| event date = 05/02/2017 09:28 EDT | | event date = 05/02/2017 09:28 EDT | ||
| last update date = 05/09/2017 | | last update date = 05/09/2017 | ||
| title = Failed Ultrasonic Testing | | title = Failed Ultrasonic Testing of Weld | ||
| event text = On May 2, 2017, during planned inspections, an ultrasonic examination performed on weld PCS-4-PRS-1P1-1, revealed an axial indication in the pressurizer nozzle to safe end area of the weld. This indication does not meet applicable acceptance criteria under ASME, Section XI. | | event text = On May 2, 2017, during planned inspections, an ultrasonic examination performed on weld PCS-4-PRS-1P1-1, revealed an axial indication in the pressurizer nozzle to safe end area of the weld. This indication does not meet applicable acceptance criteria under ASME, Section XI. | ||
The plant was in cold shutdown at 0% power for a planned refueling outage at the time of discovery. The condition will be resolved prior to plant startup. | The plant was in cold shutdown at 0% power for a planned refueling outage at the time of discovery. The condition will be resolved prior to plant startup. |
Latest revision as of 21:42, 1 March 2018
Where | |
---|---|
Palisades ![]() Michigan (NRC Region 3) | |
Reporting | |
10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded | |
Time - Person (Reporting Time:+1.97 h0.0821 days <br />0.0117 weeks <br />0.0027 months <br />) | |
Opened: | Barbara Dotson 15:26 May 2, 2017 |
NRC Officer: | Dong Park |
Last Updated: | May 9, 2017 |