ENCLOSURE 1 NOTICE OF VIOLATION | |||
NOTICE OF VIOLATION | ) | ||
Alabama Power Company | Alabama Power Company Docket No. 50-348 Farley Unit 1 License No. NPF-2 During the Nuclear Regulatory Commission (NRC) inspection conducted on April 11 - May 18,1987, violations of NRC requirements were identified. | ||
In accordance with the " General Statement of Policy and Procedure for NRC Enforce-ment Actions," 10 CFR Part 2, Appendix C (1986), the violation is listed below: | |||
During the Nuclear Regulatory Commission (NRC) inspection conducted on April 11 - May 18,1987, violations of NRC requirements were identified. In accordance with the " General Statement of Policy and Procedure for NRC Enforce-ment Actions," 10 CFR Part 2, Appendix C (1986), the violation is listed below: | TS 6.8.1 requires that applicable written procedures recommended in Appendix A of Regulatory Guide (RG) 1.33, Revision 2, 1978 shall be established, implemented, and maintained. | ||
Administrative Procedure ( AP) 16 " Conduct of Operations - Operations Group section 3.1.13.5 requires that the designated 11' :nsed operator at-the-controls (0ATC) shall not under any circumstances leave the at-the-controls area for any reason without obtaining a qualified relief operator. | |||
Contrary to the above, on April 27, 1987 at approximately 7:30 a.m., | Contrary to the above, on April 27, 1987 at approximately 7:30 a.m., | ||
the 0ATC reactor operator position on Unit 1 control board was left unattended for approximately 20 seconds. | the 0ATC reactor operator position on Unit 1 control board was left unattended for approximately 20 seconds. | ||
FOR THE NUCLEAR REGULATORY COMMISSION b | The licensed Shift Supervisor assumed this position without proper notification until the 0ATC operator returned to the position, i | ||
This is a Severity Level IV Violation (Supplement 1). | |||
Luis A. Reyes, Director Division of Reactor Projects Dated at Atlanta, Georgia this 4th day of June 1987 8706170297 870605 | FOR THE NUCLEAR REGULATORY COMMISSION b | ||
NW1 il | |||
/ | |||
Luis A. Reyes, Director Division of Reactor Projects Dated at Atlanta, Georgia this 4th day of June 1987 8706170297 870605 ADOCK 0 % y8 PDR G | |||
_}} | _}} | ||
Latest revision as of 23:16, 3 December 2024
| ML20215B346 | |
| Person / Time | |
|---|---|
| Site: | Farley |
| Issue date: | 06/04/1987 |
| From: | Reyes L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML20215B306 | List: |
| References | |
| 50-348-87-10, NUDOCS 8706170297 | |
| Download: ML20215B346 (1) | |
Text
r
=
Il i
ENCLOSURE 1 NOTICE OF VIOLATION
)
Alabama Power Company Docket No. 50-348 Farley Unit 1 License No. NPF-2 During the Nuclear Regulatory Commission (NRC) inspection conducted on April 11 - May 18,1987, violations of NRC requirements were identified.
In accordance with the " General Statement of Policy and Procedure for NRC Enforce-ment Actions," 10 CFR Part 2, Appendix C (1986), the violation is listed below:
TS 6.8.1 requires that applicable written procedures recommended in Appendix A of Regulatory Guide (RG) 1.33, Revision 2, 1978 shall be established, implemented, and maintained.
Administrative Procedure ( AP) 16 " Conduct of Operations - Operations Group section 3.1.13.5 requires that the designated 11' :nsed operator at-the-controls (0ATC) shall not under any circumstances leave the at-the-controls area for any reason without obtaining a qualified relief operator.
Contrary to the above, on April 27, 1987 at approximately 7:30 a.m.,
the 0ATC reactor operator position on Unit 1 control board was left unattended for approximately 20 seconds.
The licensed Shift Supervisor assumed this position without proper notification until the 0ATC operator returned to the position, i
This is a Severity Level IV Violation (Supplement 1).
FOR THE NUCLEAR REGULATORY COMMISSION b
NW1 il
/
Luis A. Reyes, Director Division of Reactor Projects Dated at Atlanta, Georgia this 4th day of June 1987 8706170297 870605 ADOCK 0 % y8 PDR G