#REDIRECT [[IR 05000461/2018051]]
{{Adams
| number = ML18317A402
| issue date = 11/13/2018
| title = Notice of Significant Public Licensee Meeting Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, to Discuss an Apparent Violation and Preliminary White Finding as Documented in IR 05000461/2018051
| author name = Riemer K
| author affiliation = NRC/RGN-III/DRP/B1
| addressee name =
| addressee affiliation =
| docket = 05000461
| license number = NPF-062
| contact person =
| document report number = IR 2018051
| document type = Meeting Notice
| page count = 3
}}
See also: [[see also::IR 05000461/2018051]]
 
=Text=
{{#Wiki_filter:UNITED STATES
                      NUCLEAR REGULATORY COMMISSION
                                        REGION III
                            2443 WARRENVILLE RD. SUITE 210
                              LISLE, ILLINOIS 60532-4352
                                November 13, 2018
                  NOTICE OF SIGNIFICANT LICENSEE MEETING
                  THIS MEETING IS OPEN TO PUBLIC ATTENDANCE
Name of Licensee:              Exelon Generation Company, LLC
Name of Facility:              Clinton Power Station, Unit 1
Docket Nos:                    50-461
Time and Date:                Friday, November 30, 2018
                              1:00 to 4:00 PM (CST)
Location:                      U.S. Nuclear Regulatory Commission, Region III
                              2443 Warrenville Road
                              Suite 210
                              Lisle, IL 60532-4351
Teleconference:                Bridgeline                    Passcode
                              877-952-8632                  13959
Purpose:                      A regulatory conference will be held between the
                              U.S. Nuclear Regulatory Commission (NRC) and Exelon
                              Generation Company, LLC, to discuss an apparent
                              violation and preliminary White finding concerning the
                              licensees failure to follow multiple procedures that affected
                              quality causing the Division 2 Emergency Diesel Generator
                              to be both inoperable and unavailable when it was relied
                              upon for plant safety. This issue has been preliminarily
                              determined to be of low-to-moderate significance as
                              documented in Inspection Report 05000461/2018051.
Meeting Category:              This is a Category 1 Meeting. The public is invited to
                              observe this meeting and will have one or more
                              opportunities to communicate with the NRC after the
                              business portion of the meeting but before the meeting is
                              adjourned.
 
Notice of Significant                          -2-
Licensee Meeting
NRC Attendees:                          Steven West, Regional Administrator, RIII
                                        Patrick Louden, Director, Division of Reactor
                                        Projects (DRP)
                                        Julio Lara, Deputy Director, DRP
                                        Kenneth OBrien, Director, Divison of Reactor
                                        Safety (DRS)
                                        Mohammed Shuaibi, Deputy Director, DRS
                                        Laura Kozak, Senior Reactor Analyst, DRP
                                        Kenneth Riemer, Chief, DRP Branch 1
                                        Karla Stoedter, Chief, DRS Engineering Branch 2
                                        Others as Designated
Licensee Attendees:                    Dan Enright, Senior Vice President, Operations
                                        Brad Fewell, Senior Vice President, Regulatory Affairs &
                                        General Counsel
                                        Scot Greenlee, Senior Vice President, Engineering &
                                        Technical Services
                                        George Gellrich, Vice President, Licensing and
                                        Regulatory Affairs
                                        Shane Marik, Vice President, Fleet Support
                                        Ted Stoner, Site Vice President
                                        Brad Kapellas, Plant Manager
                                        Jeff Stone, Director, Risk Management
                                        Johnny Weissinger, Director, Operations
Note: Attendance at this meeting by NRC personnel, other than those listed above, should be
      made known to Ken Riemer at 630-829-9628 by November 21, 2018.
      The NRC provides reasonable accommodation to individuals with disabilities where
      appropriate. If you need a reasonable accommodation to participate in this meeting, or
      need this meeting notice or the transcript or other information from the meeting in
      another format (e.g., braille, large print), please notify the NRCs meeting coordinator.
      Determinations on requests for reasonable accommodation will be made on a case-by-
      case basis.
      Because meetings are sometimes canceled or rescheduled as a result of unforeseen
      circumstances, such as severe weather, confirm the meeting schedule with the meeting
      contact.
                                                Approved By:      /RA/
                                                                Kenneth Riemer, Chief
                                                                Branch 1
                                                                Division of Reactor Projects
Meeting Contact: Kenneth Riemer
                  Chief, Branch 1
                  630-829-9628
                  Kenneth.Riemer@nrc.gov
 
Notice of Significant                        -3-
Licensee Meeting
DISTRIBUTION:
Christopher Cook, Region III Coordinator, OEDO
Michael King, Deputy Director, Division of Inspection and Regional Support, NRR
RidsNrrDorlLpl3
RidsNrrPMClinton Resource
Steven West, Regional Administrator, RIII
Darrell Roberts, Deputy Regional Administrator, RIII
Patrick Louden, Director, Division of Reactor Projects, RIII
Julio Lara, Deputy Director, Division of Reactor Projects, RIII
Kenneth OBrien, Director, Division of Reactor Safety, RIII
Mohammed Shuaibi, Deputy Director, Division of Reactor Safety, RIII
Kenneth Riemer, DRP Branch Chief
Elba Sanchez Santiago, SRI, Clinton
DRS Branch Chiefs:
Robert Daley
Steven Orth
David Hills
Robert Orlikowski
Karla Stoedter
Jamnes Cameron, Enforcement/Investigations Officer
Allan Barker, Regional State Liaison Officer, RIII
Viktoria Mitlyng, RIII Public Affairs
Prema Chandrathil, RIII Public Affairs
ADAMS Accession Number: ML18317A402
OFFICE      RIII
NAME        KRiemer:lg
DATE        11/13/2018
                                      OFFICIAL RECORD COPY
}}

Latest revision as of 07:02, 30 November 2019

Notice of Significant Public Licensee Meeting Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, to Discuss an Apparent Violation and Preliminary White Finding as Documented in IR 05000461/2018051
ML18317A402
Person / Time
Site: Clinton Constellation icon.png
Issue date: 11/13/2018
From: Kenneth Riemer
NRC/RGN-III/DRP/B1
To:
References
IR 2018051
Download: ML18317A402 (3)


See also: IR 05000461/2018051

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, ILLINOIS 60532-4352

November 13, 2018

NOTICE OF SIGNIFICANT LICENSEE MEETING

THIS MEETING IS OPEN TO PUBLIC ATTENDANCE

Name of Licensee: Exelon Generation Company, LLC

Name of Facility: Clinton Power Station, Unit 1

Docket Nos: 50-461

Time and Date: Friday, November 30, 2018

1:00 to 4:00 PM (CST)

Location: U.S. Nuclear Regulatory Commission, Region III

2443 Warrenville Road

Suite 210

Lisle, IL 60532-4351

Teleconference: Bridgeline Passcode

877-952-8632 13959

Purpose: A regulatory conference will be held between the

U.S. Nuclear Regulatory Commission (NRC) and Exelon

Generation Company, LLC, to discuss an apparent

violation and preliminary White finding concerning the

licensees failure to follow multiple procedures that affected

quality causing the Division 2 Emergency Diesel Generator

to be both inoperable and unavailable when it was relied

upon for plant safety. This issue has been preliminarily

determined to be of low-to-moderate significance as

documented in Inspection Report 05000461/2018051.

Meeting Category: This is a Category 1 Meeting. The public is invited to

observe this meeting and will have one or more

opportunities to communicate with the NRC after the

business portion of the meeting but before the meeting is

adjourned.

Notice of Significant -2-

Licensee Meeting

NRC Attendees: Steven West, Regional Administrator, RIII

Patrick Louden, Director, Division of Reactor

Projects (DRP)

Julio Lara, Deputy Director, DRP

Kenneth OBrien, Director, Divison of Reactor

Safety (DRS)

Mohammed Shuaibi, Deputy Director, DRS

Laura Kozak, Senior Reactor Analyst, DRP

Kenneth Riemer, Chief, DRP Branch 1

Karla Stoedter, Chief, DRS Engineering Branch 2

Others as Designated

Licensee Attendees: Dan Enright, Senior Vice President, Operations

Brad Fewell, Senior Vice President, Regulatory Affairs &

General Counsel

Scot Greenlee, Senior Vice President, Engineering &

Technical Services

George Gellrich, Vice President, Licensing and

Regulatory Affairs

Shane Marik, Vice President, Fleet Support

Ted Stoner, Site Vice President

Brad Kapellas, Plant Manager

Jeff Stone, Director, Risk Management

Johnny Weissinger, Director, Operations

Note: Attendance at this meeting by NRC personnel, other than those listed above, should be

made known to Ken Riemer at 630-829-9628 by November 21, 2018.

The NRC provides reasonable accommodation to individuals with disabilities where

appropriate. If you need a reasonable accommodation to participate in this meeting, or

need this meeting notice or the transcript or other information from the meeting in

another format (e.g., braille, large print), please notify the NRCs meeting coordinator.

Determinations on requests for reasonable accommodation will be made on a case-by-

case basis.

Because meetings are sometimes canceled or rescheduled as a result of unforeseen

circumstances, such as severe weather, confirm the meeting schedule with the meeting

contact.

Approved By: /RA/

Kenneth Riemer, Chief

Branch 1

Division of Reactor Projects

Meeting Contact: Kenneth Riemer

Chief, Branch 1

630-829-9628

Kenneth.Riemer@nrc.gov

Notice of Significant -3-

Licensee Meeting

DISTRIBUTION:

Christopher Cook, Region III Coordinator, OEDO

Michael King, Deputy Director, Division of Inspection and Regional Support, NRR

RidsNrrDorlLpl3

RidsNrrPMClinton Resource

Steven West, Regional Administrator, RIII

Darrell Roberts, Deputy Regional Administrator, RIII

Patrick Louden, Director, Division of Reactor Projects, RIII

Julio Lara, Deputy Director, Division of Reactor Projects, RIII

Kenneth OBrien, Director, Division of Reactor Safety, RIII

Mohammed Shuaibi, Deputy Director, Division of Reactor Safety, RIII

Kenneth Riemer, DRP Branch Chief

Elba Sanchez Santiago, SRI, Clinton

DRS Branch Chiefs:

Robert Daley

Steven Orth

David Hills

Robert Orlikowski

Karla Stoedter

Jamnes Cameron, Enforcement/Investigations Officer

Allan Barker, Regional State Liaison Officer, RIII

Viktoria Mitlyng, RIII Public Affairs

Prema Chandrathil, RIII Public Affairs

ADAMS Accession Number: ML18317A402

OFFICE RIII

NAME KRiemer:lg

DATE 11/13/2018

OFFICIAL RECORD COPY