{{#Wiki_filter:NRC Briefing on Region I Activities and External Engagement
{{#Wiki_filter:NRC Briefing on Region I Activities and External Engagement Matt Herr Senior Vice President Mid-Atlantic Operations


Matt Herr Senior Vice President Mid-Atlantic Operations Communications with NRC and State & Local Governments Excellent communications w ith Region I governmental entities
2 Communications with NRC and State & Local Governments Nov. 16, 2023 State and local legislative and regulatory efforts Excellent communications with Region I governmental entities
- Day-to-day operations State and local
- Day-to-day operations
- Special inspections legislative and
- Special inspections
- Workforce development initiatives regulatory efforts
- Workforce development initiatives
- Community information days
- Community information days
- Tours
- Tours


2 Nov. 16, 2023 Risk Insights in the Inspection Program
3 Risk Insights in the Inspection Program Nov. 16, 2023 Positive benefits from using risk insights in the inspection program
- Inspection Finding Review Board
- Inspections focus on issues of most safety significance Opportunity to further use risk insights to modernize data underlying the ROP
- Use more recent industry performance data to determine risk significance policy thresholds


Positive benefits from using risk insights in the inspection program
Nov. 16, 2023 4
- Inspection Finding Review Board
Transition to Digital Instrumentation & Control Limerick Digital Modernization Project is well underway
- Inspections focus on issues of most safety significance
- License amendment request filed Sept. 2022
- Several learnings:
Extensive pre-submittal meetings were very effective Audit Open Item Process is productive Communication with NRC Project Managers is excellent Potential opportunity to obtain clarity on Human Factors Evaluation Discussing with Region I plans to conduct inspections during the first installation


Opportunity to further use risk insights to modernize data underlying the ROP
Thank You Nov. 16, 2023 5}}
- Use more recent industry performance data to determine risk significance policy thresholds
 
3 Nov. 16, 2023 Transition to Digital Instrumentation & Control
 
Limerick Digital Modernization Discussing with Region I Project is well underway plans to conduct inspections
- License amendment request during the first installation filed Sept. 2022
- Several learnings:
* Extensive pre-submittal meetings were very effective
* Audit Open Item Process is productive
* Communication with NRC Project Managers is excellent
* Potential opportunity to obtain clarity on Human Factors Evaluation
 
4 Nov. 16, 2023 Thank You
 
5Nov. 16, 2023}}

Latest revision as of 08:53, 25 November 2024

M231116: Slides - Briefing on Region I Activities and External Engagement M. Herr
ML23313A029
Person / Time
Issue date: 11/09/2023
From: Herr M
NRC (Affiliation Not Assigned)
To:
Shared Package
ML23311A092 List:
References
M231116
Download: ML23313A029 (1)


Text

NRC Briefing on Region I Activities and External Engagement Matt Herr Senior Vice President Mid-Atlantic Operations

2 Communications with NRC and State & Local Governments Nov. 16, 2023 State and local legislative and regulatory efforts Excellent communications with Region I governmental entities

- Day-to-day operations

- Special inspections

- Workforce development initiatives

- Community information days

- Tours

3 Risk Insights in the Inspection Program Nov. 16, 2023 Positive benefits from using risk insights in the inspection program

- Inspection Finding Review Board

- Inspections focus on issues of most safety significance Opportunity to further use risk insights to modernize data underlying the ROP

- Use more recent industry performance data to determine risk significance policy thresholds

Nov. 16, 2023 4

Transition to Digital Instrumentation & Control Limerick Digital Modernization Project is well underway

- License amendment request filed Sept. 2022

- Several learnings:

Extensive pre-submittal meetings were very effective Audit Open Item Process is productive Communication with NRC Project Managers is excellent Potential opportunity to obtain clarity on Human Factors Evaluation Discussing with Region I plans to conduct inspections during the first installation

Thank You Nov. 16, 2023 5