In Reply Refer To: | |||
Docket: | |||
50-298/86-26 | |||
Nebraska Public Power District | |||
ATTN: | |||
J. M. Pilant, Manager, Technical | |||
Staff-Nuclear Power Group | |||
P. O. Box 499 | |||
i | Columbus, NE | ||
l | 68601 | ||
Gentlemen: | |||
l~ | This refers to the inspection conducted by Messrs. D. DuBois, E. Plettner, and | ||
i | |||
P. Harrell of this office during the period September 1-30, 1986, of activities | |||
l | |||
authorized by NRC Operating License DPR-46 for Cooper Nuclear Station and to | |||
the discussion of our findings with Mr. G. Horn and other members of your staff | |||
l ~ | |||
at the conclusion of the inspection. | |||
, | , | ||
i | i | ||
j | Areas examined during the inspection included Notification of an Unusual Event, | ||
j | |||
Licensee Event Reports, spent fuel shipment, operational safety verification, | |||
' | ' | ||
monthly. surveillance and maintenance activities, systematic assessment of | |||
l | l | ||
j | licensee performance, and annual emergency preparedness exercise. | ||
l | Within | ||
i | j | ||
j | these areas, the inspection consisted of selective examination of procedures | ||
l | |||
and representative records, interviews with personnel, and observations by the | |||
i | |||
NRC inspectors. | |||
The inspection findings are documented in the enclosed | |||
j | |||
inspection report. | |||
; | ; | ||
1 | 1 | ||
! | During this inspection, it was found that certain of your activities were in | ||
i | ! | ||
i | violation of NRC requirements. | ||
! | Consequently, you are required to respond to | ||
i | |||
this violation, in writing, in accordance with the provisions of Section 2.201 | |||
i | |||
of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal | |||
! | |||
Regulations. | |||
Your response should be based on the specifics contained in the | |||
Notice of Violation enclosed with this letter. | |||
I | I | ||
! | ! | ||
{ | The response directed by this letter and the accompanying Notice is not subject | ||
{ | |||
to the clearance procedures of the Office of Management and Budget as required | |||
; | ; | ||
by the Paperwork Reduction Act of 1980, PL 96-511. | |||
l | |||
1 | |||
Should you have any questions concerning this inspection, we will be pleased to | |||
l | |||
discuss them with you. | |||
l | |||
Sincerely, | |||
I | |||
. | |||
j | |||
j | |||
OMne! Send Gy , | |||
j | |||
E R v;nnen | |||
> | |||
l | l | ||
J. E. Gagliardo Chief | |||
j | j | ||
Reactor Projects Branch | |||
Enclosures: | |||
(see next page) | |||
8 | |||
/, | |||
- | |||
! | ! | ||
i | > | ||
') | |||
h | |||
L | |||
i | |||
D | |||
' | |||
' | |||
i | |||
RIV: RI; | |||
RIV:SR | |||
I SRI | |||
R B/A | |||
RPB/ | |||
RPB @ | |||
/ | |||
' | |||
l ardo | |||
/ | |||
l | |||
v fAPlettner/sn | |||
PHHarre | |||
LD'uBois | |||
J Jaudon | |||
DRHu er | |||
JEGag/86 | |||
; | |||
p///86 | |||
g/p(/86 | |||
\\0/)IY/86 | |||
p /;M/86 | |||
IM 86 | |||
' | |||
p/tt | |||
I | I | ||
8611030188 861024 | |||
i | i | ||
i | i | ||
hDR | |||
ADOCK 05000298 | |||
' | |||
PDR | |||
t | t | ||
< - , - , - | |||
- - . . . | |||
-m.,n,,_,.,__,,.n____,_ | |||
_ . _ , | |||
- | |||
_ _ _ . | |||
. . , , , . _ | |||
n,_ | |||
- | |||
' | |||
t | |||
i | |||
Nebraska Public Power District | |||
-2- | |||
Enclosures: | |||
1. | |||
Appendix A - Notice of Violation | |||
2. | |||
Appendix B - NRC Inspection Report | |||
50-298/86-26 | |||
cc w/ enclosures: | |||
Guy R. Horn, Division Manager | |||
of Nuclear Operations | |||
Cooper Nuclear Station | |||
P. O. Box 98 | |||
Brownville, Nebraska | |||
68321 | |||
Kansas Radiation Control Program Director | |||
' Nebraska Radiation Control Program Director | |||
bcc-to DMB (IE01) | |||
bec distrib. by RIV: | |||
, | |||
*RPB | |||
DRSP | |||
* Resident Inspector | |||
R. D. Martin, RA | |||
*Section Chief (RPB/A) | |||
*D. Weiss, LFMB (AR-2015) | |||
*E&SPB | |||
*RSB | |||
* MIS System | |||
*RIV File | |||
*RSTS Operator | |||
*P. H. Harrell, RPB/B | |||
l | |||
*w/766 | |||
, | |||
I | I | ||
i | i | ||
Latest revision as of 21:27, 3 December 2024
| ML20215M711 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 10/24/1986 |
| From: | Gagliardo J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Pilant J NEBRASKA PUBLIC POWER DISTRICT |
| Shared Package | |
| ML20215M712 | List: |
| References | |
| NUDOCS 8611030188 | |
| Download: ML20215M711 (2) | |
See also: IR 05000298/1986026
Text
_ _ _ _ _ _ _ _ _ _ _ _ _
.
.
In Reply Refer To:
Docket:
50-298/86-26
Nebraska Public Power District
ATTN:
J. M. Pilant, Manager, Technical
Staff-Nuclear Power Group
P. O. Box 499
Columbus, NE
68601
Gentlemen:
This refers to the inspection conducted by Messrs. D. DuBois, E. Plettner, and
i
P. Harrell of this office during the period September 1-30, 1986, of activities
l
authorized by NRC Operating License DPR-46 for Cooper Nuclear Station and to
the discussion of our findings with Mr. G. Horn and other members of your staff
l ~
at the conclusion of the inspection.
,
i
Areas examined during the inspection included Notification of an Unusual Event,
j
Licensee Event Reports, spent fuel shipment, operational safety verification,
'
monthly. surveillance and maintenance activities, systematic assessment of
l
licensee performance, and annual emergency preparedness exercise.
Within
j
these areas, the inspection consisted of selective examination of procedures
l
and representative records, interviews with personnel, and observations by the
i
NRC inspectors.
The inspection findings are documented in the enclosed
j
inspection report.
1
During this inspection, it was found that certain of your activities were in
!
violation of NRC requirements.
Consequently, you are required to respond to
i
this violation, in writing, in accordance with the provisions of Section 2.201
i
of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal
!
Regulations.
Your response should be based on the specifics contained in the
Notice of Violation enclosed with this letter.
I
!
The response directed by this letter and the accompanying Notice is not subject
{
to the clearance procedures of the Office of Management and Budget as required
by the Paperwork Reduction Act of 1980, PL 96-511.
l
1
Should you have any questions concerning this inspection, we will be pleased to
l
discuss them with you.
l
Sincerely,
I
.
j
j
OMne! Send Gy ,
j
E R v;nnen
>
l
J. E. Gagliardo Chief
j
Reactor Projects Branch
Enclosures:
(see next page)
8
/,
-
!
>
')
h
L
i
D
'
'
i
RIV: RI;
RIV:SR
I SRI
R B/A
RPB/
RPB @
/
'
l ardo
/
l
v fAPlettner/sn
PHHarre
LD'uBois
J Jaudon
DRHu er
JEGag/86
p///86
g/p(/86
\\0/)IY/86
p /;M/86
IM 86
'
p/tt
I
8611030188 861024
i
i
hDR
ADOCK 05000298
'
t
< - , - , -
- - . . .
-m.,n,,_,.,__,,.n____,_
_ . _ ,
-
_ _ _ .
. . , , , . _
n,_
-
'
t
i
Nebraska Public Power District
-2-
Enclosures:
1.
Appendix A - Notice of Violation
2.
Appendix B - NRC Inspection Report
50-298/86-26
cc w/ enclosures:
Guy R. Horn, Division Manager
of Nuclear Operations
Cooper Nuclear Station
P. O. Box 98
Brownville, Nebraska
68321
Kansas Radiation Control Program Director
' Nebraska Radiation Control Program Director
bcc-to DMB (IE01)
bec distrib. by RIV:
,
- RPB
DRSP
- Resident Inspector
R. D. Martin, RA
- Section Chief (RPB/A)
- D. Weiss, LFMB (AR-2015)
- E&SPB
- RSB
- MIS System
- RIV File
- RSTS Operator
- P. H. Harrell, RPB/B
l
- w/766
,
I
i
!
I