MONTHYEARML20211D1321999-08-20020 August 1999 Application for Amend to License DPR-50 to Revise TS Bases Re Degraded Undervoltage Relay Setpoint Calibration Frequency & Degraded Voltage Relay Tolerance Rev ML20210J0941999-07-29029 July 1999 Suppl TS Change Request 274 to License DPR-50,revising ESF Sys Leakage Limits in post-accident Recirculation Surveillance Tss,As Result of NRC Generic Concerns Re CR Habitability Issues ML20196K5901999-06-29029 June 1999 LAR 285 for License DPR-50,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matls Can Continue to Be Moved ML20209C0551999-06-29029 June 1999 LAR 77 for License DPR-73,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matl May Continue to Be Moved ML20195E3341999-06-0404 June 1999 TS Change Request 265 to License DPR-50,modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions ML20209B5891999-05-26026 May 1999 LAR 281 to License DPR-50,revising TMI-1 UFSAR Chapters 5 & 14 to Permit Use of Conservative Deterministic Failure Margin Methodology for Seismic Analysis of Portions of Auxiliary Steam Line.Rept 240046-R-001 Encl.Rept Withheld ML20206R1111999-05-13013 May 1999 Application for Amend to License DPR-50,requesting That License Sections 2.a.(3) & 2.c.(7) & TS Section 3.1.1 Be Revised to Incorporate Administrative Updating & Changes to Bases Statement ML20205H0691999-04-0101 April 1999 TS Change Request 262 to License DPR-50,revising TS by Adding LCO Action Statements & Making SRs More Consistent with NUREG-1430,correcting Conflicts or Inconsistencies Caused by Earlier TS Revs & Revising SFP Sampling ML20203B0421999-02-0202 February 1999 TS Change Request 274 to License DPR-50,expanding Scope of Systems & Test Requirements for post-accident RB Sump Recirculation ESF Systems & Increasing Max Allowable Leakage of TS 4.5.4 for Applicable Portions of ESF Systems ML20196G4401998-12-0303 December 1998 LAR 278 to License DPR-50,requesting Consent to Transfer & Authorize Amergen to Possess,Use & Operate TMI-1 Under Essentially Same Conditions & Authorizations Included in Existing License.Supporting Documentation,Encl ML20196H9751998-12-0303 December 1998 LAR 279 to License DPR-50,reflecting Decrease in RCS Flow Resulting from Revised Analysis to Allow Operation of Plant with 20% Average Level of SG Tubes Plugged Per SG ML20196G7671998-11-25025 November 1998 TS Change Request 277 to License DPR-50,changing Surveillance Specs for OTSG ISIs for TMI-1 Cycle 13 RFO Exams Which Would Be Applicable for One Cycle of Operation Only ML20154Q6201998-10-19019 October 1998 TS Change Request 248 to License DPR-50,adding Operability & SRs for Remote Shutdown Sys Similar to Requirements in NUREG-1430, Std Tech Specs - B&W Plants, Section 3.3.18, Remote Shutdown Sys ML20154P8441998-10-19019 October 1998 Application for Amend to License DPR-50,providing Allowable RCS Specific Activity Limit Based on OTSG Insp Results Performed Each Refueling Outage.Proprietary & non- Proprietary Calculation,Encl.Proprietary Info Withheld ML20154M3691998-10-15015 October 1998 Application for Amend to License Amend Request 276 to License DPR-50 Revising UFSAR Chapter 14 Accident Analysis Atmospheric Dispersion Factors.Ufsar Revised Pages Encl ML20249B2391998-06-11011 June 1998 TS Change Request 273 to License DPR-50,incorporating Alternate High Radiation Area Control Consistent W/Reg Guide 8.38 ML20217E5131998-03-23023 March 1998 Application for Amend to License DPR-50,revising TS Section 3.1.2 to Incorporate New Pressure Limits for Reactor Vessel IAW 10CFR50,App G for Period of Applicability Through 17.7 Efpy.Request Also Submitted in Response to NRC ML20217G0161997-10-0303 October 1997 Suppl to License Amend Request 268 to License DPR-50, Replacing Pages 4-80 & 4-81 Previously Submitted w/TMI-1 License Amend Request 268 on 970812 ML20211C3211997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re License Amend Request 269 Submitted on 970814.Suppl Includes Addl Change to TS Section 3.1.4 & Proposed Page Rev Clarifying That UFSAR Analysis Is More Conservative ML20211C2221997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re TS Change Request 266.Supplement Provides for Phased Review & Issuance of License Amends & Involves Administrative Correction to TS Decay Heat Removal Sys Leakage Rate ML20210J9951997-08-14014 August 1997 Revised License Amend Request 269 for License DPR-50, Revising TMI-1 UFSAR Section 14.1.2.9 Environ Dose Consequences for TMI-1 Steam Line Break Analysis ML20141J3981997-08-12012 August 1997 Tech Spec Change Request 268 for License DPR-50,revising Surveillance Specification for Once Through Steam Generator Inservice Insp for TMI-1 Cycle 12 Refueling (12R) Exams Applicable to TMI-1 Cycle 12 Operations ML20198E7871997-07-30030 July 1997 TS Change Request 266 to License DPR-50,incorporating Addl Sys Leakage Limits & Leak Test Requirements for Systems Outside Containment Which Were Not Previously Contained in TS 4.5.4 ML20141E1311997-05-0808 May 1997 Application for Amend to License DPR-50,consisting of Change Request 264,incorporating Addl NRC-approved Analytical Methods Used to Determine TMI-1 Core Operating Limits ML20140E2351997-04-21021 April 1997 Application for Amend to License DPR-50,requesting Rev to TS 3.3 Re Emergency Core Cooling,Reactor Bldg Emergency Cooling & Reactor Bldg Spray Systems ML20134M1111997-02-0707 February 1997 Application for Amend to License DPR-50,incorporating Certain Improvements from Revised STS for B&W Plants, NUREG-1430 & Addl Changes as Described in Encl TS ML20133D2651996-12-24024 December 1996 Application for Amend to License DPR-50,requesting Reinstatement of Auxiliary & Fuel Handling Bldg Ventilation Sys TS ML20132F3221996-12-16016 December 1996 Application for Amend to License DPR-50,consisting of Change Request 260,reflecting Change in Legal Name of Operator of Plant from Gpu Corp to Gpu Inc & Reflecting Plant License & TS Registered Trade Name of Gpu Energy ML20135C5201996-12-0202 December 1996 TS Change Request (Tscr) 75 to License DPR-73,relocating Audit Frequency Requirements to Pdms QA Plan ML20117H0181996-08-29029 August 1996 Application for Amend to License DPR-50,consisting of TS Change Request 257,incorporating Certain Improvements from STS for B&W Plants (NUREG-1430) ML20113D1901996-06-28028 June 1996 Application for Amend to License DPR-50,consisting of Change Request 259,allowing Implementation of Recently Approved Option B to 10CFR50,App J ML20112C8751996-05-24024 May 1996 Errata to Application for Amend to License DPR-50,consisting of TS Change Request 243,replacing Pages for App a ML20101R1361996-04-10010 April 1996 Application for Amend to License DPR-50,consisting of Change Request 243,revising Addl Group of Surveillances in Which Justification Has Been Completed Following Receipt of 930623 Application ML20100J6831996-02-22022 February 1996 Application for Amend to License DPR-50,consisting of Change Request 254,revising Proposed TS Page 4-46 on Paragraph 4.6.2 That Provides Addl Testing Requirements in Case Station Battery Cell Parameters Not Met ML20095J2261995-12-21021 December 1995 Revised TS Change Request 254,raising Low Voltage Action Level to 105 Volts DC ML20091L2831995-08-23023 August 1995 Rev to TS Change Request 223 to License DPR-50,incorporating Ref to 10CFR20.1302 ML20087F4881995-08-11011 August 1995 Rev to TS Change Request 252 to License DPR-50,removing TS Section 3.2 Re Makeup,Purification & Chemical Addition Sys Requirements.Certificate of Svc Encl ML20086R3001995-07-24024 July 1995 Rev to LAR 250 to License DPR-50,clarifying Section III, SE Justifying Change for source-range Nuclear Instrumentation SRs ML20085N1551995-06-22022 June 1995 TS Change Request 227 to License DPR-50,replacing Pages for App A.Certificate of Svc Encl ML20084N3461995-06-0101 June 1995 TS Change Request 223 to License DPR-50,deleting Remaining Portions of RETS & Relocating TSs Per Guidance in GL 89-01 & NUREG-1430 ML20084L4201995-06-0101 June 1995 TS Change Request 251 to DPR-50,revising TS 5.3.1.1 to Describe Use of Advanced Clad Assemblies ML20084B3261995-05-24024 May 1995 Application for Amend to License DPR-50.Amend Would Change Surveillance Test Requirements for source-range Nuclear Instrumentation ML20083N7771995-05-17017 May 1995 Application for Amend to License DPR-50,consisting of Change Request 252,removing Chemical Addition Sys Requirements from TS to COLR ML20079A7771994-12-23023 December 1994 Rev to TS Change Request 221 to License DPR-50,revising TS Page 3-32a ML20073F9241994-09-26026 September 1994 LAR 246 to License DPR-50,revising License Condition 2.C.9 Re Long Range Planning Program ML20069A6731994-05-20020 May 1994 TS Change Request 244 to License DPR-50,requesting Revised CR Trip Insertion Time Testing Acceptance Criterion for Remainder of Cycle 10 for 12 Specific CRs Which Initially Experienced Slow Rod Drop Times During Testing on 940317 ML20065M6681994-04-19019 April 1994 TS Change Request 237 to License DPR-50,deleting Audit Program Frequency Requirements from TS & Relocating Subj Requirements to Operational QA Plan ML20065K0381994-04-11011 April 1994 TS Change Request 238 to License DPR-50,relocating Detailed Insp Criteria,Methods & Frequencies of Containment Tendon Surveillance Program to FSAR ML20073C7701994-03-22022 March 1994 Application for Amend to License DPR-50 Re TS Change Request 242 Concerning Control Rod Trip Insertion Time Testing ML20064J3771994-03-11011 March 1994 Application for Amend to License DPR-50,revising TS Re Allowable Outage Time for Emergency Feedwater Pumps During Surveillance Activities 1999-08-20
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20211D1321999-08-20020 August 1999 Application for Amend to License DPR-50 to Revise TS Bases Re Degraded Undervoltage Relay Setpoint Calibration Frequency & Degraded Voltage Relay Tolerance Rev ML20210J0941999-07-29029 July 1999 Suppl TS Change Request 274 to License DPR-50,revising ESF Sys Leakage Limits in post-accident Recirculation Surveillance Tss,As Result of NRC Generic Concerns Re CR Habitability Issues ML20209D6651999-07-0808 July 1999 Corrected TS Pages 3-21,4-5a,4-9,4-38 & 6-3 to Amends 211 & 212 to License DPR-50.Pages Failed to Reflect Previously Approved Changes Granted in Amends 203 & 204 in Case of Amend 211 & 207 in Case of Amend 212 ML20196K5901999-06-29029 June 1999 LAR 285 for License DPR-50,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matls Can Continue to Be Moved ML20209C0551999-06-29029 June 1999 LAR 77 for License DPR-73,clarifying Authority in Encl License Pages to Possess Radioactive Matls Without Unit Distinction,So That After Transfer of TMI-1 License to Amergen,Radioactive Matl May Continue to Be Moved ML20195E3341999-06-0404 June 1999 TS Change Request 265 to License DPR-50,modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions ML20209B5891999-05-26026 May 1999 LAR 281 to License DPR-50,revising TMI-1 UFSAR Chapters 5 & 14 to Permit Use of Conservative Deterministic Failure Margin Methodology for Seismic Analysis of Portions of Auxiliary Steam Line.Rept 240046-R-001 Encl.Rept Withheld ML20206R1111999-05-13013 May 1999 Application for Amend to License DPR-50,requesting That License Sections 2.a.(3) & 2.c.(7) & TS Section 3.1.1 Be Revised to Incorporate Administrative Updating & Changes to Bases Statement ML20205H0691999-04-0101 April 1999 TS Change Request 262 to License DPR-50,revising TS by Adding LCO Action Statements & Making SRs More Consistent with NUREG-1430,correcting Conflicts or Inconsistencies Caused by Earlier TS Revs & Revising SFP Sampling ML20203B0421999-02-0202 February 1999 TS Change Request 274 to License DPR-50,expanding Scope of Systems & Test Requirements for post-accident RB Sump Recirculation ESF Systems & Increasing Max Allowable Leakage of TS 4.5.4 for Applicable Portions of ESF Systems ML20196H9751998-12-0303 December 1998 LAR 279 to License DPR-50,reflecting Decrease in RCS Flow Resulting from Revised Analysis to Allow Operation of Plant with 20% Average Level of SG Tubes Plugged Per SG ML20196G4401998-12-0303 December 1998 LAR 278 to License DPR-50,requesting Consent to Transfer & Authorize Amergen to Possess,Use & Operate TMI-1 Under Essentially Same Conditions & Authorizations Included in Existing License.Supporting Documentation,Encl ML20196G7671998-11-25025 November 1998 TS Change Request 277 to License DPR-50,changing Surveillance Specs for OTSG ISIs for TMI-1 Cycle 13 RFO Exams Which Would Be Applicable for One Cycle of Operation Only ML20195C6811998-11-12012 November 1998 Amend 52 to License DPR-73,relocating Audit Frequency Requirements from TMI-2 to TMI-2 Post Defueling Monitored Storage QA Plan & Extends Max Allowed Interval Between Certain Audits from 12 Months to 24 Months ML20154P8441998-10-19019 October 1998 Application for Amend to License DPR-50,providing Allowable RCS Specific Activity Limit Based on OTSG Insp Results Performed Each Refueling Outage.Proprietary & non- Proprietary Calculation,Encl.Proprietary Info Withheld ML20154Q6201998-10-19019 October 1998 TS Change Request 248 to License DPR-50,adding Operability & SRs for Remote Shutdown Sys Similar to Requirements in NUREG-1430, Std Tech Specs - B&W Plants, Section 3.3.18, Remote Shutdown Sys ML20154M3691998-10-15015 October 1998 Application for Amend to License Amend Request 276 to License DPR-50 Revising UFSAR Chapter 14 Accident Analysis Atmospheric Dispersion Factors.Ufsar Revised Pages Encl ML20249B2391998-06-11011 June 1998 TS Change Request 273 to License DPR-50,incorporating Alternate High Radiation Area Control Consistent W/Reg Guide 8.38 ML20217E5131998-03-23023 March 1998 Application for Amend to License DPR-50,revising TS Section 3.1.2 to Incorporate New Pressure Limits for Reactor Vessel IAW 10CFR50,App G for Period of Applicability Through 17.7 Efpy.Request Also Submitted in Response to NRC ML20217G0161997-10-0303 October 1997 Suppl to License Amend Request 268 to License DPR-50, Replacing Pages 4-80 & 4-81 Previously Submitted w/TMI-1 License Amend Request 268 on 970812 ML20211C2221997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re TS Change Request 266.Supplement Provides for Phased Review & Issuance of License Amends & Involves Administrative Correction to TS Decay Heat Removal Sys Leakage Rate ML20211C3211997-09-19019 September 1997 Supplemental Application for Amend to License DPR-50 Re License Amend Request 269 Submitted on 970814.Suppl Includes Addl Change to TS Section 3.1.4 & Proposed Page Rev Clarifying That UFSAR Analysis Is More Conservative ML20210J9951997-08-14014 August 1997 Revised License Amend Request 269 for License DPR-50, Revising TMI-1 UFSAR Section 14.1.2.9 Environ Dose Consequences for TMI-1 Steam Line Break Analysis ML20141J3981997-08-12012 August 1997 Tech Spec Change Request 268 for License DPR-50,revising Surveillance Specification for Once Through Steam Generator Inservice Insp for TMI-1 Cycle 12 Refueling (12R) Exams Applicable to TMI-1 Cycle 12 Operations ML20198E7871997-07-30030 July 1997 TS Change Request 266 to License DPR-50,incorporating Addl Sys Leakage Limits & Leak Test Requirements for Systems Outside Containment Which Were Not Previously Contained in TS 4.5.4 ML20141E1311997-05-0808 May 1997 Application for Amend to License DPR-50,consisting of Change Request 264,incorporating Addl NRC-approved Analytical Methods Used to Determine TMI-1 Core Operating Limits ML20140E2351997-04-21021 April 1997 Application for Amend to License DPR-50,requesting Rev to TS 3.3 Re Emergency Core Cooling,Reactor Bldg Emergency Cooling & Reactor Bldg Spray Systems ML20134M1111997-02-0707 February 1997 Application for Amend to License DPR-50,incorporating Certain Improvements from Revised STS for B&W Plants, NUREG-1430 & Addl Changes as Described in Encl TS ML20133D2651996-12-24024 December 1996 Application for Amend to License DPR-50,requesting Reinstatement of Auxiliary & Fuel Handling Bldg Ventilation Sys TS ML20132F3221996-12-16016 December 1996 Application for Amend to License DPR-50,consisting of Change Request 260,reflecting Change in Legal Name of Operator of Plant from Gpu Corp to Gpu Inc & Reflecting Plant License & TS Registered Trade Name of Gpu Energy ML20135C5201996-12-0202 December 1996 TS Change Request (Tscr) 75 to License DPR-73,relocating Audit Frequency Requirements to Pdms QA Plan ML20134D7761996-10-24024 October 1996 Amend 51 to License DPR-73,revising TS to Extend Surveillance Interval for Demonstrating Operability of Containment Airlock ML20128K1831996-10-0808 October 1996 Amend 50 to License DPR-73,revising TS to Incorporate Improvement from Administrative Controls Section of Revised STS for B&W Plants ML20117H0181996-08-29029 August 1996 Application for Amend to License DPR-50,consisting of TS Change Request 257,incorporating Certain Improvements from STS for B&W Plants (NUREG-1430) ML20113D1901996-06-28028 June 1996 Application for Amend to License DPR-50,consisting of Change Request 259,allowing Implementation of Recently Approved Option B to 10CFR50,App J ML20112C8751996-05-24024 May 1996 Errata to Application for Amend to License DPR-50,consisting of TS Change Request 243,replacing Pages for App a ML20101R1361996-04-10010 April 1996 Application for Amend to License DPR-50,consisting of Change Request 243,revising Addl Group of Surveillances in Which Justification Has Been Completed Following Receipt of 930623 Application ML20100J6831996-02-22022 February 1996 Application for Amend to License DPR-50,consisting of Change Request 254,revising Proposed TS Page 4-46 on Paragraph 4.6.2 That Provides Addl Testing Requirements in Case Station Battery Cell Parameters Not Met ML20095J2261995-12-21021 December 1995 Revised TS Change Request 254,raising Low Voltage Action Level to 105 Volts DC ML20091L2831995-08-23023 August 1995 Rev to TS Change Request 223 to License DPR-50,incorporating Ref to 10CFR20.1302 ML20087F4881995-08-11011 August 1995 Rev to TS Change Request 252 to License DPR-50,removing TS Section 3.2 Re Makeup,Purification & Chemical Addition Sys Requirements.Certificate of Svc Encl ML20086R3001995-07-24024 July 1995 Rev to LAR 250 to License DPR-50,clarifying Section III, SE Justifying Change for source-range Nuclear Instrumentation SRs ML20085N1551995-06-22022 June 1995 TS Change Request 227 to License DPR-50,replacing Pages for App A.Certificate of Svc Encl ML20084N3461995-06-0101 June 1995 TS Change Request 223 to License DPR-50,deleting Remaining Portions of RETS & Relocating TSs Per Guidance in GL 89-01 & NUREG-1430 ML20084L4201995-06-0101 June 1995 TS Change Request 251 to DPR-50,revising TS 5.3.1.1 to Describe Use of Advanced Clad Assemblies ML20084B3261995-05-24024 May 1995 Application for Amend to License DPR-50.Amend Would Change Surveillance Test Requirements for source-range Nuclear Instrumentation ML20083N7771995-05-17017 May 1995 Application for Amend to License DPR-50,consisting of Change Request 252,removing Chemical Addition Sys Requirements from TS to COLR ML20079A7771994-12-23023 December 1994 Rev to TS Change Request 221 to License DPR-50,revising TS Page 3-32a ML20073F9241994-09-26026 September 1994 LAR 246 to License DPR-50,revising License Condition 2.C.9 Re Long Range Planning Program ML20069A6731994-05-20020 May 1994 TS Change Request 244 to License DPR-50,requesting Revised CR Trip Insertion Time Testing Acceptance Criterion for Remainder of Cycle 10 for 12 Specific CRs Which Initially Experienced Slow Rod Drop Times During Testing on 940317 1999-08-20
[Table view] |
Text
., .
METROPOLITAN EDISDN COMPANY JERSEY CENTRAL POWER & LIGHT COMPANY i
AND i PENNSYLVANIA ELECTRIC COMPANY l
THREE MILE ISLAND NUCLEAR STATION; UNIT 1 i
l Operating License No. DPR-50 Docket No. 50-289 .j Technical Specification Change Request No. 197 l l
l This Technical Specification Change Request is submitted in support of Licensee's i request to change Appendix A to Operating License No. DPR-50 for Three Mile Island Nuclear Station, Unit 1. As a part of this request, proposed replacement pages for Appendix A are also included, i GPU NUCLEAR CORPORATION !
. BY: \ -
Vice Presi' dent & Director, TMI-1 Sworn and subscribed
, to before me this 80 {
8 day of ham I, ,1990.
(/ 4 i
, kwL b L4W7G '
/~ Notary Public ShamnP Drown, atryPsic M JW1 i
-Mwitxt,PorymAmin Assoassonof Notwese ;
l n
P +
Y
. UNITED STATES OF AMERICA I l
NUCLEAR REGULATORY C0!HISSION l
IN THE MATTER OF DOCKET NO 50-2B9 !
GPU NUCLEAR CORPORATION LICENSE NO. DPR-50 l
I CERTIFICATE OF SERVICE This is to certify that a copy of Technical Specification Change Request No. 197 ;
to Appendix A of the Operating License for Three Mile Island Nuclear Station Unit 1, has,.on the date given below, been filed with executives of Londonderry Township, Dauphin County, Pennsylvania; Dauphin County, Pennsylvania; and the i Pennsylvania Department of Environmental Resources, Bureau of Radiation ?
Protection, by deposit in the United States mail, addressed as follows:
i Mr. Kenneth E. Witmer, Chairman Ms. Sally S. Klein, Chairman Board of Supervisors of Board of County Commissioners :
Londonderry Township of Dauphin County :
25 Roslyn Road Dauphin County Courthouse Elizabethtown, PA 17022 Harrisburg, PA 17120 ,
i Mr. Thomas Gerusky, Director ,
PA. Dept. of Environmental Resources -
Bureau of Radiation Protection >
P.O. Box 2063 Harrisburg, PA 17120 GPU NUCLEAR CORPORAT.10
, BY: !
Vice President & Director, TMI-1 DATE: January 8, 1990 l
o I' !
L
f ,
I. TECHNICAL SPECIFICATVON CHANGE REOUEST (TSCR) NO. 197 GPUN requests that the foll> wing changed replacement pages be inserted into the existing Technical Specifications:
Revised pages: 1, 1-7, and 1-8 These pages are attached to this change request.
II. REASON FOR CHANGE This change is requested to modify the THI-1 Technical Specifications to remove the 3.25 limit on extending surveillance intervals and to add the Bases for the existing 25% allowance, in accordance with the guidance contained in NRC Generic Letter 89-14, dated August 21, 1989. This change incorporates a line-item improvement in Technical Specifications by removing an unnecessary restriction on extending surveillance requirements and provides a benefit to safety when plant conditions are not conducive to the safe conduct of surveillance requirements.
This change also modifies the THI-1 Technical Specification to be consistent with Standard Technical Specifications by including FREQUENCY NOTATION as a Technical Specification definition. Associated with this modification, the existing Technical Specification provision allowing survalliance interval extensions of a maximum of 25% is relocated from the existing Technical Specification Table 1.2 to the new FREQUENCY NOTATION definition, since this extension is currently applicable to all surveillance intervals specified within the Technical Specification.
III. SAFETY EVALUATION JUSTIFYING CHANGE THI-1 Technical Specification Table 1.2, Footnote "B", which currently specifies that a total maximum combined interval time for any three consecutive tests is not to exceed 3.25 times the specified surveillance interval, is removed, and the Bases for the existing 25% allowance is added in accordance with guidance contained in NRC Generic Letter 89-14.
The existing Table 1.2 Footnote "A",-which is being relocated to the new FREQUENCY NOTATION definition, permits a maximum allowable extension of 25% of all normal surveillance intervals to facilitate surveillance scheduling and consideration of plant operating conditions that may not be suitable for conducting the surveillance (e.g. transient conditions, or other ongoing surveillance or maintenance activities).- It also provides flexibility to accommodate the length of a fuel cycle for surveillances that are performed at each refueling outage and are specified with a fuel cycle length surveillance interval. It is not intended that this provision be used repeatedly as a convenience to extend surveillance intervals beyond that specified for surveillances that are not performed during refueling outages.
311-89C I
i
- The ute of the allowance to extend surveillance intervals by 25% provides a safety benefit when a surveillance interval is extended at a time that conditions are not suitable for performing the surveillance. Examples include transient plant operating conditions or conditions in which safety systems are out of service because of ongoing surveillance or maintenance activities. The safety benefit of allowing the use of the 25% allowance to extend a surveillance interval in such cassa outweighs any benefit derived by limiting three consecutive surveillance intervals to the 3.25 limit. Therefore, there is an overall positive effect on safety.
The administrative burden of tracking the use of the 25% allowance to ensure compliance with the 3.25 limit is also eliminated. ,
Addition of Technical Specification 1.25 FREQUENCY NOTATION is an f administrative change to be consistent with the Standard Technical Specification in this area. Relocation of the existing Footnote "A" on Table 1.2 is also an administrative change to clarify that the maximum surveillance interval extension of 25% is applicable to all surveillance ;
intervals specified within Technical Specifications and is not limited to surveillance intervals designated by the FREQUENCY NOTATION of Table 1.2.
IV. HO SIGNIFICANT HAEARDS CONSIDERATIONS ,
CPUN has determined that this Technical Specification Change Request involves no significant hazards consideration as defined by NRC in :
10 CFR 50.92,
- 1. Operation of the facility in accordance with the proposed amendment would not involve a significant increase in the probability of '
occurrence or the consequences of an accident previously evaluated.
The proposed amendment removes the 3.25 limit on extending surveillance intervals and adds the Bases statements for the existing 25% allowance, in accordance with the guidance contained in NRC Generic Letter 89-14. . Removal of the 3.25 limit on extending surveillance intervals provides a safety benefit by allowing a surveillance interval to be extended at a time that conditions are I not suitable for performing the surveillance (e.g.. transient plant operating conditions or other ongoing surveillance or maintenance i activities). The safety bencfit of allowing the use of the 25%
allowance to' extend a surveillance interval in such cases outweighs ,
any benefit derived by limiting three consecutive surveillance intervals to the 3.25 limit. This change does not involve any change i to the actual surveillance requiren.ents. The reliability ensured ;
through surveillance activities is not significantly degraded beyond
administrative change to achieve consistency with Standard Technical i specifications, and relocation of the existing provision to allow a ;
maximum surveillance interval extension of 25%, from Table 1.2 to the new definition only provides clarification that this extension is- '
applicable to all Technical Specifications surveillance requirements.
Therefore, this change does not increase this probability of l
occurrence or the consequences of an accident previously evaluated.
311-890
- 2. Operation of the f acility in accordance with the proposed amendnent !
would not create the possibility of a new or different kind of !
accident from any accident previously evaluated. This change does not involve any change to the actual surveillance requirements and i allows a surveillance interval to be extended at a time that ,
conditions are not suitable for performing the surveillance. ,
Therefore, this change has no effect on the possibility of creating a new or different kind of accident from any accident previously evaluated.
- 3. operation of the facility in accordance with the proposed amendment would not involve a significant reduction in a margin of safety.
Removal of the 3.25 limit on extending surveillance intervals provides a positive effect on safety by allowing a surveillance interval to be extended at a time that conditions are not suitable for performing the surveillance. The safety benefit of allowing the use of the 25% allowance to extend a surveillance interval in such cases outweighs any benefit derived by limiting three consecutive surveillance intervals to the 3.25 limit. This change does not involve any change to the actual surveillance requirements. The reliability ensured through surveillance activities is not significantly degraded beyond that obtained from'the specified surveillance interval. The addition of Technical Specification 1.25 FREQUENCY NOTATION is an administrative change to achieve consistency with Standard Technical Specifications, and relocation of the existing provision to allow a maximum surveillance interval. extension of 25%, from Table 1.2 to the new definition only provides.
clarification that this extension is applicable to all Technical Specifications surveillance requirements. Therefore, it is concluded that operation of the facility in accordance with the proposed amendment does not involve a significant reduction in a margin of safety.
The commission has provided guidelines pertaining to the application of the three standards by listing specific examples in 45 FR 14870. The proposed amendment is considered to be in the same category as example (1) of amendments that are considered not likely to involve significant hazards consideration in that the proposed change constitutes a purely administrative change to Technical Specifications. This change is similar in that~it '
implements the guidance contained in NRC Ceneric Letter 89-14 for removal of the 3.25 limit on extending surveillance intervals, provides additional consistency with Standard Technical Specifications and clarification of the applicability of the existing 25% allowance. Implementation of the proposed amendment in accordance with the generic letter guidance provides an overall positive effect on safety, eliminates the administrative burden of tracking the use of the 25% allowance to ensure compliance with 3.25 limit, and implements a line-item improvement in Technical Specifications. Thus, operation of the facility in accordance with the proposed amendment involves no significant hazards considerations.
V. IMPLEMENTATION It is requested that the amendment authorizing this change become effective upon issuance.