ENS 51576: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 12/01/2015 12:45 EST
| event date = 12/01/2015 12:45 EST
| last update date = 12/01/2015
| last update date = 12/01/2015
| title = Secondary Containment Inoperable Due To Reactor Building Airlock Doors Being Opened Simultaneously
| title = Secondary Containment Inoperable Due to Reactor Building Airlock Doors Being Opened Simultaneously
| event text = On December 1, 2015 at 1245 EST, Secondary Containment became inoperable due to the failure to meet a Surveillance Requirement (SR 3.6.4.1.3) on Unit 2.  
| event text = On December 1, 2015 at 1245 EST, Secondary Containment became inoperable due to the failure to meet a Surveillance Requirement (SR 3.6.4.1.3) on Unit 2.  
The inoperability was caused when RB [Reactor Building] airlock doors were inadvertently opened simultaneously.
The inoperability was caused when RB [Reactor Building] airlock doors were inadvertently opened simultaneously.

Latest revision as of 20:46, 1 March 2018

ENS 51576 +/-
Where
Susquehanna Talen Energy icon.png
Pennsylvania (NRC Region 1)
Reporting
10 CFR 50.72(b)(3)(v)(C), Loss of Safety Function - Release of Radioactive Material
LER: 05000387/LER-2015-011
Regarding Secondary Containment Declared Inoperable Due to an Airlock Door That Had Not Been Properly Latched
Time - Person (Reporting Time:+-1.63 h-0.0679 days <br />-0.0097 weeks <br />-0.00223 months <br />)
Opened: Jason Willis
16:07 Dec 1, 2015
NRC Officer: Donald Norwood
Last Updated: Dec 1, 2015
51576 - NRC Website