ML20129E474: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot insert
 
StriderTol Bot change
 
Line 18: Line 18:
=Text=
=Text=
{{#Wiki_filter:4.
{{#Wiki_filter:4.
                                        W 2 41985
W 2 41985
      In Reply Refer To:
In Reply Refer To:
      Docket:   50-285/84-12
Docket:
      Omaha Public Power District
50-285/84-12
      ATTN:   R. L. Andrews, Division Manager-
Omaha Public Power District
              Nuclear Production
ATTN:
      1623 Harney Street
R. L. Andrews, Division Manager-
      Omaha, Nebraska 68102
Nuclear Production
      Gentlemen:
1623 Harney Street
      This refers to your April 9, 1985, response (LIC-85-138) in reply to the
Omaha, Nebraska 68102
      Notice of Violation sent to you with our letter dated March 8, 1985. Our
Gentlemen:
      letter and Notice described a violation which occurred at the Fort Calhoun
This refers to your April 9, 1985, response (LIC-85-138) in reply to the
      Station which was identified during an NRC inspection and investigation
Notice of Violation sent to you with our letter dated March 8, 1985. Our
      conducted in May, June, and July respectively. The violation was discussed
letter and Notice described a violation which occurred at the Fort Calhoun
    with you during an Enforcement Conference held with Mr. P. S. Check, Deputy
Station which was identified during an NRC inspection and investigation
      Regional Administrator, Region IV on December 20, 1984.
conducted in May, June, and July respectively.
      Your response has been carefully considered. The response does not contradict
The violation was discussed
      the fact that the violation occurred, and false, inaccurate and incomplete
with you during an Enforcement Conference held with Mr. P. S. Check, Deputy
      information was provided to the NRC for review. The information requested,
Regional Administrator, Region IV on December 20, 1984.
    under oath, by the NRC through the issuance of an IE Bulletin, is considered
Your response has been carefully considered. The response does not contradict
    material since it was needed to assess the significance of an identified
the fact that the violation occurred, and false, inaccurate and incomplete
      problem, the potential degradation of threaded fasteners. The key question is
information was provided to the NRC for review. The information requested,
    whether the information furnished had a natural tendency or capability to
under oath, by the NRC through the issuance of an IE Bulletin, is considered
      influence, not whether the information was in fact relied on. In our
material since it was needed to assess the significance of an identified
    opinion, it did have a natural tendency or capability to influence. See
problem, the potential degradation of threaded fasteners. The key question is
      VirginiaElectricPowerCo.(NorthAnna1and2),4NRC480(1976), affirmed
whether the information furnished had a natural tendency or capability to
    VEPC0 v. NRC, 571 F 2d 1289 (4th. Cir. 1978.). The violation identified by the
influence, not whether the information was in fact relied on.
                ~
In our
      NRC regardTng your August 2,1982 reply to IE Bulletin 82-02 demonstrated the
opinion, it did have a natural tendency or capability to influence.
      need for more effective control of your responses to the NRC. As discussed in
See
    our Notice of Violation, in recognition of prior good performance and prompt and
VirginiaElectricPowerCo.(NorthAnna1and2),4NRC480(1976), affirmed
    extensive corrective action, the civil penalty was fully mitigated. However,
VEPC0 v. NRC, 571 F 2d 1289 (4th. Cir. 1978.). The violation identified by the
      since the false statement is considered to be material and is considered to be
NRC regardTng your August 2,1982 reply to IE Bulletin 82-02 demonstrated the
    more than an inadvertent clerical error as there was a specific lack of emphasis
~
    and attention by several levels of management and supervision within the OPPD
need for more effective control of your responses to the NRC. As discussed in
    organization, the classification of the violation as a Severity Level III is
our Notice of Violation, in recognition of prior good performance and prompt and
    appropriate.
extensive corrective action, the civil penalty was fully mitigated.
                                                                                    I I
However,
                                                                                      ,
since the false statement is considered to be material and is considered to be
more than an inadvertent clerical error as there was a specific lack of emphasis
and attention by several levels of management and supervision within the OPPD
organization, the classification of the violation as a Severity Level III is
appropriate.
I
I
,
'
'
  0506060509 050524
0506060509 050524
  PDR   ADOCK 05000295
PDR
  G                   PDR
ADOCK 05000295
G
PDR


                              ..
                                              ..~    - .        =
                                                                                                        '
      +
          -lw ,    :*i                                                                                              .
                    ~
                                            *
      ,.
                                  >
    ,
..
..
                    Omaha Public Power District-                -2--
..~
- .
=
-lw ,
:*i
'
'
                  .We find your reply responsive to the-concerns raised in our Notice of
+
l                  Violation.- We will review your. corrective action during a. future. inspection
.
                    to determine that full compliance has been achieved and will be maintained.-
~
                                                                Sincerely,
,.
                                .
*
                            '
>
!      '
,
                                                            Original signed by
                                                            Robert D.' Martin
                                                              ' Robert D. Martin                        -
                                                                                                                        !
                                                              . Regional Administrator.
                    cc:
                  W. G. Gates, Manager
                    Fort Calhoun Station
                    P..O. Box 399
                    Fort Calhoun, Nebraska 68023
                    Harry H. Voigt, Esq.          ,
                                                                                                                        ,.
                                                                                                                        '
                    LeBoeuf, Lamb, Leiby & MacRae
                  f1333 New Hampshire Avenue, NW
                  Washington, DC      20036
                    Kansas Radiation Control Program Director
                    Nebraska Radiation Control Program Director
                [.bec'lioDMB(IE01).
                  -bec distrib. by RIV:                                                                                '
                  *RPB2                  * Resident Inspector              R..D. Martin, RA
                  . *EP&RPB              *SectionChief(RPB2/A)            * MIS System
                    *RIV File              R. Denise, DRSP.                *RSTS Operator
                  .T. Westerman
(
..
..
Omaha Public Power District-
-2--
'
.We find your reply responsive to the-concerns raised in our Notice of
l
Violation.- We will review your. corrective action during a. future. inspection
to determine that full compliance has been achieved and will be maintained.-
Sincerely,
.
.
                                    '
!
                                                                              l
Original signed by
'
'
Robert D.' Martin
' Robert D. Martin
-
!
. Regional Administrator.
cc:
W. G. Gates, Manager
Fort Calhoun Station
P..O. Box 399
Fort Calhoun, Nebraska 68023
Harry H. Voigt, Esq.
,
,.
'
LeBoeuf, Lamb, Leiby & MacRae
f1333 New Hampshire Avenue, NW
Washington, DC
20036
Kansas Radiation Control Program Director
Nebraska Radiation Control Program Director
[.bec'lioDMB(IE01).
-bec distrib. by RIV:
'
*RPB2
* Resident Inspector
R..D. Martin, RA
. EP&RPB
*SectionChief(RPB2/A)
* MIS System
*
*RIV File
R. Denise, DRSP.
*RSTS Operator
.T. Westerman
(
...
E0f
l
RIV:RP,B
'
DRS&P
RA
i-
i-
                    RIV:RP,B
RHuntWr:gb
                      RHuntWr:gb
RPDenise
                                          DRS&P
TWesterman
                                          RPDenise
RDP
                                                          E0f
in
                                                          TWesterman
5/Jy/85
                                                                          RA
5/g%BS
                                                                          RDP    in
SM/85
  '
5/ i/85
                    5/Jy/85               5/g%BS         SM/85           5/ i/85
'
l
l
l
                                                                                                                        l
l
l
I
I
l>
l>
                                                                                    _ _ _ _ _ _ _ _ _ _    - _ - - -
-
- - -


I
I
                *
*
        .
.
            '
'
          6
6
    , M [*39 *ylg.),g y 1.;fii Q ( % ,y(;#fk? % R Q Q,Cf f                             ,
, M [*39 *ylg.),g y 1.;fii Q ( % ,y(;#fk? % R Q Q,Cf f
                                                                                          .
Q{
                                                                                                Q{
.
                                          Omaha Public Power District
,
                                      1623 Harney Omaha. Nebraska 68102
Omaha Public Power District
                                                  402/536 4000
1623 Harney Omaha. Nebraska 68102
                                                April 9, 1985
402/536 4000
                                                  LIC-85-138
April 9, 1985
                                                                              APRII1985
LIC-85-138
              f4r. James M. Taylcr, Director
APRII1985
              Office of Inspection and Enforcement
f4r. James M. Taylcr, Director
              U. S. Nuclear Regulatory Commission
Office of Inspection and Enforcement
              Washington, DC 20555
U. S. Nuclear Regulatory Commission
              Reference:   (1) Docket No. 50-285
Washington, DC 20555
                            (2) Letter from OPPD (W. C. Jones) to NRC (J. T. Collins)
Reference:
                                  dated August 2, 1982 (LIC-82-269)
(1)
                            (3) Letter from OPPD (R. L. Andrews) to NRC (J. T. Collins)
Docket No. 50-285
                                  dated July 2, 1984 (LIC-84-209)
(2)
                            (4) Letter from 0 PPD (R. L. Andrews) to NRC (R. D. Martin)
Letter from OPPD (W. C. Jones) to NRC (J. T. Collins)
                                  dated December 27, 1984 (LIC-84-434)
dated August 2, 1982 (LIC-82-269)
                            (5) Letter from NRC (R. D. Martin) to OPPD (R. L. Andrews)
(3)
                                  dated March 8,1985 (EA-84-63)
Letter from OPPD (R. L. Andrews) to NRC (J. T. Collins)
              Dear fir. Taylor:
dated July 2, 1984 (LIC-84-209)
                                            IE Inspection Report 84-12
(4)
                                                Notice of Violation
Letter from 0 PPD (R. L. Andrews) to NRC (R. D. Martin)
                                                                                                    '
dated December 27, 1984 (LIC-84-434)
              The Omaha Public Power District received IE Inspection Report 84-12 and Reference
(5)
              (5) both dated March 8, 1985. These documents idertified a potential material
Letter from NRC (R. D. Martin) to OPPD (R. L. Andrews)
              false statement and violation of NRC requirements relative to the District's re-
dated March 8,1985 (EA-84-63)
              sponse to NRC IE Bulletin 82-02. Pursuant to 10 CFR 2.201, please find attached
Dear fir. Taylor:
              the District's response to these allegations.
IE Inspection Report 84-12
                                                      Sincerely,
Notice of Violation
                                                    /        Th/sC     /
'
                                                      R. L. Andrews
The Omaha Public Power District received IE Inspection Report 84-12 and Reference
                                                      Division Manager
(5) both dated March 8, 1985.
                                                      Nuclear Production                             )
These documents idertified a potential material
                                                                                                    1
false statement and violation of NRC requirements relative to the District's re-
              RLA/CWN/dao
sponse to NRC IE Bulletin 82-02.
                        "                                       V
Pursuant to 10 CFR 2.201, please find attached
                                                                  44      &c
the District's response to these allegations.
                                                                        -       .,
Sincerely,
                                                                              s
Th/sC
                                                                                Ng
/
                  (
/
                                                                                          4
R. L. Andrews
  ...s,.
Division Manager
                                            ~-ggnoo,m.,,
Nuclear Production
)
1
RLA/CWN/dao
V
"
4
&c
4
-
.,
s
N g
(
4
~-ggnoo,m.,,
...s,.


              ..       _       -
..
                    -
_
      : ;..
-
          ,      ..
:
      s          ;  LIC-85-138'
-
                  -:Page' 2
;..
            ,
..
p                 .cc:     LeBoeuf, Lamb,~Leiby & MacRae
,
                          .1333 New Hampshire Avenue,.N.W.
LIC-85-138'
;
s
-:Page' 2
,
p
.cc:
LeBoeuf, Lamb,~Leiby & MacRae
.1333 New Hampshire Avenue,.N.W.
p.;
p.;
  ,.
,.
                          Washington, DC 20036
Washington, DC 20036
                          Mr. James R. Miller, Chief ~     .
Mr. James R. Miller, Chief ~
                          Office of Nuclear Reactor Regulation
.
                          Division of Licensing'
Office of Nuclear Reactor Regulation
                          U. S. Nuclear Regulatory Commission-
Division of Licensing'
U. S. Nuclear Regulatory Commission-
Washington, DC 20555
<
<
                          Washington, DC 20555
Mr. Robert D. Martin
                          Mr. Robert D. Martin
Regional Administrator-
                          Regional Administrator-         .
.
r                         U. S. Nuclear Regulatory Commission
r
                          Region IV
U. S. Nuclear Regulatory Commission
Region IV
611 Ryan Plaza Drive, Suite 1000
,
,
                          611 Ryan Plaza Drive, Suite 1000
Arlington, TX 76011-
                          Arlington, TX 76011-
Mr. E. G. Tourigny, NRC Project Manager
                          Mr. E. G. Tourigny, NRC Project Manager
l
l                       .Mr. L. A..Yandell, NRC Senior Resident Inspector
.Mr. L. A..Yandell, NRC Senior Resident Inspector
!
!
:
:
Line 219: Line 278:


r
r
            *
*
    .
.
  ,
-
          -
,
                                        UNITED STATES OF AMERICA
UNITED STATES OF AMERICA
                                      NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION
            In the Matter of                                                             -
In the Matter of
            Omaha Public Power District         )     Docket flo. 50-285
-
            (Fort Calhoun Station,               )
Omaha Public Power District
            Unit No. 1)
)
                                                                                          '
Docket flo. 50-285
                                                )
(Fort Calhoun Station,
                            '
)
                                                  AFFIDAVIT
Unit No. 1)
            R. L. Andrews, being duly sworn, hereby deposes and says that he is Division
)
            Manager - Nuclear Production of the Omaha Public Power District; that he is
'
            duly authorized to sign and file with the Nuclear Regulatory Commission the
'
            attached response to the flotice of Violation identified in the Commission's
AFFIDAVIT
            letter dated March 8, 1985 (EA-84-63); that he is familiar with the content
R. L. Andrews, being duly sworn, hereby deposes and says that he is Division
            thereof; and that the matters set forth therein are true and correct to the
Manager - Nuclear Production of the Omaha Public Power District; that he is
            best of his knowledge, information and belief.
duly authorized to sign and file with the Nuclear Regulatory Commission the
                                                          ',.''b'.?ftie'L ''
attached response to the flotice of Violation identified in the Commission's
                                                  R. L. Andrews
letter dated March 8, 1985 (EA-84-63); that he is familiar with the content
                                                  Division llanager
thereof; and that the matters set forth therein are true and correct to the
                                                  fluclear Production
best of his knowledge, information and belief.
            STATE OF NEBRASKA)
' ''b'.?ftie'L ''
                              ) ss
,.
            COUNTY OF DOUGLAS)
R. L. Andrews
            Subscribed and sworn to before me, a Notcry Public in and for the State of
Division llanager
            Nebraska on this 9       day of April, 1985.
fluclear Production
                .
STATE OF NEBRASKA)
      -r       enum neuer-se e m e.
)
                  Er    k        Y                    0amy''l.(liAzp>
ss
                                                      fj       ilotjry Public
COUNTY OF DOUGLAS)
Subscribed and sworn to before me, a Notcry Public in and for the State of
Nebraska on this
9
day of April, 1985.
.
-r
enum neuer-se e m e.
0amy''l.(liAzp>
Er
k
Y
fj
ilotjry Public
;
;
I-
I-
k.
k.


}
l
r
r
      .
.
          }                                                                          l
.,
        .,
. . ,
  ..,
,
,
                                                ATTACHMENT
ATTACHMENT
                                            NOTICE OF VIOLATION
NOTICE OF VIOLATION
                                  0 PPD Response Pursuant to 10 CFR 2.201
0 PPD Response Pursuant to 10 CFR 2.201
            In accordance with Reference 5 and as required therein, the District is
In accordance with Reference 5 and as required therein, the District is
            responding to the subject Notice of Violation associated with OPPD's
responding to the subject Notice of Violation associated with OPPD's
            initial. response to IE Bulletin 82-02 (Reference 2).
initial. response to IE Bulletin 82-02 (Reference 2).
            VIOLATION
VIOLATION
            The NOTICE OF VIOLATION attached to Reference 5 states:
The NOTICE OF VIOLATION attached to Reference 5 states:
                    The following is a material false statement within the meaning
The following is a material false statement within the meaning
                      of Section 186 of the Atomic Energy Act of 1954, as amended.
of Section 186 of the Atomic Energy Act of 1954, as amended.
                      In the August 2,1982, response to NRC IE Bulletin No. 82-02,
In the August 2,1982, response to NRC IE Bulletin No. 82-02,
                  '" Degradation of Threaded Fasteners in Reactor Coolant Pressure
'" Degradation of Threaded Fasteners in Reactor Coolant Pressure
                      Boundaries in PWR Plants," the licensee stated, in part, that
Boundaries in PWR Plants," the licensee stated, in part, that
                      "The Fort Calhoun Station approved maintenance procedures cal!
"The Fort Calhoun Station approved maintenance procedures cal!
                    'for the use of NEVERSIEZE (sic) (Pure Nickel #65) on all
'for the use of NEVERSIEZE (sic) (Pure Nickel #65) on all
                      threaded fasteners."
threaded fasteners."
                    Contrary to the above statement:
Contrary to the above statement:
                      *
*
                            Special Maintenance Procedure SP-RC-11, Revision 1,
Special Maintenance Procedure SP-RC-11, Revision 1,
                            " Reactor Coolant Pump Assembly," (effective between
" Reactor Coolant Pump Assembly," (effective between
                            May 24, 1980, and March 1,1983) designated no specific
May 24, 1980, and March 1,1983) designated no specific
                            lubricant on the reactor coolant pump (RCP) studs.
lubricant on the reactor coolant pump (RCP) studs.
                            Discussions revealed that it had been common practice to
Discussions revealed that it had been common practice to
                            use molybdenum disulfide lubricant on both.the RCP and
use molybdenum disulfide lubricant on both.the RCP and
reactor vessel studs.
Revision 6 of Special Maintenance
'
'
                            reactor vessel studs. Revision 6 of Special Maintenance
Procedure SP-RC-11, dated March 16, 1984, specifically
                            Procedure SP-RC-11, dated March 16, 1984, specifically
required the use of " Super-Moly" (molybdenum disulfide)
                            required the use of " Super-Moly" (molybdenum disulfide)
on RCP Studs.
                            on RCP Studs.
*
                    *
Maintenance Procedure RC-2-1-B, Revision 12, "S/G Primary
                            Maintenance Procedure RC-2-1-B, Revision 12, "S/G Primary
Manway Replacement," (effective between June 9,1981, and
                            Manway Replacement," (effective between June 9,1981, and
January 20, 1983) designated a mixture of 50% oil and 50%
                            January 20, 1983) designated a mixture of 50% oil and 50%
graphite to be used on manway studs.
                            graphite to be used on manway studs.
The August 2,1982, statement was false in that contrary to the
                    The August 2,1982, statement was false in that contrary to the
statement, a number of different types of lubricants were
                    statement, a number of different types of lubricants were
utilized at Fort Calhoun Station, including " Super-Moly"
                    utilized at Fort Calhoun Station, including " Super-Moly"
(molybdenum disulfide).
                    (molybdenum disulfide). The false statement was material in
The false statement was material in
that one of the purposes of IE Bulletin No. 82-02 was to find
'
'
                    that one of the purposes of IE Bulletin No. 82-02 was to find
out which licensees used " Super-Moly" (molybdenum disulfide) as
                    out which licensees used " Super-Moly" (molybdenum disulfide) as
a fastener lubricant and what plant experience the licensee had
                    a fastener lubricant and what plant experience the licensee had
with stress-corrosion cracking of fasteners using molybdenum
                    with stress-corrosion cracking of fasteners using molybdenum
disulfide lubricants.
At the time IE Bulletin 82-02 was
,
,
                    disulfide lubricants. At the time IE Bulletin 82-02 was
l
l                    issued, the NRC thought that molybdenum disulfide might have
issued, the NRC thought that molybdenum disulfide might have
,
,
I
Io
o


  n
n
          '
'
      .
.
        -
-
    .
.
            VIOLATION'(Continued)
VIOLATION'(Continued)
                    a pronounced tendency to decompose in the presence of high
a pronounced tendency to decompose in the presence of high
                    temperature and moisture conditions to release sulfide, a
temperature and moisture conditions to release sulfide, a
                    known promoter of stress-corrosing cracking. Although the
known promoter of stress-corrosing cracking. Although the
                    NRC subsequently found molybdenum disulfide lubricant to be
NRC subsequently found molybdenum disulfide lubricant to be
                    acceptable, this fact was not known when the licensee sub-
acceptable, this fact was not known when the licensee sub-
                    mitted its response.
mitted its response.
                    This. is a Severity Level III violation (Supplement VII).
This. is a Severity Level III violation (Supplement VII).
                    (No Civil Penalty)
(No Civil Penalty)
            DISTRICT'S RESPONSE
DISTRICT'S RESPONSE
            1.       Admission or Denial of the Alleged Violation
1.
                    The District admits that its August 2,1982 response was incomplete,
Admission or Denial of the Alleged Violation
                    but den.ies that the alleged violation is a material false statement.
The District admits that its August 2,1982 response was incomplete,
                    Supplement VII to 10 CFR, Part 2, Appendix C provides that:
but den.ies that the alleged violation is a material false statement.
                            A false statement caused by an inadvertent clerical or
Supplement VII to 10 CFR, Part 2, Appendix C provides that:
                            similar error involving information which, had it been
A false statement caused by an inadvertent clerical or
                            available to NRC and accurate at the time the information
similar error involving information which, had it been
                            should have been submitted, would probably not have
available to NRC and accurate at the time the information
                            resulted in regulatory action or NRC seeking additional
should have been submitted, would probably not have
                            information
resulted in regulatory action or NRC seeking additional
                    is a " Severity IV violation."
information
                    The complete text of that portion of the District's August 2,1982
is a " Severity IV violation."
                    response that led to the Notice of Violation is as follows:
The complete text of that portion of the District's August 2,1982
                            Request
response that led to the Notice of Violation is as follows:
                            Identify those closures and connections, if any, where
Request
                            fastener lubricants and injection sealant materials have
Identify those closures and connections, if any, where
                            been or are being used and report on plant experience
fastener lubricants and injection sealant materials have
                            with their application particularly any instances of SCC
been or are being used and report on plant experience
                            of fasteners. Include types and composition of materials
with their application particularly any instances of SCC
,                          used.
of fasteners.
Include types and composition of materials
used.
,
!
!
                            District's Response
l
l
                            Maintenance records indicate that injection sealant
District's Response
                            canpounds have never been used on any of the RCPB
Maintenance records indicate that injection sealant
                            enclosures within the scope of IE Bulletin 82-02 at
canpounds have never been used on any of the RCPB
                            the Fort Calhoun Station.
enclosures within the scope of IE Bulletin 82-02 at
                            The Fort Calhoun Station approved maintenance proce-
the Fort Calhoun Station.
                            dures call for use of NEVERSIEZE Pure Nickel #65 on
The Fort Calhoun Station approved maintenance proce-
                            all threaded fasteners.   To date, the District has ex-
dures call for use of NEVERSIEZE Pure Nickel #65 on
                            perienced no problems related to use of the NEVERSIEZE
all threaded fasteners.
                            lubricant.
To date, the District has ex-
                                                  -2-
perienced no problems related to use of the NEVERSIEZE
              .- --     -           _ -   -_ .       . - _ _ _ _ - _ _ _ - _ -     -. - - _ - _ _ _
lubricant.
-2-
.- --
-
_ -
-_ .
. - _ _ _ _ - _ _ _ - _
-
-. - - _ - _ _ _


  _
_
            *
*
      ,
,
    ,
,
          .
.
'
'
              1. LAdmission or Denial of the Alleged Violation (Continued)
1.
                  In essence,.the District furdshed three categories of information
LAdmission or Denial of the Alleged Violation (Continued)
                  to the NRC:
In essence,.the District furdshed three categories of information
                  (1)     Injection . sealant compounds used,
to the NRC:
        '
'
                                                                                -
(1)
                  (2)     Lubricants used on-threaded fasteners, and
Injection . sealant compounds used,
                  (3).
-
                  _
(2)
                          Plant' experience with sealants and lubricants, particularly
Lubricants used on-threaded fasteners, and
                          instances-of stress corrosion cracking of threaded fasteners.
(3).
                  Infomation furnished under Category 1 was accurate; infomation
Plant' experience with sealants and lubricants, particularly
                  under Category 2 was incomplete and therefore inaccurate; and
_
                  infomation under Category 3 was accurate. The District believes
instances-of stress corrosion cracking of threaded fasteners.
                  that its answer in Category 3 must be considered to determine
Infomation furnished under Category 1 was accurate; infomation
                whether there was any material false statement. The District
under Category 2 was incomplete and therefore inaccurate; and
                  accurately reported that it had experienced no problems. That
infomation under Category 3 was accurate. The District believes
                  infomation~was correct with respect to all lubricants used, even
that its answer in Category 3 must be considered to determine
                  though the lubricants themselves were not al1~1isted. Had the-
whether there was any material false statement.
                  other lubricants been identified, no different conclusion con-
The District
                  cerning their effect would have been presented. Therefore, con-
accurately reported that it had experienced no problems. That
                  trary to the Notice of Violation, the statement was not material .
infomation~was correct with respect to all lubricants used, even
                  If complete and accurate information had been included in the
though the lubricants themselves were not al1~1isted.
                  District's 1982 response of IE Bulletin 82-02, .it "would probably -
Had the-
                  not have resulted in regulatory action or NRC seeking additional
other lubricants been identified, no different conclusion con-
                  infomation."
cerning their effect would have been presented. Therefore, con-
                  Since the NRC acknowledges that the District's incomplete response
trary to the Notice of Violation, the statement was not material .
                was not intentional and was not intended to conceal or mislead, we
If complete and accurate information had been included in the
                also believe it is appropriate to classify it as " inadvertent."     In
District's 1982 response of IE Bulletin 82-02, .it "would probably -
                addition, the Commission has determined that " materiality" should be
not have resulted in regulatory action or NRC seeking additional
                contingent upon the safety significance of the. infomation (47 Fed.
infomation."
                Reg. 8584 (1984)). Based upon the above discussion, the District
Since the NRC acknowledges that the District's incomplete response
                has-concluded that the inco'nplete response has no safety signifi-
was not intentional and was not intended to conceal or mislead, we
                cance.- For all of these reasons, the District submits that its 1982
also believe it is appropriate to classify it as " inadvertent."
                  response was not a material false statement and that classification
In
                as a Severity Level III is not warranted.
addition, the Commission has determined that " materiality" should be
              2. Reasons for the Violation
contingent upon the safety significance of the. infomation (47 Fed.
                Reference 3 described the steps taken to correct the District's
Reg. 8584 (1984)). Based upon the above discussion, the District
                response to Item 5 of IE Bulletin 82-02. Reference 3 also identi-
has-concluded that the inco'nplete response has no safety signifi-
                fied the procedures which were in effect in 1982 when the initial
cance.- For all of these reasons, the District submits that its 1982
                response was prepared. Further, the inspection conducted by the
response was not a material false statement and that classification
                NRC's Office of Investigations during June and July of 1984 defines
as a Severity Level III is not warranted.
                the causes for the occurrence. The results of the NRC's inspection
2.
                are summarized in the third paragraph of Reference 5. The submis-
Reasons for the Violation
                sion of the statement occurred due to failures on the part of the
Reference 3 described the steps taken to correct the District's
                District including inadequate review of documentation, failure to
response to Item 5 of IE Bulletin 82-02.
                adequately coordinate and discuss the matter with knowledgeable
Reference 3 also identi-
                personnel in the specific area of concern, failure of management
fied the procedures which were in effect in 1982 when the initial
                to assign the response to an experienced employee, and failure of
response was prepared.
                                                  -3
Further, the inspection conducted by the
NRC's Office of Investigations during June and July of 1984 defines
the causes for the occurrence. The results of the NRC's inspection
are summarized in the third paragraph of Reference 5.
The submis-
sion of the statement occurred due to failures on the part of the
District including inadequate review of documentation, failure to
adequately coordinate and discuss the matter with knowledgeable
personnel in the specific area of concern, failure of management
to assign the response to an experienced employee, and failure of
-3


e==w-s-
e==w-s-
                                                            -
-
              .
          ,
            .
          .
        -
                2. Reason for the Violation (Continued)
                  management to identify the incomplete statement during the required
                  procedural review of all the responses to the NRC. The circum-
                  stances associated with the preparation of the response to the NRC
                  indicated a specific lack of emphasis and attention to detail by a
                  number of levels of management and supervision within the District.
                3. Corrective Steps Which Have Been Taken and the Results Achieved
                  As described in the District's presentations to Mr. P. S. Check and
                  other members of the NRC Region IV staff during the December 20,
                  1984 Enforcement Conference, corrective measures have been taken in
                  three-areas:
                  (1)    Review of the qualifications of those responsible for
                          preparing NRC response for the years 1983 and 1984.
                  (2)    Re' vision of the trainirg program for new technical
                          employees.
                  (3)    Establishment of internal procedures for checking sub-
                          mittals to the NRC and independently reviewing submittals
                          requiring oath or affimation and as otherwise deemed
                          appropriate prior to management review.              '
                  These measures and the results achieved are summarized below.
                  (1)  . Review of Preparer's Qualifications
                          An undocumented review and evaluation of correspondence
                          submitted under oath or affirmation for the last two years
                          (1983-1984) was conducted to address the following functions:
                          a.    Were the individuals who prepared responses experienced
                                  in the area of the response?
                          b.      Is it necessary to perfom a technical review of any
                                responses submitted during 1983 and 1984?
                          c.      Is it necessary to conduct a review and evaluation of
                                correspondence submitted prior to 1983?
                          The results of that review and evaluation are as follows:
                          Items submitted under oath or affirmation fit into three
                          general categories:
                          -      Technical Specification Amendment Applications (both
                                initial applications and revisions to previously filed
                                applications)
.
.
,
,
                          -
.
                                Proprietary Information Declarations
.
                          -     IE Bulletin and Generic Letter Responses
-
                                                    -4-
2.
Reason for the Violation (Continued)
management to identify the incomplete statement during the required
procedural review of all the responses to the NRC.
The circum-
stances associated with the preparation of the response to the NRC
indicated a specific lack of emphasis and attention to detail by a
number of levels of management and supervision within the District.
3.
Corrective Steps Which Have Been Taken and the Results Achieved
As described in the District's presentations to Mr. P. S. Check and
other members of the NRC Region IV staff during the December 20,
1984 Enforcement Conference, corrective measures have been taken in
three-areas:
(1)
Review of the qualifications of those responsible for
preparing NRC response for the years 1983 and 1984.
(2)
Re' vision of the trainirg program for new technical
employees.
(3)
Establishment of internal procedures for checking sub-
mittals to the NRC and independently reviewing submittals
requiring oath or affimation and as otherwise deemed
appropriate prior to management review.
'
These measures and the results achieved are summarized below.
(1)
. Review of Preparer's Qualifications
An undocumented review and evaluation of correspondence
submitted under oath or affirmation for the last two years
(1983-1984) was conducted to address the following functions:
a.
Were the individuals who prepared responses experienced
in the area of the response?
b.
Is it necessary to perfom a technical review of any
responses submitted during 1983 and 1984?
c.
Is it necessary to conduct a review and evaluation of
correspondence submitted prior to 1983?
The results of that review and evaluation are as follows:
Items submitted under oath or affirmation fit into three
general categories:
Technical Specification Amendment Applications (both
-
initial applications and revisions to previously filed
applications)
,
Proprietary Information Declarations
.
-
IE Bulletin and Generic Letter Responses
-
-4-


                                                                  . _ _ _ _ _ _ _ _ _ _
. _ _ _ _ _ _ _ _ _ _
                                                                                            ____- _
____-
    -
_
.
-
  .
.
.
.
      3. Corrective Steps Which Have Been Taken and the Results Achieved
.
  ,
3.
          (Continued)
Corrective Steps Which Have Been Taken and the Results Achieved
                Technical Specification Amendment Application
(Continued)
                The review and evaluation concluded that since Technical
,
                Specification Amendments were reviewed and approved by the
Technical Specification Amendment Application
                Plant Review Committee and the Safety Audit and Review
The review and evaluation concluded that since Technical
                Committee, the detailed reviews and approvals of these two
Specification Amendments were reviewed and approved by the
                groups was sufficient to ensure that the information was
Plant Review Committee and the Safety Audit and Review
                correct.     In addition, the Commission approved such appli-
Committee, the detailed reviews and approvals of these two
                cations in the form of Amendments to the District's Technical
groups was sufficient to ensure that the information was
                Specifications. Based on the above, the District believes
correct.
                that no additional review is necessary for the Technical
In addition, the Commission approved such appli-
                Specification Amendments submitted during 1983-1984.                   The
cations in the form of Amendments to the District's Technical
                review and evaluation also concluded that it is highly un-
Specifications.
                likely that a similar situation to the IE Bulletin 82-02
Based on the above, the District believes
                response could occur with Technical Specification Amendment
that no additional review is necessary for the Technical
                applications. It was also detemined that it was not neces-
Specification Amendments submitted during 1983-1984.
                sary to do additional reviews on the Technical Specification
The
                Amendments submitted prior to 1983 since they were handled
review and evaluation also concluded that it is highly un-
                in a similar manner as the 1983-1934 applications.
likely that a similar situation to the IE Bulletin 82-02
        ,
response could occur with Technical Specification Amendment
                Proprietary Information Declarations
applications.
                The review and evaluation concluded that Proprietary Infor-
It was also detemined that it was not neces-
                mation Declarations are not nomally of a type where safety
sary to do additional reviews on the Technical Specification
                significant information is provided to the Commission.
Amendments submitted prior to 1983 since they were handled
                Therefore, no additional review of Proprietary Infomation
in a similar manner as the 1983-1934 applications.
                Declarations submitted during 1983-1984 was needed nor was
Proprietary Information Declarations
                it necessary to review such submittals prior to 1983. The
,
                review and evaluation also concluded that it is highly un-
The review and evaluation concluded that Proprietary Infor-
                likely that a similar situation to the IEB 82-02 response
mation Declarations are not nomally of a type where safety
                could occur with Proprietary Information Declarations.
significant information is provided to the Commission.
  -
Therefore, no additional review of Proprietary Infomation
                IE Bulletin and Generic Letter Responses
Declarations submitted during 1983-1984 was needed nor was
                The review and evaluation concluded that the personnel who
it necessary to review such submittals prior to 1983. The
                initially prepared IE Bulletin and Generic Letter responses
review and evaluation also concluded that it is highly un-
                submitted under oath or affirmation during 1983-1984 were
likely that a similar situation to the IEB 82-02 response
                sufficiently experienced to prepare such responses. These
could occur with Proprietary Information Declarations.
                IE Bulletins and Generic Letter responses were processed
IE Bulletin and Generic Letter Responses
                through the District's management review cycle. As described
-
                in Item (3) on Page 7 of this response, the District procedure
The review and evaluation concluded that the personnel who
                for processing of f1RC and other regulatory correspondence
initially prepared IE Bulletin and Generic Letter responses
                (DAS-L-03) was revised in September 1984 to incorporate an
submitted under oath or affirmation during 1983-1984 were
                independent review and checking function. Since that revi-
sufficiently experienced to prepare such responses.
                sion, IE Bulletins and Generic Letters submitted under oath
These
                of affimation have been independently reviewed as required.
IE Bulletins and Generic Letter responses were processed
                For 1983 and 1984 IE Bulletins and Generic Letter responses
through the District's management review cycle. As described
                that were submitted prior to September 24, 1984, the following
in Item (3) on Page 7 of this response, the District procedure
                action was taken.
for processing of f1RC and other regulatory correspondence
                                                          -5-
(DAS-L-03) was revised in September 1984 to incorporate an
                            _ _ _ _     _____-__ __ _ __
independent review and checking function.
Since that revi-
sion, IE Bulletins and Generic Letters submitted under oath
of affimation have been independently reviewed as required.
For 1983 and 1984 IE Bulletins and Generic Letter responses
that were submitted prior to September 24, 1984, the following
action was taken.
-5-
_ _ _ _
_____-__ __ _ __


    *
*
.
.
    -
-
  .
.
      3. Corrective Steps Which Have Been Taken and the Results Achieved
3.
        (Continued)                                                             g
Corrective Steps Which Have Been Taken and the Results Achieved
                a.     Many of the personnel responsible for preparing           i
(Continued)
                        these responses have been interviewed in order to       4
g
                        determine if additional review is required.   During   -
a.
                        these interviews, personnel were asked to describe
Many of the personnel responsible for preparing
                        the steps they used in preparing the response with
i
                        the intention of determining whether the necessary
these responses have been interviewed in order to
                        steps were taken. Based on these interviews it was
4
                        determined that the necessary steps were taken;         -
determine if additional review is required.
                        consequently, no additional review was required.
During
                b.     Some responses were discussed at several meetings
-
                        where sufficient qualified personnel were present       %
these interviews, personnel were asked to describe
                        and extensively discussed the subject matter. The         -:
the steps they used in preparing the response with
                        responses were then prepared ba;ed on those discus-         _
the intention of determining whether the necessary
                        sions and the documents were subsequently processed     *
steps were taken.
                        through the District's correspondence review cycle.
Based on these interviews it was
                c.     Some of the IE Bulletins or Generic Letter re-           Y
determined that the necessary steps were taken;
                        sponses have subsequently been reviewed by the               J
-
                        Commission and closed.
consequently, no additional review was required.
                Based on the above information it has been concluded that it     7
b.
                is not necessary to conduct further reviews of the IE Bulletin   5
Some responses were discussed at several meetings
                                                                                '"
where sufficient qualified personnel were present
                and Generic Letter responses submitted for the 1983-1984
%
                period or made before 1983.                                     g
and extensively discussed the subject matter. The
                                                                                _
- :
                this review provides confidence that it is unlikely that a       3
responses were then prepared ba;ed on those discus-
                similar situation to the IEB 82-02 response could occur with     I
_
                the IE Bulletin and Generic Letter responses submitted before   2
sions and the documents were subsequently processed
                or during the 1983-1984 period.                                 j
*
                                                                                '=
through the District's correspondence review cycle.
                The District cannot positively state that all responses             '
c.
                submitted to the Commission are 100'. complete and accurate;     7
Some of the IE Bulletins or Generic Letter re-
                however, the District can state there is a high degree of         -
Y
                assurance that responses submitted to the Commission are           =
sponses have subsequently been reviewed by the
                complete and accurate based on past reviews and the results     7
J
                of the review and evaluation which was conducted prior to         i
Commission and closed.
                the December 20, 1984, Enforcement Conference.
Based on the above information it has been concluded that it
        (2)   Revision of the Training Program for New Technical Employees
7
                Training of new tehnical employees has been upgraded by the       i
is not necessary to conduct further reviews of the IE Bulletin
                availability of additional courses in reactor and power plant     a
5
                fundamentals. Further, availability of training materials and     y
'"
                resources has been formalized and implemented by the Nuclear       l
and Generic Letter responses submitted for the 1983-1984
                Production Division (NPD) as described in the NPD Policy /         i
period or made before 1983.
                Procedure No. C-3, R0 2/15/85, " Orientation / Training of Newly   ?
g
                Hired Technical Employees Performing Safety-Related Activi-       e
_
                ti es . " Policy / Procedure C-3 training of managers and super-   3
this review provides confidence that it is unlikely that a
                visors in NPD and managers in the Engineering Division was
3
                                                                                  }
similar situation to the IEB 82-02 response could occur with
                                                                                  N.
I
                                                                                  d
the IE Bulletin and Generic Letter responses submitted before
                                          -6-                                     y
2
                                                                                  i -
or during the 1983-1984 period.
                                                              _.
j
'=
The District cannot positively state that all responses
'
submitted to the Commission are 100'. complete and accurate;
7
however, the District can state there is a high degree of
-
assurance that responses submitted to the Commission are
=
complete and accurate based on past reviews and the results
7
of the review and evaluation which was conducted prior to
i
the December 20, 1984, Enforcement Conference.
(2)
Revision of the Training Program for New Technical Employees
Training of new tehnical employees has been upgraded by the
i
availability of additional courses in reactor and power plant
a
fundamentals.
Further, availability of training materials and
y
resources has been formalized and implemented by the Nuclear
l
Production Division (NPD) as described in the NPD Policy /
i
Procedure No. C-3, R0 2/15/85, " Orientation / Training of Newly
?
Hired Technical Employees Performing Safety-Related Activi-
e
ti es . " Policy / Procedure C-3 training of managers and super-
3
visors in NPD and managers in the Engineering Division was
}
N.
d
-6-
y
i
-
_.


. ..     . . _ . . . - . . . , . . , _ _ . -             . . . . . , . . . . . - ~ _             .     . - , . . - _ . -
.
                                            #
..
                      .
. . _ . . . - . . . , . . , _ _ . -
      ,
. . . . . , . . . . . - ~ _
    .
.
                -
. - , . .
                                                                                                                                          g
- _ . -
                          3.                   Corrective Steps Which Have Been Taken and the Results Achieved                                 1
#
                                              (Conti nued)                                                                               7
.
                                                                                                                                                .
,
                                                      completed on February 12, 1985. New technical employees in                         j
g
                                                      the Nuclear Production Division will be trained under this                         a
-
                                                      upgraded training and orientation policy. These improve-                           $
.
                                                      ments improve employee awareness of existing documentation,                         y
3.
                                                      resources, and 'nfonnation prior to preparation of responses.                       ]
Corrective Steps Which Have Been Taken and the Results Achieved
                                                      Also, utilization of this policy encourages communication
1
                                                      between the supervisor and new employee to provide the
(Conti nued)
                                                      supervisor with a thorough understanding of the employee's                         4
7
                                                      capabilities.                                                                       4
.
                                                                                                                                          -)
completed on February 12, 1985. New technical employees in
                                                      The improvement of the training program and formal establish-                         4
j
                                                      ment of an NPD training policy for new employees has resulted                       -d
the Nuclear Production Division will be trained under this
                                                      in increased managerial and supervisory awareness that indivi-                     2
a
                                                      duals preparing responses must be properly qualified prior to                       ;
upgraded training and orientation policy. These improve-
                                                      being assigned as a preparer. Similar policies are in effect                       g
$
                                                      in the Engineering Division.                                                       I
ments improve employee awareness of existing documentation,
                                                                                                                                          Al
y
                                                      Establishment of Internal Procedures for Checking and
resources, and 'nfonnation prior to preparation of responses.
                                                                                                                                          --
]
                                              (3)                                                                                            -
Also, utilization of this policy encourages communication
                                                      Independently Reviewing Submittals to the NRC.
between the supervisor and new employee to provide the
                                                                                                                                                  :
supervisor with a thorough understanding of the employee's
                                                      The District's Nuclear Regulatory & Industry Affairs depart-                       7
4
                                                      mental procedure for processing of NRC and other regulatory                         m
capabilities.
                                                      correspondence (DAS-L-03) was revised in September 1984 to                           a
4
                                                      incorporate appropriate Independent Review requirements as                           ?
-)
                                                      well as Checks of responses. In accordance with the proce-                             i
The improvement of the training program and formal establish-
                                                      dure as revised, NRC submittals now undergo a Check which is                         j
4
                                                      generally an intradepartmental review of the originating NRC                         3
ment of an NPD training policy for new employees has resulted
                                                      document against the submittal to confinn that items are                               -
-d
                                                      adequately addressed, properly stated and the responses are                               _
in increased managerial and supervisory awareness that indivi-
                                                      complete. A Check is normally done by a knowledgeable person                         i
2
                                                      or the preparer's supervisor or manager.                                             Q
duals preparing responses must be properly qualified prior to
                                                      Correspondence from the NRC is reviewed upon receipt to deter-                       I
;
                                                      mine if a response is required and if that response should be                           =
being assigned as a preparer. Similar policies are in effect
                                                      independently reviewed.                       Review of such responses are assigned ;
g
                                                      to an OPPD organization separate from the initial preparer's                             -
in the Engineering Division.
                                                      for an Independent Review, which is generally an interdepart-                           s
I
                                                                                                                                              "
Al
                                                      mental review of the NRC originating document against the
(3)
                                                      submittal to confinn that all items are adequately addressed,                         3
Establishment of Internal Procedures for Checking and
                                                      properly stated and the responses are complete and technically                         4
--
                                                      correct.                       The Independent Reviewer confirms that information   5
Independently Reviewing Submittals to the NRC.
                                                      in the submittal is accurate and correct. Also, the Indepen-                         '
-
                                                      dent Reviewer confirms that the supporting data in the sub-
:
                                                      mittal supports the submitted conclusion.                                           j?
The District's Nuclear Regulatory & Industry Affairs depart-
                                                      Either a Check or the Independent Review are completed prior                         3
7
                                                      to management review of the proposed NRC response.                       These       i
mental procedure for processing of NRC and other regulatory
                                                      Checks assure that the preparer and the preparer's super-                             5
m
                                                      visor have reviewed apprcpriate documentation and available                           j
correspondence (DAS-L-03) was revised in September 1984 to
                                                      resources so that responses are complete and accurate in                                     ,
a
                                                                                                                                            4
incorporate appropriate Independent Review requirements as
                                                                                                                                            3-
?
                                                                                                -7-                                         J
well as Checks of responses.
                                                                                                                                                  l
In accordance with the proce-
i
dure as revised, NRC submittals now undergo a Check which is
j
generally an intradepartmental review of the originating NRC
3
document against the submittal to confinn that items are
-
adequately addressed, properly stated and the responses are
_
complete. A Check is normally done by a knowledgeable person
i
or the preparer's supervisor or manager.
Q
Correspondence from the NRC is reviewed upon receipt to deter-
I
mine if a response is required and if that response should be
=
independently reviewed.
Review of such responses are assigned
;
to an OPPD organization separate from the initial preparer's
-
for an Independent Review, which is generally an interdepart-
s
mental review of the NRC originating document against the
"
submittal to confinn that all items are adequately addressed,
3
properly stated and the responses are complete and technically
4
correct.
The Independent Reviewer confirms that information
5
in the submittal is accurate and correct. Also, the Indepen-
'
dent Reviewer confirms that the supporting data in the sub-
j?
mittal supports the submitted conclusion.
Either a Check or the Independent Review are completed prior
3
to management review of the proposed NRC response.
These
i
Checks assure that the preparer and the preparer's super-
5
visor have reviewed apprcpriate documentation and available
j
resources so that responses are complete and accurate in
,
4
3
-
-7-
J
l


r'
r'
  '
. ,l
    . ,l
'
      '
'
          3. Corrective Steps Which Have Been Taken and the Results Achieved
3.
            (Continued)
Corrective Steps Which Have Been Taken and the Results Achieved
                    detail.   Independent Reviews add these same features plus
(Continued)
                    the review of a knowledgeable third party.
detail.
                    The District's experience since revision of DAS-L-03 has
Independent Reviews add these same features plus
                    indicated that Independent Reviews and Checks are providing
the review of a knowledgeable third party.
                    a thorough review of the responses, thereby reducing the
The District's experience since revision of DAS-L-03 has
                    likelihood of further similar violations.
indicated that Independent Reviews and Checks are providing
          4. The Corrective Steps Which Will Be Taken to Avoid Further Violations
a thorough review of the responses, thereby reducing the
            Experience'with the process of Independent Reviews and Checks of
likelihood of further similar violations.
            responses indicates that additional corrective steps are not neces-
4.
            sary; however, the training programs for new and seasoned employees
The Corrective Steps Which Will Be Taken to Avoid Further Violations
            are anticipated to improve as further training resources become
Experience'with the process of Independent Reviews and Checks of
            available and supervisors become better acquainted with application
responses indicates that additional corrective steps are not neces-
            of these training resources to their employees' training and re-
sary; however, the training programs for new and seasoned employees
            training needs.
are anticipated to improve as further training resources become
          5. The Date When Full Compliance Will Be Achieved
available and supervisors become better acquainted with application
            The District is currently in full compliance.
of these training resources to their employees' training and re-
                                            -8-
training needs.
5.
The Date When Full Compliance Will Be Achieved
The District is currently in full compliance.
-8-
}}
}}

Latest revision as of 11:35, 12 December 2024

Discusses 850409 Response to Violations Noted in Insp Rept 50-285/84-12.Civil Penalty Fully Mitigated Based on Prior Good Performance & Prompt & Extensive Corrective Action. Violation Classified as Severity Level III
ML20129E474
Person / Time
Site: Fort Calhoun 
Issue date: 05/24/1985
From: Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Andrews R
OMAHA PUBLIC POWER DISTRICT
References
IEB-82-02, IEB-82-2, NUDOCS 8506060509
Download: ML20129E474 (2)


See also: IR 05000285/1984012

Text

4.

W 2 41985

In Reply Refer To:

Docket:

50-285/84-12

Omaha Public Power District

ATTN:

R. L. Andrews, Division Manager-

Nuclear Production

1623 Harney Street

Omaha, Nebraska 68102

Gentlemen:

This refers to your April 9, 1985, response (LIC-85-138) in reply to the

Notice of Violation sent to you with our letter dated March 8, 1985. Our

letter and Notice described a violation which occurred at the Fort Calhoun

Station which was identified during an NRC inspection and investigation

conducted in May, June, and July respectively.

The violation was discussed

with you during an Enforcement Conference held with Mr. P. S. Check, Deputy

Regional Administrator, Region IV on December 20, 1984.

Your response has been carefully considered. The response does not contradict

the fact that the violation occurred, and false, inaccurate and incomplete

information was provided to the NRC for review. The information requested,

under oath, by the NRC through the issuance of an IE Bulletin, is considered

material since it was needed to assess the significance of an identified

problem, the potential degradation of threaded fasteners. The key question is

whether the information furnished had a natural tendency or capability to

influence, not whether the information was in fact relied on.

In our

opinion, it did have a natural tendency or capability to influence.

See

VirginiaElectricPowerCo.(NorthAnna1and2),4NRC480(1976), affirmed

VEPC0 v. NRC, 571 F 2d 1289 (4th. Cir. 1978.). The violation identified by the

NRC regardTng your August 2,1982 reply to IE Bulletin 82-02 demonstrated the

~

need for more effective control of your responses to the NRC. As discussed in

our Notice of Violation, in recognition of prior good performance and prompt and

extensive corrective action, the civil penalty was fully mitigated.

However,

since the false statement is considered to be material and is considered to be

more than an inadvertent clerical error as there was a specific lack of emphasis

and attention by several levels of management and supervision within the OPPD

organization, the classification of the violation as a Severity Level III is

appropriate.

I

I

,

'

0506060509 050524

PDR

ADOCK 05000295

G

PDR

..

..~

- .

=

-lw ,

  • i

'

+

.

~

,.

>

,

..

Omaha Public Power District-

-2--

'

.We find your reply responsive to the-concerns raised in our Notice of

l

Violation.- We will review your. corrective action during a. future. inspection

to determine that full compliance has been achieved and will be maintained.-

Sincerely,

.

!

Original signed by

'

'

Robert D.' Martin

' Robert D. Martin

-

!

. Regional Administrator.

cc:

W. G. Gates, Manager

Fort Calhoun Station

P..O. Box 399

Fort Calhoun, Nebraska 68023

Harry H. Voigt, Esq.

,

,.

'

LeBoeuf, Lamb, Leiby & MacRae

f1333 New Hampshire Avenue, NW

Washington, DC

20036

Kansas Radiation Control Program Director

Nebraska Radiation Control Program Director

[.bec'lioDMB(IE01).

-bec distrib. by RIV:

'

  • RPB2
  • Resident Inspector

R..D. Martin, RA

. EP&RPB

  • SectionChief(RPB2/A)
  • MIS System
  • RIV File

R. Denise, DRSP.

  • RSTS Operator

.T. Westerman

(

...

E0f

l

RIV:RP,B

'

DRS&P

RA

i-

RHuntWr:gb

RPDenise

TWesterman

RDP

in

5/Jy/85

5/g%BS

SM/85

5/ i/85

'

l

l

l

I

l>

-

- - -

I

.

'

6

, M [*39 *ylg.),g y 1.;fii Q ( % ,y(;#fk? % R Q Q,Cf f

Q{

.

,

Omaha Public Power District

1623 Harney Omaha. Nebraska 68102

402/536 4000

April 9, 1985

LIC-85-138

APRII1985

f4r. James M. Taylcr, Director

Office of Inspection and Enforcement

U. S. Nuclear Regulatory Commission

Washington, DC 20555

Reference:

(1)

Docket No. 50-285

(2)

Letter from OPPD (W. C. Jones) to NRC (J. T. Collins)

dated August 2, 1982 (LIC-82-269)

(3)

Letter from OPPD (R. L. Andrews) to NRC (J. T. Collins)

dated July 2, 1984 (LIC-84-209)

(4)

Letter from 0 PPD (R. L. Andrews) to NRC (R. D. Martin)

dated December 27, 1984 (LIC-84-434)

(5)

Letter from NRC (R. D. Martin) to OPPD (R. L. Andrews)

dated March 8,1985 (EA-84-63)

Dear fir. Taylor:

IE Inspection Report 84-12

Notice of Violation

'

The Omaha Public Power District received IE Inspection Report 84-12 and Reference

(5) both dated March 8, 1985.

These documents idertified a potential material

false statement and violation of NRC requirements relative to the District's re-

sponse to NRC IE Bulletin 82-02.

Pursuant to 10 CFR 2.201, please find attached

the District's response to these allegations.

Sincerely,

Th/sC

/

/

R. L. Andrews

Division Manager

Nuclear Production

)

1

RLA/CWN/dao

V

"

4

&c

4

-

.,

s

N g

(

4

~-ggnoo,m.,,

...s,.

..

_

-

-

..

..

,

LIC-85-138'

s

-:Page' 2

,

p

.cc:

LeBoeuf, Lamb,~Leiby & MacRae

.1333 New Hampshire Avenue,.N.W.

p.;

,.

Washington, DC 20036

Mr. James R. Miller, Chief ~

.

Office of Nuclear Reactor Regulation

Division of Licensing'

U. S. Nuclear Regulatory Commission-

Washington, DC 20555

<

Mr. Robert D. Martin

Regional Administrator-

.

r

U. S. Nuclear Regulatory Commission

Region IV

611 Ryan Plaza Drive, Suite 1000

,

Arlington, TX 76011-

Mr. E. G. Tourigny, NRC Project Manager

l

.Mr. L. A..Yandell, NRC Senior Resident Inspector

!

,-

L

l

l

I

L-

r

.

-

,

UNITED STATES OF AMERICA

NUCLEAR REGULATORY COMMISSION

In the Matter of

-

Omaha Public Power District

)

Docket flo. 50-285

(Fort Calhoun Station,

)

Unit No. 1)

)

'

'

AFFIDAVIT

R. L. Andrews, being duly sworn, hereby deposes and says that he is Division

Manager - Nuclear Production of the Omaha Public Power District; that he is

duly authorized to sign and file with the Nuclear Regulatory Commission the

attached response to the flotice of Violation identified in the Commission's

letter dated March 8, 1985 (EA-84-63); that he is familiar with the content

thereof; and that the matters set forth therein are true and correct to the

best of his knowledge, information and belief.

' b'.?ftie'L

,.

R. L. Andrews

Division llanager

fluclear Production

STATE OF NEBRASKA)

)

ss

COUNTY OF DOUGLAS)

Subscribed and sworn to before me, a Notcry Public in and for the State of

Nebraska on this

9

day of April, 1985.

.

-r

enum neuer-se e m e.

0amyl.(liAzp>

Er

k

Y

fj

ilotjry Public

I-

k.

}

l

r

.

.,

. . ,

,

ATTACHMENT

NOTICE OF VIOLATION

0 PPD Response Pursuant to 10 CFR 2.201

In accordance with Reference 5 and as required therein, the District is

responding to the subject Notice of Violation associated with OPPD's

initial. response to IE Bulletin 82-02 (Reference 2).

VIOLATION

The NOTICE OF VIOLATION attached to Reference 5 states:

The following is a material false statement within the meaning

of Section 186 of the Atomic Energy Act of 1954, as amended.

In the August 2,1982, response to NRC IE Bulletin No. 82-02,

'" Degradation of Threaded Fasteners in Reactor Coolant Pressure

Boundaries in PWR Plants," the licensee stated, in part, that

"The Fort Calhoun Station approved maintenance procedures cal!

'for the use of NEVERSIEZE (sic) (Pure Nickel #65) on all

threaded fasteners."

Contrary to the above statement:

Special Maintenance Procedure SP-RC-11, Revision 1,

" Reactor Coolant Pump Assembly," (effective between

May 24, 1980, and March 1,1983) designated no specific

lubricant on the reactor coolant pump (RCP) studs.

Discussions revealed that it had been common practice to

use molybdenum disulfide lubricant on both.the RCP and

reactor vessel studs.

Revision 6 of Special Maintenance

'

Procedure SP-RC-11, dated March 16, 1984, specifically

required the use of " Super-Moly" (molybdenum disulfide)

on RCP Studs.

Maintenance Procedure RC-2-1-B, Revision 12, "S/G Primary

Manway Replacement," (effective between June 9,1981, and

January 20, 1983) designated a mixture of 50% oil and 50%

graphite to be used on manway studs.

The August 2,1982, statement was false in that contrary to the

statement, a number of different types of lubricants were

utilized at Fort Calhoun Station, including " Super-Moly"

(molybdenum disulfide).

The false statement was material in

that one of the purposes of IE Bulletin No. 82-02 was to find

'

out which licensees used " Super-Moly" (molybdenum disulfide) as

a fastener lubricant and what plant experience the licensee had

with stress-corrosion cracking of fasteners using molybdenum

disulfide lubricants.

At the time IE Bulletin 82-02 was

,

l

issued, the NRC thought that molybdenum disulfide might have

,

Io

n

'

.

-

.

VIOLATION'(Continued)

a pronounced tendency to decompose in the presence of high

temperature and moisture conditions to release sulfide, a

known promoter of stress-corrosing cracking. Although the

NRC subsequently found molybdenum disulfide lubricant to be

acceptable, this fact was not known when the licensee sub-

mitted its response.

This. is a Severity Level III violation (Supplement VII).

(No Civil Penalty)

DISTRICT'S RESPONSE

1.

Admission or Denial of the Alleged Violation

The District admits that its August 2,1982 response was incomplete,

but den.ies that the alleged violation is a material false statement.

Supplement VII to 10 CFR, Part 2, Appendix C provides that:

A false statement caused by an inadvertent clerical or

similar error involving information which, had it been

available to NRC and accurate at the time the information

should have been submitted, would probably not have

resulted in regulatory action or NRC seeking additional

information

is a " Severity IV violation."

The complete text of that portion of the District's August 2,1982

response that led to the Notice of Violation is as follows:

Request

Identify those closures and connections, if any, where

fastener lubricants and injection sealant materials have

been or are being used and report on plant experience

with their application particularly any instances of SCC

of fasteners.

Include types and composition of materials

used.

,

!

l

District's Response

Maintenance records indicate that injection sealant

canpounds have never been used on any of the RCPB

enclosures within the scope of IE Bulletin 82-02 at

the Fort Calhoun Station.

The Fort Calhoun Station approved maintenance proce-

dures call for use of NEVERSIEZE Pure Nickel #65 on

all threaded fasteners.

To date, the District has ex-

perienced no problems related to use of the NEVERSIEZE

lubricant.

-2-

.- --

-

_ -

-_ .

. - _ _ _ _ - _ _ _ - _

-

-. - - _ - _ _ _

_

,

,

.

'

1.

LAdmission or Denial of the Alleged Violation (Continued)

In essence,.the District furdshed three categories of information

to the NRC:

'

(1)

Injection . sealant compounds used,

-

(2)

Lubricants used on-threaded fasteners, and

(3).

Plant' experience with sealants and lubricants, particularly

_

instances-of stress corrosion cracking of threaded fasteners.

Infomation furnished under Category 1 was accurate; infomation

under Category 2 was incomplete and therefore inaccurate; and

infomation under Category 3 was accurate. The District believes

that its answer in Category 3 must be considered to determine

whether there was any material false statement.

The District

accurately reported that it had experienced no problems. That

infomation~was correct with respect to all lubricants used, even

though the lubricants themselves were not al1~1isted.

Had the-

other lubricants been identified, no different conclusion con-

cerning their effect would have been presented. Therefore, con-

trary to the Notice of Violation, the statement was not material .

If complete and accurate information had been included in the

District's 1982 response of IE Bulletin 82-02, .it "would probably -

not have resulted in regulatory action or NRC seeking additional

infomation."

Since the NRC acknowledges that the District's incomplete response

was not intentional and was not intended to conceal or mislead, we

also believe it is appropriate to classify it as " inadvertent."

In

addition, the Commission has determined that " materiality" should be

contingent upon the safety significance of the. infomation (47 Fed.

Reg. 8584 (1984)). Based upon the above discussion, the District

has-concluded that the inco'nplete response has no safety signifi-

cance.- For all of these reasons, the District submits that its 1982

response was not a material false statement and that classification

as a Severity Level III is not warranted.

2.

Reasons for the Violation

Reference 3 described the steps taken to correct the District's

response to Item 5 of IE Bulletin 82-02.

Reference 3 also identi-

fied the procedures which were in effect in 1982 when the initial

response was prepared.

Further, the inspection conducted by the

NRC's Office of Investigations during June and July of 1984 defines

the causes for the occurrence. The results of the NRC's inspection

are summarized in the third paragraph of Reference 5.

The submis-

sion of the statement occurred due to failures on the part of the

District including inadequate review of documentation, failure to

adequately coordinate and discuss the matter with knowledgeable

personnel in the specific area of concern, failure of management

to assign the response to an experienced employee, and failure of

-3

e==w-s-

-

.

,

.

.

-

2.

Reason for the Violation (Continued)

management to identify the incomplete statement during the required

procedural review of all the responses to the NRC.

The circum-

stances associated with the preparation of the response to the NRC

indicated a specific lack of emphasis and attention to detail by a

number of levels of management and supervision within the District.

3.

Corrective Steps Which Have Been Taken and the Results Achieved

As described in the District's presentations to Mr. P. S. Check and

other members of the NRC Region IV staff during the December 20,

1984 Enforcement Conference, corrective measures have been taken in

three-areas:

(1)

Review of the qualifications of those responsible for

preparing NRC response for the years 1983 and 1984.

(2)

Re' vision of the trainirg program for new technical

employees.

(3)

Establishment of internal procedures for checking sub-

mittals to the NRC and independently reviewing submittals

requiring oath or affimation and as otherwise deemed

appropriate prior to management review.

'

These measures and the results achieved are summarized below.

(1)

. Review of Preparer's Qualifications

An undocumented review and evaluation of correspondence

submitted under oath or affirmation for the last two years

(1983-1984) was conducted to address the following functions:

a.

Were the individuals who prepared responses experienced

in the area of the response?

b.

Is it necessary to perfom a technical review of any

responses submitted during 1983 and 1984?

c.

Is it necessary to conduct a review and evaluation of

correspondence submitted prior to 1983?

The results of that review and evaluation are as follows:

Items submitted under oath or affirmation fit into three

general categories:

Technical Specification Amendment Applications (both

-

initial applications and revisions to previously filed

applications)

,

Proprietary Information Declarations

.

-

IE Bulletin and Generic Letter Responses

-

-4-

. _ _ _ _ _ _ _ _ _ _

____-

_

-

.

.

.

3.

Corrective Steps Which Have Been Taken and the Results Achieved

(Continued)

,

Technical Specification Amendment Application

The review and evaluation concluded that since Technical

Specification Amendments were reviewed and approved by the

Plant Review Committee and the Safety Audit and Review

Committee, the detailed reviews and approvals of these two

groups was sufficient to ensure that the information was

correct.

In addition, the Commission approved such appli-

cations in the form of Amendments to the District's Technical

Specifications.

Based on the above, the District believes

that no additional review is necessary for the Technical

Specification Amendments submitted during 1983-1984.

The

review and evaluation also concluded that it is highly un-

likely that a similar situation to the IE Bulletin 82-02

response could occur with Technical Specification Amendment

applications.

It was also detemined that it was not neces-

sary to do additional reviews on the Technical Specification

Amendments submitted prior to 1983 since they were handled

in a similar manner as the 1983-1934 applications.

Proprietary Information Declarations

,

The review and evaluation concluded that Proprietary Infor-

mation Declarations are not nomally of a type where safety

significant information is provided to the Commission.

Therefore, no additional review of Proprietary Infomation

Declarations submitted during 1983-1984 was needed nor was

it necessary to review such submittals prior to 1983. The

review and evaluation also concluded that it is highly un-

likely that a similar situation to the IEB 82-02 response

could occur with Proprietary Information Declarations.

IE Bulletin and Generic Letter Responses

-

The review and evaluation concluded that the personnel who

initially prepared IE Bulletin and Generic Letter responses

submitted under oath or affirmation during 1983-1984 were

sufficiently experienced to prepare such responses.

These

IE Bulletins and Generic Letter responses were processed

through the District's management review cycle. As described

in Item (3) on Page 7 of this response, the District procedure

for processing of f1RC and other regulatory correspondence

(DAS-L-03) was revised in September 1984 to incorporate an

independent review and checking function.

Since that revi-

sion, IE Bulletins and Generic Letters submitted under oath

of affimation have been independently reviewed as required.

For 1983 and 1984 IE Bulletins and Generic Letter responses

that were submitted prior to September 24, 1984, the following

action was taken.

-5-

_ _ _ _

_____-__ __ _ __

.

-

.

3.

Corrective Steps Which Have Been Taken and the Results Achieved

(Continued)

g

a.

Many of the personnel responsible for preparing

i

these responses have been interviewed in order to

4

determine if additional review is required.

During

-

these interviews, personnel were asked to describe

the steps they used in preparing the response with

the intention of determining whether the necessary

steps were taken.

Based on these interviews it was

determined that the necessary steps were taken;

-

consequently, no additional review was required.

b.

Some responses were discussed at several meetings

where sufficient qualified personnel were present

%

and extensively discussed the subject matter. The

- :

responses were then prepared ba;ed on those discus-

_

sions and the documents were subsequently processed

through the District's correspondence review cycle.

c.

Some of the IE Bulletins or Generic Letter re-

Y

sponses have subsequently been reviewed by the

J

Commission and closed.

Based on the above information it has been concluded that it

7

is not necessary to conduct further reviews of the IE Bulletin

5

'"

and Generic Letter responses submitted for the 1983-1984

period or made before 1983.

g

_

this review provides confidence that it is unlikely that a

3

similar situation to the IEB 82-02 response could occur with

I

the IE Bulletin and Generic Letter responses submitted before

2

or during the 1983-1984 period.

j

'=

The District cannot positively state that all responses

'

submitted to the Commission are 100'. complete and accurate;

7

however, the District can state there is a high degree of

-

assurance that responses submitted to the Commission are

=

complete and accurate based on past reviews and the results

7

of the review and evaluation which was conducted prior to

i

the December 20, 1984, Enforcement Conference.

(2)

Revision of the Training Program for New Technical Employees

Training of new tehnical employees has been upgraded by the

i

availability of additional courses in reactor and power plant

a

fundamentals.

Further, availability of training materials and

y

resources has been formalized and implemented by the Nuclear

l

Production Division (NPD) as described in the NPD Policy /

i

Procedure No. C-3, R0 2/15/85, " Orientation / Training of Newly

?

Hired Technical Employees Performing Safety-Related Activi-

e

ti es . " Policy / Procedure C-3 training of managers and super-

3

visors in NPD and managers in the Engineering Division was

}

N.

d

-6-

y

i

-

_.

.

..

. . _ . . . - . . . , . . , _ _ . -

. . . . . , . . . . . - ~ _

.

. - , . .

- _ . -

.

,

g

-

.

3.

Corrective Steps Which Have Been Taken and the Results Achieved

1

(Conti nued)

7

.

completed on February 12, 1985. New technical employees in

j

the Nuclear Production Division will be trained under this

a

upgraded training and orientation policy. These improve-

$

ments improve employee awareness of existing documentation,

y

resources, and 'nfonnation prior to preparation of responses.

]

Also, utilization of this policy encourages communication

between the supervisor and new employee to provide the

supervisor with a thorough understanding of the employee's

4

capabilities.

4

-)

The improvement of the training program and formal establish-

4

ment of an NPD training policy for new employees has resulted

-d

in increased managerial and supervisory awareness that indivi-

2

duals preparing responses must be properly qualified prior to

being assigned as a preparer. Similar policies are in effect

g

in the Engineering Division.

I

Al

(3)

Establishment of Internal Procedures for Checking and

--

Independently Reviewing Submittals to the NRC.

-

The District's Nuclear Regulatory & Industry Affairs depart-

7

mental procedure for processing of NRC and other regulatory

m

correspondence (DAS-L-03) was revised in September 1984 to

a

incorporate appropriate Independent Review requirements as

?

well as Checks of responses.

In accordance with the proce-

i

dure as revised, NRC submittals now undergo a Check which is

j

generally an intradepartmental review of the originating NRC

3

document against the submittal to confinn that items are

-

adequately addressed, properly stated and the responses are

_

complete. A Check is normally done by a knowledgeable person

i

or the preparer's supervisor or manager.

Q

Correspondence from the NRC is reviewed upon receipt to deter-

I

mine if a response is required and if that response should be

=

independently reviewed.

Review of such responses are assigned

to an OPPD organization separate from the initial preparer's

-

for an Independent Review, which is generally an interdepart-

s

mental review of the NRC originating document against the

"

submittal to confinn that all items are adequately addressed,

3

properly stated and the responses are complete and technically

4

correct.

The Independent Reviewer confirms that information

5

in the submittal is accurate and correct. Also, the Indepen-

'

dent Reviewer confirms that the supporting data in the sub-

j?

mittal supports the submitted conclusion.

Either a Check or the Independent Review are completed prior

3

to management review of the proposed NRC response.

These

i

Checks assure that the preparer and the preparer's super-

5

visor have reviewed apprcpriate documentation and available

j

resources so that responses are complete and accurate in

,

4

3

-

-7-

J

l

r'

. ,l

'

'

3.

Corrective Steps Which Have Been Taken and the Results Achieved

(Continued)

detail.

Independent Reviews add these same features plus

the review of a knowledgeable third party.

The District's experience since revision of DAS-L-03 has

indicated that Independent Reviews and Checks are providing

a thorough review of the responses, thereby reducing the

likelihood of further similar violations.

4.

The Corrective Steps Which Will Be Taken to Avoid Further Violations

Experience'with the process of Independent Reviews and Checks of

responses indicates that additional corrective steps are not neces-

sary; however, the training programs for new and seasoned employees

are anticipated to improve as further training resources become

available and supervisors become better acquainted with application

of these training resources to their employees' training and re-

training needs.

5.

The Date When Full Compliance Will Be Achieved

The District is currently in full compliance.

-8-