05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot insert
 
StriderTol Bot change
 
(2 intermediate revisions by the same user not shown)
Line 17: Line 17:
| Title = Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators
| Title = Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators
| Plant =  
| Plant =  
| Reporting criterion = 10 CFR 50.73(a)(2)(iv)(A), 10 CFR 50.73(a)(2)(iv)(A)
| Reporting criterion = 10 CFR 50.73(a)(2)(iv)(A)
| Power level =  
| Power level =  
| Mode =  
| Mode =  
Line 31: Line 31:


=text=
=text=
{{#Wiki_filter:TENNESSEE VALLEY 1\\14 AUTHORITY
{{#Wiki_filter:Post Office Box 2000, Decatur, Alabama 35609-2000 October 29, 2024 10 CFR 50.73 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-33 and DPR-52 NRC Docket Nos. 50-259 and 50-260  
 
Post Office Box 2000, Decatur, Alabama 35609-2000
 
October 29, 2024 10 CFR 50.73
 
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
 
Browns Ferry Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-33 and DPR-52 NRC Docket Nos. 50-259 and 50-260
 
Subject: Licensee Event Report 50-259/2024-003-00
 
The enclosed Licensee Event Report provides details of a breaker trip which automatically started Emergency Diesel Generators on Browns Ferry Nuclear Plant, Units 1 and 2. The Tennessee Valley Authority is submitting this report in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 50.73(a)(2)(iv)(A), as an event or condition that resulted in the unplanned, valid, manual or automatic actuation of emergency AC electrical power systems.


==Subject:==
Licensee Event Report 50-259/2024-003-00 The enclosed Licensee Event Report provides details of a breaker trip which automatically started Emergency Diesel Generators on Browns Ferry Nuclear Plant, Units 1 and 2. The Tennessee Valley Authority is submitting this report in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 50.73(a)(2)(iv)(A), as an event or condition that resulted in the unplanned, valid, manual or automatic actuation of emergency AC electrical power systems.
There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact David J. Renn, Nuclear Site Licensing Manager, at (256) 729-2636.
There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact David J. Renn, Nuclear Site Licensing Manager, at (256) 729-2636.
Respectfully, Daniel A. Komm Site Vice President Enclosure: Licensee Event Report 50-259/2024-003 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators cc (w/ Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant 1\14 TENNESSEE VALLEY AUTHORITY


Respectfully,
U.S. Nuclear Regulatory Commission Page 2 October 29, 2024 DJR:RWC Enclosure bcc (w/ Enclosure):
 
A. Aboulfaida K. S. Adams M. B. Bruce D. M. Delk R. C. Dreke S. T. Earley C. Edmondson D. E. Ferrell J. E. Gordon K. D. Hulvey J. T. Johnson D. Komm E. Q. Leonard R. Medina M. W. Oliver J. L. Paul M. Rasmussen T. S. Rausch D. J. Renn C. L. Rice D. K. Riggs M. Sivaraman J. A. Yarbrough ECM  
Daniel A. Komm Site Vice President
 
Enclosure: Licensee Event Report 50-259/2024-003 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators
 
cc (w/ Enclosure):
 
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant
 
U.S. Nuclear Regulatory Commission Page 2 October 29, 2024
 
DJR:RWC Enclosure bcc (w/ Enclosure):
 
A. Aboulfaida K. S. Adams M. B. Bruce D. M. Delk R. C. Dreke S. T. Earley C. Edmondson D. E. Ferrell J. E. Gordon K. D. Hulvey J. T. Johnson D. Komm E. Q. Leonard R. Medina M. W. Oliver J. L. Paul M. Rasmussen T. S. Rausch D. J. Renn C. L. Rice D. K. Riggs M. Sivaraman J. A. Yarbrough ECM


=Abstract=
=Abstract=
On August 30, 2024, at 1051 Central Daylight Time Breaker 1622 failed to close during the transfer of Shutdown Bus 1 from 4kV Unit Board 1A to 4kV Unit Board 2B. This failure resulted in deenergizing 4kV Shutdown (SD) Boards A and B, and the A and B Emergency Diesel Generators started and tied to their respective 4kV SD Boards in response.
On August 30, 2024, at 1051 Central Daylight Time Breaker 1622 failed to close during the transfer of Shutdown Bus 1 from 4kV Unit Board 1A to 4kV Unit Board 2B. This failure resulted in deenergizing 4kV Shutdown (SD) Boards A and B, and the A and B Emergency Diesel Generators started and tied to their respective 4kV SD Boards in response.
 
The cause of the event was a loose LS-9 appliance lug which resulted in a loss of power on 4kV SD Boards A and B. As corrective action, the lug was repaired. Additional actions to prevent recurrence will include, briefing of operators and maintenance personnel on this event, as well as procedure enhancements to operating instructions.  
The cause of the event was a loose LS-9 appliance lug which resulted in a loss of power on 4kV SD Boards A and B. As corrective action, the lug was repaired. Additional actions to prevent recurrence will include, briefing of operators and maintenance personnel on this event, as well as procedure enhancements to operating instructions.
.::.¢1>""£au(.,>
 
f ¥.'
==I. Plant Operating Conditions before the Event==
l
At the time of occurrence, Browns Ferry Nuclear Plant (BFN) Unit 1 was in Mode 1 at approximately 73 percent power. Power decreased throughout this event as part of a planned shutdown to support Unit 1 Refueling Outage 15 (U1R15). BFN Unit 2 was in Mode 1 at approximately 100 percent power.
"'+.,
 
,t,d" [8]
==II. Description of Event==
I [8]
==A. Event Summary==
I I
On August 30, 2024, at 1051 Central Daylight Time (CDT) Breaker 1622 (BFN-0-BKR-211-000D/001) [BKR] failed to close during the planned transfer of Shutdown Bus 1 from 4kV Unit Board 1A to 4kV Unit Board 2B in preparation for U1R15. This failure resulted in deenergizing 4kV Shutdown Boards (SD BDs) A and B, and the A and B Emergency Diesel Generators (EDGs) [EK] automatically started and tied to their respective 4kV SD BDs in response.
I I
 
I I I I
The Tennessee Valley Authority is submitting this report in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 50.73(a)(2)(iv)(A), as an event or condition that resulted in the manual or automatic actuation of emergency alternating current (AC) electrical power systems, including: EDGs.
I I
 
I I
B. Status of structures, components, or systems that were inoperable at the start of the event and that contributed to the event
I I
 
I I I
There were no structures, systems, or components (SSCs) whose inoperability contributed to this event.
I I
 
[8]
C. Dates and approximate times of occurrences
ID Page 6 of 6  
 
DATES AND APPROXIMATE OCCURRENCE TIMES August 30, 2024 4kV Shutdown Bus 1 failed to transfer. Breaker 1622 failed to close, 1051 CDT and BFN, Unit 1, lost power to the A and B 4kV SD BDs. EDGs A and B started and tied to their respective boards.
August 30, 2024 4kV SD BD A energized through the normal feeder breaker.
1250 CDT August 30, 2024 4kV SD BD B energized through the normal feeder breaker.
1336 CDT August 30, 2024 Ops personnel reported this event to the Nuclear Regulatory 1730 CDT Commission (NRC) as Event Notification 57298, in accordance with 10 CFR 50.72(b)(3)(iv)(A).
 
==D. Manufacturer and model number of each component that failed during the event==
BFN-0-BKR-211-000D/001 (Breaker 1622) is a General Electric circuit breaker, Part Number 317A7502P005.
 
==E. Other systems or secondary functions affected==
The equipment powered by the SD BD lost power until restarted following re-energization of the board.
 
==F. Method of discovery of each component or system failure or procedural error==
The failure of the breaker was discovered to be a loose lug that was discovered during troubleshooting of the breaker.
 
==G. The failure mode, mechanism, and effect of each failed component==
The breaker failed due to a loose LS-9 appliance lug.
 
==H. Operator actions==
The operators ensured the EDGs started and supplied power to the shutdown board and shutdown the EDGs once the normal power supply was restored to the SD boards.
 
==I. Automatically and manually initiated safety system responses==
The loss of power to the SD BDs is condition also caused a loss of the 1A and 2A reactor protection system (RPS), resulting in the invalid actuation of Primary Containment Isolation System Groups 2, 3, and 6 on BFN, Units 1 and 2.
 
The loss of the A RPS on BFN, Units 1 and 2 was not a specified system actuation, only the actuation of the A and B EDGs were a specified system actuation.
 
==III. Cause of the event==
The direct cause of the event was a loose LS-9 appliance lug which resulted in a loss of power on 4kV SD BDs A and B. There had been previous issues with this appliance lug coming loose which had yet to be permanently corrected.
 
==A. Cause of each component or system failure or personnel error==
The LS-9 appliance lug is uniquely specific to this application. The LS-9 appliance lug inputs into the charging spring indicating light. The LS-9 appliance lug required replacement, however, the required tooling had not been permitted for use at TVA.
 
B. Cause(s) and circumstances for each human performance related root cause
 
No human performance related root causes were identified.
 
==IV. Analysis of the event==
The 4kV bus under-voltage condition was a valid EDG signal, which caused the EDG to fulfil its designed safety function by automatically starting and tying to the board.
 
==V. Assessment of Safety Consequences==
All safety systems and alarms performed as designed in response to the unplanned, valid, automatic actuation signal. No actual safety consequences or radiological releases resulted from this event. All Technical Specification and Technical Requirements Manual conditions were met throughout this event. All mitigating systems remained functional and capable of fulfilling their required safety functions throughout this event. No fission product barriers were challenged during this event.
 
Based on the above, the TVA has concluded that sufficient systems were available to provide the required safety functions needed to protect the health and safety of the public.
 
A. Availability of systems or components that could have performed the same function as the components and systems that failed during the event
 
The breakers failure caused a valid actuation signal for the EDGs, which continued to power the affected SD BDs.
 
B. For events that occurred when the reactor was shut down, availability of systems or components needed to shutdown the reactor and maintain safe shutdown conditions, remove residual heat, control the release of radioactive material, or mitigate the consequences of an accident
 
This event did not occur when the reactor was shut down.
 
C. For failure that rendered a train of a safety system inoperable, estimate of the elapsed time from discovery of the failure until the train was returned to service
 
No safety systems were rendered inoperable during this event.
 
==VI. Corrective Actions==
Corrective Actions are being managed by the TVAs Corrective Action Program (CAP) under Condition Report (CR) 1954797.


==A. Immediate Corrective Actions==
==A. Immediate Corrective Actions==
Troubleshooting on Breaker 1622 and identified a loose wire on the charging spring limit switch. This wire was tightened and reattached.
Troubleshooting on Breaker 1622 and identified a loose wire on the charging spring limit switch. This wire was tightened and reattached.
 
B. Corrective Actions to Prevent Recurrence or to reduce the probability of similar events occurring in the future To prevent a recurrence of this event, BFN will perform the following corrective actions:
B. Corrective Actions to Prevent Recurrence or to reduce the probability of similar events occurring in the future
Verify the completion of Work Order (WO) 124788330, which replaces the LS-9 appliance lug for BFN-0-BKR-211-000D/001.
 
Verify that WOs exist to inspect safety-related 4kV Siemens breakers identified in the extent of condition and replaces their appliance lugs as required.
To prevent a recurrence of this event, BFN will perform the following corrective actions:
Conduct briefings to operations and maintenance personnel regarding this event.
* Verify the completion of Work Order (WO) 124788330, which replaces the LS-9 appliance lug for BFN-0-BKR-211-000D/001.
Revise 0-OI-57A, Switchyard and 4160V AC Electrical System, to include the guidance on precautions and limitations associated with the charging spring failure light.  
* Verify that WOs exist to inspect safety-related 4kV Siemens breakers identified in the extent of condition and replaces their appliance lugs as required.
* Conduct briefings to operations and maintenance personnel regarding this event.
* Revise 0-OI-57A, Switchyard and 4160V AC Electrical System, to include the guidance on precautions and limitations associated with the charging spring failure light.


==VII. Previous Similar Events at the Same Site==
==VII. Previous Similar Events at the Same Site==
A review of the BFN Licensee Event Reports (LERs) over the last five years revealed two similar events at BFN:
A review of the BFN Licensee Event Reports (LERs) over the last five years revealed two similar events at BFN:
LER 50-296/2024-002-00 describes a breaker trip which automatically started an EDG on BFN, Unit 3. This event was believed to have been caused by an intermittent loose connection, which was resolved during troubleshooting activities.
LER 50-296/2024-002-00 describes a breaker trip which automatically started an EDG on BFN, Unit 3. This event was believed to have been caused by an intermittent loose connection, which was resolved during troubleshooting activities.
LER 50-296/2020-001-00 describes an offsite lightning strike which caused the loss of the 4 kV SD BDs on BFN, Unit 3, and automatic actuated its EDGs.
LER 50-296/2020-001-00 describes an offsite lightning strike which caused the loss of the 4 kV SD BDs on BFN, Unit 3, and automatic actuated its EDGs.  


==VIII. Additional Information==
==VIII. Additional Information==
There is no additional information.
There is no additional information.
 
IX. Commitments There are no new commitments.
IX. Commitments
 
There are no new commitments.
}}
}}


{{LER-Nav}}
{{LER-Nav}}

Latest revision as of 03:41, 21 February 2026

Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators
ML24303A034
Person / Time
Site: Browns Ferry  
Issue date: 10/29/2024
From: Komm D
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
LER 2024-003-00
Download: ML24303A034 (1)


LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(iv)(A), System Actuation
2592024003R00 - NRC Website

text

Post Office Box 2000, Decatur, Alabama 35609-2000 October 29, 2024 10 CFR 50.73 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-33 and DPR-52 NRC Docket Nos. 50-259 and 50-260

Subject:

Licensee Event Report 50-259/2024-003-00 The enclosed Licensee Event Report provides details of a breaker trip which automatically started Emergency Diesel Generators on Browns Ferry Nuclear Plant, Units 1 and 2. The Tennessee Valley Authority is submitting this report in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 50.73(a)(2)(iv)(A), as an event or condition that resulted in the unplanned, valid, manual or automatic actuation of emergency AC electrical power systems.

There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact David J. Renn, Nuclear Site Licensing Manager, at (256) 729-2636.

Respectfully, Daniel A. Komm Site Vice President Enclosure: Licensee Event Report 50-259/2024-003 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators cc (w/ Enclosure):

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant 1\14 TENNESSEE VALLEY AUTHORITY

U.S. Nuclear Regulatory Commission Page 2 October 29, 2024 DJR:RWC Enclosure bcc (w/ Enclosure):

A. Aboulfaida K. S. Adams M. B. Bruce D. M. Delk R. C. Dreke S. T. Earley C. Edmondson D. E. Ferrell J. E. Gordon K. D. Hulvey J. T. Johnson D. Komm E. Q. Leonard R. Medina M. W. Oliver J. L. Paul M. Rasmussen T. S. Rausch D. J. Renn C. L. Rice D. K. Riggs M. Sivaraman J. A. Yarbrough ECM

Abstract

On August 30, 2024, at 1051 Central Daylight Time Breaker 1622 failed to close during the transfer of Shutdown Bus 1 from 4kV Unit Board 1A to 4kV Unit Board 2B. This failure resulted in deenergizing 4kV Shutdown (SD) Boards A and B, and the A and B Emergency Diesel Generators started and tied to their respective 4kV SD Boards in response.

The cause of the event was a loose LS-9 appliance lug which resulted in a loss of power on 4kV SD Boards A and B. As corrective action, the lug was repaired. Additional actions to prevent recurrence will include, briefing of operators and maintenance personnel on this event, as well as procedure enhancements to operating instructions.

.::.¢1>""£au(.,>

f ¥.'

l

"'+.,

,t,d" [8]

I [8]

I I

I I

I I I I

I I

I I

I I

I I I

I I

[8]

ID Page 6 of 6

A. Immediate Corrective Actions

Troubleshooting on Breaker 1622 and identified a loose wire on the charging spring limit switch. This wire was tightened and reattached.

B. Corrective Actions to Prevent Recurrence or to reduce the probability of similar events occurring in the future To prevent a recurrence of this event, BFN will perform the following corrective actions:

Verify the completion of Work Order (WO) 124788330, which replaces the LS-9 appliance lug for BFN-0-BKR-211-000D/001.

Verify that WOs exist to inspect safety-related 4kV Siemens breakers identified in the extent of condition and replaces their appliance lugs as required.

Conduct briefings to operations and maintenance personnel regarding this event.

Revise 0-OI-57A, Switchyard and 4160V AC Electrical System, to include the guidance on precautions and limitations associated with the charging spring failure light.

VII. Previous Similar Events at the Same Site

A review of the BFN Licensee Event Reports (LERs) over the last five years revealed two similar events at BFN:

LER 50-296/2024-002-00 describes a breaker trip which automatically started an EDG on BFN, Unit 3. This event was believed to have been caused by an intermittent loose connection, which was resolved during troubleshooting activities.

LER 50-296/2020-001-00 describes an offsite lightning strike which caused the loss of the 4 kV SD BDs on BFN, Unit 3, and automatic actuated its EDGs.

VIII. Additional Information

There is no additional information.

IX. Commitments There are no new commitments.