ENS 51664: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 01/20/2016 04:00 CST
| event date = 01/20/2016 04:00 CST
| last update date = 01/22/2016
| last update date = 01/22/2016
| title = Technical Support Center Out Of Service For Planned Preventative Maintenance  
| title = Technical Support Center Out of Service for Planned Preventative Maintenance  
| event text = At 0400 CST on Wednesday, January 20, 2016, the Dresden Nuclear Power Station (DNPS) Technical Support Center (TSC) emergency ventilation system will be removed from service for planned maintenance activities.  During the maintenance, the TSC Ventilation will be shut down.  The TSC air filtration fan and dampers will be non-functional, rendering the TSC HVAC accident mode non-functional.  This maintenance is scheduled to minimize out of service time.  The planned TSC ventilation outage is scheduled to be completed in approximately 43 hours.
| event text = At 0400 CST on Wednesday, January 20, 2016, the Dresden Nuclear Power Station (DNPS) Technical Support Center (TSC) emergency ventilation system will be removed from service for planned maintenance activities.  During the maintenance, the TSC Ventilation will be shut down.  The TSC air filtration fan and dampers will be non-functional, rendering the TSC HVAC accident mode non-functional.  This maintenance is scheduled to minimize out of service time.  The planned TSC ventilation outage is scheduled to be completed in approximately 43 hours.
Contingency plans are in place so that if an emergency is declared requiring TSC activation during this period, the TSC will be staffed and activated using existing Emergency Planning (EP) procedures and checklists.  If radiological or environmental conditions require TSC facility evacuation during ventilation system restoration; the Station Emergency Director will relocate the TSC staff in accordance with station procedures.
Contingency plans are in place so that if an emergency is declared requiring TSC activation during this period, the TSC will be staffed and activated using existing Emergency Planning (EP) procedures and checklists.  If radiological or environmental conditions require TSC facility evacuation during ventilation system restoration; the Station Emergency Director will relocate the TSC staff in accordance with station procedures.

Latest revision as of 21:45, 1 March 2018

ENS 51664 +/-
Where
Dresden Constellation icon.png
Illinois (NRC Region 3)
Reporting
10 CFR 50.72(b)(3)(xiii), Loss of Emergency Preparedness
Time - Person (Reporting Time:+-15.32 h-0.638 days <br />-0.0912 weeks <br />-0.021 months <br />)
Opened: Robert Montgomery
18:41 Jan 19, 2016
NRC Officer: Steve Sandin
Last Updated: Jan 22, 2016
51664 - NRC Website
Loading map...