LOUISI AN A / 442 oe-o~oe smeer o oox 00.
P O W E F1 & L 1 G H T / NEW oALeANS LoUSANA 70174-6006 9 (So4]3880345 MIDDLE SOUTH UDUDES SGTEM October 10, 1985 W3P85-2696 A4.05 QA Director of Nuclear Reactor Regulation Attention:
Mr. G.W. Knighton, Chief Licensing Branch No. 3 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555
SUBJECT:
Waterford SES Unit No. 3 Docket No. 50-382 Schedule for Compliance with 10CFR50.62
REFERENCES:
(1) 10CFR50.62, ATWS Final Rule (49FR26036)
(2) NRR Generic Letter 85-06, dated 04/16/85,
" Quality Assurance Guidance for ATWS Equipment that is not Safety-Related" (3) "RPS/AFAS Diversity and the ATWS Rule" (RWW-85-66) from R.W. Wells (CEOG) to F. Rosa (NRC/ICSB) dated 09/18/85
Dear Sir:
Pursuant to References (1) and (2), Louisiana Power & Light Company hereby submits its proposed schedule for meeting the reporting requirements of 10CFR50.62, paragraphs (C)(1) and (C)(2).
Since Spring, 1985, the CE Owners Group and LP&L have been conducting a dialogue with the NRC to define the ATWS Rule requirements with respect to CE plants. These discussions culminated in the submittal of Reference (3) which indicated that diversity between the reactor protection system and the emergency feedwater actuation function currently exists sufficient to meet the intent of the ATWS Rule.
It is our understanding that the NRC has accepted this position and will shortly issue an SER to that effect.
As a result, and as discussed with our NRC Project Manager, LP&L's implementation of the ATWS Rule calls for the installation of a diverse scram system and turbine trip prior to completion of the second refueling outage.
8S10150126 8 % 9302 pog ADOCK O PDR
'9 P
I O
<:f
.r.
Mr. G.W.~Knighton' W3P85-2696.
- Page'2 Should' you require any additional-information regarding this matter, please -
contact Tim Gaudet at (504) 595-2835.
Yours very truly, K.W. Cook Nuclear Support & Licensing-Manager KWC/TJG/pcl cc:
B.W. Churchill, W.M. Stevenson, R.D. Martin, J. Wilson, T.A. Flippo, F. Rosa (NRC/ICSB)-