ML042020035: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 2: Line 2:
| number = ML042020035
| number = ML042020035
| issue date = 07/09/2004
| issue date = 07/09/2004
| title = RAI Training and Qualification Plan (TAC Nos. MC2957 and MC2958)
| title = RAI Training and Qualification Plan
| author name = Vaidya B
| author name = Vaidya B
| author affiliation = NRC/NRR/DLPM
| author affiliation = NRC/NRR/DLPM

Latest revision as of 16:54, 24 March 2020

RAI Training and Qualification Plan
ML042020035
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/09/2004
From: Bhalchandra Vaidya
NRC/NRR/DLPM
To: Vanmiddlesworth G
Nuclear Management Co
Fretz R, NRR/DLPM, 415-1324
References
TAC MC2957, TAC MC2958
Download: ML042020035 (3)


Text

SAFEGUARDS INFORMATION July 9, 2004 Mr. Gary D. Van Middlesworth Site Vice President Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NOS. MC2957 AND MC2958)

Dear Mr. Van Middlesworth:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Point Beach Nuclear Plant, Units 1 and 2.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301)415-3498.

Sincerely,

/RA/

Bhalchandra Vaidya, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosure:

As stated cc w/o encl: See next page WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards NOTICE: The Enclosure contains Safeguards Information is subject to Civil and Information. Upon separation from the Criminal Penalties Enclosure, this letter is DECONTROLLED.

SAFEGUARDS INFORMATION

July 9, 2004 Mr. Gary D. Van Middlesworth Site Vice President Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NOS. MC2957 AND MC2958)

Dear Mr. Van Middlesworth:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Point Beach Nuclear Plant, Units 1 and 2.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301)415-3498.

Sincerely,

/RA/

Bhalchandra Vaidya, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION:

SPRT R/F RidsNsirDns RidsNrrDlpm OGC ACRS H. Chernoff L. Raghavan B. Ruland S. Reynolds, RIII ADAMS Accession Number: ML042020035 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR SPRT/NRR/SC NAME BVaidya, CHawes JPeralta JNakoski DATE 7/9/04 7/9/04 07/09/04 07/09/04 OFFICIAL RECORD COPY

Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esquire Mr. Ken Duveneck Vice President, Counsel & Secretary Town Chairman Nuclear Management Company, LLC Town of Two Creeks 700 First Street 13017 State Highway 42 Hudson, WI 54016 Mishicot, WI 54228 Mr. F. D. Kuester Chairman President & Chief Executive Officer Public Service Commission WE Generation of Wisconsin 231 West Michigan Street P.O. Box 7854 Milwaukee, WI 53201 Madison, WI 53707-7854 Regulatory Affairs Manager Regional Administrator, Region III Point Beach Nuclear Plant U.S. Nuclear Regulatory Commission Nuclear Management Company, LLC 801 Warrenville Road 6610 Nuclear Road Lisle, IL 60532-4351 Two Rivers, WI 54241 Resident Inspectors Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Douglas E. Cooper Mr. Jeffery Kitsembel Senior Vice President - Group Operations Electric Division Palisades Nuclear Plant Public Service Commission of Wisconsin Nuclear Management Company, LLC P.O. Box 7854 27780 Blue Star Memorial Highway Madison, WI 53707-7854 Covert, MI 49043 Nuclear Asset Manager Site Director of Operations Wisconsin Electric Power Company Nuclear Management Company, LLC 231 West Michigan Street 6610 Nuclear Road Milwaukee, WI 53201 Two Rivers, WI 54241 John Paul Cowan Dennis L. Koehl Executive Vice President & Chief Nuclear Site Vice-President Officer Nuclear Management Company, LLC Nuclear Management Company, LLC 6590 Nuclear Road 700 First Street Two Rivers, WI 54241 Hudson, WI 54016