RS-13-159, Response to Request for Additional - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
(One intermediate revision by the same user not shown)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:1
{{#Wiki_filter:Generat RS-13-159 Order No. EA-12-051 July 3, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
)
Generatti Order Order No.No. EA-12-051 EA-12-051 RS-13-159 RS-13-159 July  3,2013 July 3, 2013 Nuclear Regulatory U.S. Nuclear     Regulatory Commission Commission ATTN: Document Control Control Desk Desk Washington, DC   DC 20555-0001 20555-0001 Quad Cities Quad    Cities Nuclear Nuclear Power Power Station, Station, Units Units 11 and and 22 Renewed Facility Operating License Nos. DPR-29         DPR-29 and and DPR-30 DPR-30 NRC Docket Nos. 50-254 and 50-265       50-265 ResponsetotoRequest


==Subject:==
==Subject:==
Response           Request     forAdditional for   AdditionalInformation Information -- Overall Overall Integrated Plan in Response Response to Commission Order Order Modifying Modifying License Requirements Requirements for  for Reliable Reliable Spent SpentFuel FuelPool Pool Instrumentation (Order (Order No.No. EA-12-051)
Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)
EA-12-051)


==References:==
==References:==
1.
Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-1 2-051), dated February 28, 2013 (RS-13-035) 2.
NRC Order Number EA-1 2-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 3.
USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7, 2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the Quad Cities Nuclear Power Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).
The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the Quad Cities Nuclear Power Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to Quad Cities Nuclear Power Station, Units 1 and 2. This item is included and addressed in Enclosure 1 to this letter.
The Quad Cities Nuclear Power Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1.
The enclosed responses to the NRC request for additional information are intended not to provide preliminary or conceptual information. The requested information, when fully developed, will be
)
1 ti Order No. EA-12-051 RS-13-159 July 3,2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265


Exelon Generation Company, LLC
==Subject:==
: 1. Exelon                                          Letter to LLC Letter      to USNRC, USNRC, Overall OverallIntegrated Integrated PlanPlan inin Response
Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)


===Response===
==References:==
to March 12, 2012 Commission Order         Order Modifying        Licenses with Modifying Licenses       with Regard Regard to to Requirements for Reliable Spent Fuel for                    Fuel Pool Pool Instrumentation Instrumentation (Order(Order Number NumberEA-1        2-051), dated EA-12-051),       dated February February 28,2013    (RS-13-035) 28, 2013 (RS-13-035)
: 1. Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28,2013 (RS-13-035)
: 2. NRCNRC Order Number EA-1  EA-12-051, 2-051, Issuance Issuance ofof Order Order toto Modify Modify Licenses     with Regard Licenses with      Regardto  to Reliable Reliable Spent Fuel Pool Instrumentation, Instrumentation, dated dated March March 12, 12, 2012 2012
: 2. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012
: 3. USNRC letter to Exelon GenerationGeneration Company, Company,LLC,  LLC, Request Requestfor forAdditional Additional Information Information Regarding Overall Regarding   Overall Integrated Plan for ReliableReliable Spent Fuel Fuel Pool Pool Instrumentation, Instrumentation, dated dated June 7, 2013 In In Reference        Exelon Generation Reference 1, Exelon       Generation Company, Company, LLC                  provided the LLC (EGC) provided         the Quad Cities Nuclear Power Power Station, Station, Units Units 11 and and 2, 2, Overall Overall Integrated IntegratedPlan PlanininResponse Response to  to the the March March 12, 12, 2012 2012 Commission Order Order Modifying       Licenses with Modifying Licenses        with Regard to Requirements for        for Reliable Spent Spent Fuel Fuel Pool Pool Instrumentation,     pursuant Instrumentation, pursuant to    to NRC     Order Order   No.       051 EA-12-051 EA              (Reference     2).
: 3. USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7, 2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the Quad Cities Nuclear Power Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).
purpose of The purpose     of this letter is to provide the response responseto  tothe theNRC NRCrequest requestfor foradditional additionalinformation information (Reference 3) regarding the Quad   Quad Cities Cities Nuclear Nuclear Power Power Station, Station, Units Units 11 and and 22Overall Overall Integrated Integrated Plan Plan in in Response Response to  to the the Commission Commission Order OrderModifying Modifying Licenses with  with Regard to Requirements Requirements for    for Reliable Reliable Spent Spent Fuel Fuel Pool Pool Instrumentation Instrumentation (Order (Order No.No. EA-12-051).
The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the Quad Cities Nuclear Power Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to Quad Cities Nuclear Power Station, Units 1 and 2. This item is included and addressed in Enclosure 1 to this letter.
EA-12-051). Subsequent                issuanceof Subsequent to issuance           of Reference Reference 3, thethe NRC NRC identified identified that Request Requestfor  for Additional Additional Information Information ItemItem No.
The Quad Cities Nuclear Power Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1.
No. 6.a 6.a was also applicable applicable toto Quad Quad Cities Cities Nuclear Nuclear Power Power Station, Station, Units Units 11 and and 2. This item
The enclosed responses to the NRC request for additional information are intended not to provide preliminary or conceptual information. The requested information, when fully developed, will be  
: 2. This    item is included and addressed addressed in in Enclosure Enclosure 11to  to this this letter.
letter.
The Quad Cities Nuclear The                  Nuclear Power Power Station, Station, Units Units 11 and and 22 Spent Fuel Pool Instrumentation design is proceeding proceeding on the schedule schedule identified identified in in the Overall Integrated Plan Plan provided provided in in Reference Reference 1. 1.
The enclosed responses The              responsestotothe theNRCNRCrequest requestfor foradditional additional information information are intended intended not not toto provide provide preliminaryor preliminary     orconceptual conceptual information.
information. The requested requestedinformation, information, when when fully fully developed, developed, will  will be


U.S. Nuclear U.S. Nuclear Regulatory Commission Response to Response      to Request Request for Additional Information (Order  (Order EA-1     2-051)
U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-1 2-051)
EA-12-051)
July 3, 2013 Page 2 provided upon detailed design completion based on the milestone schedule dates provided in each response.
July 3,2013 July  3, 2013 Page 22 Page provided upon provided     upon detailed detailed design design completion completion based based on  on the the milestone schedule dates provided in      in each  response.
This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.
each response.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.
This letter This  letter contains contains nono new new regulatory regulatory commitments.
Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC
commitments. If        you have If you   have any questions questions regarding regarding this this response, please response,      please contact contact David David P.
P. Helker Helker at 610-765-5525.
IIdeclare declare under under penalty of of perjury perjury that that the the foregoing foregoing isis true true and and correct. Executed Executedon onthe  3rd day the3rd  day of  July  2013.
of July 2013.
Respectfully submitted, Respectfully
  ~~~
Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC Exelon                              LLC


==Enclosure:==
==Enclosure:==
: 1. Quad CitiesCities Nuclear Power Station, Station, Units Units 11 and and 22 -- Response ResponsetotoRequest RequestforforAdditional Additional Information --Overall Information      OverallIntegrated Integrated Plan Plan inin Response Response to    to Commission CommissionOrder OrderModifying Modifying License License Requirements for Requirements       for Reliable Reliable Spent SpentFuel FuelPool PoolInstrumentation Instrumentation(Order (OrderNo.
1.
No.EA-12-051)
Quad Cities Nuclear Power Station, Units 1 and 2 - Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:
EA-12-051) cc:     Director, Office of Nuclear Nuclear Reactor Reactor Regulation Regulation NRC Regional Administrator Administrator -- Region Region III III NRC NRC Senior Resident Inspector - Quad     QuadCitiesCities Nuclear Nuclear Power PowerStation, Station, Units Units 11 and and 22 NRC Project Manager, NRR - Quad     QuadCities Cities Nuclear NuclearPower PowerStation, Station,Units Units11and and22 Mr.
Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station, Units 1 and 2 NRC Project Manager, NRR - Quad Cities Nuclear Power Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-12-051)
Mr. Robert J. J. Fretz, Fretz,Jr, Jr,NRRIJLD/PMB, NRRIJLD/PMB, NRC    NRC Mr. Robert Robert L.L. Dennig, Dennig, NRRIDSS/SCVB, NRRIDSS/SCVB, NRC      NRC Mr. Blake Purnell, Purnell, NRC NRC Project Project Manager, Manager, NRR  NRR Illinois Emergency Management Illinois Emergency      Management Agency Agency--Division Division of of Nuclear Nuclear Safety Safety
July 3,2013 Page 2 provided upon detailed design completion based on the milestone schedule dates provided in each response.
This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.
Respectfully submitted,
~~~
Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC


Enclosure Enclosure 11 Quad Quad Cities Nuclear Nuclear Power Station, Station, Units 1 and 2 Response to Request for Additional Information Information Overall Integrated Plan in Response to Commission Order Modifying Overall License Requirements for Reliable Spent Fuel Pool Instrumentation License (Order No. EA-12-051)
==Enclosure:==
EA-12-0S1)
: 1. Quad Cities Nuclear Power Station, Units 1 and 2 - Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:
(11 (11 pages)
Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station, Units 1 and 2 NRC Project Manager, NRR - Quad Cities Nuclear Power Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety Quad Cities Nuclear Power Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)
(11 pages)
Quad Cities Nuclear Power Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-0S1)
(11 pages)  


Response to Response      to Request Request for  for Additional Information (Order EA-12-051)      EA-12-051)
Response to Request for Additional Information (Order EA-12-051)
Enclosure Page 1 of 11 Page          11 1.0
Page 1 of 11


==1.0       INTRODUCTION==
==1.0 INTRODUCTION==
By {{letter dated|date=February 28, 2013|text=letter dated February 28, 2013}} (Agency wide Documents Access and Management System (ADAMS) Accession No. ML13060A124), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12, 2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for Quad Cities Nuclear Power Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).
The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.
2.0 LEVELS OF REQUIRED MONITORING The OIP states, in part, that:
Level adequate to support operation of the normal fuel pool cooling system (L1):
For both units, indicated level on either primary or backup instrument channel must be greater than 23 feet 1 inch (elevation 689' 3") plus instrument accuracy above the top of the storage racks based on the design accuracy of the instrument channel (which is to be determined) and a resolution of 1 foot or better for both the primary and backup instrument channels. This is based on the 11 inch opening of the SFP weir gate design demonstrating a water level above 23 feet 1 inch (elevation 689'3") is adequate for normal fuel pool cooling system operation.
Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (L2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet (elevation 676' 2") plus instrument channel accuracy above the top of the storage racks based on specification of this level as adequate in NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3), the specified design accuracy of the instrument channel, and the relatively low sensitivity of dose rates to changes in water depth at this level.
This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored spent fuel.
Level where fuel remains covered (L3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 6662") plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.
Response to Request for Additional Information (Order EA-12-051)
Page 1 of 11


INTRODUCTION Byletter By   letterdated dated February February28,   28, 2013 2013 (Agency (Agencywide  wideDocuments DocumentsAccess  Access and  and Management Management System (ADAMS) Accession No. ML13060A124), Exelon Generation Company, LLC, submitted an (ADAMS)      Accession      No. ML13060A124),            Exelon    Generation        Company,        LLC, overall integrated overall   integrated plan  plan (OIP)
==1.0 INTRODUCTION==
(OIP) ininresponse response to the March 12,             2012, U.S.
By {{letter dated|date=February 28, 2013|text=letter dated February 28, 2013}} (Agency wide Documents Access and Management System (ADAMS) Accession No. ML13060A124), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12,2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for Quad Cities Nuclear Power Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).
12,2012,        U.S. Nuclear Nuclear Regulatory Regulatory Commission (NRC)
The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.
Commission        (NRC) Order Order modifying modifyinglicenses licenses withwith regard regard to to reliable reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; instrumentation                  EA-12-051; ADAMS  ADAMS Accession No.          No. ML12054A679)
2.0 LEVELS OF REQUIRED MONITORING The 01 P states, in part, that:
ML12054A679) for        for Quad Quad Cities Cities Nuclear Power Nuclear    Power Station, Station, Units Units 11and  and 2.2. The NRC NRC staff endorsed endorsed NuclearNuclear Energy Energy Institute, Institute, NEI 12-02, "Industry NEI12-02,      "IndustryGuidance Guidance for   for Compliance Compliance with    with NRC NRC Order EA-12-051, to Modify                      Licenses Modify Licenses with   Regard with Regard      to Reliable     SFP     Instrumentation,"        Revision      1,  dated Instrumentation," Revision 1, dated August 2012 (ADAMSAugust    2012    (ADAMS Accession No. ML12240A307),
Level adequate to support operation of the normal fuel pool cooling system (L 1):
ML12240A307), with       withexceptions exceptions as documented documentedin          in NRC NRC Interim Interim StaffStaff Guidance, Guidance, JLD-ISG-2012-03, "Compliance with JLD-ISG-2012-03,                                with Order Order EA-12-051, EA-12-051, Reliable Spent       Spent FuelFuelPool Pool Instrumentation," Revision Instrumentation,"        Revision 0, dated dated August August 29,  29, 2012 2012(ADAMS (ADAMS Accession AccessionNo.      No.ML12221A339).
For both units, indicated level on either primary or backup instrument channel must be greater than 23 feet 1 inch (elevation 689' 3") plus instrument accuracy above the top of the storage racks based on the design accuracy of the instrument channel (which is to be determined) and a resolution of 1 foot or better for both the primary and backup instrument channels. This is based on the 11 inch opening of the SFP weir gate design demonstrating a water level above 23 feet 1 inch (elevation 689' 3") is adequate for normal fuel pool cooling system operation.
ML12221A339).
Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (L2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet (elevation 676' 2") plus instrument channel accuracy above the top of the storage racks based on specification of this level as adequate in NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3), the specified design accuracy of the instrument channel, and the relatively low sensitivity of dose rates to changes in water depth at this level.
NRC staff The NRC      staffhas has reviewed reviewedthe    the February February 28,  28, 2013, 2013, response response by the licensee and determined        determined that the following       request for following request                additional information for additional       information (RAI) (RAI)isisneeded needed to    to complete complete its technical review.
This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored spent fuel.
2.0     LEVELS OF REQUIRED MONITORING          MONITORING The OIP 01 P states, in in part, part, that:
Level where fuel remains covered (L3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 666' 2") plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.  
Level adequate Level    adequate to    to support supportoperation operationof    ofthe thenormal normalfuel  fuelpool poolcooling coolingsystem system(L1): (L 1):
For both units, indicated level on either primary          primary or backup backup instrument instrumentchannelchannel must be greater greater than than 23  23 feet feet 11inch inch (elevation (elevation 689'  689' 3")
3") plus instrument accuracy above the top of           the storage racks based on of the                                   on the the design design accuracy accuracy of    of the instrument channel (which      (which is to be determined) and         and aaresolution resolution of   of 11foot foot oror better for      both the for both     the primary primary and  and backup backup instrument instrument channels.
channels. This is based    based on  on the the 11 inch opening 11 inch    opening of    of the the SFP weirweir gate design demonstrating demonstrating aa water     water level level above above 23 feet 11 inchinch (elevation (elevation 689'3")
689' 3") isis adequate adequatefor    fornormal normalfuel  fuelpool poolcooling cooling system system operation.
Level     adequate to Level adequate          to provide provide substantial substantial radiation radiation shielding shielding for   for aa person personstanding standingon    on the spent spent fuelfuel pool pool operating operating deck deck (L2):
(L2): For Forboth bothunits, units,indicated indicatedlevel levelon  oneither either the the primary primary or backup instrument  instrument channel channel of  of greater greaterthanthan10    10feet feet(elevation (elevation676'  676' 2")
2")  plus   instrument        channel instrument channel accuracy   accuracy      above     the   top   of the of the    storage     racks     based based on specification specification of this level as        as adequate adequateininNRC  NRCJLD-ISG-2012-03 JLD-ISG-2012-03(Ref.         (Ref.2)  2)and and NEI NEI 12-02 (Ref.  (Ref. 3),
3), the the specified specified design accuracyaccuracy of  of the instrument instrument channel, channel, and  and the the relatively relatively low        sensitivityof low sensitivity       ofdose dose rates rates to changes changes in    in water water depth depthatatthis thislevel.
level.
This monitoring monitoring level  level ensures ensures there is    is an adequate adequatewater  waterlevel level to to provide provide substantial substantial radiation radiation shielding shielding for for a person person standing standingon    onthethespent spentfuelfuelpool pool operating operating deck  deck from from direct direct gamma gamma radiation radiation fromfrom stored spent   spentfuel.
fuel.
Level Level where fuel remains covered       covered (L3):(L3): For For both both units, units, indicated indicated level level onon either eitherthe the primary primary or backup instrument channel of greater than 0 feet (elevation                       (elevation 6662")
666' 2")plusplus instrument instrument channel accuracy above the                  the top top of of the storage storage racks racks based basedupon  uponthe thedesign design accuracy accuracy (which (which is to to bebe determined) determined) of    of the the instrument instrumentchannelchannelfor    forboth both the theprimary primary and and backup backup instrument instrument channels.
channels. This This monitoring monitoring level         assures that level assures        that water wateris  is covering covering thethe stored stored fuel fuel seated seatedinin the theracks.
racks.


Response to Response  to Request for Additional Information Information (Order (Order EA-12-051)
Response to Request for Additional Information (Order EA-12-051)
EA-12-051)
Page 2 of 11
Enclosure 1 Page 2 of 11 Page      11


===RAI-1===
===RAI-1===
Please provide the following:
Please provide the following:
Please a) For a)  For level level LL1,   specify how the 1, specify          the identified identified location location represents the higher of the two points described in the NEI 12-02 guidance    guidance for for this this level.
a)
level.
For level L1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.
b) A b)  A clearly clearly labeled labeled sketch sketch depicting the elevation elevation viewview of the proposed proposedtypical typical mounting mounting arrangement for the portions of          of instrument instrument channel channel consisting consisting of of permanent permanent measurement channel measurement         channel equipment equipment(e.g., (e.g., fixed fixed level level sensors sensorsand/or and/orstilling stilling wells, and mounting brackets).
b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing L1, L2, and L3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the L1, L2, and L3 datum points.
mounting      brackets). Indicate Indicate onon this this sketch sketch thethe datum datum values valuesrepresenting representingL1,  L1,L2, L2, and and L3 as L3  as well well asas the top top of of the the fuel.
fuel. Indicate Indicate on this sketch the    the portion portion of the level     sensor level sensor measurement range measurement           range that thatisis sensitive sensitiveto  tomeasurement measurementofofthe    thefuel fuelpool poollevel, level, with with respect respect to the L1, L 1, L2, L2, and L3 datum points.


===Response===
===Response===
a) The Spent Fuel Pool a)                          Pool at Quad Cities Cities Station has skimmers and scuppers   scupperslocated locatedat  atthe the 689' 3"'   elevation that 3'" elevation      that water water must must flow flowinto.
a) The Spent Fuel Pool at Quad Cities Station has skimmers and scuppers located at the 689' 3"' elevation that water must flow into. From there the water is routed to surge tanks from which the Fuel Pool Cooling and Cleanup (FC) pumps draw suction. The suction trip is at an approximate 6676" elevation. Thus the 689' 3"' elevation reflects the higher of the two points noted in NEI 12-02, section 2.3.1.
into. From From there there the the water is routed to    to surge tanks from      whichthe from which       the Fuel Fuel Pool Pool Cooling Coolingand  and Cleanup Cleanup (FC)(FC)pumps pumps draw draw suction.
b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.
suction. The suction trip suction    trip isis at at an an approximate approximate 667'  6676"  6" elevation.
Response to Request for Additional Information (Order EA-12-051)
elevation. Thus Thusthethe689' 689'3"'
Page 2 of 11 Please provide the following:
3'"elevation elevation reflects reflects the higher higher    of the two   points   noted   in NEI in NEI    12-02,   section   2.3.1.
a) For level L 1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.
Please reference b) Please     reference the  the sketch sketch below.
b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing L 1, L2, and L3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the L 1, L2, and L3 datum points.  
below. Instrument Instrumentprobe probemounting mounting details details in in the the Spent SpentFuel Fuel area will Pool area     will be provided in accordance accordancewith    with the the response responsetotoRAI-3.
RAI-3.


Response to Request for Additional Information            Information (Order      (Order EA-12-051)
===Response===
EA-12-051)
a) The Spent Fuel Pool at Quad Cities Station has skimmers and scuppers located at the 689' 3'" elevation that water must flow into. From there the water is routed to surge tanks from which the Fuel Pool Cooling and Cleanup (FC) pumps draw suction. The suction trip is at an approximate 667' 6" elevation. Thus the 689' 3'" elevation reflects the higher of the two points noted in NEI 12-02, section 2.3.1.
Enclosure Enclosure 11 Page 3 of     of 1111
b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.
                                                                                                      !      11 EL, 689'-9" EL. 689'-(r                                           r          EL. 689'-9 FlOOR EL EL 6il0'-6" r° i
 
                  .~:_. 1'"1.
Response to Request for Additional Information (Order EA-12-051)
              )( _,',
Page 3 of 11 11 EL, 689'-9" L 'riATE' LEVEL EL EL 6 89'-,T
                  '''!.
/EEL rbty'-6' r°
                          ----, 1 I
'.I-L iTER LEVEL FLOOR EL,- -c EL. 669'-3"-7 EL 690'$
EL
LEVEL i LEVEL-1 IE EL 66W-3° LEVEL 1 UNIT #2 SPENT FUEL STORAGE POOL SKIMMER SURGE TANK EL. 616'-2" LEVEL 2 I
                                    ~EL * -
w UNIT # 1 SPENT FUEL STORAGE POOL T:j /F. EL i':CK-EL LEVEL 3 SKIMMER SJROE TANK DIA.
89' -,T EL 6689'-J'       ,
w EFFECTIVE r ;
rNORMALL 'riATE' I/EEL EL
TF'':SFEH CF' L
                                                                      -
-EL F
WATER LEVEL 6Il9'-6" rbty'-6' LEVEL kr.'.~.,                 4
TOP/FUEL R EL 668'-2" LEVEL 3 w
:,~: ..'
EL 665'-E' TO FC P}MPS -
                                                                                                                                                  -4
I uIT 33'4 33'-0" a
                                                                                                                                                  .. .
! LOW POOL LEVEL ALARM ELEVATION VI EL 665'-6" TO FC PUMPS Response to Request for Additional Information (Order EA-12-051)
                                                                                                                                                      ..
Page 3 of 11 EL. 689'-(r r EL. 689'-9 FlOOR EL 6il0'-6" ( _,',
1, *
EL  
                                                                                                                                                    /.~   : TIb                      ~-
)
                                                                                                                                                                                        ,NORMAL EL
.~:_. 1'"1. 1 689'-J' i
                                                                                                                                                                                                '.I-L WATER EL 6Il9'-6'
'''!. I  
                                                                                                                                                                                                  ,- -c LEVEL iTER LEVEL EL 669'-3"-7 EL. 6Il9'-:l",
~EL
LrYEL i14<
* rNORMAL WATER LEVEL I EL 6Il9'-6" SKlt.llJER SURGE, TANK
LEVEL FlOw"R FLOOR EL 690'-6" EL  690'$
\\
EL 665'-6" TO Fe P.iMPS 5'-3"
:lI,i, LNIT #1 SPENT FLEL STORAGE POOL TOP/fJEL RACK, EL 5S6'-t I
lEVELS j
kr.'.~.,
TIb
:,~:.. '
4 1, *  
.. /.~.. :
LEVEL......
LEVEL......
LEVEL-1 PROBE   IE L lEVEL' EL IlB1r-J" EL 66W-3&deg; LEVEL 1 Ir-LEVEL PROBE
PROBE 4
                                                                                                                                                                            !l:
L EL IlB1r-J" lEVEL' Ir-LEVEL PROBE  
UNIT #1 LNIT  # 1 SPENT SPENT FUEL  FLEL                                                                                            gL..l     UNIT #2 UNIT            SPENT FUEL
!l:
                                                                                                                                                                                                  #2 SPENT          FUEL SKlt.llJER SKIMMER SURGE, SJROE STORAGE STORAGE POOL                                                                                                                ~~         STORAGE POOL    POOL                                I IS~[IJUER    SURGE SKIMMER SURGE TANK                    \                                      POOL j... ..JI-                                                                           IIJ~      STORAGE                                            V TANKTANK
gL..l  
                                                                                      ~I L..I,
~~
                                                                                            ~~         1 1               EL. 616'-2" LEVEL EL. 515'-t     lEVEL 22        1 1         I ~~
IIJ~
                                                                                                                                                                          "I.JI-
j.....JI-I L..I, 1
                                                                                                                                                                          .I ~::;w
~ ~~
                                                                                              -II::
1 EL. 515'-t lEVEL 2 1 1 "I.JI-I ~~
x.:;                                                                         ~ -~w o(/)                                                                             x::>
. ~::;  
~ -~
-II::
x.:;
o(/)
f~
f~
0....,
0....,
o(~
o(~
EFfECTIVE EFFECTIVE BOTTOM r ;                            ~~
EFfECTIVE BOTTOM r-TRI\\NSFEF! CANAL I
p:w 5'-3"                                                                                      r-TRI\NSFEF!
EL 6S6'-8Yl:'
TF'':SFEH CANAL CF' L                                                                                      5'-5'
I Uf\\IT ~I I UNIT #2 x::>
:lI,i, DIA.
~~
TOP/fJEL T:j /F. ELRACK, i':CK-IF-EL EL 6S6'-8Yl:'
p:  
TOP/FUEL RACK-TOP/FUEL    R FA EL EL 5S6'-t            I I                                                                      EL 668'-2" EL    655'-2"       I lEVELS LEVEL 3            j                                                                                                           LEVEL 3j LEVEL              I EL  665'-6" EL 665'-E'                                                                                                                                                                                                                      EL. 665'-6" EL  665'-5'"
,NORMAL WATER LEVEL FlOw"R EL 6Il9'-6' EL 6Il9'-:l",
TO TO Fe FC P.iMPS P} MPS -                                                                                                                                                                                                          -t:.. TO FC TO Fe PUIJPS PUMPS I
EL 690'-6" LrYEL 14<
uIT ~I Uf\IT      I    UNIT #2 33'4 33'-0"                                   ..1                                                 I..                               33'-0" 33'-i"                             a
~-
                                        !jt LO'II LOW POOL           ,oILo\~M lEVEL ALARM POOL LEVEL ELEVATION VI ELEVATION             VIEW
UNIT #2 SPENT FUEL STORAGE POOL TOP/FUEL RACK-EL 655'-2" I
LEVEL j I
5'-5' FA I IS~[IJUER SURGE V TANK EL. 665'-5'"  
-t:.. TO Fe PUIJPS 33'-0"  
.. 1 I..
33'-i" jt LO'II POOL lEVEL,oILo\\~M ELEVATION VIEW  


Response to Response    to Request Requestfor    forAdditional AdditionalInformation Information (Order (OrderEA-1       2-051)
Response to Request for Additional Information (Order EA-1 2-051)
EA-12-051)
Page 4 of 11 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The OIP states, in part, that:
Enclosure 1 Page 4 of 11 Page      11 3.0 3.0     INSTRUMENTATION DESIGN FEATURES INSTRUMENTATION 3.2     Arrangement OIP The 01  P states, in part, that:
The current plan is to install SFP level sensors in the southwest corner of the Unit 1 SFP and in the northwest corner of the Unit 2 SFP separated by a distance in excess of 50 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB [Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services as required by the Quad Cities design basis.
The current plan  plan is to to install install SFP SFP level level sensors sensors in in the southwest southwest cornercorner of of the Unit Unit 1 SFP and in and  in the the northwest northwest cornercorner of ofthe the Unit Unit22SFP  SFPseparated separated by   by aa distance in    in excess of  of 50 feet. The sensors sensors themselves themselveswill  will be be mounted, mounted, to  to the the extent extentpractical, practical, near nearthe thepool pool walls and walls  and below the pool curb to minimize      minimize their  their exposure exposure to  to damaging debris and       and not not interfere with interfere    withSFP SFP activities.
activities. Instrument channel  channel electronics electronics and  and power powersupplies supplieswill will be be located in     seismic and missile protected areas in seismic                                        areaseither eitherbelow below the the SFP SFPoperating operatingfloor floor or or in in buildings other buildings    other than than the RB [Reactor Building]. Building]. The areas areas to to be beselected selectedwill will provide provide suitable radiation shielding shielding and environmental conditions for                     the equipment consistent for the                    consistent with instrument with  instrumentmanufacturer's manufacturer's recommendations.
recommendations. Equipment    Equipment and   andcabling cabling for for power power supplies and indication indication for each channelchannel will  will be separated separatedequivalent equivalentto    tothat thatprovided providedfor for redundant safety related services as              as required required byby the Quad Quad Cities Cities design basis.basis.


===RAI-2===
===RAI-2===
Please provide Please  provide aa clearly clearly labeled labeled sketch sketchor  ormarked-up marked-upplant  plantdrawing drawingof    of the theplan planview view ofof the the SFP SFP area, depicting depicting the SFP SFP inside inside dimensions, dimensions, the     theplanned plannedlocations/placement locations/placementofofthe        theprimary primary andand back-up SFP level level sensor, sensor, and andthetheproposed proposedrouting  routingof ofthe thecables cablesthat thatwill will extend extend fromfrom the sensors toward sensors  toward the thelocation location of of the the read-out/display read-ouVdisplay device. device.
Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.


===Response===
===Response===
The current plan for       the SFPI for the    SFPI design of the system based         basedon  onthe thecurrent currentExelon ExelonNuclear Nuclear program schedule for    for Quad Cities Cities is to begin the design phase       phaseinin October Octoberof    of 2013 2013 withwith the design completion completion and 100%    100% acceptance acceptanceof      ofthethedesign designininMarch March of  of 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
2014. The The requested requested information will willbe be provided provided with withthe the August August of    of 2014, 2014, 6-month integrated integrated plan plan update.
3.3 Mounting The OIP states, in part, that:
update.
Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Installed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.
3.3     Mounting Mounting The OIP OIP states, states, in in part, part, that:
that:
Design of the the mounting mounting of   ofthe the sensors sensors in    in the SFP SFP shall shall bebe consistent consistentwith  with the the seismic seismic Class Class II criteria. Installed Insta"ed equipment equipmentwill    will be verified verified to be seismically adequate adequate for  for the the seismic motions motions associated associatedwith  with the themaximum maximum seismic seismicground groundmotionmotionconsidered consideredininthe    the design design of of the the plant plant area areaininwhich which itit isis installed.
installed.


===RAI-3===
===RAI-3===
Please provide the the following:
Please provide the following:
following:
a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic Response to Request for Additional Information (Order EA-12-051)
a) a) The The design design criteria criteria that that will   be used to will be            to estimate estimatethe thetotal total loading loading on  on the themounting mounting device(s), including          static weight including static       weight loads loads and  and dynamic dynamic loads.
Page 4 of 11 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The 01 P states, in part, that:
loads. Describe Describethe  themethodology methodology that that will will bebe used to estimate estimate the thetotal total loading, loading, inclusive inclusive of of design design basis basismaximum maximum seismicseismic
The current plan is to install SFP level sensors in the southwest corner of the Unit 1 SFP and in the northwest corner of the Unit 2 SFP separated by a distance in excess of 50 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB [Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services as required by the Quad Cities design basis.
Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-ouVdisplay device.


Responsetoto Request Response            Requestfor    forAdditional Additional Information Information (Order (Order EA-12-051)
===Response===
EA-12-051)
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
Enclosure Page 55 of Page         of 11 11 loads and loads    and thethe hydrodynamic hydrodynamic loads that could result from pool sloshing or other effects                            effects that could that    couldaccompany accompany such    such seismic forces.
3.3 Mounting The OIP states, in part, that:
b) b) AAdescription description of   ofthe the manner manner in which the level      level sensor sensor(and   (andstilling stillingwell, well, ifif appropriate) appropriate)will will be  attached be attached to the refueling                floorand/or refueling floor       and/orother other support support structures structures for  for each each planned point   point ofofattachment attachment of     ofthethe probe probe assembly.
Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Insta"ed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.
assembly. Indicate Indicate in   in aa schematic schematicthe    theportions portionsof    ofthe thelevel level sensor that will sensor                  serve as points of will serve                    of attachment attachment for  for mechanical/
Please provide the following:
mechanical/mountingmounting or     or electrical electrical connections conn    ections..
a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic
c)c) AA description descriptionof    ofthethe manner manner by  by which whichthethe mechanical mechanical connections will           will attach attach the level instrument instrument to     topermanent permanent 8FP    SFP structures structures so as   as toto support support the  the level level sensor sensor assembly.
 
assembly.
Response to Request for Additional Information (Order EA-12-051)
Page 5 of 11 loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.
b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical connections.
c) A description of the manner by which the mechanical connections will attach the level instrument to permanent SFP structures so as to support the level sensor assembly.


===Response===
===Response===
Response The current The    current plan plan forfor the the 8FPI SFPI design design of of the the system basedbased on    on the thecurrent currentExelon Exelon Nuclear Nuclear program program       schedule       for Quad     Cities     to begin is to   begin the design phase   phasein    in October Octoberof    of 2013 2013 withwith the design completion design    completion and      and 100%
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
100% acceptance acceptance of the design in            in March March of   of 2014.            requested 2014. The requested information will information        willbe beprovided providedwith  withthetheAugust Augustofof2014, 2014,6-month 6-monthintegrated integrated plan plan update.
3.4 Qualification The OIP states, in part, that:
3.4 3.4        Qualification Qualification The OIP The    OIP states, states, in in part, part, that:
Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:
that:
components are supplied by manufacturers using commercial quality programs (such as IS09001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; or components are inherently resistant to shock and vibration loadings, such as cables.
Components Components of       of the the instrument instrumentchannels channelswill  will be bequalified qualifiedfor    for shock shockand  andvibration vibration using using oneone or or more more of  of the the following following methods:
For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:
    **    components components are       are supplied supplied by by manufacture manufacturers     rs using usingcommercial commercial quality  quality programs programs (such (suchasas IS09001,      "Quality 1809001, "Quality management managemen        t systems systems--Requiremen Requirements")    ts") with withshock shockand  andvibration vibration requirement requirements       s included included in the purchase purchasespecificatio specification     n atat levels levels commensur commensurate             with ate with portable portable hand-held hand-held devicesdevicesor    ortransportatio transportation   n applications applications;     ;
instrument channel components use known operating principles and are supplied by manufacturers with commercial quality programs (such as IS09001). The procurement specification and/or instrument channel design shall include the seismic requirements and specify the need for commercial design and testing under seismic loadings consistent with design basis values at the installed locations; Response to Request for Additional Information (Order EA-12-051)
    **    components componentshave      havesubstantial substantialhistory historyofofoperational operationalreliability reliabilityininenvironmen environments         with ts with significant significant      shock     and   vibration      loadings, vibration loadings, such    such as portable portable hand-held hand-held devices devicesor    or transportatio transportation     n applications applications;   ; or or
Page 5 of 11 loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.
    **    components components are       areinherently inherently resistant resistant to to shock shock and and vibration vibration loadings, such as          as cables.
b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical conn ections.
cables.
c) A description of the manner by which the mechanical connections will attach the level instrument to permanent 8FP structures so as to support the level sensor assembly.
For For seismic effects effects on instrument instrument channel channel components componentsused        usedafterafteraapotential potentialseismic seismicevent event for for only installed components components (with    (with the exception of      of battery chargers chargers and   andreplaceable replaceable batteries),
batteries), the thefollowing        measures will following measures             will be used usedto  toverify verify that the    the design designand  andinstallation installationisis adequate.       Applicable adequate. Applicablecomponents    componentsare      arerated ratedbybythe themanufactur manufacturer     er (or(orotherwise otherwisetested)tested)for for seismic seismic effects effects at at levels levels commensur commensurate     ate with with those those of  of postulated design  design basis basiseventevent conditions conditions in  in the area areaof  of instrument instrument channel channel component componentuse      useusingusingone oneorormore moreofofthe  the following following methods:
methods:
    ** instrument instrument channel channel components componentsuse        useknown knownoperating operatingprinciples principlesand  andare aresupplied suppliedby by manufactur manufacturers   ers with with commercial commercial quality quality programs programs (such  (such as as 1809001).
IS09001). The     Theprocuremen procurement   t specificatio speCification    n and/or and/or instrument instrument channel channel design designshall shall include include the theseismic seismicrequirement requirements s and andspecify specify the theneed needfor  forcommercial commercial design designand  andtesting testingunder underseismic seismicloadings loadings consistent consistentwith    with design designbasisbasisvalues valuesatatthe theinstalled installedlocations; locations;


Response to Request Request for Additional Additional Information Information (Order (OrderEA-12-051)
===Response===
EA-12-051)
The current plan for the 8FPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
Enclosure  1 Page 66of11 Page      of 11
3.4 Qualification The OIP states, in part, that:
* substantial history substantial    historyof  of operational operationalreliability reliability in in environments environmentswith    withsignificant significantvibration, vibration, such asas for for portable portable hand-held hand-held devicesdevices or  or transportation transportation applications.
Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:
applications. Such Sucha avibration vibration design envelope envelope shallshall be beinclusive inclusive of  of the the effects effectsof  of seismic seismicmotion motion imparted imparted to  to the the components proposed proposed at   atthe thelocation location of  of the the proposed proposedinstallation; installation;
components are supplied by manufacturers using commercial quality programs (such as 1809001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; or components are inherently resistant to shock and vibration loadings, such as cables.
* adequacy of adequacy     of seismic design and    and installation installation is    is demonstrated based   based on  on the the guidance guidancein      in Sections 7, Sections      8, 9, and 7,8,9,    and10  10ofofIEEE IEEE[Institute
For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:
[Institute of  of Electrical Electrical and and Electronics Electronics Engineers]
instrument channel components use known operating principles and are supplied by manufacturers with commercial quality programs (such as 1809001). The procurement speCification and/or instrument channel design shall include the seismic requirements and specify the need for commercial design and testing under seismic loadings consistent with design basis values at the installed locations;
Engineers]
 
Standard 344-2004, Standard    344-2004, "IEEE "IEEE Recommended RecommendedPractice      Practicefor  forSeismic SeismicQualification QualificationofofClass Class1 1EE Equipment for  for Nuclear Power Generating Generating Stations,"
Response to Request for Additional Information (Order EA-12-051)
Stations," or   or aasubstantially substantiallysimilar similarindustrial industrial standard;
Page 6of11 substantial history of operational reliability in environments with significant vibration, such as for portable hand-held devices or transportation applications. Such a vibration design envelope shall be inclusive of the effects of seismic motion imparted to the components proposed at the location of the proposed installation; adequacy of seismic design and installation is demonstrated based on the guidance in Sections 7, 8, 9, and 10 of IEEE [Institute of Electrical and Electronics Engineers]
* demonstration that proposedproposed devices devices are aresubstantially substantiallysimilarsimilar in in design to  to models models thatthat have been previously previously tested for seismic effects      effects in  in excess excess of the plantplant design design basis at the location where the instrument is to be installed location                                              installed (g-levels (g-Ievels and and frequency frequency ranges);
Standard 344-2004, "IEEE Recommended Practice for Seismic Qualification of Class 1 E Equipment for Nuclear Power Generating Stations," or a substantially similar industrial standard; demonstration that proposed devices are substantially similar in design to models that have been previously tested for seismic effects in excess of the plant design basis at the location where the instrument is to be installed (g-levels and frequency ranges); or seismic qualification using seismic motion consistent with that of existing design basis loading at the installation location.
ranges); or or
* seismic qualification qualification usingusing seismic motionmotion consistent with             that of with that    of existing existing design design basis loading at the installation installation location.
location.
RAi-4 Please provide the following:
RAi-4 Please provide the following:
a) A A description of   of the the specific method or combination of methods              methods you you intend intend toto apply applyto  to demonstrate the demonstrate      the reliability reliability ofof the the permanently installed installed equipment under beyond-design-beyond-design-basis ambient ambient temperature, temperature,humidity, humidity, shock, shock, vibration, vibration, and and radiation radiation conditions.
a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.
conditions.
b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.
b) A b)      description of A description      ofthe the testing testing and/or and/or analyses analyses that will         be conducted will be    conducted to    to provide provide assurance assurance that the equipment equipment will       perform reliably will perform      reliablyunderunderthe  the worst-case worst-case credible design basis      basis loading at loading    at the the location      where the location where         the equipment will     willbe bemounted.
c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.
mounted. Include Include a discussion of        of this seismic reliability       demonstration as reliability demonstration            as it   applies to a) the level sensor it applies                          sensor mounted mountedin    in the the SFP area, area, and andb) b) any anycontrol control boxes, boxes,electronics, electronics, or     orread-out read-outand  andre-transmitting re-transmitting devicesdevices that will   be employed to convey the level will be                                      level information information from from thethe level level sensor sensor to to the the plant plant operators or emergency responders. responders.
 
c) A c)      description of A description     of the the specific method or combination of methods             methods thatthat will will be used used to to confirm the confirm    the reliability reliabilityof  ofthe the permanently permanently installed equipment  equipment such suchthatthatfollowing following aa seismic event event the the instrument instrumentwill  will maintain its required accuracy. accuracy.
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
3.5 Independence The OIP states, in part, that:
The primary instrument channel will be independent of the backup instrument channel.
This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.
Response to Request for Additional I nformation (Order EA-12-051)
Page 6 of 11 substantial history of operational reliability in environments with significant vibration, such as for portable hand-held devices or transportation applications. Such a vibration design envelope shall be inclusive of the effects of seismic motion imparted to the components proposed at the location of the proposed installation; adequacy of seismic design and installation is demonstrated based on the guidance in Sections 7,8,9, and 10 of IEEE [Institute of Electrical and Electronics Engineers]
Standard 344-2004, "IEEE Recommended Practice for Seismic Qualification of Class 1 E Equipment for Nuclear Power Generating Stations," or a substantially similar industrial standard; demonstration that proposed devices are substantially similar in design to models that have been previously tested for seismic effects in excess of the plant design basis at the location where the instrument is to be installed (g-Ievels and frequency ranges); or seismic qualification using seismic motion consistent with that of existing design basis loading at the installation location.
Please provide the following:
a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.
b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.
c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.  


===Response===
===Response===
The current plan for for the the SFPI SFPI design of the system based         based on  on the thecurrent currentExelon Exelon Nuclear Nuclear program schedule schedule forfor Quad Cities Cities isis to to begin begin thethe design design phasephaseininOctober Octoberofof2013 2013withwiththethe design completion completion and  and 100% acceptance of            of the design in     in March March of  of 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
2014. The requested requested information will information    willbebeprovided provided with withthethe August August of of 2014, 2014, 6-month 6-month integrated plan     plan update.
3.5 Independence The 01 P states, in part, that:
update.
The primary instrument channel will be independent of the backup instrument channel.
3.5     Independence The OIP 01 P states, inin part, part, that:
This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.  
that:
The primary primary instrument channel will                be independent will be   independent of the backup instrument channel.            channel.
This independence independence will         be achieved through physical and electrical will be                                                  electrical separation of each channels' components components commensurate commensuratewith        with hazard hazardand  andelectrical electricalisolation isolation needs.
needs.


Response to Request for AdditionalAdditional Information Information (Order (OrderEA-12-051)
Response to Request for Additional Information (Order EA-12-051)
EA-12-051) 1 Enclosure Page 7 of of 1111
Page 7 of 11


===RAI-5===
===RAI-5===
Please provide the following:
Please provide the following:
a) A   description of A description        of how howthe thetwo twochannels channels ofofthe the proposed proposed level level measurement measurement system system meet meet this requirement so that the potential  potential for a common cause    cause event eventto  toadversely adverselyaffect affectboth both channels isis minimized channels          minimized to the extent extent practicable.
a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.
practicable.
b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.
b) Further information b)            informationon    onhow howeacheach level levelmeasurement measurement system, consisting of            of level sensor sensor electronics, cabling, electronics,      cabling, andand readout readout devices will         be designed will be    designed andand installed installed to to address address independence through the application independence                          application and selection of independent power sources, the                  the use of of physical and spatial separation, separation, independence independenceofofsignals  signalssent senttotothe thelocation(s) location(s)ofof the readout devices, and      and the the independence independenceof    ofthe thedisplays.
displays.


===Response===
===Response===
The current plan for for the the SFPI SFPI design of the system based     basedon  onthe thecurrent currentExelon ExelonNuclear Nuclear program schedule for    for Quad Cities is to begin the design phase         phaseinin October Octoberof  of 2013 2013 with with the design completion completion and    and 100% acceptance acceptance of  of the design in  in March March of  of 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
2014. The requested requested information will information    willbebeprovided providedwith  withthe theAugust Augustofof2014, 2014,6-month 6-month integrated integrated plan plan update.
3.6 Power supplies The OIP states, in part, that:
3.6   Power supplies The OIP states, in  in part, that:
Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049 (Ref. 4). Additionally, each channel will have provisions for connection to another suitable power source.
Each channel channel willwill be normally normally powered powered from from aadifferent different 120Vac 120Vac[120 [120volts-alternating volts-alternating current] bus. Upon current]            Upon loss lossofofnormal normalac  acpower, power,individual individual channel channel installed installedbatteries batterieswill will automatically maintain automatically        maintaincontinuous continuous channel channel operation.
operation. The The batteries batteries will will be replaceable replaceable and be sizedsized toto maintain maintain channel channel operation operation until until off-site off-site resources can be     be deployed deployed by by the mitigating      strategies resulting mitigating strategies       resulting from from Order Order EA-12-049 EA-12-049 (Ref.(Ref. 4).
4). Additionally, Additionally, each each channel will      have provisions will have     provisions for for connection connection to  to another another suitable power source. source.


===RAI-6===
===RAI-6===
Please provide the following:
Please provide the following:
a) A   description of A description        of the the electrical electrical ac ac power sources sources and and capacities capacitiesfor forthe theprimary primary andand backup channels.
a) A description of the electrical ac power sources and capacities for the primary and backup channels.
b) IfIfthe b)      the level levelmeasurement measurement channels are        are to to be be powered powered through through aabattery batterysystem system(either (either directly     or through directly or through        an   uninterruptible   power     supply),   please   provide   the design please provide the design criteria criteria that will will bebe applied applied to to size size the the battery battery in in aa manner manner that ensures, ensures, withwith margin, that the channel will       be available to run reliably and continuously following will be                                                            following the the onset onset of the beyond-design-basis event beyond-design-basis            event for for the the minimum       duration needed, consistent minimum duration                    consistent withwith the plant plant mitigation strategies mitigation      strategies for for beyond-design-basis beyond-design-basis external  external events events(Order (OrderEA-12-049).
b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).
EA-12-049).
Response to Request for Additional Information (Order EA-12-051)
Page 7 of 11 Please provide the following:
a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.
b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.  


                                                                                                                      ~~----~~----
===Response===
Response to Request Request for for Additional Additional Information Information (Order (OrderEA-1       2-051)
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
EA-12-051) 1 Enclosure Page 8 of of 11 11
3.6 Power supplies The OIP states, in part, that:
Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049 (Ref. 4). Additionally, each channel will have provisions for connection to another suitable power source.
Please provide the following:
a) A description of the electrical ac power sources and capacities for the primary and backup channels.
b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).
 
Response to Request for Additional Information (Order EA-1 2-051)
Page 8 of 11


===Response===
===Response===
Response The current plan forfor the the SFPI SFPI design of the system based       basedon  onthe thecurrent currentExelon ExelonNuclear Nuclear program schedule for Quad Cities is to begin the design phase               phaseinin October Octoberof  of 2013 2013 with with the design completion completion      and   100%     acceptance acceptance of   of  the design   in March     of in March of 2014.2014. The   requested requested information will information  willbe beprovided provided with withthe the August August of of 2014, 2014, 6-month integrated integrated plan plan update.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
update.
3.7 Accuracy The OIP states, in part, that:
3.7   Accuracy The OIP states, in in part, part, that:
The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment, concentrated borated water), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.
The instrument channels channels will will be designed designed to  to maintain maintain their their design design accuracy accuracyfollowing following aa interruption or power interruption         or change change in  in power source without recalibration.
recalibration. Instrument Instrument channel channel accuracy, to be  be determined determinedduringduring detailed detailed design, design,willwill consider consider Spent SpentFuel FuelPool Pool conditions (e.g.,
conditions    (e.g., saturated saturated water, steam environment, environment, concentrated borated water), as                  as well   as, other applicable radiological well as,                          radiological and environmental conditions and include            include display accuracy. Instrument Instrumentchannelchannelaccuracy accuracywill will be besufficient sufficient toto allow allow trained personnel personnelto    to determine when the      the actual actual level level exceeds exceedsthe  thespecified specifiedlower lowerlevel levelofofeach eachindicating indicating range (levels (levels 1,1, 22 or or3)3) without without conflicting conflicting or ambiguous ambiguous indications.
indications.


===RAI-7===
===RAI-7===
Please provide the following:
Please provide the following:
a) An An estimate of   of the the expected instrument channel accuracy        accuracy performance performance under under both both a)  a) normal SFP level conditions (approximately normal                                 (approximately LL1        or higher) 1 or higher)and and b)b) at at the the beyond design-basis conditions conditions (i.e., radiation, temperature, temperature, humidity, humidity, post-seismic and      and post-shock post-shock conditions) that conditions)     that would would be  be present present ifif the SFP level level were at  at the the L2L2 and and L3L3 datum datum points.
a) An estimate of the expected instrument channel accuracy performance under both a) normal SFP level conditions (approximately L1 or higher) and b) at the beyond design-basis conditions (i.e., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the L2 and L3 datum points.
points.
b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.
b) A b)    description of the methodology A description                methodology that  that will will be used used for for determining determiningthe  themaximum maximumallowedallowed deviation from deviation    from thethe instrument instrument channel channel design accuracy accuracy thatthat will will be employed under  under normal operating conditions normal                    conditions as an  an acceptance acceptancecriterion criterionforfor aacalibration calibration procedure procedureto    toflag flag to operators and and to  to technicians technicians that that the the channel channelrequires requiresadjustment adjustmenttotowithinwithin the the normal normal condition design condition   design accuracy.
 
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
3.8 Testing The OIP states, in part, that:
Response to Request for Additional Information (Order EA-12-051)
Page 8 of 11
 
===Response===
~~-~ ---~~----
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
3.7 Accuracy The OIP states, in part, that:
The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment, concentrated borated water), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.
Please provide the following:
a) An estimate of the expected instrument channel accuracy performance under both a) normal SFP level conditions (approximately L 1 or higher) and b) at the beyond design-basis conditions (i.e., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the L2 and L3 datum points.
b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.  


===Response===
===Response===
Response The current plan forfor the the SFPI SFPI design of the system based       basedon  onthe thecurrent currentExelon Exelon Nuclear Nuclear program schedule schedule for for Quad Quad Cities Cities is is to to begin begin the the design designphasephaseininOctober Octoberofof2013 2013with withthe the design completion completion and  and 100% acceptance of          of the design in    in March March of of 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
2014. The requested requested information will information  willbe beprovided provided with withthe the August August ofof 2014, 2014, 6-month 6-month integrated plan   plan update.
3.8 Testing The OIP states, in part, that:  
update.
3.8   Testing The OIP states, in part, that:


Response to Response    to Request for  for Additional Information (Order  (Order EA-1       2-051)
Response to Request for Additional Information (Order EA-1 2-051)
EA-12-051)
Page 9 of 11 Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3). Details will be determined during detailed design engineering.
Enclosure Page 9 of 11 Page Instrument channel Instrument       channel design will        provide for will provide     for routine routine testing testing and and calibration       consistent with calibration consistent        with the guidelines of NRC the                      NRC JLD-ISG-2012-03 JLD-ISG-2012-03 (Ref.     (Ref. 2)
: 2) and and NEI NEI 12-02 (Ref.  (Ref. 3).
3). Details Details will will be determined during determined      during detailed detailed design design engineering.


===RAI-8===
===RAI-8===
Please provide Please    provide the following:
Please provide the following:
a) AA description a)      description of of the the capability capability andand provisions the proposed proposed levellevel sensing sensingequipment equipmentwill  will have to enable enable periodic periodic testing and and calibration, calibration, including including how this capability            enables the capability enables       the equipment to    to be tested tested in-situ.
a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.
in-situ.
b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation.
b) A b)  A description description of  of how how suchsuch testing andand calibration calibration will     enable the conduct will enable            conduct of of regular regular channel checks of channel                of each each independent channel against the other, and against any                      any other other permanently-installed SFP level instrumentation.
c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.
permanently-installed c) A c)  A description description of of how how functional functionalchecks checks will willbebe performed, performed, and  and the frequency frequency at at which which willbe they will   beconducted.
d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.
conducted. Describe Describe howhow calibration calibration tests testswill will be performed, performed, and    and the the frequency at which frequency          whichtheytheywillwillbebeconducted.
conducted. Provide Provide aa discussion discussion as to how these surveillances will       be incorporated into the plant will be                                plant surveillance surveillance program.
program.
d) A d)   A description description of   ofwhat whatpreventative preventativemaintenance maintenance tasks  tasks are required required to be     be performed performed during normal during  normal operation, operation, and the plannedplanned maximum maximum surveillance surveillance interval interval that that is is necessary to necessary      to ensure ensurethat thatthe thechannels channelsare arefully fullyconditioned conditionedto    toaccurately accuratelyand  andreliably reliably perform their perform    their functions functions when when needed.
needed.


===Response===
===Response===
Response The current plan for the SFPI design of the system based             basedon  onthethecurrent currentExelonExelonNuclear Nuclear program schedule for    for Quad Cities is to begin the design    design phase phaseininOctober Octoberof    of 2013 2013 with with the design completion completion and 100%  100% acceptance acceptanceof    ofthe thedesign designininMarch March of of 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.
2014. Following Following thetheissue issueofof the the design, design, procedures procedureswill  will start start being being developed developedwith  with aaprojected projectedOctober October2014  2014completion completion date. The Therequested requestedinformation informationwill  will be beprovided providedininthe theAugust August2014, 2014,6-month 6-monthintegrated integratedplan plan update.
3.9 Display The OIP states, in part, that:
update.
The primary and backup instrument displays will be located at the control room, alternate shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design. An appropriate and accessible location will include the following characteristics:
3.9     Display Display The The OIP OIP states, states, inin part, part, that:
occupied promptly accessible to the appropriate plant staff giving appropriate consideration to various drain down scenarios, Response to Request for Additional Information (Order EA-12-051)
that:
Page 9 of 11 Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3). Details will be determined during detailed design engineering.
The The primary primary and and backup backup instrument instrument displays displayswillwill be located located at  at the thecontrol control room, room, alternate alternate shutdown shutdown panel,panel, or or other other appropriate appropriate and accessible accessiblelocation.
Please provide the following:
location. TheThe specific specific location location willwill bebe determined during detailed detailed design.
a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.
design.An  An appropriate appropriateand  and accessible accessiblelocation locationwillwill include includethethefollowing following characteristics:
b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation.
characteristics:
c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.
        **  occupied occupied promptly promptly accessible accessibleto  tothe theappropriate appropriateplant plantstaff staffgiving giving appropriate appropriate consideration consideration to    to various various drain drain down down scenarios, scenarios,
d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.


Response to Response     to Request for Additional Information (Order         (Order EA-12-051)
===Response===
EA-12-051)
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.
Enclosure Page 10 of 11 Page          11
3.9 Display The OIP states, in part, that:
        **    outside the outside   the area area surrounding surrounding the SFP floor           (e.g., an floor (e.g.,  an appropriate appropriate distance fromthe from   the radiological radiologicalsources sources resulting resulting from from an an event event impacting impacting thethe Spent Fuel Pool),
The primary and backup instrument displays will be located at the control room, alternate shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design. An appropriate and accessible location will include the following characteristics:
Fuel Pool),
occupied promptly accessible to the appropriate plant staff giving appropriate consideration to various drain down scenarios,
        **    inside aa structure inside     structure providing providingprotection protectionagainstagainstadverse adverse weather, and
 
        **    outside of any Very outside              Very High High radiation areas areasororLOCKED LOCKEDHIGH    HIGH RAD RAD AREA AREA during normal during   normal operation.
Response to Request for Additional Information (Order EA-12-051)
Page 10 of 11 outside the area surrounding the SFP floor (e.g., an appropriate distance from the radiological sources resulting from an event impacting the Spent Fuel Pool),
inside a structure providing protection against adverse weather, and outside of any Very High radiation areas or LOCKED HIGH RAD AREA during normal operation.


===RAI-9===
===RAI-9===
Please provide the following:
Please provide the following:
Please a) The specific a)          specific location location for foreach each of of the the primary primary and and backup backup instrument channel displays.
a) The specific location for each of the primary and backup instrument channel displays.
b) IfIfthe b)      the primary primaryand  and backup backup display location location is other than the  the main main control control room, room, provide provide justification for justification    forprompt prompt accessibility accessibility to  to displays displays including primary and alternate alternate route route evaluation, habitability evaluation,    habitability at  at display display location(s),
b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.
location(s), continual continual resource availability availability forfor personnel personnel responsible to promptly promptly read displays, displays, and andprovisions provisionsforforcommunications communicationswith      with decision decision makers for for the the various various SFPSFP drain drain down down scenarios scenarios and external events.
c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.
c) The reasons c)          reasons justifying justifying why the locations selected selected enable enablethe theinformation information from from these these instruments to be considered "promptly                   accessible" to "promptly accessible"          to various various drain-down drain-down scenarios scenarios and external events.


===Response===
===Response===
Response The current plan for for the the SFPI SFPI design of the system based       basedon onthe thecurrent currentExelon ExelonNuclear Nuclear program schedule for Quad Cities is to begin the design phase                 phasein  in October Octoberof  of 2013 2013 withwith the design completion completion and  and 100% acceptance acceptance of    of the design in in March March of  of 2014.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
2014. The requested requested information information willwillbe be provided provided with withthethe August August of   of 2014, 2014, 6-month integrated integrated planplan update.
4.0 PROGRAM FEATURES 4.2 Procedures The OIP states, in part, that:
update.
Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.
4.0     PROGRAM PROGRAM FEATURES FEATURES 4.2     Procedures Procedures The OIP 01 P states, states, in in part, part, that:
that:
Procedures Procedures will  will be developed using  using guidelines and  and vendor vendor instructions instructions to address addressthe the maintenance, operation operation andand abnormal abnormal response responseissues issuesassociated associatedwith withthetheprimary primaryand and backup channels channels of    of SFP SFPinstrumentation.
instrumentation.


===RAI-10===
===RAI-10===
RAI-10 Please Pleaseprovide provideaadescription descriptionof    ofthe thestandards, standards,guidelines guidelinesand/or and/orcriteria criteriathat thatwill willbe beutilized utilized to to develop   procedures     for   inspection, develop procedures for inspection,              maintenance,        repair, repair, operation,     abnormal     response, response, and and administrative    controls associated administrative controls         associated with with the SFPSFP level level instrumentation, as   as well well as storage storage and and installation installation ofof portable portable instruments.
Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.
instruments.
Response to Request for Additional Information (Order EA-12-051)
Page 10 of 11 outside the area surrounding the SFP floor (e.g., an appropriate distance from the radiological sources resulting from an event impacting the Spent Fuel Pool),
inside a structure providing protection against adverse weather, and outside of any Very High radiation areas or LOCKED HIGH RAD AREA during normal operation.
Please provide the following:
a) The specific location for each of the primary and backup instrument channel displays.
b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.
c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.  


Responseto Response     to Request Request for  for Additional Additional Information (Order EA-1       EA-12-051) 2-051)
===Response===
Enclosure Enclosure    1 Page 11 Page  11 of of 11 11
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.
4.0 PROGRAM FEATURES 4.2 Procedures The 01 P states, in part, that:
 
===RAI-10===
Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.
Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.
 
Response to Request for Additional Information (Order EA-1 2-051)
Page 11 of 11
 
===Response===
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.
4.3 Testing and Calibration The OIP states, in part, that:
The testing and calibration of the instrumentation will be consistent with vendor recommendations or other documented basis. Calibration will be specific to the mounted instruments and the displays. Instrument performance will be trended as described in Exelon procedural requirements.
 
===RAI-11===
Please provide the following:
a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.
b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.
c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.


===Response===
===Response===
Response The current The   current plan planforforthe theSFPI SFPIdesign design of ofthe the system system based on    on the the current current Exelon Exelon Nuclear Nuclear program  schedule program schedule for    for Quad Quad Cities Cities isis to to begin begin thethe design design phase phase in in October October of 2013 with  with the design completion design  completion and   and 100%
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.
100% acceptance acceptance of    of the design design inin March March of 2014.         Following the issue 2014. Following              issue of of the design, the design, procedures procedures will  will start being developed developed with with aa projected projected October October 20142014completion completion date. The date. The requested requestedinformation information will      be provided will be   provided in in the the August August 2014, 2014, 6-month 6-month integrated integrated planplan update.
Response to Request for Additional Information (Order EA-12-051)
update.
Page 11 of 11
4.3 4.3      Testing and Testing     and Calibration The OIP The  OIP states, in part, that:
 
The testing The    testing and calibration calibration of the instrumenta instrumentationtion will will be consistent consistent with      vendor with vendor recommend recommendations  ations  or  other  documented basis. basis. Calibration Calibrationwill  will be be specific specific to the mounted instruments mounted      instruments and  and the the displays.
===Response===
displays. Instrument Instrument performanc performance        will be e will  be trended trended as described in Exelon described                    procedural requirements.
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.
Exelon procedural          requirements.
4.3 Testing and Calibration The OIP states, in part, that:  


===RAI-11===
===RAI-11===
RAI-11 Please provide the following:
The testing and calibration of the instrumentation will be consistent with vendor recommendations or other documented basis. Calibration will be specific to the mounted instruments and the displays. Instrument performance will be trended as described in Exelon procedural requirements.
Please a) Further information a) Further    informationdescribing describingthe  the maintenance maintenance and  and testing testing program program the thelicensee licenseewill will establish establish and and implement implement to ensureensure that thatregular regular testing testing andandcalibration calibration is is performed performed and  and verified verified by by inspection inspection and and audit audit to  to demonstrate demonstrate conformance conformance with  with design design and system readiness readiness requirement requirements. s. Include Includeaadescription descriptionof  of your your plans plans for for ensuring ensuring that necessary necessary channel    checks,    functional    tests,  periodic channel checks, functional tests, periodic calibration, and calibration,    andmaintenance maintenancewill  will be beconducted conducted for the level for the            measurement system level measurement          system and   anditsitssupporting supporting equipment.
Please provide the following:
equipment.
a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.
b) A b) A description description of  of how how thethe guidance in NEI    NEI 12-02 Section 4.3 regarding compensato  compensatory     ry actions actions forfor one one or or both both non-functio non-functioning ning channels channels willwill be addressed.
b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.
addressed.
c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.  
c) A c)    description of A description      of what what compensatory compensatory actions are planned in                      event that in the event     that one one of of the the instrument      channels instrument channels cannot becannot    berestored restoredtotofunctional functional status statuswithin within 9090 days.
days.


===Response===
===Response===
Response The The current current plan plan for for the SFPI design design of  of the the system system based basedon  onthethecurrent currentExelon ExelonNuclear Nuclear program    schedule      for  Quad    Cities  is program schedule for Quad Cities is to begin the to  begin    the design designphase phaseininOctober Octoberofof2013 2013with with the the design designcompletion completion and  and 100%
The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the deSign, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.}}
100%acceptance acceptanceofofthe    thedesign designininMarch Marchof  of2014.
2014.Following Followingthe  theissue issueofof the thedesign, deSign,procedures procedureswill  willstart startbeing beingdeveloped developedwith  withaaprojected projectedOctober October2014 2014completion completion date.
date.The Therequested requested   information informationwill willbebeprovided providedininthe theAugust August2014, 2014,6-month 6-monthintegrated integratedplan  plan update.
update.}}

Latest revision as of 07:15, 11 January 2025

Response to Request for Additional - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation
ML13186A003
Person / Time
Site: Quad Cities  
Issue date: 07/03/2013
From: Kaegi G
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-051, RS-13-159
Download: ML13186A003 (14)


Text

Generat RS-13-159 Order No. EA-12-051 July 3, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265

Subject:

Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)

References:

1.

Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-1 2-051), dated February 28, 2013 (RS-13-035) 2.

NRC Order Number EA-1 2-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 3.

USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7, 2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the Quad Cities Nuclear Power Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).

The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the Quad Cities Nuclear Power Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to Quad Cities Nuclear Power Station, Units 1 and 2. This item is included and addressed in Enclosure 1 to this letter.

The Quad Cities Nuclear Power Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1.

The enclosed responses to the NRC request for additional information are intended not to provide preliminary or conceptual information. The requested information, when fully developed, will be

)

1 ti Order No. EA-12-051 RS-13-159 July 3,2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265

Subject:

Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)

References:

1. Exelon Generation Company, LLC Letter to USNRC, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28,2013 (RS-13-035)
2. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012
3. USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated June 7, 2013 In Reference 1, Exelon Generation Company, LLC (EGC) provided the Quad Cities Nuclear Power Station, Units 1 and 2, Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, pursuant to NRC Order No. EA-12-051 (Reference 2).

The purpose of this letter is to provide the response to the NRC request for additional information (Reference 3) regarding the Quad Cities Nuclear Power Station, Units 1 and 2 Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051). Subsequent to issuance of Reference 3, the NRC identified that Request for Additional Information Item No. 6.a was also applicable to Quad Cities Nuclear Power Station, Units 1 and 2. This item is included and addressed in Enclosure 1 to this letter.

The Quad Cities Nuclear Power Station, Units 1 and 2 Spent Fuel Pool Instrumentation design is proceeding on the schedule identified in the Overall Integrated Plan provided in Reference 1.

The enclosed responses to the NRC request for additional information are intended not to provide preliminary or conceptual information. The requested information, when fully developed, will be

U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-1 2-051)

July 3, 2013 Page 2 provided upon detailed design completion based on the milestone schedule dates provided in each response.

This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.

Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1.

Quad Cities Nuclear Power Station, Units 1 and 2 - Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:

Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station, Units 1 and 2 NRC Project Manager, NRR - Quad Cities Nuclear Power Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety U.S. Nuclear Regulatory Commission Response to Request for Additional Information (Order EA-12-051)

July 3,2013 Page 2 provided upon detailed design completion based on the milestone schedule dates provided in each response.

This letter contains no new regulatory commitments. If you have any questions regarding this response, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of July 2013.

Respectfully submitted,

~~~

Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1. Quad Cities Nuclear Power Station, Units 1 and 2 - Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) cc:

Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station, Units 1 and 2 NRC Project Manager, NRR - Quad Cities Nuclear Power Station, Units 1 and 2 Mr. Robert J. Fretz, Jr, NRRIJLD/PMB, NRC Mr. Robert L. Dennig, NRRIDSS/SCVB, NRC Mr. Blake Purnell, NRC Project Manager, NRR Illinois Emergency Management Agency - Division of Nuclear Safety Quad Cities Nuclear Power Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)

(11 pages)

Quad Cities Nuclear Power Station, Units 1 and 2 Response to Request for Additional Information Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-0S1)

(11 pages)

Response to Request for Additional Information (Order EA-12-051)

Page 1 of 11

1.0 INTRODUCTION

By letter dated February 28, 2013 (Agency wide Documents Access and Management System (ADAMS) Accession No. ML13060A124), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12, 2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for Quad Cities Nuclear Power Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).

The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.

2.0 LEVELS OF REQUIRED MONITORING The OIP states, in part, that:

Level adequate to support operation of the normal fuel pool cooling system (L1):

For both units, indicated level on either primary or backup instrument channel must be greater than 23 feet 1 inch (elevation 689' 3") plus instrument accuracy above the top of the storage racks based on the design accuracy of the instrument channel (which is to be determined) and a resolution of 1 foot or better for both the primary and backup instrument channels. This is based on the 11 inch opening of the SFP weir gate design demonstrating a water level above 23 feet 1 inch (elevation 689'3") is adequate for normal fuel pool cooling system operation.

Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (L2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet (elevation 676' 2") plus instrument channel accuracy above the top of the storage racks based on specification of this level as adequate in NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3), the specified design accuracy of the instrument channel, and the relatively low sensitivity of dose rates to changes in water depth at this level.

This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored spent fuel.

Level where fuel remains covered (L3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 6662") plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.

Response to Request for Additional Information (Order EA-12-051)

Page 1 of 11

1.0 INTRODUCTION

By letter dated February 28, 2013 (Agency wide Documents Access and Management System (ADAMS) Accession No. ML13060A124), Exelon Generation Company, LLC, submitted an overall integrated plan (OIP) in response to the March 12,2012, U.S. Nuclear Regulatory Commission (NRC) Order modifying licenses with regard to reliable spent fuel pool (SFP) instrumentation (Order EA-12-051; ADAMS Accession No. ML12054A679) for Quad Cities Nuclear Power Station, Units 1 and 2. The NRC staff endorsed Nuclear Energy Institute, NEI12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable SFP Instrumentation," Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307), with exceptions as documented in NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).

The NRC staff has reviewed the February 28, 2013, response by the licensee and determined that the following request for additional information (RAI) is needed to complete its technical review.

2.0 LEVELS OF REQUIRED MONITORING The 01 P states, in part, that:

Level adequate to support operation of the normal fuel pool cooling system (L 1):

For both units, indicated level on either primary or backup instrument channel must be greater than 23 feet 1 inch (elevation 689' 3") plus instrument accuracy above the top of the storage racks based on the design accuracy of the instrument channel (which is to be determined) and a resolution of 1 foot or better for both the primary and backup instrument channels. This is based on the 11 inch opening of the SFP weir gate design demonstrating a water level above 23 feet 1 inch (elevation 689' 3") is adequate for normal fuel pool cooling system operation.

Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (L2): For both units, indicated level on either the primary or backup instrument channel of greater than 10 feet (elevation 676' 2") plus instrument channel accuracy above the top of the storage racks based on specification of this level as adequate in NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3), the specified design accuracy of the instrument channel, and the relatively low sensitivity of dose rates to changes in water depth at this level.

This monitoring level ensures there is an adequate water level to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck from direct gamma radiation from stored spent fuel.

Level where fuel remains covered (L3): For both units, indicated level on either the primary or backup instrument channel of greater than 0 feet (elevation 666' 2") plus instrument channel accuracy above the top of the storage racks based upon the design accuracy (which is to be determined) of the instrument channel for both the primary and backup instrument channels. This monitoring level assures that water is covering the stored fuel seated in the racks.

Response to Request for Additional Information (Order EA-12-051)

Page 2 of 11

RAI-1

Please provide the following:

a)

For level L1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.

b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing L1, L2, and L3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the L1, L2, and L3 datum points.

Response

a) The Spent Fuel Pool at Quad Cities Station has skimmers and scuppers located at the 689' 3"' elevation that water must flow into. From there the water is routed to surge tanks from which the Fuel Pool Cooling and Cleanup (FC) pumps draw suction. The suction trip is at an approximate 6676" elevation. Thus the 689' 3"' elevation reflects the higher of the two points noted in NEI 12-02, section 2.3.1.

b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.

Response to Request for Additional Information (Order EA-12-051)

Page 2 of 11 Please provide the following:

a) For level L 1, specify how the identified location represents the higher of the two points described in the NEI 12-02 guidance for this level.

b) A clearly labeled sketch depicting the elevation view of the proposed typical mounting arrangement for the portions of instrument channel consisting of permanent measurement channel equipment (e.g., fixed level sensors and/or stilling wells, and mounting brackets). Indicate on this sketch the datum values representing L 1, L2, and L3 as well as the top of the fuel. Indicate on this sketch the portion of the level sensor measurement range that is sensitive to measurement of the fuel pool level, with respect to the L 1, L2, and L3 datum points.

Response

a) The Spent Fuel Pool at Quad Cities Station has skimmers and scuppers located at the 689' 3'" elevation that water must flow into. From there the water is routed to surge tanks from which the Fuel Pool Cooling and Cleanup (FC) pumps draw suction. The suction trip is at an approximate 667' 6" elevation. Thus the 689' 3'" elevation reflects the higher of the two points noted in NEI 12-02, section 2.3.1.

b) Please reference the sketch below. Instrument probe mounting details in the Spent Fuel Pool area will be provided in accordance with the response to RAI-3.

Response to Request for Additional Information (Order EA-12-051)

Page 3 of 11 11 EL, 689'-9" L 'riATE' LEVEL EL EL 6 89'-,T

/EEL rbty'-6' r°

'.I-L iTER LEVEL FLOOR EL,- -c EL. 669'-3"-7 EL 690'$

LEVEL i LEVEL-1 IE EL 66W-3° LEVEL 1 UNIT #2 SPENT FUEL STORAGE POOL SKIMMER SURGE TANK EL. 616'-2" LEVEL 2 I

w UNIT # 1 SPENT FUEL STORAGE POOL T:j /F. EL i':CK-EL LEVEL 3 SKIMMER SJROE TANK DIA.

w EFFECTIVE r ;

TF:SFEH CF' L

-EL F

TOP/FUEL R EL 668'-2" LEVEL 3 w

EL 665'-E' TO FC P}MPS -

I uIT 33'4 33'-0" a

! LOW POOL LEVEL ALARM ELEVATION VI EL 665'-6" TO FC PUMPS Response to Request for Additional Information (Order EA-12-051)

Page 3 of 11 EL. 689'-(r r EL. 689'-9 FlOOR EL 6il0'-6" ( _,',

EL

)

.~:_. 1'"1. 1 689'-J' i

!. I

~EL

  • rNORMAL WATER LEVEL I EL 6Il9'-6" SKlt.llJER SURGE, TANK

\\

EL 665'-6" TO Fe P.iMPS 5'-3"

lI,i, LNIT #1 SPENT FLEL STORAGE POOL TOP/fJEL RACK, EL 5S6'-t I

lEVELS j

kr.'.~.,

TIb

,~:.. '

4 1, *

.. /.~.. :

LEVEL......

PROBE 4

L EL IlB1r-J" lEVEL' Ir-LEVEL PROBE

!l:

gL..l

~~

IIJ~

j.....JI-I L..I, 1

~ ~~

1 EL. 515'-t lEVEL 2 1 1 "I.JI-I ~~

. ~::;

~ -~

-II::

x.:;

o(/)

f~

0....,

o(~

EFfECTIVE BOTTOM r-TRI\\NSFEF! CANAL I

EL 6S6'-8Yl:'

I Uf\\IT ~I I UNIT #2 x::>

~~

p:

,NORMAL WATER LEVEL FlOw"R EL 6Il9'-6' EL 6Il9'-:l",

EL 690'-6" LrYEL 14<

~-

UNIT #2 SPENT FUEL STORAGE POOL TOP/FUEL RACK-EL 655'-2" I

LEVEL j I

5'-5' FA I IS~[IJUER SURGE V TANK EL. 665'-5'"

-t:.. TO Fe PUIJPS 33'-0"

.. 1 I..

33'-i" jt LO'II POOL lEVEL,oILo\\~M ELEVATION VIEW

Response to Request for Additional Information (Order EA-1 2-051)

Page 4 of 11 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The OIP states, in part, that:

The current plan is to install SFP level sensors in the southwest corner of the Unit 1 SFP and in the northwest corner of the Unit 2 SFP separated by a distance in excess of 50 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB [Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services as required by the Quad Cities design basis.

RAI-2

Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.3 Mounting The OIP states, in part, that:

Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Installed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.

RAI-3

Please provide the following:

a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic Response to Request for Additional Information (Order EA-12-051)

Page 4 of 11 3.0 INSTRUMENTATION DESIGN FEATURES 3.2 Arrangement The 01 P states, in part, that:

The current plan is to install SFP level sensors in the southwest corner of the Unit 1 SFP and in the northwest corner of the Unit 2 SFP separated by a distance in excess of 50 feet. The sensors themselves will be mounted, to the extent practical, near the pool walls and below the pool curb to minimize their exposure to damaging debris and not interfere with SFP activities. Instrument channel electronics and power supplies will be located in seismic and missile protected areas either below the SFP operating floor or in buildings other than the RB [Reactor Building]. The areas to be selected will provide suitable radiation shielding and environmental conditions for the equipment consistent with instrument manufacturer's recommendations. Equipment and cabling for power supplies and indication for each channel will be separated equivalent to that provided for redundant safety related services as required by the Quad Cities design basis.

Please provide a clearly labeled sketch or marked-up plant drawing of the plan view of the SFP area, depicting the SFP inside dimensions, the planned locations/placement of the primary and back-up SFP level sensor, and the proposed routing of the cables that will extend from the sensors toward the location of the read-ouVdisplay device.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.3 Mounting The OIP states, in part, that:

Design of the mounting of the sensors in the SFP shall be consistent with the seismic Class I criteria. Insta"ed equipment will be verified to be seismically adequate for the seismic motions associated with the maximum seismic ground motion considered in the design of the plant area in which it is installed.

Please provide the following:

a) The design criteria that will be used to estimate the total loading on the mounting device(s), including static weight loads and dynamic loads. Describe the methodology that will be used to estimate the total loading, inclusive of design basis maximum seismic

Response to Request for Additional Information (Order EA-12-051)

Page 5 of 11 loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.

b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical connections.

c) A description of the manner by which the mechanical connections will attach the level instrument to permanent SFP structures so as to support the level sensor assembly.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.4 Qualification The OIP states, in part, that:

Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:

components are supplied by manufacturers using commercial quality programs (such as IS09001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; or components are inherently resistant to shock and vibration loadings, such as cables.

For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:

instrument channel components use known operating principles and are supplied by manufacturers with commercial quality programs (such as IS09001). The procurement specification and/or instrument channel design shall include the seismic requirements and specify the need for commercial design and testing under seismic loadings consistent with design basis values at the installed locations; Response to Request for Additional Information (Order EA-12-051)

Page 5 of 11 loads and the hydrodynamic loads that could result from pool sloshing or other effects that could accompany such seismic forces.

b) A description of the manner in which the level sensor (and stilling well, if appropriate) will be attached to the refueling floor and/or other support structures for each planned point of attachment of the probe assembly. Indicate in a schematic the portions of the level sensor that will serve as points of attachment for mechanical/mounting or electrical conn ections.

c) A description of the manner by which the mechanical connections will attach the level instrument to permanent 8FP structures so as to support the level sensor assembly.

Response

The current plan for the 8FPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.4 Qualification The OIP states, in part, that:

Components of the instrument channels will be qualified for shock and vibration using one or more of the following methods:

components are supplied by manufacturers using commercial quality programs (such as 1809001, "Quality management systems - Requirements") with shock and vibration requirements included in the purchase specification at levels commensurate with portable hand-held devices or transportation applications; components have substantial history of operational reliability in environments with significant shock and vibration loadings, such as portable hand-held devices or transportation applications; or components are inherently resistant to shock and vibration loadings, such as cables.

For seismic effects on instrument channel components used after a potential seismic event for only installed components (with the exception of battery chargers and replaceable batteries), the following measures will be used to verify that the design and installation is adequate. Applicable components are rated by the manufacturer (or otherwise tested) for seismic effects at levels commensurate with those of postulated design basis event conditions in the area of instrument channel component use using one or more of the following methods:

instrument channel components use known operating principles and are supplied by manufacturers with commercial quality programs (such as 1809001). The procurement speCification and/or instrument channel design shall include the seismic requirements and specify the need for commercial design and testing under seismic loadings consistent with design basis values at the installed locations;

Response to Request for Additional Information (Order EA-12-051)

Page 6of11 substantial history of operational reliability in environments with significant vibration, such as for portable hand-held devices or transportation applications. Such a vibration design envelope shall be inclusive of the effects of seismic motion imparted to the components proposed at the location of the proposed installation; adequacy of seismic design and installation is demonstrated based on the guidance in Sections 7, 8, 9, and 10 of IEEE [Institute of Electrical and Electronics Engineers]

Standard 344-2004, "IEEE Recommended Practice for Seismic Qualification of Class 1 E Equipment for Nuclear Power Generating Stations," or a substantially similar industrial standard; demonstration that proposed devices are substantially similar in design to models that have been previously tested for seismic effects in excess of the plant design basis at the location where the instrument is to be installed (g-levels and frequency ranges); or seismic qualification using seismic motion consistent with that of existing design basis loading at the installation location.

RAi-4 Please provide the following:

a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.

b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.

c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.5 Independence The OIP states, in part, that:

The primary instrument channel will be independent of the backup instrument channel.

This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.

Response to Request for Additional I nformation (Order EA-12-051)

Page 6 of 11 substantial history of operational reliability in environments with significant vibration, such as for portable hand-held devices or transportation applications. Such a vibration design envelope shall be inclusive of the effects of seismic motion imparted to the components proposed at the location of the proposed installation; adequacy of seismic design and installation is demonstrated based on the guidance in Sections 7,8,9, and 10 of IEEE [Institute of Electrical and Electronics Engineers]

Standard 344-2004, "IEEE Recommended Practice for Seismic Qualification of Class 1 E Equipment for Nuclear Power Generating Stations," or a substantially similar industrial standard; demonstration that proposed devices are substantially similar in design to models that have been previously tested for seismic effects in excess of the plant design basis at the location where the instrument is to be installed (g-Ievels and frequency ranges); or seismic qualification using seismic motion consistent with that of existing design basis loading at the installation location.

Please provide the following:

a) A description of the specific method or combination of methods you intend to apply to demonstrate the reliability of the permanently installed equipment under beyond-design-basis ambient temperature, humidity, shock, vibration, and radiation conditions.

b) A description of the testing and/or analyses that will be conducted to provide assurance that the equipment will perform reliably under the worst-case credible design basis loading at the location where the equipment will be mounted. Include a discussion of this seismic reliability demonstration as it applies to a) the level sensor mounted in the SFP area, and b) any control boxes, electronics, or read-out and re-transmitting devices that will be employed to convey the level information from the level sensor to the plant operators or emergency responders.

c) A description of the specific method or combination of methods that will be used to confirm the reliability of the permanently installed equipment such that following a seismic event the instrument will maintain its required accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.5 Independence The 01 P states, in part, that:

The primary instrument channel will be independent of the backup instrument channel.

This independence will be achieved through physical and electrical separation of each channels' components commensurate with hazard and electrical isolation needs.

Response to Request for Additional Information (Order EA-12-051)

Page 7 of 11

RAI-5

Please provide the following:

a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.

b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.6 Power supplies The OIP states, in part, that:

Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049 (Ref. 4). Additionally, each channel will have provisions for connection to another suitable power source.

RAI-6

Please provide the following:

a) A description of the electrical ac power sources and capacities for the primary and backup channels.

b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).

Response to Request for Additional Information (Order EA-12-051)

Page 7 of 11 Please provide the following:

a) A description of how the two channels of the proposed level measurement system meet this requirement so that the potential for a common cause event to adversely affect both channels is minimized to the extent practicable.

b) Further information on how each level measurement system, consisting of level sensor electronics, cabling, and readout devices will be designed and installed to address independence through the application and selection of independent power sources, the use of physical and spatial separation, independence of signals sent to the location(s) of the readout devices, and the independence of the displays.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.6 Power supplies The OIP states, in part, that:

Each channel will be normally powered from a different 120Vac [120 volts-alternating current] bus. Upon loss of normal ac power, individual channel installed batteries will automatically maintain continuous channel operation. The batteries will be replaceable and be sized to maintain channel operation until off-site resources can be deployed by the mitigating strategies resulting from Order EA-12-049 (Ref. 4). Additionally, each channel will have provisions for connection to another suitable power source.

Please provide the following:

a) A description of the electrical ac power sources and capacities for the primary and backup channels.

b) If the level measurement channels are to be powered through a battery system (either directly or through an uninterruptible power supply), please provide the design criteria that will be applied to size the battery in a manner that ensures, with margin, that the channel will be available to run reliably and continuously following the onset of the beyond-design-basis event for the minimum duration needed, consistent with the plant mitigation strategies for beyond-design-basis external events (Order EA-12-049).

Response to Request for Additional Information (Order EA-1 2-051)

Page 8 of 11

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.7 Accuracy The OIP states, in part, that:

The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment, concentrated borated water), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.

RAI-7

Please provide the following:

a) An estimate of the expected instrument channel accuracy performance under both a) normal SFP level conditions (approximately L1 or higher) and b) at the beyond design-basis conditions (i.e., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the L2 and L3 datum points.

b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.8 Testing The OIP states, in part, that:

Response to Request for Additional Information (Order EA-12-051)

Page 8 of 11

Response

~~-~ ---~~----

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.7 Accuracy The OIP states, in part, that:

The instrument channels will be designed to maintain their design accuracy following a power interruption or change in power source without recalibration. Instrument channel accuracy, to be determined during detailed design, will consider Spent Fuel Pool conditions (e.g., saturated water, steam environment, concentrated borated water), as well as, other applicable radiological and environmental conditions and include display accuracy. Instrument channel accuracy will be sufficient to allow trained personnel to determine when the actual level exceeds the specified lower level of each indicating range (levels 1, 2 or 3) without conflicting or ambiguous indications.

Please provide the following:

a) An estimate of the expected instrument channel accuracy performance under both a) normal SFP level conditions (approximately L 1 or higher) and b) at the beyond design-basis conditions (i.e., radiation, temperature, humidity, post-seismic and post-shock conditions) that would be present if the SFP level were at the L2 and L3 datum points.

b) A description of the methodology that will be used for determining the maximum allowed deviation from the instrument channel design accuracy that will be employed under normal operating conditions as an acceptance criterion for a calibration procedure to flag to operators and to technicians that the channel requires adjustment to within the normal condition design accuracy.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

3.8 Testing The OIP states, in part, that:

Response to Request for Additional Information (Order EA-1 2-051)

Page 9 of 11 Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3). Details will be determined during detailed design engineering.

RAI-8

Please provide the following:

a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.

b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation.

c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.

d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.

3.9 Display The OIP states, in part, that:

The primary and backup instrument displays will be located at the control room, alternate shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design. An appropriate and accessible location will include the following characteristics:

occupied promptly accessible to the appropriate plant staff giving appropriate consideration to various drain down scenarios, Response to Request for Additional Information (Order EA-12-051)

Page 9 of 11 Instrument channel design will provide for routine testing and calibration consistent with the guidelines of NRC JLD-ISG-2012-03 (Ref. 2) and NEI 12-02 (Ref. 3). Details will be determined during detailed design engineering.

Please provide the following:

a) A description of the capability and provisions the proposed level sensing equipment will have to enable periodic testing and calibration, including how this capability enables the equipment to be tested in-situ.

b) A description of how such testing and calibration will enable the conduct of regular channel checks of each independent channel against the other, and against any other permanently-installed SFP level instrumentation.

c) A description of how functional checks will be performed, and the frequency at which they will be conducted. Describe how calibration tests will be performed, and the frequency at which they will be conducted. Provide a discussion as to how these surveillances will be incorporated into the plant surveillance program.

d) A description of what preventative maintenance tasks are required to be performed during normal operation, and the planned maximum surveillance interval that is necessary to ensure that the channels are fully conditioned to accurately and reliably perform their functions when needed.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.

3.9 Display The OIP states, in part, that:

The primary and backup instrument displays will be located at the control room, alternate shutdown panel, or other appropriate and accessible location. The specific location will be determined during detailed design. An appropriate and accessible location will include the following characteristics:

occupied promptly accessible to the appropriate plant staff giving appropriate consideration to various drain down scenarios,

Response to Request for Additional Information (Order EA-12-051)

Page 10 of 11 outside the area surrounding the SFP floor (e.g., an appropriate distance from the radiological sources resulting from an event impacting the Spent Fuel Pool),

inside a structure providing protection against adverse weather, and outside of any Very High radiation areas or LOCKED HIGH RAD AREA during normal operation.

RAI-9

Please provide the following:

a) The specific location for each of the primary and backup instrument channel displays.

b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.

c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

4.0 PROGRAM FEATURES 4.2 Procedures The OIP states, in part, that:

Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.

RAI-10

Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.

Response to Request for Additional Information (Order EA-12-051)

Page 10 of 11 outside the area surrounding the SFP floor (e.g., an appropriate distance from the radiological sources resulting from an event impacting the Spent Fuel Pool),

inside a structure providing protection against adverse weather, and outside of any Very High radiation areas or LOCKED HIGH RAD AREA during normal operation.

Please provide the following:

a) The specific location for each of the primary and backup instrument channel displays.

b) If the primary and backup display location is other than the main control room, provide justification for prompt accessibility to displays including primary and alternate route evaluation, habitability at display location(s), continual resource availability for personnel responsible to promptly read displays, and provisions for communications with decision makers for the various SFP drain down scenarios and external events.

c) The reasons justifying why the locations selected enable the information from these instruments to be considered "promptly accessible" to various drain-down scenarios and external events.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. The requested information will be provided with the August of 2014, 6-month integrated plan update.

4.0 PROGRAM FEATURES 4.2 Procedures The 01 P states, in part, that:

RAI-10

Procedures will be developed using guidelines and vendor instructions to address the maintenance, operation and abnormal response issues associated with the primary and backup channels of SFP instrumentation.

Please provide a description of the standards, guidelines and/or criteria that will be utilized to develop procedures for inspection, maintenance, repair, operation, abnormal response, and administrative controls associated with the SFP level instrumentation, as well as storage and installation of portable instruments.

Response to Request for Additional Information (Order EA-1 2-051)

Page 11 of 11

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.

4.3 Testing and Calibration The OIP states, in part, that:

The testing and calibration of the instrumentation will be consistent with vendor recommendations or other documented basis. Calibration will be specific to the mounted instruments and the displays. Instrument performance will be trended as described in Exelon procedural requirements.

RAI-11

Please provide the following:

a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.

b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.

c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.

Response to Request for Additional Information (Order EA-12-051)

Page 11 of 11

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the design, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.

4.3 Testing and Calibration The OIP states, in part, that:

RAI-11

The testing and calibration of the instrumentation will be consistent with vendor recommendations or other documented basis. Calibration will be specific to the mounted instruments and the displays. Instrument performance will be trended as described in Exelon procedural requirements.

Please provide the following:

a) Further information describing the maintenance and testing program the licensee will establish and implement to ensure that regular testing and calibration is performed and verified by inspection and audit to demonstrate conformance with design and system readiness requirements. Include a description of your plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.

b) A description of how the guidance in NEI 12-02 Section 4.3 regarding compensatory actions for one or both non-functioning channels will be addressed.

c) A description of what compensatory actions are planned in the event that one of the instrument channels cannot be restored to functional status within 90 days.

Response

The current plan for the SFPI design of the system based on the current Exelon Nuclear program schedule for Quad Cities is to begin the design phase in October of 2013 with the design completion and 100% acceptance of the design in March of 2014. Following the issue of the deSign, procedures will start being developed with a projected October 2014 completion date. The requested information will be provided in the August 2014, 6-month integrated plan update.