U-600743, Forwards Changes to Physical Security Plan,Per 10CFR50.54(p).Changes Withheld

From kanterella
Jump to navigation Jump to search
Forwards Changes to Physical Security Plan,Per 10CFR50.54(p).Changes Withheld
ML20214S384
Person / Time
Site: Clinton 
Issue date: 12/01/1986
From: Spangenberg F
ILLINOIS POWER CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
U-600743, NUDOCS 8612080270
Download: ML20214S384 (1)


Text

U 600743 L13-86 ( 12. 01)-L 8E.120

/LLINDIS POWER COMPANY CLINTON POWER STATION. P.

dOx 678, CLINTON. ILLINOIS 61727 December 1, 19F g n _ q t, (

Mr. Harold Denton Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Clinton Power Station Miscellaneous Amendments for 10 CFR Parts 50 and 73, Concerning Physical Protection of Nuclear Power Plants; Final Rule, August 4, 1986

Dear Mr. Denton:

Pursuant to a discussion with Mr. Robert Skeleton, Office of Nuclear Material and Safeguards, the changes to the Clinton Power Station Physical Security Plan required by the final rule are being submitted in accordance with 10CFR50.54(p). The changes are as described in the attechment and do not decrease the effectiveness of the Clinton Power Station security plan.

Sincerely yours, G'.

)

F.A.Sangenf erg Manager - Lice nsing and Safety JAB /ckc Attachment cc: Regional Administrator, Region III, USNRC (w/ attachment)

NRC Resident Office (w/o attachment)

Illinois Department of Nuclear Safety (w/o attachment)

B. L. Siegel, NRC Clinton Project Manager (w/o attachment) gol o

8612080270 861201 i/

PDR

/+ DOCK 05000461 I

F PDR SAFEGUARDS INFORMATION Unclassified upon removal of enclosures.