ML15323A433: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (6 intermediate revisions by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML15323A433 | | number = ML15323A433 | ||
| issue date = 11/16/2015 | | issue date = 11/16/2015 | ||
| title = Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions | | title = Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions | ||
| author name = Gebbie J | | author name = Gebbie J | ||
| author affiliation = American Electric Power, Indiana Michigan Power Co | | author affiliation = American Electric Power, Indiana Michigan Power Co | ||
| addressee name = | | addressee name = | ||
| Line 14: | Line 14: | ||
| page count = 2 | | page count = 2 | ||
| project = TAC:MF2916 | | project = TAC:MF2916 | ||
| stage = | | stage = Supplement | ||
}} | }} | ||
=Text= | =Text= | ||
{{#Wiki_filter:INIA NA MICHIGAN POWER A unit of American Electric Power November 16, 2015 Indiana Michigan Power-Cook Nuclear Plant One Cook Place Bridgrnan, MI 49106 IndianaMichiganPower.com AEP-N RC-201 5-114 10 CFR 50.90 Docket No.: 50-315 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC, 20555-0001 Donald C. Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions (TAO No. MF2916)" | {{#Wiki_filter:INIA NA MICHIGAN POWER | ||
* A unit of American Electric Power November 16, 2015 Indiana Michigan Power | |||
-Cook Nuclear Plant One Cook Place Bridgrnan, MI 49106 IndianaMichiganPower.com AEP-N RC-201 5-114 10 CFR 50.90 Docket No.: 50-315 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC, 20555-0001 Donald C. Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions (TAO No. MF2916)" | |||
==Reference:== | ==Reference:== | ||
: 1. Letter from Q. S. Lies, Indiana Michigan Power Company, to U. S. Nuclear Regulatory Commission Document Control Desk, "Donald C. Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions," dated September 18, 2015, Agencywide Documents Access and Management System Accession Number ML15265A036. | : 1. Letter from Q. S. Lies, Indiana Michigan Power Company, to U. S. Nuclear Regulatory Commission Document Control Desk, "Donald C. | ||
By letter dated September 18, 2015 (Reference 1), Indiana Michigan Power Company, licensee for Donald C. Cook Nuclear Plant (CNP) Unit 1, made a Commitment that: "The CNP Unit 1 analysis for containment pressure, which is based on WCAP-17721-P and the associated NRC Safety Evaluation dated August 24, 2015, will be implemented into the Donald C. Cook Nuclear Plant license basis." This letter is to inform the U. S. Nuclear Regulatory Commission that the commitment has been met for CNP Unit 1. | Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions," | ||
dated September 18, | |||
: 2015, Agencywide Documents Access and Management System Accession Number ML15265A036. | |||
By {{letter dated|date=September 18, 2015|text=letter dated September 18, 2015}} (Reference 1), Indiana Michigan Power Company, licensee for Donald C. Cook Nuclear Plant (CNP) Unit 1, made a Commitment that: "The CNP Unit 1 analysis for containment pressure, which is based on WCAP-17721-P and the associated NRC Safety Evaluation dated August 24, 2015, will be implemented into the Donald C. Cook Nuclear Plant license basis." | |||
This letter is to inform the U. S. Nuclear Regulatory Commission that the commitment has been met for CNP Unit 1. | |||
U. S. Nuclear Regulatory Commission AEP-NRC-2015-1 14 Page 2 This letter contains no new commitments. | U. S. Nuclear Regulatory Commission AEP-NRC-2015-1 14 Page 2 This letter contains no new commitments. | ||
Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.Sincerely, oelp ebbi~e Site Vice President, Indiana Michigan Power JMT/ams c: R. J. Ancona, MPSC A. W. Dietrich, NRC Washington DC MDEQ -RMD/RPS NRC Resident Inspector C. 0. Pederson, NRC Region Ill A. J, Williamson, AEP Ft. Wayne}} | Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649. | ||
Sincerely, oelp ebbi~e Site Vice President, Indiana Michigan Power JMT/ams c: | |||
R. J. Ancona, MPSC A. W. Dietrich, NRC Washington DC MDEQ - RMD/RPS NRC Resident Inspector C. 0. Pederson, NRC Region Ill A. J, Williamson, AEP Ft. Wayne}} | |||
Latest revision as of 06:25, 10 January 2025
| ML15323A433 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 11/16/2015 |
| From: | Gebbie J American Electric Power, Indiana Michigan Power Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| AEP-NRC-201-114, TAC MF2916 | |
| Download: ML15323A433 (2) | |
Text
INIA NA MICHIGAN POWER
-Cook Nuclear Plant One Cook Place Bridgrnan, MI 49106 IndianaMichiganPower.com AEP-N RC-201 5-114 10 CFR 50.90 Docket No.: 50-315 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC, 20555-0001 Donald C. Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions (TAO No. MF2916)"
Reference:
- 1. Letter from Q. S. Lies, Indiana Michigan Power Company, to U. S. Nuclear Regulatory Commission Document Control Desk, "Donald C.
Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions,"
dated September 18,
- 2015, Agencywide Documents Access and Management System Accession Number ML15265A036.
By letter dated September 18, 2015 (Reference 1), Indiana Michigan Power Company, licensee for Donald C. Cook Nuclear Plant (CNP) Unit 1, made a Commitment that: "The CNP Unit 1 analysis for containment pressure, which is based on WCAP-17721-P and the associated NRC Safety Evaluation dated August 24, 2015, will be implemented into the Donald C. Cook Nuclear Plant license basis."
This letter is to inform the U. S. Nuclear Regulatory Commission that the commitment has been met for CNP Unit 1.
U. S. Nuclear Regulatory Commission AEP-NRC-2015-1 14 Page 2 This letter contains no new commitments.
Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.
Sincerely, oelp ebbi~e Site Vice President, Indiana Michigan Power JMT/ams c:
R. J. Ancona, MPSC A. W. Dietrich, NRC Washington DC MDEQ - RMD/RPS NRC Resident Inspector C. 0. Pederson, NRC Region Ill A. J, Williamson, AEP Ft. Wayne