ML12272A215: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (One intermediate revision by the same user not shown) | |||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: Beltz, Terry Sent: Wednesday, September 26, 2012 6:01 AM To: Loeffler, Richard A. | {{#Wiki_filter:From: | ||
Cc: Kissinger, Peter W.; gene.eckholt@xenuclear.com; Frankl, Istvan | Beltz, Terry Sent: | ||
Wednesday, September 26, 2012 6:01 AM To: | |||
Loeffler, Richard A. | |||
Cc: | |||
Kissinger, Peter W.; gene.eckholt@xenuclear.com; Frankl, Istvan | |||
==Subject:== | ==Subject:== | ||
Monticello Nuclear Generating Plant - Acceptance Review re: | Monticello Nuclear Generating Plant - Acceptance Review re: License Amendment Request to Adopt TSTF-501, Revision 1 (TAC No. ME9601) | ||
==Dear Mr. Loeffler:== | ==Dear Mr. Loeffler:== | ||
By {{letter dated|date=September 18, 2012|text=letter dated September 18, 2012}} (Agencywide Documents Access and Management System (ADAMS) Accession No. ML122630070), Northern States Power Company - Minnesota, doing business as Xcel Energy, Inc., submitted a license amendment request (LAR) for the Monticello Nuclear Generating Plant. The LAR proposes to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control. | |||
By letter dated September 18, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML122630070), Northern States Power Company - Minnesota, doing business as Xcel Energy, Inc., submitted a license amendment request (LAR) for the Monticello Nuclear Generating Plant. The LAR proposes to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, | The purpose of this e-mail is to provide the final results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed change. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | ||
The NRC staff has reviewed your application and concluded that there appears to be sufficient technical information, both in scope and depth, to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the LAR in terms of regulatory requirements and the protection of public health and safety and the environment. | |||
The purpose of this e-mail is to provide the final results of the U.S. Nuclear Regulatory | If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. | ||
Commission (NRC) | |||
The NRC staff has reviewed your application and | |||
environment. | |||
If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. | |||
Should you have any questions regarding this review, please contact me at (301) 415-3049. | Should you have any questions regarding this review, please contact me at (301) 415-3049. | ||
Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov}} | Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov}} | ||
Latest revision as of 22:16, 11 January 2025
| ML12272A215 | |
| Person / Time | |
|---|---|
| Site: | Monticello |
| Issue date: | 09/26/2012 |
| From: | Beltz T Plant Licensing Branch III |
| To: | Loeffler R Xcel Energy |
| Beltz T | |
| References | |
| TAC ME9601 | |
| Download: ML12272A215 (1) | |
Text
From:
Beltz, Terry Sent:
Wednesday, September 26, 2012 6:01 AM To:
Loeffler, Richard A.
Cc:
Kissinger, Peter W.; gene.eckholt@xenuclear.com; Frankl, Istvan
Subject:
Monticello Nuclear Generating Plant - Acceptance Review re: License Amendment Request to Adopt TSTF-501, Revision 1 (TAC No. ME9601)
Dear Mr. Loeffler:
By letter dated September 18, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML122630070), Northern States Power Company - Minnesota, doing business as Xcel Energy, Inc., submitted a license amendment request (LAR) for the Monticello Nuclear Generating Plant. The LAR proposes to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control.
The purpose of this e-mail is to provide the final results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed change. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that there appears to be sufficient technical information, both in scope and depth, to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the LAR in terms of regulatory requirements and the protection of public health and safety and the environment.
If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
Should you have any questions regarding this review, please contact me at (301) 415-3049.
Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov