{{finding
{{finding
| title = Failure to Provide an Evaluation of a Change to the Facility AS Described in the Ufsar, Under 10 CFR 50.59 Requirements
| title = Failure to Provide an Evaluation of a Change to the Facility as Described in the UFSAR, Under 10 CFR 50.59 Requirements
| docket = 05000528, 05000529, 05000530
| docket = 05000528, 05000529, 05000530
| inspection report = IR 05000528/2004006
| inspection report = IR 05000528/2004006
Line 12: Line 12:
| identified by = NRC
| identified by = NRC
| Inspection procedure = IP 71152
| Inspection procedure = IP 71152
| Inspector = J Clarkr Mullikin, L Smith, J Melfi, G Miller,
| Inspector = J Clark, R Mullikin, L Smith, J Melfi, G Miller
| CCA = N/A for ROP
| CCA = N/A for ROP
| INPO aspect =  
| INPO aspect =  

Latest revision as of 22:03, 29 May 2018

02
Site: Palo Verde Arizona Public Service icon.png
Report IR 05000528/2004006 Section 4OA2
Date counted Jun 30, 2004 (2004Q2)
Type: TEV: Severity level IV
cornerstone Barrier Integrity
Identified by: NRC identified
Inspection Procedure: IP 71152
Inspectors (proximate) J Clark
R Mullikin
L Smith
J Melfi
G Miller
INPO aspect
'