MONTHYEARW3F1-2024-0049, Notification of Readiness for Supplemental Inspection2024-10-21021 October 2024 Notification of Readiness for Supplemental Inspection W3F1-2024-0042, License Amendment Request to Extend Allowable Outage Times for One or More Control Room Air Conditioning Units Inoperable2024-10-16016 October 2024 License Amendment Request to Extend Allowable Outage Times for One or More Control Room Air Conditioning Units Inoperable W3F1-2024-0038, Response to Request for Additional Information - Proposed Alternative WF3-RR-24-01 for Examinations of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-09-24024 September 2024 Response to Request for Additional Information - Proposed Alternative WF3-RR-24-01 for Examinations of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds W3F1-2024-0039, Response to Request for Additional Information - Proposed Alternative WF3-RR-24-02 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-09-24024 September 2024 Response to Request for Additional Information - Proposed Alternative WF3-RR-24-02 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles W3F1-2024-0041, Reply to a Notice of Violation, EA-24-0522024-09-19019 September 2024 Reply to a Notice of Violation, EA-24-052 W3F1-2024-0040, Special Report SR 2024-001-00 Radiation Monitor Inoperable Greater than 7 Days2024-09-0303 September 2024 Special Report SR 2024-001-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2024-0019, (Waterford 3) - Steam Generator Tube Inspection Report for the 25th Rf Inspection Performed During Operating Cycle 25 / Refuel 252024-07-22022 July 2024 (Waterford 3) - Steam Generator Tube Inspection Report for the 25th Rf Inspection Performed During Operating Cycle 25 / Refuel 25 W3F1-2024-0032, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-07-17017 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation W3F1-2024-0024, Special Report SR 2023-004-02 Radiation Monitor Inoperable Greater than 7 Days2024-06-17017 June 2024 Special Report SR 2023-004-02 Radiation Monitor Inoperable Greater than 7 Days W3F1-2024-0011, Licensee Amendment Request to Modify Surveillance Requirements in Support of Surveillance Frequency Control Program2024-05-0808 May 2024 Licensee Amendment Request to Modify Surveillance Requirements in Support of Surveillance Frequency Control Program W3F1-2024-0018, Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 25 / Refuel 252024-05-0101 May 2024 Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 25 / Refuel 25 W3F1-2024-0014, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20242024-04-29029 April 2024 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2024 W3F1-2024-0015, Annual Radioactive Effluent Release Report (ARERR) 2023 with Revised ODCM and Revised Process Control Program Procedure2024-04-24024 April 2024 Annual Radioactive Effluent Release Report (ARERR) 2023 with Revised ODCM and Revised Process Control Program Procedure W3F1-2024-0016, Annual Radiological Environmental Operating Report (AREOR) - 20232024-04-24024 April 2024 Annual Radiological Environmental Operating Report (AREOR) - 2023 W3F1-2024-0017, Annual Report of Individual Monitoring of Radiation Exposure for 2023 Per 10 CFR 20.22062024-04-23023 April 2024 Annual Report of Individual Monitoring of Radiation Exposure for 2023 Per 10 CFR 20.2206 W3F1-2024-0020, Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 20232024-04-11011 April 2024 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2023 W3F1-2024-0008, Proposed Alternative WF3-RR-24-01 for Examinations of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-18018 March 2024 Proposed Alternative WF3-RR-24-01 for Examinations of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds W3F1-2024-0009, Proposed Alternative WF3-RR-24-02 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-03-18018 March 2024 Proposed Alternative WF3-RR-24-02 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles W3F1-2024-0012, Response to NRC Integrated Inspection Report 05000382/20230042024-03-11011 March 2024 Response to NRC Integrated Inspection Report 05000382/2023004 W3F1-2024-0006, Special Report SR-2023-004-01, Radiation Monitor Inoperable Greater than 7 Days2024-02-28028 February 2024 Special Report SR-2023-004-01, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0056, Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242023-12-19019 December 2023 Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2023-0055, Reply to a Notice of Violation2023-12-14014 December 2023 Reply to a Notice of Violation W3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O W3F1-2023-0049, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal2023-09-28028 September 2023 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal W3F1-2023-0048, Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-09-25025 September 2023 Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program W3F1-2023-0036, Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-05-0404 May 2023 Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0032, Annual Radioactive Effluent Release Report (ARERR) 20222023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) 2022 W3F1-2023-0033, Submittal of Annual Radiological Environmental Operating Report - 20222023-04-27027 April 2023 Submittal of Annual Radiological Environmental Operating Report - 2022 W3F1-2023-0025, Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.22062023-04-11011 April 2023 Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.2206 W3F1-2023-0018, Updated Final Supplemental Response to NRC Generic Letter 2004-022023-03-30030 March 2023 Updated Final Supplemental Response to NRC Generic Letter 2004-02 W3F1-2023-0022, Registration of Dry Fuel Storage Cask Use2023-03-22022 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0021, Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days2023-03-17017 March 2023 Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0016, Registration of Dry Fuel Storage Cask Use2023-03-0303 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0014, Reply to a Notice of Violation; EA-22-1192023-02-20020 February 2023 Reply to a Notice of Violation; EA-22-119 W3F1-2023-0013, Notification of Readiness for Supplemental Inspection2023-02-15015 February 2023 Notification of Readiness for Supplemental Inspection W3F1-2023-0007, Registration of Dry Fuel Storage Cask Use2023-02-0606 February 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0010, Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days2023-01-25025 January 2023 Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0002, SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days2023-01-0505 January 2023 SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days W3F1-2022-0067, Commitment Change Notification for Generic Safety Issue – 191 and Generic Letter 2004-022022-12-20020 December 2022 Commitment Change Notification for Generic Safety Issue – 191 and Generic Letter 2004-02 W3F1-2022-0054, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability2022-11-0101 November 2022 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability W3F1-2022-0063, Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 372022-10-27027 October 2022 Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 37 W3F1-2022-0059, Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-5052022-10-13013 October 2022 Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-505 W3F1-2022-0058, Reply to a Notice of Violation; EA-22-0332022-10-12012 October 2022 Reply to a Notice of Violation; EA-22-033 W3F1-2022-0049, Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-5052022-08-19019 August 2022 Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 W3F1-2022-0037, Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242022-08-0808 August 2022 Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2022-0044, SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-07-0606 July 2022 SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0042, SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-06-27027 June 2022 SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.2022-05-16016 May 2022 Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf. W3F1-2022-0026, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20222022-04-28028 April 2022 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2022 2024-09-03
[Table view] |
Text
Entergy Operations, Inc.
17265 River Road Killona, LA 70057 a I~fl~f'JTel 504 739 6660 Fax 504 739 6678 jkowale@entergy.com Joseph A. Kowalewski Vice President, Operations Waterford 3 W3F1-2009-0025 June 3, 2009 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Withdrawal of License Amendment Request License Condition to Support Implementation of Extended In-Service Inspection Interval Waterford Steam Electric Station, Unit 3 Docket No. 50-382 License No. NPF-38
REFERENCE:
- 1. Entergy letter dated September 18, 2008, Request for Alternative W3-ISI-006 Proposed Alternative to Extend the Second. 10-Year Inservice Inspection Interval for Reactor Vessel Internal Weld Examinations (W3F1-2008-0060)
- 2. Entergy letter dated September 17, 2008, License Amendment Request NPF-38-280, License Condition to Support Implementation of Extended In-Service Inspection Interval (W3F1-2008-0061)
Dear Sir or Madam:
In Reference 1, Waterford Steam Electric Station, Unit 3, (Waterford 3), had proposed an alternative to the requirements of ASME Section XI, paragraph IWB-2412, Inspection Program B, to extend the In-Service Inspection (ISI) intervals for the Reactor Vessel Internal (RVI) weld inspections through the end of the facility's operating license. This proposal was based upon the Safety Evaluation (SE) for Topical Report WCAP-16168-NP-A, Revision 2. In this SE, the NRC required licensees to amend their facility operating license to provide the NRC with the information and analyses requested in Section (e) of the final rule for paragraph 10CFR 50.61(a) or the proposed rule published in the Federal Register on October 3, 2007 (72 FR 56275) within one year following completion of each ASME Code,Section XI, Category B-A and B-D weld inspection.
Accordingly, in Reference 2, Waterford 3 submitted a license amendment request to add a license condition to support the implementation of the extended RVI ISI interval.
W3F1 -2009-0025 Page 2 Subsequently, we understand the NRC has reconsidered their position on allowing licensees to extend RVI ISI weld inspections through the end of the facility's operating license and the NRC will grant ISI interval extensions on an interval-by interval basis only (i.e., only a facility's current ISI interval will be extended for up to 20 years). Based on this NRC position, the requirement in the staff's SE on WCAP-16168-NP is no longer necessary, and the license amendment requested by Waterford 3 in Reference 2 will not be issued in conjunction with the requested alternative, W3-1SI-006, in Reference 1.
In view of the foregoing information, Waterford 3 hereby withdraws the request for License Amendment Request NPF-38-280.
There are no regulatory commitments contained in this submittal.
Please contact Robert Murillo, Manager, Licensing, at (504) 739-6715, if you have any questions or require additional information.
I declare under penalty of perjury that the foregoing is true and correct. This submittal is executed on June 3, 2009.
Sincerely, JAK/R M/MEM/ssf
.. W3F1-2009-0025 Page 3 cc: Mr. Elmo E. Collins, Jr.
Regional Administrator U. S. Nuclear Regulatory Commission Region IV 612 E. Lamar Blvd., Suite 400 Arlington, TX 76011-4125 NRC Senior Resident Inspector Waterford Steam Electric Station Unit 3 P.O. Box 822 Killona, LA 70066-0751 U. S. Nuclear Regulatory Commission Attn: Mr. N. Kalyanam Mail Stop O-07D1 Washington, DC 20555-0001 Wise, Carter, Child & Caraway ATTN: J. Smith P.O. Box 651 Jackson, MS 39205 Winston & Strawn ATTN: N.S. Reynolds 1700 K Street, NW Washington, DC 20006-3817 Morgan, Lewis & Bockius LLP ATTN: T.C. Poindexter 1111 Pennsylvania Avenue, NW Washington, DC 20004