| number = ML19156A416
| number = ML19171A302
| issue date = 06/04/2019
| issue date = 05/20/2019
| title = EA-19-020; Jan X-Ray Services, Inc. - Notice of Violation; NRC Routine Inspection Report No. 03011772/2019001(DNMS)
| title = Super Asphalt Pavement Corp., NRC Form 591M Part 1, Inspection Report No. 03035472/2019001
| author name = Roberts D
| author name = Reichard M
| author affiliation = NRC/RGN-III
| author affiliation = NRC/RGN-I
| addressee name = Reeve W
| addressee name = Roldan H
| addressee affiliation = JAN X-ray Services, Inc
| addressee affiliation = Super Asphalt Pavement Corp
| docket = 03011772
| docket = 03035472
| license number = 21-16560-01
| license number = 52-25537-01
| contact person =  
| contact person =  
| case reference number = EA-19-020
| document report number = IR 2019001
| document report number = IR 209001
| document type = Inspection Report, Safety and Compliance Inspection Record, NRC Form 591
| document type = Inspection Report Correspondence
| page count = 1
| page count = 4
}}
}}


Line 19: Line 18:


=Text=
=Text=
{{#Wiki_filter:June 4, 2019
{{#Wiki_filter:This document becomes an NRC Official Agency Record once it is signed by the Branch Chief NRC FORM 591 M PART 1 (07-20 1 2)* 10 CFR 2.201 U.S. NUCLEAR REGULATORY COMMISSION SAFETY INSPECTION REPORT AND COMPLIANCE INSPECTION LICENSEE/LOCATION INSPECTED: NRC/REGIONAL OFFICE Super Asphalt Pavement Corp. P.O. Box 1849 Guaynabo, PR 00970-1849 U.S. Nuclear Regulatory Commission Region I, 2100 Renaissance Blvd, Suite 100 King of Prussia, Pennsylvania 19406-2713 REPORT NUMBER(S) 201 9-00 1 DOCKET NUMBER(S) LICENSE NUMBER(S) DATE(S)
 
OF INSPECTION 030-35472 52-25537-01 May 20, 2019 LICENSEE: The inspection was an examination of the activities conducted under your license as they relate to radiation safety and to compliance with the Nuclear Regulatory Commission (NRC) rules and regulations and the conditions of your licens The inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspecto The inspection findings are as follows:
==SUBJECT:==
X Based on the inspection findings, no violations were identifie . Previous violation(s) close . The violation(s), specifically described to you by the inspector as non-cited violations, are not being cited because they were self
JAN X-RAY SERVICES, INC. - NOTICE OF VIOLATION; NRC ROUTINE INSPECTION REPORT NO. 03011772/2019001(DNMS)
- identified, non-repetitive, and corrective action was or is being taken, and the remaining criteria in the NRC Enforcement Policy, to exercise discretion, were satisfie Non-cited violation(s)
 
were discussed involving the following requirement(s) an d corrective action(s): During this inspection
==Dear Mr. Reeve:==
, certain of your activities, as described below and/or attached, were in violation of NRC requirements and are being cited in accordance with the NRC Enforcement Policy. This form is a NOTICE OF VIOLATION, which may be subject to posting in accordance with 10 CFR 19.1 (Violations and Corrective Actions)
This letter refers to the inspection conducted on January 7 through 10, 2019, at your facility in Parma, Michigan, and at two temporary job sites in Michigan, with continued in-office review through March 15, 2019. The purpose of the inspection was to review activ i t i es performed under your U. S. Nuclear Regulatory Commission (NRC) license to ensure they were being performed in accordance with NRC requirements, including an evaluation of the circumstances of a recent radiographer audit finding. Details of the inspection were provided in the non-public version of NRC Inspection Report No. 03011772/2019001(DNMS), issued on April 26, 2019. During the inspection, the NRC determined that an apparent violation of NRC requirements occurred. The circumstances surrounding the apparent violation, the significance of the issue, and the need for lasting and effective corrective action were discussed with you at the inspection exit meeting on [[Exit meeting date::March 29, 2019]].
Statement of Corrective Actions I hereby state that, within 30 days, the actions described by me to the Inspector will be taken to correct the violations identifie This statement of corrective actions is made in accordance with the requirements of 10 CFR 2.201 (corrective steps already taken, corrective steps which will be taken, date when full compliance will be achieved). I understand that no further written response to NRC will be required, unless specifically requeste Title Printed Name Signature Date LICENSEE'S REPRESENTATIVE NRC INSPECTOR Michael Reichard 6/10/2019 XMichael ReichardMichael ReichardSigned by: Michael C. Reichard NA BRANCH CHIEF Arthur Burritt 6/17/2019 XArthur L BurrittArthur BurrittSigned by: NRC-PIV N/A *NRC FO RM 591 M PART 1 (07-201 2) (RI Rev. 0 9/12/201 3) G:\WBL Documents
In the letter transmitting the inspection report, we provided you with the opportunity to address the apparent violation identified in the report by either attending a predecisional enforcement conference or by providing a written response before we made our final enforcement decision. In a letter
\WBL Inspection Records
, dated May 2, 2019, you provided a response to the apparent violation
\R52-25537-01.2019001.591M-Part1 DigitalSig-Public B1.doc SUNSI Review Completed By:
. Based on the information developed during the inspection and the information that you provided in your response to the inspection report
Michael Reichard X Public X Non-Sensitive
, dated May 2, 2019, the NRC has determined that a violation of NRC requirements occurred. The violation is cited in the enclosed Notice of Violation (Notice)(Enclosure 1)
(n on-public) and the circumstances surrounding it are described in detail in the non-public version of the subject inspection report. The violation is of concern to the NRC for the reasons stated in the Final Determination of Significance (Enclosure 2) (n on-public). Enclosure s 1 and 2 contain Sensitive Unclassified Non-Safeguards Information. When separated from Enclosures 1 and 2, this transmittal document is decontrolled. Therefore, this violation has been categorized in accordance with the NRC Enforcement Policy at Severity Level III. In accordance with the NRC Enforcement Policy, a base civil penalty in the amount of
$14,500 is considered for a Severity Level III violation. Because your facility has been the subject of escalated enforcement actions within the last 2 years, the NRC considered whether credit was warranted for Identification and Corrective Action in accordance with the civil penalty assessment process in Section 2.3.4 of the Enforcement Policy. Credit was warranted for Identification, because you, as the Radiation Safety Officer, identified the violation during a semiannual audit of radiographers. In NRC Inspection Report No.
 
3011772/2019001(DNMS), the NRC described its understanding of the corrective actions implemented to correct the violation. In your May 2, 2019, letter you described the corrective actions taken to correct the violation. These corrective actions are also documented in Enclosure 2
. Based on these corrective actions, the NRC has determined that Corrective Action credit is warranted.
 
Therefore, to encourage prompt identification and comprehensive correction of violations, I have been authorized, after consultation with the Director, Office of Enforcement, not to propose a civil penalty in this case. However, significant violations in the future could result in a civil penalty. In addition, issuance of this Severity Level III violation constitutes escalated enforcement action that may subject you to increased inspection effort. The NRC also includes significant enforcement actions on its Web site at http://www.nrc.gov/reading-rm/doc-collections/enforcement/actions
/. The NRC has concluded that information regarding
: (1) the reason for the violation; (2) the corrective actions that have been taken and the results achieved; and (3) the date when full compliance was achieved is already adequately addressed on the docket in Inspection Report No.03011772/2019001 (DNMS) and your letter dated May 2, 2019. Therefore, you are not required to respond to this letter unless the description therein does not accurately reflect your corrective actions or your position. In that case, or if you choose to provide additional information, you should follow the instructions specified in the enclosed Notice.
 
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390 of the NRC
's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or in the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
. However, the enclosures to this letter contain security-related information in accordance with 10 CFR 2.390(d)(1)
and its disclosure to unauthorized individuals could present a security vulnerability.
 
Therefore, the material in the enclosure s will not be made available electronically for public inspection in the NRC Public Document Room or in the NRC
's ADAMS. If you choose to respond and security-related information is necessary to provide an acceptable response, please mark the top of each page of your entire response
"security-related information
- Withhold under 10 CFR 2.390
" and follow the instructions for withholding in 10 CFR 2.390(b)(1).
 
Sincerely,
/RA by John B. Giessner acting for/
Darrell J. Roberts Regional Administrator Docket No.
 
030-11772 License No.
 
21-16560-01 Enclosures: 1. Notice of Violation 2. Final Determination of Significance cc w/o encl: State of Michigan
 
ML19156A416
}}
}}

Revision as of 15:42, 11 July 2019

Super Asphalt Pavement Corp., NRC Form 591M Part 1, Inspection Report No. 03035472/2019001
ML19171A302
Person / Time
Site: 07200201, 03031172
Issue date: 05/20/2019
From: Michael Reichard
NRC Region 1
To: Roldan H
Super Asphalt Pavement Corp
References
IR 2019001
Download: ML19171A302 (1)


Text

This document becomes an NRC Official Agency Record once it is signed by the Branch Chief NRC FORM 591 M PART 1 (07-20 1 2)* 10 CFR 2.201 U.S. NUCLEAR REGULATORY COMMISSION SAFETY INSPECTION REPORT AND COMPLIANCE INSPECTION LICENSEE/LOCATION INSPECTED: NRC/REGIONAL OFFICE Super Asphalt Pavement Corp. P.O. Box 1849 Guaynabo, PR 00970-1849 U.S. Nuclear Regulatory Commission Region I, 2100 Renaissance Blvd, Suite 100 King of Prussia, Pennsylvania 19406-2713 REPORT NUMBER(S) 201 9-00 1 DOCKET NUMBER(S) LICENSE NUMBER(S) DATE(S)

OF INSPECTION 030-35472 52-25537-01 May 20, 2019 LICENSEE: The inspection was an examination of the activities conducted under your license as they relate to radiation safety and to compliance with the Nuclear Regulatory Commission (NRC) rules and regulations and the conditions of your licens The inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspecto The inspection findings are as follows:

X Based on the inspection findings, no violations were identifie . Previous violation(s) close . The violation(s), specifically described to you by the inspector as non-cited violations, are not being cited because they were self

- identified, non-repetitive, and corrective action was or is being taken, and the remaining criteria in the NRC Enforcement Policy, to exercise discretion, were satisfie Non-cited violation(s)

were discussed involving the following requirement(s) an d corrective action(s): During this inspection

, certain of your activities, as described below and/or attached, were in violation of NRC requirements and are being cited in accordance with the NRC Enforcement Policy. This form is a NOTICE OF VIOLATION, which may be subject to posting in accordance with 10 CFR 19.1 (Violations and Corrective Actions)

Statement of Corrective Actions I hereby state that, within 30 days, the actions described by me to the Inspector will be taken to correct the violations identifie This statement of corrective actions is made in accordance with the requirements of 10 CFR 2.201 (corrective steps already taken, corrective steps which will be taken, date when full compliance will be achieved). I understand that no further written response to NRC will be required, unless specifically requeste Title Printed Name Signature Date LICENSEE'S REPRESENTATIVE NRC INSPECTOR Michael Reichard 6/10/2019 XMichael ReichardMichael ReichardSigned by: Michael C. Reichard NA BRANCH CHIEF Arthur Burritt 6/17/2019 XArthur L BurrittArthur BurrittSigned by: NRC-PIV N/A *NRC FO RM 591 M PART 1 (07-201 2) (RI Rev. 0 9/12/201 3) G:\WBL Documents

\WBL Inspection Records

\R52-25537-01.2019001.591M-Part1 DigitalSig-Public B1.doc SUNSI Review Completed By:

Michael Reichard X Public X Non-Sensitive