{{#Wiki_filter:R i W *4REG,,' UNITED STATES pClijr A i. NUCLEAR REGULATORY  
{{#Wiki_filter:R Wi *4REG,,
COMMISSION  
              '                           UNITED STATES                                     pClijr A i.           NUCLEAR REGULATORY COMMISSION                     _     RLLI~f1)
_ RLLI~f1)WASHINGTON, D. C. 20555 8.,. AY 20 19lh VISA NJOVImaI May 4, 1981 OMM /TO ALL LICENSEES  
                                        WASHINGTON, D. C. 20555
OF OPERATING  
                                                                                8.,.     AY 20 19lh VISA NJOVImaI
PLANTS AND HOLDERS OF CONSTRUCTION  
                                                May 4, 1981                                   OMM       /
PERMITS Gentlemen:
    TO ALL LICENSEES OF OPERATING PLANTS AND HOLDERS OF CONSTRUCTION PERMITS
SUBJECT: QUALIFICATION  
      Gentlemen:
OF INSPECTION, EXAMINATION, AND TESTING AND AUDIT PERSONNEL (Generic Letter 81-01)Appendix B, "Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants," to 10 CFR Part 50 establishes overall quality assurance requirements for nuclear power plants. Two Regulatory Guides, discussed below, have been issued which provide guidance on an acceptable way to meet., Appendix B requirements.
      SUBJECT:     QUALIFICATION OF INSPECTION, EXAMINATION, AND TESTING AND AUDIT
                    PERSONNEL (Generic Letter 81-01)
      Appendix B, "Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants," to 10 CFR Part 50 establishes overall quality assurance requirements for nuclear power plants. Two Regulatory Guides, discussed below, have been issued which provide guidance on an acceptable way to meet.,
      Appendix B requirements. Enclosed for your information and use is-a copy of Regulatory Guide 1.58, Revision 1, dated September 1980, "Qualification of.


Enclosed for your information and use is-a copy of Regulatory Guide 1.58, Revision 1, dated September
Nuclear Power Plant Inspection, Examination, and Testing Personnel."                 /
1980, "Qualification of.Nuclear Power Plant Inspection, Examination, and Testing Personnel." /Regulatory Guide 1.58 endorses ANSI N45.2.6 with certain exceptions.
      Regulatory Guide 1.58 endorses   ANSI N45.2.6   with   certain exceptions.    The NRC staff has determined that the intent of regulatory positions C.5, 6, 7,
      8 and 10, which provide additional guidance concerning the qualification of
    *nuclear power plant inspection, examination, and testing personnel, should be implemented by all operating nuclear plants and those under construction.


The NRC staff has determined that the intent of regulatory positions C.5, 6, 7, 8 and 10, which provide additional guidance concerning the qualification of*nuclear power plant inspection, examination, and testing personnel, should be implemented by all operating nuclear plants and those under construction.
Also enclosed for your information and use is a copy of Regulatory Guide 1.146, dated August 1980, "Oualification of Quality Assurance Program Audit Personnel for Nuclear Power Plants." This guide endorses ANSI/ASME N45.2.23-1978 with certain exceptions. The NRC staff has determined that the intent of this guide should be implemented by all operating nuclear plants and those 'under construction.


Also enclosed for your information and use is a copy of Regulatory Guide 1.146, dated August 1980, "Oualification of Quality Assurance Program Audit Personnel for Nuclear Power Plants." This guide endorses ANSI/ASME
Therefore,,you are requested to furnish the following by 90 days from the date of this letter:
N45.2.23-1978 with certain exceptions.
        1. Commitments to meet regulatory positions C.5, 6, 7, 8, and 10 of Regulatory Guide 1.58, Revision 1, and Regulatory Guide 1.146, and your planned date for doing so; or
        2. If you elect not to adopt the methods given in Regulatory Guides 1.58, Revision 1, and 1.146 describe your alternative methods of complying with
            10 CFR Part 50, Appendix B regarding qualification of nuclear power plant inspection, examination, and testing personnel, and qualification of audit personnel, and your schedule for implementing the alternative methods.


The NRC staff has determined that the intent of this guide should be implemented by all operating nuclear plants and those 'under construction.
te .
  016020005


Therefore,,you are requested to furnish the following by 90 days from the date of this letter: 1. Commitments to meet regulatory positions C.5, 6, 7, 8, and 10 of Regulatory Guide 1.58, Revision 1, and Regulatory Guide 1.146, and your planned date for doing so; or 2. If you elect not to adopt the methods given in Regulatory Guides 1.58, Revision 1, and 1.146 describe your alternative methods of complying with 10 CFR Part 50, Appendix B regarding qualification of nuclear power plant inspection, examination, and testing personnel, and qualification of audit personnel, and your schedule for implementing the alternative methods.te .01 6020005
;..
-2-In your response please refer to this letter by title and number.Any questions regarding this matter may be addressed to your project manager.;..I it, uirector ing Reactor Regulation Enclosuress:
                                                                                  I
1. Regulatory Guide 1.58, Revision 1, dated September.1980
                                      -2- In your response please refer to this letter by title and number.
2. Regulatory Gutde 1.146, dated August 1980 cc: Service List I'  
 
.-DISTRIBUTION  
Any questions regarding this matter may be addressed to your project manager.
OF GNERIC LETTER 81-01, DATED MAY 4, 1981 Braidwood  
 
50-456/457 Beaver Valley 2 50-412 Bailly 50-367 Bellefonte  
it, uirector ing Reactor Regulation Enclosuress:
50-438/439 Byron 50-454/455 Cafl away Comanche Peak Cherokee Catawba Clinton 'Diablo Canyon Farley 2 Fermi 2 Grand Gulf Hartsville Hope Creek Harris TaSalle Limerick Marble Hills Millstone
1. Regulatory Guide 1.58, Revision
3 McGuire Midland 50-416/417
    1, dated September.1980
50-518/519/520/521
2. Regulatory Gutde 1.146, dated August 1980
50-354/355
cc:   Service List I'
50-400/401/402/403
 
50-373/.374
. -
50-352/353
    DISTRIBUTION OF GNERIC LETTER 81-01, DATED MAY 4, 1981 Braidwood                                   50-456/457 Beaver Valley 2                             50-412 Bailly                                     50-367 Bellefonte                                 50-438/439 Byron                                       50-454/455 Cafl away Comanche Peak Cherokee Catawba Clinton '
50-546/547
    Diablo Canyon Farley 2 Fermi 2 Grand Gulf                                 50-416/417 Hartsville                                  50-518/519/520/521 Hope Creek                                  50-354/355 Harris                                      50-400/401/402/403 TaSalle                                      50-373/.374 Limerick                                    50-352/353 Marble Hills                                50-546/547 Millstone 3                                  50-423 McGuire                                      50-369/370
50-423 50-369/370
    Midland                                      50-329/330
50-329/330
    Nine Mile Poit 2                             50-410
Nine Mile Poit 2 Phipps Bend Palo Verde Perry River Bend Summer Susquehanna Shoreham San Qnofre 2/3 Salem 2 St. Iucie 2 Seabrook South Texas Sequoyah 50-410 50-553/554
    Phipps Bend                                  50-553/554 Palo Verde                                  50-528/529/530
50-528/529/530
    Perry                                        50-440/441 River Bend                                  50-458/459 Summer                                      50-395 Susquehanna                                  50-387/388 Shoreham                                    50-322 San Qnofre 2/3                              50-361/362 Salem 2                                      50-311 St. Iucie 2                                  50-389 ,
50-440/441
    Seabrook                                    50-443/444 South Texas                                  50-498/499 Sequoyah                                    50-327/328 Vog0le                                       50-424/425 Wolf Creek                                  50-482 Waterford                                    50-382 WNP-2                                        50-397 WNP 3&5                                      50-508/509 Watts Bar                                    5 0-390/391 WNP 1 & 4                                    50-460/513 Yellow Creek                                  50-566/567 Zimmer                                        50-358
50-458/459
 
50-395 50-387/388
'I ,.
50-322 50-361/362
                                                            4C9enjro- Aies ALL POWER REACTOR LICENSEES
50-311 50-389 , 50-443/444
      Docket No. 50-348                         Docket No. 50-3 Farley Unit 1                            Indian Point Unit 1 Docket No. 50-313                         Docket No. 50-247 Arkansas Unit 1                           Indian Point Unit 2 Docket No. 50-368                         Docket 50-286 Arkansas Unit 2                           Indian Point Unit 3 Docket No. 50-317                         Docket No. 50-155 Calvert Cliffs Unit 1                     Big Rock Point Docket No. 50-318                        Docket No. 50-255 Calvert Cliffs Unit 2                     Palisades Docket No. 50-293                        Docket No. 50-409 Pilgrim Unit 1                           Lacrosse Docket No. 50-325                        Docket No. 50-269 Brunswick Unit 1                          Oconee Unit 1 Docket No. 50-324                        Docket No. 50-270
50-498/499
      Brunswick Unit 2                         Oconee Unit 2 Docket No. 50-261                        Docket No. 50-287 H. B. Robinson Unit 2                    Oconee Unit 3 Docket No. 50-10                          Docket No. 50-334 Dresden Unit 1                            Beaver Valley Unit 1 Docket No. 50-237                        Docket No. 50-302 Dresden Unit 2                            Crystal River 3 Docket No. 50-249                        Docket No. 50-335 Dresden Unit 3                           St. Lucie Unit 1 Docket No. 50-254                         Docket No. 50-250
50-327/328 Vog0le Wolf Creek Waterford WNP-2 WNP 3&5 Watts Bar WNP 1 & 4 50-424/425
      Quad-Cities Unit 1                        Turkey Point Unit 3 Docket No. 50-265                          Docket No. 50-251 Quad-Cities Unit 2                         Turkey Point Unit 4 Docket No. 50-295                          Docket No. 50-321 Zion Unit 1                                Edwin I. Hatch Unit 1 Docket No. 50-304                        Docket No. 50-366 Zion Unit 2                              Edwin I. Hatch Unit 2 Docket No. 50-213                        Docket No. 50-315 Connecticut Yankee (Haddam Neck)          D. C. Cook Unit 1
50-482 50-382 50-397 50-508/509
 
5 0-390/391 50-460/513
I
50-566/567
                          - 2 -
50-358 Yellow Creek Zimmer
  Docket No. 50-316       Docket No. 50-344  Docket No. 50-305 D. C. Cook Unit 2       Trojan              Kewaunee Docket No. 50-331       Docket No. 50-333  Docket No. 50-29 Duane Arnold            FitzPatrick        Yankee-Rowe Docket No. 50-219        Docket No. 50-267  Docket No. 50-339 Oyster Creek Unit 1      Ft. St. Vrain      North Anna 2 Docket No. 50-309        Docket No. 50-272  Docket No. 50-311 Maine Yankee            Salem Unit 1       Salem 2 Docket No. 50-289        Docket No. 50-244  Docket No. 50-327 Three Mile Island Unit 1 R. E. Ginna 1      Sequoyah 1 Docket No. 50-320        Docket No. 50-312  Docket No. 50-369 Three Mile Island Unit 2 Rancho Seco        McGuire 1 Docket No. 50-298        Docket No. 50-206  Docket No. 50-364 Cooper Station          San Onofre 1        Farley 2 Docket No. 50-220       Docket No. 50-259 Nine Mile Point Unit 1  Browns Ferry Unit 1 Docket No. 50-245       Docket No. 50-260
4C9enjro-'I ,.Aies ALL POWER REACTOR LICENSEES Docket No. 50-348 Farley Unit 1 Docket No. 50-313 Arkansas Unit 1 Docket No. 50-368 Arkansas Unit 2 Docket No. 50-317 Calvert Cliffs Unit 1 Docket No. 50-318 Calvert Cliffs Unit 2 Docket No. 50-293 Pilgrim Unit 1 Docket No. 50-325 Brunswick Unit 1 Docket No. 50-324 Brunswick Unit 2 Docket No. 50-261 H. B. Robinson Unit 2 Docket No. 50-10 Dresden Unit 1 Docket No. 50-237 Dresden Unit 2 Docket No. 50-249 Dresden Unit 3 Docket No. 50-3 Indian Point Unit 1 Docket No. 50-247 Indian Point Unit 2 Docket 50-286 Indian Point Unit 3 Docket No. 50-155 Big Rock Point Docket No. 50-255 Palisades Docket No. 50-409 Lacrosse Docket No. 50-269 Oconee Unit 1 Docket No. 50-270 Oconee Unit 2 Docket No. 50-287 Oconee Unit 3 Docket No. 50-334 Beaver Valley Unit 1 Docket No. 50-302 Crystal River 3 Docket No. 50-335 St. Lucie Unit 1 Docket No. 50-254 Quad-Cities Unit 1 Docket No. 50-265 Quad-Cities Unit 2 Docket No. 50-295 Zion Unit 1 Docket No. 50-304 Zion Unit 2 Docket No. 50-213 Connecticut Yankee Docket Turkey No. 50-250 Point Unit 3 Docket No. 50-251 Turkey Point Unit 4 Docket No. 50-321 Edwin I. Hatch Unit 1 Docket No. 50-366 Edwin I. Hatch Unit 2 Docket No. 50-315 D. C. Cook Unit 1 (Haddam Neck)
  Millstone Unit 1        Browns Ferry Unit 2 Docket No. 50-336       Docket No. 50-296     MAY 2 0 1981 - -.
I-2 -Docket No. 50-316 D. C. Cook Unit 2 Docket No. 50-331 Duane Arnold Docket No. 50-219 Oyster Creek Unit 1 Docket No. 50-309 Maine Yankee Docket No. 50-289 Three Mile Island Unit 1 Docket No. 50-320 Three Mile Island Unit 2 Docket No. 50-298 Cooper Station Docket No. 50-344 Trojan Docket No. 50-333 FitzPatrick Docket No. 50-267 Ft. St. Vrain Docket No. 50-272 Salem Unit 1 Docket No. 50-244 R. E. Ginna 1 Docket No. 50-312 Rancho Seco Docket No. 50-206 San Onofre 1 Docket No. 50-305 Kewaunee Docket No. 50-29 Yankee-Rowe Docket No. 50-339 North Anna 2 Docket No.Salem 2 Docket No.Sequoyah 1 Docket No.McGuire 1 50-311 50-327 50-369 Docket No. 50-364 Farley 2 Docket No. 50-220 Nine Mile Point Unit 1 Docket No. 50-259 Browns Ferry Unit 1 Docket No. 50-245 Millstone Unit 1 Docket No. 50-260 Browns Ferry Unit 2 Docket No. 50-336 Millstone Unit 2 Docket No. 50-296 Browns Ferry Unit 3 MAY 2 0 1981 --.W1U N3=1D UOKLAO-G co*COMN A Docket No. 50-263 Monticello Docket No. 50-346 Davis-Besse  
  Millstone Unit 2        Browns Ferry Unit 3    W1UN3=1D UOKLAO-G
1 Docket No. 50-282 Prairie Island Unit 1 Docket No. 50-306 Prairie Island Unit 2 Docket No. 50-285 Ft. Calhoun Docket No. 50-133 Humboldt Bay Docket No. 50-277 Peach Bottom 2 Docket No. 50-278 Peach Bottom 3 Docket No. 50-271 Vermont Yankee Docket No. 50-338 North Anna 1 Docket No. 50-280 Surry Unit 1 Docket No. 50-281 Surry Unit 2 Docket No. 50-266 Point Beach Unit 1 Docket No. 50-301 Point Beach Unit 2}}
                                                      co*COMN     A
  Docket No. 50-263       Docket No. 50-346 Monticello              Davis-Besse 1 Docket No. 50-282       Docket No. 50-271 Prairie Island Unit 1    Vermont Yankee Docket No. 50-306        Docket No. 50-338 Prairie Island Unit 2    North Anna 1 Docket No. 50-285        Docket No. 50-280
  Ft. Calhoun              Surry Unit 1 Docket No. 50-133        Docket No. 50-281 Humboldt Bay              Surry Unit 2 Docket No. 50-277        Docket No. 50-266 Peach Bottom 2            Point Beach Unit 1 Docket No. 50-278        Docket No. 50-301 Peach Bottom 3            Point Beach Unit 2}}


{{GL-Nav}}
{{GL-Nav}}

Latest revision as of 02:17, 24 November 2019

NRC Generic Letter 1981-001: Qualification of Inspection, Examination, and Testing and Audit Personnel
ML031210093
Person / Time
Site: Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, 05000000, Zimmer, Fort Saint Vrain, Washington Public Power Supply System, Shoreham, Satsop, Trojan, Bailly, Cherokee, Marble Hill, Hartsville, Phipps Bend, Yellow Creek, Crane
Issue date: 05/04/1981
From: Eisenhut D
Office of Nuclear Reactor Regulation
To:
References
RG-1-058, RG-1-146 GL-81-001, NUDOCS 8106020005
Download: ML031210093 (5)


R Wi *4REG,,

' UNITED STATES pClijr A i. NUCLEAR REGULATORY COMMISSION _ RLLI~f1)

WASHINGTON, D. C. 20555

8.,. AY 20 19lh VISA NJOVImaI

May 4, 1981 OMM /

TO ALL LICENSEES OF OPERATING PLANTS AND HOLDERS OF CONSTRUCTION PERMITS

Gentlemen:

SUBJECT: QUALIFICATION OF INSPECTION, EXAMINATION, AND TESTING AND AUDIT

PERSONNEL (Generic Letter 81-01)

Appendix B, "Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants," to 10 CFR Part 50 establishes overall quality assurance requirements for nuclear power plants. Two Regulatory Guides, discussed below, have been issued which provide guidance on an acceptable way to meet.,

Appendix B requirements. Enclosed for your information and use is-a copy of Regulatory Guide 1.58, Revision 1, dated September 1980, "Qualification of.

Nuclear Power Plant Inspection, Examination, and Testing Personnel." /

Regulatory Guide 1.58 endorses ANSI N45.2.6 with certain exceptions. The NRC staff has determined that the intent of regulatory positions C.5, 6, 7,

8 and 10, which provide additional guidance concerning the qualification of

  • nuclear power plant inspection, examination, and testing personnel, should be implemented by all operating nuclear plants and those under construction.

Also enclosed for your information and use is a copy of Regulatory Guide 1.146, dated August 1980, "Oualification of Quality Assurance Program Audit Personnel for Nuclear Power Plants." This guide endorses ANSI/ASME N45.2.23-1978 with certain exceptions. The NRC staff has determined that the intent of this guide should be implemented by all operating nuclear plants and those 'under construction.

Therefore,,you are requested to furnish the following by 90 days from the date of this letter:

1. Commitments to meet regulatory positions C.5, 6, 7, 8, and 10 of Regulatory Guide 1.58, Revision 1, and Regulatory Guide 1.146, and your planned date for doing so; or

2. If you elect not to adopt the methods given in Regulatory Guides 1.58, Revision 1, and 1.146 describe your alternative methods of complying with

10 CFR Part 50, Appendix B regarding qualification of nuclear power plant inspection, examination, and testing personnel, and qualification of audit personnel, and your schedule for implementing the alternative methods.

te .

016020005

..

I

-2- In your response please refer to this letter by title and number.

Any questions regarding this matter may be addressed to your project manager.

it, uirector ing Reactor Regulation Enclosuress:

1. Regulatory Guide 1.58, Revision

1, dated September.1980

2. Regulatory Gutde 1.146, dated August 1980

cc: Service List I'

. -

DISTRIBUTION OF GNERIC LETTER 81-01, DATED MAY 4, 1981 Braidwood 50-456/457 Beaver Valley 2 50-412 Bailly 50-367 Bellefonte 50-438/439 Byron 50-454/455 Cafl away Comanche Peak Cherokee Catawba Clinton '

Diablo Canyon Farley 2 Fermi 2 Grand Gulf 50-416/417 Hartsville 50-518/519/520/521 Hope Creek 50-354/355 Harris 50-400/401/402/403 TaSalle 50-373/.374 Limerick 50-352/353 Marble Hills 50-546/547 Millstone 3 50-423 McGuire 50-369/370

Midland 50-329/330

Nine Mile Poit 2 50-410

Phipps Bend 50-553/554 Palo Verde 50-528/529/530

Perry 50-440/441 River Bend 50-458/459 Summer 50-395 Susquehanna 50-387/388 Shoreham 50-322 San Qnofre 2/3 50-361/362 Salem 2 50-311 St. Iucie 2 50-389 ,

Seabrook 50-443/444 South Texas 50-498/499 Sequoyah 50-327/328 Vog0le 50-424/425 Wolf Creek 50-482 Waterford 50-382 WNP-2 50-397 WNP 3&5 50-508/509 Watts Bar 5 0-390/391 WNP 1 & 4 50-460/513 Yellow Creek 50-566/567 Zimmer 50-358

'I ,.

4C9enjro- Aies ALL POWER REACTOR LICENSEES

Docket No. 50-348 Docket No. 50-3 Farley Unit 1 Indian Point Unit 1 Docket No. 50-313 Docket No. 50-247 Arkansas Unit 1 Indian Point Unit 2 Docket No. 50-368 Docket 50-286 Arkansas Unit 2 Indian Point Unit 3 Docket No. 50-317 Docket No. 50-155 Calvert Cliffs Unit 1 Big Rock Point Docket No. 50-318 Docket No. 50-255 Calvert Cliffs Unit 2 Palisades Docket No. 50-293 Docket No. 50-409 Pilgrim Unit 1 Lacrosse Docket No. 50-325 Docket No. 50-269 Brunswick Unit 1 Oconee Unit 1 Docket No. 50-324 Docket No. 50-270

Brunswick Unit 2 Oconee Unit 2 Docket No. 50-261 Docket No. 50-287 H. B. Robinson Unit 2 Oconee Unit 3 Docket No. 50-10 Docket No. 50-334 Dresden Unit 1 Beaver Valley Unit 1 Docket No. 50-237 Docket No. 50-302 Dresden Unit 2 Crystal River 3 Docket No. 50-249 Docket No. 50-335 Dresden Unit 3 St. Lucie Unit 1 Docket No. 50-254 Docket No. 50-250

Quad-Cities Unit 1 Turkey Point Unit 3 Docket No. 50-265 Docket No. 50-251 Quad-Cities Unit 2 Turkey Point Unit 4 Docket No. 50-295 Docket No. 50-321 Zion Unit 1 Edwin I. Hatch Unit 1 Docket No. 50-304 Docket No. 50-366 Zion Unit 2 Edwin I. Hatch Unit 2 Docket No. 50-213 Docket No. 50-315 Connecticut Yankee (Haddam Neck) D. C. Cook Unit 1

I

- 2 -

Docket No. 50-316 Docket No. 50-344 Docket No. 50-305 D. C. Cook Unit 2 Trojan Kewaunee Docket No. 50-331 Docket No. 50-333 Docket No. 50-29 Duane Arnold FitzPatrick Yankee-Rowe Docket No. 50-219 Docket No. 50-267 Docket No. 50-339 Oyster Creek Unit 1 Ft. St. Vrain North Anna 2 Docket No. 50-309 Docket No. 50-272 Docket No. 50-311 Maine Yankee Salem Unit 1 Salem 2 Docket No. 50-289 Docket No. 50-244 Docket No. 50-327 Three Mile Island Unit 1 R. E. Ginna 1 Sequoyah 1 Docket No. 50-320 Docket No. 50-312 Docket No. 50-369 Three Mile Island Unit 2 Rancho Seco McGuire 1 Docket No. 50-298 Docket No. 50-206 Docket No. 50-364 Cooper Station San Onofre 1 Farley 2 Docket No. 50-220 Docket No. 50-259 Nine Mile Point Unit 1 Browns Ferry Unit 1 Docket No. 50-245 Docket No. 50-260

Millstone Unit 1 Browns Ferry Unit 2 Docket No. 50-336 Docket No. 50-296 MAY 2 0 1981 - -.

Millstone Unit 2 Browns Ferry Unit 3 W1UN3=1D UOKLAO-G

co*COMN A

Docket No. 50-263 Docket No. 50-346 Monticello Davis-Besse 1 Docket No. 50-282 Docket No. 50-271 Prairie Island Unit 1 Vermont Yankee Docket No. 50-306 Docket No. 50-338 Prairie Island Unit 2 North Anna 1 Docket No. 50-285 Docket No. 50-280

Ft. Calhoun Surry Unit 1 Docket No. 50-133 Docket No. 50-281 Humboldt Bay Surry Unit 2 Docket No. 50-277 Docket No. 50-266 Peach Bottom 2 Point Beach Unit 1 Docket No. 50-278 Docket No. 50-301 Peach Bottom 3 Point Beach Unit 2