{{#Wiki_filter:July 10, 2023 Mr. Barry N. Blair Site Vice President Energy Harbor Nuclear Corp.
{{#Wiki_filter:July 10, 2023
 
Mr. Barry N. Blair Site Vice President Energy Harbor Nuclear Corp.
Beaver Valley Power Station Mail Stop P-BV-SSB P.O. Box 4, Route 168 Shippingport, PA 15077-0004
Beaver Valley Power Station Mail Stop P-BV-SSB P.O. Box 4, Route 168 Shippingport, PA 15077-0004


Line 22: Line 24:


==Dear Mr. Blair:==
==Dear Mr. Blair:==
This letter is to inform you that effective July 7, 2023, Dr. V. Sreenivas will be assigned
as the U.S. Nuclear Regulatory Commissions Licensing Project Manager for Beaver Valley
Power Station, Units 1 and 2. Dr. V. Sreenivas may be reached at 301-415-2597 or by e-mail at
V.Sreenivas@nrc.gov.


This letter is to inform you that effective July 7, 2023, Dr. V. Sreenivas will be assigned as the U.S. Nuclear Regulatory Commissions Licensing Project Manager for Beaver Valley Power Station, Units 1 and 2. Dr. V. Sreenivas may be reached at 301-415-2597 or by e-mail at V.Sreenivas@nrc.gov.
Sincerely,
Sincerely,
                                                /RA/
Hipólito J. González, Chief Plant Licensing Branch LPL1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: Listserv


ML23188A067 OFFICE NRR/DORL/LPL1/PM         NRR/DORL/LPL1/LA     NRR/DORL/LPL1/BC NAME     VSreenivas             KZeleznock           HGonzalez DATE     07/06/2023             07/07/2023           7/10/2023}}
/RA/
 
Hipólito J. González, Chief Plant Licensing Branch LPL1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
 
Docket Nos. 50-334 and 50-412
 
cc: Listserv
 
ML23188A067 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NAME VSreenivas KZeleznock HGonzalez DATE 07/06/2023 07/07/2023 7/10/2023}}

Revision as of 19:28, 13 November 2024

Project Manager Assignment
ML23188A067
Person / Time
Site: Beaver Valley
Issue date: 07/10/2023
From: Hipolito Gonzalez
Plant Licensing Branch 1
To: Blair B
Energy Harbor Nuclear Corp
Goetz S
References
Download: ML23188A067 (1)


Text

July 10, 2023

Mr. Barry N. Blair Site Vice President Energy Harbor Nuclear Corp.

Beaver Valley Power Station Mail Stop P-BV-SSB P.O. Box 4, Route 168 Shippingport, PA 15077-0004

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - PROJECT MANAGER ASSIGNMENT

Dear Mr. Blair:

This letter is to inform you that effective July 7, 2023, Dr. V. Sreenivas will be assigned

as the U.S. Nuclear Regulatory Commissions Licensing Project Manager for Beaver Valley

Power Station, Units 1 and 2. Dr. V. Sreenivas may be reached at 301-415-2597 or by e-mail at

V.Sreenivas@nrc.gov.

Sincerely,

/RA/

Hipólito J. González, Chief Plant Licensing Branch LPL1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Docket Nos. 50-334 and 50-412

cc: Listserv

ML23188A067 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NAME VSreenivas KZeleznock HGonzalez DATE 07/06/2023 07/07/2023 7/10/2023