ML080910312: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
(One intermediate revision by the same user not shown)
Line 18: Line 18:
=Text=
=Text=
{{#Wiki_filter:March 28, 2008  
{{#Wiki_filter:March 28, 2008  
  Mr. James McCarthy Site Vice President FPL Energy Point Beach, LLC  
6610 Nuclear Road Two Rivers, WI  54241  
  SUBJECT: POINT BEACH NUCLEAR PLANT   REQUEST FOR INFORMATION FOR AN NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS) Dear Mr. McCarthy: On June 23, 2008, the NRC will begin a triennial baseline Component Design Bases Inspection (CDBI) at the Point Beach Nuclear Plant.  A team of six inspectors will perform this  
3-week inspection.  This inspection will be performed in accordance with NRC Baseline Inspection Procedure (IP) 71111.21.  The CDBI inspection focuses on components that have high risk and low design margins.  The components to be reviewed during this baseline inspection will be identified during an in-office preparation week prior to the first week of the on-site inspection.  In addition, a number of risk  
Mr. James McCarthy  
significant operator actions and operating experience issues, associated with the component samples, will also be selected for review.  The inspection will include three weeks on-site, including the information gathering during the first on-site week.  The inspection team will consist of six NRC inspectors, of which five will focus on engineering and one on operations.  The current inspection schedule is as follows:   
Site Vice President  
* On-site weeks:  June 23, 2008, through June 27, 2008;   July 7, 2008, through July 11, 2008; and     July 21, 2008, through July 25, 2008. The team will be preparing for the inspection, mainly during the week of June 16, 2008, as discussed in the attached enclosure.  A Region III Senior Reactor Analyst may accompany the inspection team during the week of June 23, 2008, to review probabilistic risk assessment data, and assist in identifying risk significant components, which will be reviewed during the  
FPL Energy Point Beach, LLC  
inspection. Experience with previous baseline design inspections of similar depth and length has shown that these types of inspections are extremely resource intensive, both for the NRC inspectors and the licensee staff.  In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for  
6610 Nuclear Road  
the inspection.
Two Rivers, WI  54241  
J. McCarthy -2- It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.  Insofar as possible, this information should be provided electronically to the lead  
   
SUBJECT:  
POINT BEACH NUCLEAR PLANT
REQUEST FOR INFORMATION FOR AN NRC TRIENNIAL BASELINE  
COMPONENT DESIGN BASES INSPECTION (CDBI) 05000266/2008009(DRS);  
05000301/2008009(DRS)  
Dear Mr. McCarthy:  
On June 23, 2008, the NRC will begin a triennial baseline Component Design Bases Inspection  
(CDBI) at the Point Beach Nuclear Plant.  A team of six inspectors will perform this  
3-week inspection.  This inspection will be performed in accordance with NRC Baseline  
Inspection Procedure (IP) 71111.21.   
The CDBI inspection focuses on components that have high risk and low design margins.  The  
components to be reviewed during this baseline inspection will be identified during an in-office  
preparation week prior to the first week of the on-site inspection.  In addition, a number of risk  
significant operator actions and operating experience issues, associated with the component  
samples, will also be selected for review.   
The inspection will include three weeks on-site, including the information gathering during the  
first on-site week.  The inspection team will consist of six NRC inspectors, of which five will  
focus on engineering and one on operations.  The current inspection schedule is as follows:   
*  
On-site weeks:  June 23, 2008, through June 27, 2008;  
July 7, 2008, through July 11, 2008; and
July 21, 2008, through July 25, 2008.  
The team will be preparing for the inspection, mainly during the week of June 16, 2008, as  
discussed in the attached enclosure.  A Region III Senior Reactor Analyst may accompany the  
inspection team during the week of June 23, 2008, to review probabilistic risk assessment data,  
and assist in identifying risk significant components, which will be reviewed during the  
inspection.  
Experience with previous baseline design inspections of similar depth and length has shown  
that these types of inspections are extremely resource intensive, both for the NRC inspectors  
and the licensee staff.  In order to minimize the inspection impact on the site and to ensure a  
productive inspection for both parties, we have enclosed a request for information needed for  
the inspection.  
 
J. McCarthy  
-2-  
It is important that all of these documents are up to date and complete in order to minimize the  
number of additional documents requested during the preparation and/or the on-site portions of  
the inspection.  Insofar as possible, this information should be provided electronically to the lead  
inspector.  The information request has been divided into three groups:  
inspector.  The information request has been divided into three groups:  
* The first group lists information necessary for our initial inspection scoping activities.  This information should be provided to the lead inspector no later than May 12, 2008.  By May 30, 2008, the lead inspector will communicate the initial selected set of approximately 30 high risk components.   
*  
* The second group of documents requested are those items needed to support our in-office preparation activities.  This set of documents, including the calculations associated with the  
The first group lists information necessary for our initial inspection scoping activities.   
initial selected components, should be provided to the lead inspector at the Regional Office no later than June 9, 2008.  During the in-office preparation activities, the team may identify additional information needed to support the inspection.   
This information should be provided to the lead inspector no later than May 12, 2008.  By  
* The third and last group includes the additional information above, as well as plant specific reference material.  This information should be available to the team onsite on  
May 30, 2008, the lead inspector will communicate the initial selected set of approximately  
June 23, 2008.  It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated.  The lead inspector for this inspection is Mr. Zelig Falevits.  We understand that our licensing contact for this inspection is Ms. Fritzie Flentje of your organization.  If there are any questions  
30 high risk components.   
about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9717 or via e-mail at zelig.falevits@nrc.gov. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide  
*  
Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely,  /RA/  Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety  Docket No. 50-266; 50-301 License No. DPR-24; DPR-27 Enclosure: Component Design Bases Inspection (CDBI) Document Request  
The second group of documents requested are those items needed to support our in-office  
  See Attached Distribution  
preparation activities.  This set of documents, including the calculations associated with the  
initial selected components, should be provided to the lead inspector at the Regional Office  
no later than June 9, 2008.  During the in-office preparation activities, the team may identify  
additional information needed to support the inspection.   
*  
The third and last group includes the additional information above, as well as plant  
specific reference material.  This information should be available to the team onsite on  
June 23, 2008.  It is also requested that corrective action documents and/or questions  
developed during the inspection be provided to the lead inspector as the documents are  
generated.   
The lead inspector for this inspection is Mr. Zelig Falevits.  We understand that our licensing  
contact for this inspection is Ms. Fritzie Flentje of your organization.  If there are any questions  
about the inspection or the material requested in the enclosure, please contact the lead  
inspector at (630) 829-9717 or via e-mail at zelig.falevits@nrc.gov.  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and  
its enclosure will be available electronically for public inspection in the NRC Public Document  
Room or from the Publicly Available Records System (PARS) component of NRCs Agencywide  
Documents Access and Management System (ADAMS), accessible from the NRC Web site at  
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
Sincerely,  
   
/RA/  
   
Ann Marie Stone, Chief  
Engineering Branch 2  
Division of Reactor Safety   
Docket No. 50-266; 50-301  
License No. DPR-24; DPR-27  
Enclosure:  
Component Design Bases Inspection (CDBI) Document Request  
See Attached Distribution
 
Letter to Mr. James McCarthy from Ms. A. M. Stone dated March 28, 2008.  
Letter to Mr. James McCarthy from Ms. A. M. Stone dated March 28, 2008.  
  SUBJECT: POINT BEACH NUCLEAR PLANT REQUEST FOR INFORMATION FOR AN NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS)  
  cc w/encl: M. Nazar, Senior Vice President and Nuclear     Chief Operating Officer   J. Stall, Senior Vice President and   
    Chief Nuclear Officer   R. Kundalkar, Vice President, Nuclear Technical Services   Licensing Manager, Point Beach Nuclear Plant   M. Ross, Managing Attorney A. Fernandez, Senior Attorney   K. Duveneck, Town Chairman     Town of Two Creeks  Chairperson    Public Service Commission of Wisconsin   J. Kitsembel, Electric Division  
SUBJECT:  
    Public Service Commission of Wisconsin   P. Schmidt, State Liaison Officer  
POINT BEACH NUCLEAR PLANT REQUEST FOR INFORMATION FOR AN  
 
NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION  
 
(CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS)  
  J. McCarthy -2-  
cc w/encl:  
M. Nazar, Senior Vice President and Nuclear  
  Chief Operating Officer  
J. Stall, Senior Vice President and   
  Chief Nuclear Officer  
R. Kundalkar, Vice President, Nuclear Technical Services  
Licensing Manager, Point Beach Nuclear Plant  
M. Ross, Managing Attorney  
A. Fernandez, Senior Attorney  
K. Duveneck, Town Chairman  
  Town of Two Creeks  
Chairperson
   Public Service Commission of Wisconsin  
J. Kitsembel, Electric Division  
  Public Service Commission of Wisconsin  
P. Schmidt, State Liaison Officer  
 
J. McCarthy  
-2-  
   
   
It is important that all of these documents are up to date and complete in order to minimize the number of  
It is important that all of these documents are up to date and complete in order to minimize the number of  
additional documents requested during the preparation and/or the on-site portions of the inspection.   
additional documents requested during the preparation and/or the on-site portions of the inspection.   
Insofar as possible, this information should be provided electronically to the lead inspector.  The  
Insofar as possible, this information should be provided electronically to the lead inspector.  The  
information request has been divided into three groups: * The first group lists information necessary for our initial inspection scoping activities.  This information should be provided to the lead inspector no later than May 12, 2008.  By May 30, 2008, the lead  
information request has been divided into three groups:  
inspector will communicate the initial selected set of approximately 30 high risk components.  * The second group of documents requested are those items needed to support our in-office preparation activities.  This set of documents, including the calculations associated with the initial selected components, should be provided to the lead inspector at the Regional Office no later than June 9, 2008.  During the in-office preparation activities, the team may identify additional information  
*  
needed to support the inspection.  * The last group includes the additional information above as well as plant specific reference material.  This information should be available to the team onsite on June 23, 2008.  It is also requested that  
The first group lists information necessary for our initial inspection scoping activities.  This information  
corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated.  The lead inspector for this inspection is Mr. Zelig Falevits.  We understand that our licensing contact for this inspection is Ms. Fritzie Flentje of your organization.  If there are any questions about the inspection  
should be provided to the lead inspector no later than May 12, 2008.  By May 30, 2008, the lead  
inspector will communicate the initial selected set of approximately 30 high risk components.   
*  
The second group of documents requested are those items needed to support our in-office  
preparation activities.  This set of documents, including the calculations associated with the initial  
selected components, should be provided to the lead inspector at the Regional Office no later than  
June 9, 2008.  During the in-office preparation activities, the team may identify additional information  
needed to support the inspection.   
*  
The last group includes the additional information above as well as plant specific reference material.   
This information should be available to the team onsite on June 23, 2008.  It is also requested that  
corrective action documents and/or questions developed during the inspection be provided to the lead  
inspector as the documents are generated.   
The lead inspector for this inspection is Mr. Zelig Falevits.  We understand that our licensing contact for  
this inspection is Ms. Fritzie Flentje of your organization.  If there are any questions about the inspection  
or the material requested in the enclosure, please contact the lead inspector at (630) 829-9717 or via e-
or the material requested in the enclosure, please contact the lead inspector at (630) 829-9717 or via e-
mail at zelig.falevits@nrc.gov. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and  
mail at zelig.falevits@nrc.gov.  
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure  
will be available electronically for public inspection in the NRC Public Document Room or from the  
Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and  
Management System (ADAMS), accessible from the NRC Web site at  
Management System (ADAMS), accessible from the NRC Web site at  
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely,   Ann Marie Stone, Chief  
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
Sincerely,  
Ann Marie Stone, Chief  
Engineering Branch 2  
Engineering Branch 2  
Division of Reactor Safety  Docket No. 50-266; 50-301 License No. DPR-24; DPR-27 Enclosure: Component Design Bases Inspection (CDBI) Document Request  
Division of Reactor Safety   
DISTRIBUTION
Docket No. 50-266; 50-301  
See next page G:\DRS\Work in Progress\Ltr. 03__08 Point Beach CDBI RFI CEA.doc  Publicly Available  Non-Publicly Available  Sensitive  Non-Sensitive
License No. DPR-24; DPR-27  
To receive a copy of this document, indicate in the concurrence  box "C" = Copy without attach/encl "E" = Copy with attach/encl  "N" = No copy
Enclosure:  
OFFICE: RIII  RIII  RIII  RIII  NAME: AMStone for CAcosta:  ls AMStone   DATE: 03/28/08 03/28/08  
Component Design Bases Inspection (CDBI) Document Request  
  OFFICIAL RECORD COPY  
DISTRIBUTION  
  Letter to Mr. James McCarthy from Ms. A M. Stone dated March 28, 2008.  
See next page  
  SUBJECT: POINT BEACH NUCLEAR PLANT REQUEST FOR INFORMATION FOR AN NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION (CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS)  
G:\\DRS\\Work in Progress\\Ltr. 03__08 Point Beach CDBI RFI CEA.doc  
  cc w/encl: M. Nazar, Senior Vice President and Nuclear     Chief Operating Officer   J. Stall, Senior Vice President and   
  Publicly Available  
    Chief Nuclear Officer   R. Kundalkar, Vice President, Nuclear Technical Services   Licensing Manager, Point Beach Nuclear Plant   M. Ross, Managing Attorney A. Fernandez, Senior Attorney   K. Duveneck, Town Chairman     Town of Two Creeks  
  Non-Publicly Available  
   Chairperson    Public Service Commission of Wisconsin   J. Kitsembel, Electric Division     Public Service Commission of Wisconsin   P. Schmidt, State Liaison Officer  
  Sensitive  
  Non-Sensitive  
To receive a copy of this document, indicate in the concurrence  box "C" = Copy without attach/encl "E" = Copy with attach/encl  "N" = No copy  
OFFICE: RIII  
   
RIII  
   
RIII  
   
RIII  
   
NAME:  
AMStone for CAcosta:  ls  
AMStone  
DATE:  
03/28/08  
03/28/08  
   
OFFICIAL RECORD COPY
 
Letter to Mr. James McCarthy from Ms. A M. Stone dated March 28, 2008.  
   
SUBJECT:  
POINT BEACH NUCLEAR PLANT REQUEST FOR INFORMATION FOR AN  
NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION  
(CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS)  
cc w/encl:  
M. Nazar, Senior Vice President and Nuclear  
  Chief Operating Officer  
J. Stall, Senior Vice President and   
  Chief Nuclear Officer  
R. Kundalkar, Vice President, Nuclear Technical Services  
Licensing Manager, Point Beach Nuclear Plant  
M. Ross, Managing Attorney  
A. Fernandez, Senior Attorney  
K. Duveneck, Town Chairman  
  Town of Two Creeks  
Chairperson
   Public Service Commission of Wisconsin  
J. Kitsembel, Electric Division  
  Public Service Commission of Wisconsin  
P. Schmidt, State Liaison Officer  
DISTRIBUTION:
TEB
CFL
EMH1
LXR1
RidsNrrDirsIrib
MAS
KGO
JKH3
CAA1
RGK
DRPIII
DRSIII
PLB1
TXN
ROPreports@nrc.gov 


  DISTRIBUTION:
TEB CFL
EMH1 LXR1 RidsNrrDirsIrib
MAS KGO
JKH3 CAA1 RGK DRPIII DRSIII
PLB1 TXN ROPreports@nrc.gov
 
INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
  COMPONENT DESING BASES INSPECTION (CDBI)  
   
  Enclosure  
COMPONENT DESING BASES INSPECTION (CDBI)  
1Inspection Report:  05000266/2008009; 05000301/2008009 (DRS) Inspection Dates:  June 23, 2008, through June 27, 2008;     July 7, 2008, through July 11, 2008; and      July 21, 2008, through July 25, 2008 Inspection Procedure:  IP 71111.21 "Component Design Bases Inspection" Lead Inspector:  Zelig Falevits, Lead Inspector  (630) 829-9717      zelig,falevits@nrc.gov
I. Information Requested Prior to the On-site Information Gathering/Inspection Week
  The following information is requested by May 12, 2008, or sooner, to facilitate inspection preparation.  If you have any questions regarding this information, please call the team leader as soon as possible.  (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on CDROM.  The CDROM
Enclosure  
should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use.  Information in "lists" should contain enough information to be easily understood by someone who has knowledge of boiling water reactor technology). 1. Risk ranking of top 150 components from your site specific probabilistic safety analysis (PSA) sorted by Risk Achievement Worth (RAW). Include values for
1
Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV) (as applicable). 2. Provide a list of the top 200 cut-sets from your PSA. 3. Risk ranking of operator actions from your site specific PSA sorted by RAW.  Provide copies of your human reliability worksheets for these items. 4. If you have an External Events or Fire PSA Model, provide the information requested in Items 1 and 2 for external events and fire. Provide narrative description of each coded event (including fire, flood zone description). 5. Any pre-existing evaluation or list of components and associated calculations with low design margins, (i.e., pumps closest to the design limit for flow or pressure,
Inspection Report:  
diesel generator close to design required output, heat exchangers close to rated design heat removal etc.).
   
05000266/2008009; 05000301/2008009 (DRS)  
Inspection Dates:   
June 23, 2008, through June 27, 2008;  
   
   
    
    
  INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
July 7, 2008, through July 11, 2008; and 
  COMPONENT DESIGN BASES INSPECTION (CDBI)  
    Enclosure  
26. List of available design (setup) margins for valves in the motor-operated valve (MOV) and air-operated valve (AOV) programs.  
 
  7. List of high risk Maintenance Rule Systems/components based on engineering or expert panel judgment.  
July 21, 2008, through July 25, 2008
  8. Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1) category.  
Inspection Procedure: 
  9. Site top ten issues list (if applicable).   
IP 71111.21 Component Design Bases Inspection
  10. A list of operating experience evaluations for the last 3 years.  
Lead Inspector:
  11. Information of any common cause failure of components experienced in the last 5 years at your facility.  
  12. List of Root Cause Evaluations associated with component failures or design issues initiated/completed in the last 5 years.  
Zelig Falevits, Lead Inspector 
  13. List of open operability evaluations.  
(630) 829-9717 
  14. Current management and engineering organizational chart.  
  15. Electronic copies of Updated Final Safety Analysis Report, Technical Specifications, Technical Specifications Bases, and Technical Requirements Manual. 16. One line electrical drawings (ac and dc) and key diagrams (paper copies). II. Information requested (for the approximate 30 selected components) to be available by June 9, 2008, (will be reviewed by the team in the Regional Office during the week of June 16, 2008).  This information should be separated for each selected component, especially if provided electronically (e.g., folder with component name that includes calculations, condition reports, maintenance history, etc). 1. List of condition reports (corrective action documents) associated with each of the selected components for the last 4 years. 2. The corrective maintenance history associated with each of the selected components for the last 4 years. 3. Copies of calculations associated with each of the selected components (if not previously provided), excluding data files.  Please review the calculations and also provide copies of referenced material (such as drawings, engineering requests,   
INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
  COMPONENT DESIGN BASES INSPECTION (CDBI)  
    Enclosure  
zelig,falevits@nrc.gov
3and vendor letters). 4. System Health Reports, System Descriptions, and/or Design Basis Documents that are associated with each of the selected components. 5. A list of modifications associated with each of the selected components.
I.
  This list should include a descriptive paragraph on the purpose of the modification.  Please ensure this list only includes design completed (not canceled) modifications. 6. Copies of operability evaluations (open/closed for last 3 years) associated with each of the selected components and plans for restoring operability, if applicable. 7. Copies of selected operator work-around evaluations associated with each of the selected components and plans for resolution, if applicable. 8. Copies of any open temporary modifications associated with each of the selected components, if applicable. 9. Trend data on the selected electrical/mechanical components' performance for last 3 years (For example, pumps' performance including in-service testing, other vibration monitoring, oil sample results, etc., as applicable). 10. A copy of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection. 11. A copy of engineering/operations related audits completed in the last 2 years.  
Information Requested Prior to the On-site Information Gathering/Inspection Week  
12. Provide list of PRA assumptions regarding operator actions and the associated procedures. 13. Provide copies of any simulator scenarios, lesson plans, or job performance measures for the selected operator actions. 14. Provide copies of the results of any time-dependent simulator scenarios or job performance measures for operator crews/individuals for the selected operator actions.  15. Provide copies of the emergency operating procedures, normal and abnormal operating procedures and any alarm response procedures for the selected operator actions.  Also provide copies of the conduct for operations and operability  
The following information is requested by May 12, 2008, or sooner, to facilitate
determination procedures.  
inspection preparation.  If you have any questions regarding this information, please call
  INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
the team leader as soon as possible.  (Please provide the information electronically in
  COMPONENT DESIGN BASES INSPECTION (CDBI)  
pdf files, Excel, or other searchable formats, preferably on CDROM.  The CDROM
    Enclosure  
should contain descriptive names, and be indexed and hyperlinked to facilitate ease of
4III. Additional Information to be provided on June 23, 2008 on-site (for final 15 - 20 selected components)  
use.  Information in lists should contain enough information to be easily understood by
During the in-office preparation activities, the team will be making final selections and may identify additional information needed to support the inspection.  The lead inspector will provide a list of the additional information needed during the week of April 28, 2008.  IV. Information Requested to be provided throughout the inspection
someone who has knowledge of boiling water reactor technology).
  1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection. 2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member). 3. One complete set of P&IDs (paper copies).  
1.
4. Reference materials.  (make available if needed during all on-site weeks): a. IPE/PRA Report; b. Procurement documents for components selected (verify retrievable);  
Risk ranking of top 150 components from your site specific probabilistic safety
c. Plant procedures (normal, abnormal, emergency, surveillance, etc.); and d. Vendor manuals. If you have questions regarding the information requested, please contact the lead inspector.
analysis (PSA) sorted by Risk Achievement Worth (RAW).  Include values for
Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV)
(as applicable).
2.
Provide a list of the top 200 cut-sets from your PSA.
3.
Risk ranking of operator actions from your site specific PSA sorted by RAW.
Provide copies of your human reliability worksheets for these items.
4.
If you have an External Events or Fire PSA Model, provide the information
requested in Items 1 and 2 for external events and fire.  Provide narrative
description of each coded event (including fire, flood zone description).
5.
Any pre-existing evaluation or list of components and associated calculations with
low design margins, (i.e., pumps closest to the design limit for flow or pressure,
diesel generator close to design required output, heat exchangers close to rated
design heat removal etc.).
 
INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
COMPONENT DESIGN BASES INSPECTION (CDBI)  
Enclosure  
2
6.  
List of available design (setup) margins for valves in the motor-operated valve  
(MOV) and air-operated valve (AOV) programs.  
   
7.  
List of high risk Maintenance Rule Systems/components based on engineering or  
expert panel judgment.  
   
8.  
Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)  
category.  
   
9.  
Site top ten issues list (if applicable).   
   
10. A list of operating experience evaluations for the last 3 years.  
   
11. Information of any common cause failure of components experienced in the last  
5 years at your facility.  
   
12. List of Root Cause Evaluations associated with component failures or design  
issues initiated/completed in the last 5 years.  
   
13. List of open operability evaluations.  
   
14. Current management and engineering organizational chart.  
   
15. Electronic copies of Updated Final Safety Analysis Report, Technical  
Specifications, Technical Specifications Bases, and Technical Requirements  
Manual.  
16. One line electrical drawings (ac and dc) and key diagrams (paper copies).  
II.  
Information requested (for the approximate 30 selected components) to be  
available by June 9, 2008, (will be reviewed by the team in the Regional Office  
during the week of June 16, 2008).  This information should be separated for each  
selected component, especially if provided electronically (e.g., folder with  
component name that includes calculations, condition reports, maintenance  
history, etc).  
1.  
List of condition reports (corrective action documents) associated with each of the  
selected components for the last 4 years.  
2.  
The corrective maintenance history associated with each of the selected  
components for the last 4 years.  
3.  
Copies of calculations associated with each of the selected components (if not  
previously provided), excluding data files.  Please review the calculations and also  
provide copies of referenced material (such as drawings, engineering requests,  
 
   
INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
COMPONENT DESIGN BASES INSPECTION (CDBI)  
Enclosure  
3
and vendor letters).  
4.  
System Health Reports, System Descriptions, and/or Design Basis Documents that  
are associated with each of the selected components.  
5.  
A list of modifications associated with each of the selected components. This list  
should include a descriptive paragraph on the purpose of the modification.  Please  
ensure this list only includes design completed (not canceled) modifications.  
6.  
Copies of operability evaluations (open/closed for last 3 years) associated with  
each of the selected components and plans for restoring operability, if applicable.  
7.  
Copies of selected operator work-around evaluations associated with each of the  
selected components and plans for resolution, if applicable.  
8.  
Copies of any open temporary modifications associated with each of the selected  
components, if applicable.  
9.  
Trend data on the selected electrical/mechanical components performance for last  
3 years (For example, pumps performance including in-service testing, other  
vibration monitoring, oil sample results, etc., as applicable).  
10. A copy of any internal/external self-assessments and associated corrective action  
documents generated in preparation for the inspection.  
11. A copy of engineering/operations related audits completed in the last 2 years.  
12. Provide list of PRA assumptions regarding operator actions and the associated  
procedures.  
13. Provide copies of any simulator scenarios, lesson plans, or job performance  
measures for the selected operator actions.  
14. Provide copies of the results of any time-dependent simulator scenarios or job  
performance measures for operator crews/individuals for the selected operator  
actions.   
15. Provide copies of the emergency operating procedures, normal and abnormal  
operating procedures and any alarm response procedures for the selected  
operator actions.  Also provide copies of the conduct for operations and operability  
determination procedures.
 
   
INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT  
COMPONENT DESIGN BASES INSPECTION (CDBI)  
Enclosure  
4
III.  
Additional Information to be provided on June 23, 2008 on-site (for final 15 - 20  
selected components)
During the in-office preparation activities, the team will be making final selections and  
may identify additional information needed to support the inspection.  The lead inspector  
will provide a list of the additional information needed during the week of April 28, 2008.   
IV.  
Information Requested to be provided throughout the inspection  
1. Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.  
2. Copies of the list of questions submitted by the team members and the  
status/resolution of the information requested (provide daily during the inspection to  
each team member).  
3. One complete set of P&IDs (paper copies).  
4. Reference materials.  (make available if needed during all on-site weeks):  
a. IPE/PRA Report;  
b. Procurement documents for components selected (verify retrievable);  
c. Plant procedures (normal, abnormal, emergency, surveillance, etc.); and  
d. Vendor manuals.  
If you have questions regarding the information requested, please contact the lead inspector.
}}
}}

Latest revision as of 18:25, 14 January 2025

Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) 05000266/2008009 (Drs); 05000301/2008009 (DRS)
ML080910312
Person / Time
Site: Point Beach  
Issue date: 03/28/2008
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Mccarthy J
Florida Power & Light Energy Point Beach
References
IR-08-009
Download: ML080910312 (9)


See also: IR 05000266/2008009

Text

March 28, 2008

Mr. James McCarthy

Site Vice President

FPL Energy Point Beach, LLC

6610 Nuclear Road

Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT

REQUEST FOR INFORMATION FOR AN NRC TRIENNIAL BASELINE

COMPONENT DESIGN BASES INSPECTION (CDBI) 05000266/2008009(DRS);

05000301/2008009(DRS)

Dear Mr. McCarthy:

On June 23, 2008, the NRC will begin a triennial baseline Component Design Bases Inspection

(CDBI) at the Point Beach Nuclear Plant. A team of six inspectors will perform this

3-week inspection. This inspection will be performed in accordance with NRC Baseline

Inspection Procedure (IP) 71111.21.

The CDBI inspection focuses on components that have high risk and low design margins. The

components to be reviewed during this baseline inspection will be identified during an in-office

preparation week prior to the first week of the on-site inspection. In addition, a number of risk

significant operator actions and operating experience issues, associated with the component

samples, will also be selected for review.

The inspection will include three weeks on-site, including the information gathering during the

first on-site week. The inspection team will consist of six NRC inspectors, of which five will

focus on engineering and one on operations. The current inspection schedule is as follows:

On-site weeks: June 23, 2008, through June 27, 2008;

July 7, 2008, through July 11, 2008; and

July 21, 2008, through July 25, 2008.

The team will be preparing for the inspection, mainly during the week of June 16, 2008, as

discussed in the attached enclosure. A Region III Senior Reactor Analyst may accompany the

inspection team during the week of June 23, 2008, to review probabilistic risk assessment data,

and assist in identifying risk significant components, which will be reviewed during the

inspection.

Experience with previous baseline design inspections of similar depth and length has shown

that these types of inspections are extremely resource intensive, both for the NRC inspectors

and the licensee staff. In order to minimize the inspection impact on the site and to ensure a

productive inspection for both parties, we have enclosed a request for information needed for

the inspection.

J. McCarthy

-2-

It is important that all of these documents are up to date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into three groups:

The first group lists information necessary for our initial inspection scoping activities.

This information should be provided to the lead inspector no later than May 12, 2008. By

May 30, 2008, the lead inspector will communicate the initial selected set of approximately

30 high risk components.

The second group of documents requested are those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with the

initial selected components, should be provided to the lead inspector at the Regional Office

no later than June 9, 2008. During the in-office preparation activities, the team may identify

additional information needed to support the inspection.

The third and last group includes the additional information above, as well as plant

specific reference material. This information should be available to the team onsite on

June 23, 2008. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the lead inspector as the documents are

generated.

The lead inspector for this inspection is Mr. Zelig Falevits. We understand that our licensing

contact for this inspection is Ms. Fritzie Flentje of your organization. If there are any questions

about the inspection or the material requested in the enclosure, please contact the lead

inspector at (630) 829-9717 or via e-mail at zelig.falevits@nrc.gov.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records System (PARS) component of NRCs Agencywide

Documents Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-266; 50-301

License No. DPR-24; DPR-27

Enclosure:

Component Design Bases Inspection (CDBI) Document Request

See Attached Distribution

Letter to Mr. James McCarthy from Ms. A. M. Stone dated March 28, 2008.

SUBJECT:

POINT BEACH NUCLEAR PLANT REQUEST FOR INFORMATION FOR AN

NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION

(CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS)

cc w/encl:

M. Nazar, Senior Vice President and Nuclear

Chief Operating Officer

J. Stall, Senior Vice President and

Chief Nuclear Officer

R. Kundalkar, Vice President, Nuclear Technical Services

Licensing Manager, Point Beach Nuclear Plant

M. Ross, Managing Attorney

A. Fernandez, Senior Attorney

K. Duveneck, Town Chairman

Town of Two Creeks

Chairperson

Public Service Commission of Wisconsin

J. Kitsembel, Electric Division

Public Service Commission of Wisconsin

P. Schmidt, State Liaison Officer

J. McCarthy

-2-

It is important that all of these documents are up to date and complete in order to minimize the number of

additional documents requested during the preparation and/or the on-site portions of the inspection.

Insofar as possible, this information should be provided electronically to the lead inspector. The

information request has been divided into three groups:

The first group lists information necessary for our initial inspection scoping activities. This information

should be provided to the lead inspector no later than May 12, 2008. By May 30, 2008, the lead

inspector will communicate the initial selected set of approximately 30 high risk components.

The second group of documents requested are those items needed to support our in-office

preparation activities. This set of documents, including the calculations associated with the initial

selected components, should be provided to the lead inspector at the Regional Office no later than

June 9, 2008. During the in-office preparation activities, the team may identify additional information

needed to support the inspection.

The last group includes the additional information above as well as plant specific reference material.

This information should be available to the team onsite on June 23, 2008. It is also requested that

corrective action documents and/or questions developed during the inspection be provided to the lead

inspector as the documents are generated.

The lead inspector for this inspection is Mr. Zelig Falevits. We understand that our licensing contact for

this inspection is Ms. Fritzie Flentje of your organization. If there are any questions about the inspection

or the material requested in the enclosure, please contact the lead inspector at (630) 829-9717 or via e-

mail at zelig.falevits@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure

will be available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and

Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-266; 50-301

License No. DPR-24; DPR-27

Enclosure:

Component Design Bases Inspection (CDBI) Document Request

DISTRIBUTION

See next page

G:\\DRS\\Work in Progress\\Ltr. 03__08 Point Beach CDBI RFI CEA.doc

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE: RIII

RIII

RIII

RIII

NAME:

AMStone for CAcosta: ls

AMStone

DATE:

03/28/08

03/28/08

OFFICIAL RECORD COPY

Letter to Mr. James McCarthy from Ms. A M. Stone dated March 28, 2008.

SUBJECT:

POINT BEACH NUCLEAR PLANT REQUEST FOR INFORMATION FOR AN

NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION

(CDBI) 05000266/2008009(DRS); 05000301/2008009(DRS)

cc w/encl:

M. Nazar, Senior Vice President and Nuclear

Chief Operating Officer

J. Stall, Senior Vice President and

Chief Nuclear Officer

R. Kundalkar, Vice President, Nuclear Technical Services

Licensing Manager, Point Beach Nuclear Plant

M. Ross, Managing Attorney

A. Fernandez, Senior Attorney

K. Duveneck, Town Chairman

Town of Two Creeks

Chairperson

Public Service Commission of Wisconsin

J. Kitsembel, Electric Division

Public Service Commission of Wisconsin

P. Schmidt, State Liaison Officer

DISTRIBUTION:

TEB

CFL

EMH1

LXR1

RidsNrrDirsIrib

MAS

KGO

JKH3

CAA1

RGK

DRPIII

DRSIII

PLB1

TXN

ROPreports@nrc.gov

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESING BASES INSPECTION (CDBI)

Enclosure

1

Inspection Report: 05000266/2008009; 05000301/2008009 (DRS)

Inspection Dates:

June 23, 2008, through June 27, 2008;

July 7, 2008, through July 11, 2008; and

July 21, 2008, through July 25, 2008

Inspection Procedure:

IP 71111.21 Component Design Bases Inspection

Lead Inspector:

Zelig Falevits, Lead Inspector

(630) 829-9717

zelig,falevits@nrc.gov

I.

Information Requested Prior to the On-site Information Gathering/Inspection Week

The following information is requested by May 12, 2008, or sooner, to facilitate

inspection preparation. If you have any questions regarding this information, please call

the team leader as soon as possible. (Please provide the information electronically in

pdf files, Excel, or other searchable formats, preferably on CDROM. The CDROM

should contain descriptive names, and be indexed and hyperlinked to facilitate ease of

use. Information in lists should contain enough information to be easily understood by

someone who has knowledge of boiling water reactor technology).

1.

Risk ranking of top 150 components from your site specific probabilistic safety

analysis (PSA) sorted by Risk Achievement Worth (RAW). Include values for

Birnbaum Importance, Risk Reduction Worth (RRW), and Fussell-Veseley (FV)

(as applicable).

2.

Provide a list of the top 200 cut-sets from your PSA.

3.

Risk ranking of operator actions from your site specific PSA sorted by RAW.

Provide copies of your human reliability worksheets for these items.

4.

If you have an External Events or Fire PSA Model, provide the information

requested in Items 1 and 2 for external events and fire. Provide narrative

description of each coded event (including fire, flood zone description).

5.

Any pre-existing evaluation or list of components and associated calculations with

low design margins, (i.e., pumps closest to the design limit for flow or pressure,

diesel generator close to design required output, heat exchangers close to rated

design heat removal etc.).

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESIGN BASES INSPECTION (CDBI)

Enclosure

2

6.

List of available design (setup) margins for valves in the motor-operated valve

(MOV) and air-operated valve (AOV) programs.

7.

List of high risk Maintenance Rule Systems/components based on engineering or

expert panel judgment.

8.

Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)

category.

9.

Site top ten issues list (if applicable).

10. A list of operating experience evaluations for the last 3 years.

11. Information of any common cause failure of components experienced in the last

5 years at your facility.

12. List of Root Cause Evaluations associated with component failures or design

issues initiated/completed in the last 5 years.

13. List of open operability evaluations.

14. Current management and engineering organizational chart.

15. Electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, Technical Specifications Bases, and Technical Requirements

Manual.

16. One line electrical drawings (ac and dc) and key diagrams (paper copies).

II.

Information requested (for the approximate 30 selected components) to be

available by June 9, 2008, (will be reviewed by the team in the Regional Office

during the week of June 16, 2008). This information should be separated for each

selected component, especially if provided electronically (e.g., folder with

component name that includes calculations, condition reports, maintenance

history, etc).

1.

List of condition reports (corrective action documents) associated with each of the

selected components for the last 4 years.

2.

The corrective maintenance history associated with each of the selected

components for the last 4 years.

3.

Copies of calculations associated with each of the selected components (if not

previously provided), excluding data files. Please review the calculations and also

provide copies of referenced material (such as drawings, engineering requests,

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESIGN BASES INSPECTION (CDBI)

Enclosure

3

and vendor letters).

4.

System Health Reports, System Descriptions, and/or Design Basis Documents that

are associated with each of the selected components.

5.

A list of modifications associated with each of the selected components. This list

should include a descriptive paragraph on the purpose of the modification. Please

ensure this list only includes design completed (not canceled) modifications.

6.

Copies of operability evaluations (open/closed for last 3 years) associated with

each of the selected components and plans for restoring operability, if applicable.

7.

Copies of selected operator work-around evaluations associated with each of the

selected components and plans for resolution, if applicable.

8.

Copies of any open temporary modifications associated with each of the selected

components, if applicable.

9.

Trend data on the selected electrical/mechanical components performance for last

3 years (For example, pumps performance including in-service testing, other

vibration monitoring, oil sample results, etc., as applicable).

10. A copy of any internal/external self-assessments and associated corrective action

documents generated in preparation for the inspection.

11. A copy of engineering/operations related audits completed in the last 2 years.

12. Provide list of PRA assumptions regarding operator actions and the associated

procedures.

13. Provide copies of any simulator scenarios, lesson plans, or job performance

measures for the selected operator actions.

14. Provide copies of the results of any time-dependent simulator scenarios or job

performance measures for operator crews/individuals for the selected operator

actions.

15. Provide copies of the emergency operating procedures, normal and abnormal

operating procedures and any alarm response procedures for the selected

operator actions. Also provide copies of the conduct for operations and operability

determination procedures.

INFORMATION REQUEST FOR PERRY NUCLEAR POWER PLANT

COMPONENT DESIGN BASES INSPECTION (CDBI)

Enclosure

4

III.

Additional Information to be provided on June 23, 2008 on-site (for final 15 - 20

selected components)

During the in-office preparation activities, the team will be making final selections and

may identify additional information needed to support the inspection. The lead inspector

will provide a list of the additional information needed during the week of April 28, 2008.

IV.

Information Requested to be provided throughout the inspection

1. Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

2. Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the inspection to

each team member).

3. One complete set of P&IDs (paper copies).

4. Reference materials. (make available if needed during all on-site weeks):

a. IPE/PRA Report;

b. Procurement documents for components selected (verify retrievable);

c. Plant procedures (normal, abnormal, emergency, surveillance, etc.); and

d. Vendor manuals.

If you have questions regarding the information requested, please contact the lead inspector.