exception of the pilot team. The pilot team was rescheduled due to the Unit 2 and 3 forced outages and will be examined after Unit 3 PICS is installed in the Simulator.
In order to accommodate this, the warranty load, which is the previous training load without PICS will be used to examine the pilot team. The next Annual Operating Exams on Unit 3 are scheduled well after PICS being installed in both the plant and Simulator.
Entergy is making no new commitments in this letter. Should you have any questions regarding this matter, please contact Mr. John Ferrick, Manager Training and Development, at Indian Point Energy Center at (914) 788-2611.Sincerely yours, RW/as cc: NRC Resident Inspector's Office Mr. John Boska, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region 1 Mr. Francis J. Murray, Jr., President and CEO, NYSERDA Mr. Paul Eddy, New York State Dept. of Public Service Mr. Larry Vick, NRC NRR DIRS IOLB