| {{#Wiki_filter:}} | | {{#Wiki_filter:SECY-00-045 RIS 2000-17 LG-13-147 November 26, 2013 |
| | |
| | U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353 |
| | |
| | ==Subject:== |
| | Annual Commitment Change Summary Report |
| | |
| | This report summarizes Limerick changes to NRC commitments that meet the threshold for reporting for the period from July 1, 2012 to June 30, 2013. Changes to these commitments are performed using procedure LS-AA-110, Commitment Management , which employs the guidance provided in NEI 99-04, Guidelines for Managing NRC Commitment Changes. NEI 99-04 was approved by the NRC for licensee use by SECY-00-045, Acceptance of NEI 99-04, 'Guidelines for Managing NRC Commitments'. Licensees were informed that NEI 99-04 was an acceptable process for control of regulatory commitments by the issuance of RIS 2000-17, Managing Regulatory Commitments made by Power Reactor Licensees to the NRC Staff, on September 21, 2000. |
| | There are no new regulatory commitments contained in this letter. |
| | |
| | If you have any questions or require additional information, please do not hesitate to contact us. |
| | |
| | Sincerely, |
| | |
| | Original signed by |
| | |
| | Thomas J. Dougherty Vice President - Limerick Exelon Generation Company, LLC |
| | |
| | ==Attachment:== |
| | List of changes to NRC commitments cc: Administrator Region I, USNRC USNRC Senior Resident Inspector, LGS |
| | |
| | Attachment - List of changes to NRC commitments November 26, 2013 |
| | |
| | Page 1 of 1 LS-AA-110 Commitment Management, Section 4.7, "NRC Notification of Commitment Changes/Deletions," requires submittal of a written report once per calendar year. This report shall contain a summary of commitment changes that require NRC notification. |
| | |
| | The following commitment change was implemented between July 1, 2012 and June 30, 2013 and requires NRC notification. |
| | |
| | Commitment change tracking number: 2012-015 CT number: T03114 Commitment source document: NRC Inspection Report 50-352/87-18 and 87-12 Change: Deleted Requestor: Engineering |
| | |
| | ==Subject:== |
| | |
| | Procedure to Control Equipment Classification (Q-list) |
| | |
| | Statement of commitment: |
| | Amended Engineering and Research Department Procedure (ERDP) for revising the Limerick Unit 1 Project Q-List to meet commitments by the licensee which were associated with NRC Generic Letter 83-28, in order to administratively assign responsibility for Q-List revisions. |
| | Change to commitment: |
| | |
| | Deleted |
| | |
| | Justification for change: |
| | The commitment has been captured as part of an ongoing program that is subject to a revision review process (e.g., Station Qualified Reviewer (SQR)). Guidance remains in CC-MA-304 "Establishing and Maintaining Component Classification." The commitment |
| | |
| | has been met and the NRC has closed this unresolved issue.}} |
Revision as of 20:15, 13 July 2018
|
---|
Category:Letter
MONTHYEARIR 05000352/20243012024-02-0202 February 2024 Initial Operator Licensing Examination Report 05000352/2024301 and 05000353/2024301 IR 05000352/20230042024-01-31031 January 2024 Integrated Inspection Report 05000352/2023004 and 05000353/2023004 IR 05000352/20240112024-01-31031 January 2024 Information Request to Support Post-Approval Site Inspection for License Renewal; Inspection Report 05000352/2024011 ML24026A2962024-01-26026 January 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)- Syrs, . ML24004A0342024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0026 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000352/20230102024-01-11011 January 2024 Age-Related Degradation Report 05000352/2023010 and 05000353/2023010 IR 05000352/20234012023-12-21021 December 2023 Cybersecurity Inspection Report 05000352/2023401 and 05000353/2023401 ML23321A2362023-12-14014 December 2023 Issuance of Amendment Nos. 262 and 224 Adoption of TSTF-477, Revision 3 and Associated Technical Specification Changes ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23333A2182023-11-29029 November 2023 Operator Licensing Examination Approval ML23325A2062023-11-21021 November 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23313A0432023-11-13013 November 2023 Summary of Regulatory Audit in Support of Amendment Request for Control Room Air Conditioning Technical Specifications ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000352/20230032023-10-27027 October 2023 Integrated Inspection Report 05000352/2023003 and 05000353/2023003 and Independent Spent Fuel Storage Installation Inspection 07200065/2023001 ML23297A1722023-10-24024 October 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000352/2024010 and 05000353/2024010 IR 05000352/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000352/2023501 and 05000353/2023501 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23276A5162023-10-0303 October 2023 Federal Emergency Management Agency Level 1 Finding from 2023 Evaluated Emergency Preparedness Exercise ML23275A1082023-09-29029 September 2023 FEMA Level 1 Findings Limerick NPP- Boyertown/Colebrookdale ML23241A9452023-09-27027 September 2023 Generation Station, Units 1 and 2 Regulatory Audit Plan Supporting Review of the Equipment Qualification Portion of Limerick Digital Instrumentation and Controls License Amendment Request ML23269A0522023-09-26026 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000352/2023010 and 05000353/2023010 ML23255A0952023-09-12012 September 2023 Resubmittal of License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) to Address ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A1002023-09-0606 September 2023 Requalification Program Inspection IR 05000352/20230052023-08-31031 August 2023 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2023005 and 05000353/2023005) ML23248A2082023-08-31031 August 2023 UFSAR Cover Page ML23242A2172023-08-30030 August 2023 Response to Request for Additional Information for Application to Adopt TSTF-477, Revision 3, Add Action for Two Inoperable Control Room AC Subsystems and Associated Technical Specification Changes NMP2L2851, Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations2023-08-25025 August 2023 Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations ML23228A0942023-08-16016 August 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . IR 05000352/20230022023-08-14014 August 2023 Integrated Inspection Report 05000352/2023002 and 05000353/2023002 ML23220A0182023-08-0808 August 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000352/2023401 and 05000353/2023401 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212B2362023-07-31031 July 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System - WEC Documents ML23212B1052023-07-31031 July 2023 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation - Revise ML23202A2192023-07-21021 July 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . ML23193B0122023-07-20020 July 2023 Audit Plan in Support of Review of License Amendment Request and Exemption Request for Digital Instrumentation and Controls Installation Support (Epids L-2023-LLA-0025 and L-2023-LLE-0005) ML23187A0962023-07-19019 July 2023 Generation Station, Unit Nos. 1 and 2 - Revised Estimated Review Completion Date Concerning License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23208A1522023-07-0606 July 2023 PEMA Letter Dated 7-6-23 Re Limerick Exercise 9-26-23 ML23177A2242023-06-26026 June 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection . ML23145A1972023-06-23023 June 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 255, 256, 257, 258, 259, and 260 2024-02-02
[Table view] |
Text
SECY-00-045 RIS 2000-17 LG-13-147 November 26, 2013
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353
Subject:
Annual Commitment Change Summary Report
This report summarizes Limerick changes to NRC commitments that meet the threshold for reporting for the period from July 1, 2012 to June 30, 2013. Changes to these commitments are performed using procedure LS-AA-110, Commitment Management , which employs the guidance provided in NEI 99-04, Guidelines for Managing NRC Commitment Changes. NEI 99-04 was approved by the NRC for licensee use by SECY-00-045, Acceptance of NEI 99-04, 'Guidelines for Managing NRC Commitments'. Licensees were informed that NEI 99-04 was an acceptable process for control of regulatory commitments by the issuance of RIS 2000-17, Managing Regulatory Commitments made by Power Reactor Licensees to the NRC Staff, on September 21, 2000.
There are no new regulatory commitments contained in this letter.
If you have any questions or require additional information, please do not hesitate to contact us.
Sincerely,
Original signed by
Thomas J. Dougherty Vice President - Limerick Exelon Generation Company, LLC
Attachment:
List of changes to NRC commitments cc: Administrator Region I, USNRC USNRC Senior Resident Inspector, LGS
Attachment - List of changes to NRC commitments November 26, 2013
Page 1 of 1 LS-AA-110 Commitment Management, Section 4.7, "NRC Notification of Commitment Changes/Deletions," requires submittal of a written report once per calendar year. This report shall contain a summary of commitment changes that require NRC notification.
The following commitment change was implemented between July 1, 2012 and June 30, 2013 and requires NRC notification.
Commitment change tracking number: 2012-015 CT number: T03114 Commitment source document: NRC Inspection Report 50-352/87-18 and 87-12 Change: Deleted Requestor: Engineering
Subject:
Procedure to Control Equipment Classification (Q-list)
Statement of commitment:
Amended Engineering and Research Department Procedure (ERDP) for revising the Limerick Unit 1 Project Q-List to meet commitments by the licensee which were associated with NRC Generic Letter 83-28, in order to administratively assign responsibility for Q-List revisions.
Change to commitment:
Deleted
Justification for change:
The commitment has been captured as part of an ongoing program that is subject to a revision review process (e.g., Station Qualified Reviewer (SQR)). Guidance remains in CC-MA-304 "Establishing and Maintaining Component Classification." The commitment
has been met and the NRC has closed this unresolved issue.